Rate analsis Chapter No. 20 (Surface Drainage)
-
Upload
m-hafeez-raja -
Category
Documents
-
view
222 -
download
0
Transcript of Rate analsis Chapter No. 20 (Surface Drainage)
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 1/43
H PTER N .
SURFACE DRAINAGE
DESCRIPTION OF ITEM NO 1: Tega formed of pacca bricks on end, laid in and over cement
sand mortar projecting to a height of not more than 6"
(150mm) top of drain along the property side where required,
laid to lines, grades, slopes and shape according to the
engineer's drawing.
a) 3" (75mm) Thick.
i) Ratio (1:3)
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Cement 0.96 Bag 230.00 Each 220.80
Sand 3.20 Cft 3.50 P. Cft 11.20
Bricks 260.00 Nos 1200.00 Per 1000 Nos 312.00
Total 544.00
Contractor's Profit & Overheads 20 Percent 108.80
Total 652.80
Labour for 125 Rft
Mason 0.67 No 300.00 P. Day 201.00
Unskilled Cooly 1.00 No 140.00 P. Day 140.00
Bahishti 0.25 No 160.00 P. Day 40.00
Total 381.00
Sundries 10 Percent 38.10
Total 419.10
Contractor's Profit & Overheads 20 Percent 83.82
Total 502.92
Item Rates
Labour Rate Per 100 Rft Rs. 402.34 Say 402.35
Labour Rate Per Rm Rs. 13.20 Say 13.20
Composite Rate Per 100 Rft Rs. 1055.14 Say 1,055.15
Composite Rate Per Rm Rs. 34.61 Say 34.60
Unit Rate (British System) per 100 Rft
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 2/43
Item No. 1 Tega formed of pacca bricks on end, laid in and over cement
sand mortar projecting to a height of not more than 6"
(150mm) top of drain along the property side where required,
laid to lines, grades, slopes and shape according to the
engineer's drawing.
a) 3" (75mm) Thick.
ii) Ratio (1:5)
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Cement 0.64 Bag 230.00 Each 147.20
Sand 4.00 Cft 3.50 P. Cft 14.00
Bricks 260.00 Nos 1200.00 Per 1000 Nos 312.00
Total 473.20
Contractor's Profit & Overheads 20 Percent 94.64
Total 567.84
Labour for 125 Rft
Mason 0.67 No 300.00 P. Day 201.00
Unskilled Cooly 1.00 No 140.00 P. Day 140.00
Bahishti 0.25 No 160.00 P. Day 40.00
Total 381.00 Sundries 10 Percent 38.10
Total 419.10
Contractor's Profit & Overheads 20 Percent 83.82
Total 502.92
Item Rates
Labour Rate Per 100 Rft Rs. 402.34 Say 402.35
Labour Rate Per Rm Rs. 13.20 Say 13.20
Composite Rate Per 100 Rft Rs. 970.18 Say 970.20
Composite Rate Per Rm Rs. 31.82 Say 31.80
Unit Rate (British System) per 100 Rft
Page 2
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 3/43
Item No. 1 Tega formed of pacca bricks on end, laid in and
over cement sand mortar projecting to a height of
not more than 6" (150mm) top of drain along the
property side where required, laid to lines,
grades, slopes and shape according to the
engineer's drawing.
b) 4½" (115mm) Thick.
i) Ratio (1:3)
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Cement 1.30 Bag 230.00 Each 299.00
Sand 4.70 Cft 3.50 P. Cft 16.45
Bricks 380.00 Nos 1200.00 Per 1000 Nos 456.00
Total 771.45
Contractor's Profit & Overheads 20 Percent 154.29
Total 925.74
Labour for 125 Rft
Mason 1.00 No 300.00 P. Day 300.00
Unskilled Cooly 1.50 No 140.00 P. Day 210.00
Bahishti 0.38 No 160.00 P. Day 60.80
Total 570.80 Sundries 10 Percent 57.08
Total 627.88
Contractor's Profit & Overheads 20 Percent 125.58
Total 753.46
Item Rates
Labour Rate Per 100 Rft Rs. 602.76 Say 602.75
Labour Rate Per Rm Rs. 19.77 Say 19.75
Composite Rate Per 100 Rft Rs. 1528.50 Say 1,528.50
Composite Rate Per Rm Rs. 50.13 Say 50.15
Unit Rate (British System) per 100 Rft
Page 3
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 4/43
Item No. 1 Tega formed of pacca bricks on end, laid in and
over cement sand mortar projecting to a height of
not more than 6" (150mm) top of drain along the
property side where required, laid to lines,
grades, slopes and shape according to the
engineer's drawing.
b) 4½" (115mm) Thick.
ii) Ratio (1:5)
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Cement 0.83 Bag 230.00 Each 190.90
Sand 5.20 Cft 3.50 P. Cft 18.20
Bricks 380.00 Nos 1200.00 Per 1000 Nos 456.00
Total 665.10
Contractor's Profit & Overheads 20 Percent 133.02
Total 798.12
Labour for 125 Rft
Mason 1.00 No 300.00 P. Day 300.00
Unskilled Cooly 1.50 No 140.00 P. Day 210.00
Bahishti 0.38 No 160.00 P. Day 60.80
Total 570.80 Sundries 10 Percent 57.08
Total 627.88
Contractor's Profit & Overheads 20 Percent 125.58
Total 753.46
Item Rates
Labour Rate Per 100 Rft Rs. 602.76 Say 602.75
Labour Rate Per Rm Rs. 19.77 Say 19.75
Composite Rate Per 100 Rft Rs. 1400.88 Say 1,400.90
Composite Rate Per Rm Rs. 45.95 Say 45.95
Unit Rate (British System) per 100 Rft
Page 4
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 5/43
DESCRIPTION OF ITEM NO 2: Pacca flat brick 3" (75mm) thick, laid in
reimbursement, in cement, sand mortar on sides
of drains and in other works where required. All
joints to be completely filled and struck flush.
a) Ratio (1:3)
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Pacca Bricks 350.00 Nos 1200.00 Per 1000 Nos 420.00
Cement 1.50 Bag 230.00 Each 345.00
Sand 5.60 Cft 3.50 P. Cft 19.60
Total 784.60
Contractor's Profit & Overheads 20 Percent 156.92
Total 941.52
Labour for 125 Sft
Mason 1.00 No 300.00 P. Day 300.00
Unskilled Cooly 1.50 No 140.00 P. Day 210.00
Bahishti 0.33 No 160.00 P. Day 52.80
Total 562.80
Sundries 10 Percent 56.28
Total 619.08
Contractor's Profit & Overheads 20 Percent 123.82
Total 742.90
Item Rates
Labour Rate Per 100 Sft Rs. 594.32 Say 594.30
Labour Rate Per Sqm Rs. 63.95 Say 63.95
Composite Rate Per 100 Sft Rs. 1535.84 Say 1,535.85
Composite Rate Per Sqm Rs. 165.26 Say 165.25
Unit Rate (British System) per 100 Sft
Page 5
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 6/43
Item No. 2 Pacca flat brick 3" (75mm) thick, laid in
reimbursement, in cement, sand mortar on sides
of drains and in other works where required. All
joints to be completely filled and struck flush.
b) Ratio (1:5)
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Bricks 350.00 Nos 1200.00 Per 1000 Nos 420.00
Cement 1.00 Bag 230.00 Each 230.00
Sand 6.25 Cft 3.50 P. Cft 21.88
Total 671.88
Contractor's Profit & Overheads 20 Percent 134.38
Total 806.25
Labour for 125 Sft
Mason 1.00 No 300.00 P. Day 300.00
Unskilled Cooly 1.50 No 140.00 P. Day 210.00
Bahishti 0.33 No 160.00 P. Day 52.80
Total 562.80
Sundries 10 Percent 56.28
Total 619.08
Contractor's Profit & Overheads 20 Percent 123.82
Total 742.90
Item Rates
Labour Rate Per 100 Sft Rs. 594.32 Say 594.30
Labour Rate Per Sqm Rs. 63.95 Say 63.95
Composite Rate Per 100 Sft Rs. 1400.57 Say 1,400.55
Composite Rate Per Sqm Rs. 150.70 Say 150.70
Unit Rate (British System) per 100 Sft
Page 6
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 7/43
Item No. 2 Pacca flat brick 3" (75mm) thick, laid in
reimbursement, in cement, sand mortar on sides
of drains and in other works where required. All
joints to be completely filled and struck flush.
c) Ratio (1:6)
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Bricks 350.00 Nos 1200.00 Per 1000 Nos 420.00
Cement 0.86 Bag 230.00 Each 197.80
Sand 6.40 Cft 3.50 P. Cft 22.40
Total 640.20
Contractor's Profit & Overheads 20 Percent 128.04
Total 768.24
Labour for 125 Sft
Mason 1.00 No 300.00 P. Day 300.00
Unskilled Cooly 1.50 No 140.00 P. Day 210.00
Bahishti 0.33 No 160.00 P. Day 52.80
Total 562.80
Sundries 10 Percent 56.28
Total 619.08
Contractor's Profit & Overheads 20 Percent 123.82
Total 742.90
Item Rates
Labour Rate Per 100 Sft Rs. 594.32 Say 594.30
Labour Rate Per Sqm Rs. 63.95 Say 63.95
Composite Rate Per 100 Sft Rs. 1362.56 Say 1,362.55
Composite Rate Per Sqm Rs. 146.61 Say 146.60
Unit Rate (British System) per 100 Sft
Page 7
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 8/43
DESCRIPTION OF ITEM NO 3: Pacca brick on edge, laid in reimbursement, in
cement, sand mortar on sides of drains and in
other works where required. All joints to be
completely filled and struck flush.
a) Ratio (1:3)
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Bricks 525.00 Nos 1200.00 Per 1000 Nos 630.00
Cement 2.30 Bag 230.00 Each 529.00
Sand 8.55 Cft 3.50 P. Cft 29.93
Total 1,188.93
Contractor's Profit & Overheads 20 Percent 237.79
Total 1,426.71
Labour for 125 Sft
Mason 1.50 No 300.00 P. Day 450.00
Unskilled Cooly 2.00 No 140.00 P. Day 280.00
Bahishti 0.50 No 160.00 P. Day 80.00
Total 810.00
Sundries 10 Percent 81.00
Total 891.00
Contractor's Profit & Overheads 20 Percent 178.20
Total 1,069.20
Item Rates
Labour Rate Per 100 Sft Rs. 855.36 Say 855.35
Labour Rate Per Sqm Rs. 92.04 Say 92.05
Composite Rate Per 100 Sft Rs. 2282.07 Say 2,282.05
Composite Rate Per Sqm Rs. 245.55 Say 245.55
Unit Rate (British System) per 100 Sft
Page 8
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 9/43
Item No. 3 Pacca brick on edge, laid in reimbursement, in
cement, sand mortar on sides of drains and in
other works where required. All joints to be
completely filled and struck flush.
b) Ratio (1:5)
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Bricks 525.00 Nos 1200.00 Per 1000 Nos 630.00
Cement 1.50 Bag 230.00 Each 345.00
Sand 9.50 Cft 3.50 P. Cft 33.25
Total 1,008.25
Contractor's Profit & Overheads 20 Percent 201.65
Total 1,209.90
Labour for 125 Sft
Mason 1.50 No 300.00 P. Day 450.00
Unskilled Cooly 2.00 No 140.00 P. Day 280.00
Bahishti 0.50 No 160.00 P. Day 80.00
Total 810.00
Sundries 10 Percent 81.00
Total 891.00
Contractor's Profit & Overheads 20 Percent 178.20
Total 1,069.20
Item Rates
Labour Rate Per 100 Sft Rs. 855.36 Say 855.35
Labour Rate Per Sqm Rs. 92.04 Say 92.05
Composite Rate Per 100 Sft Rs. 2065.26 Say 2,065.25
Composite Rate Per Sqm Rs. 222.22 Say 222.20
Unit Rate (British System) per 100 Sft
Page 9
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 10/43
Item No. 3 Pacca brick on edge, laid in reimbursement, in
cement, sand mortar on sides of drains and in
other works where required. All joints to be
completely filled and struck flush.
c) Ratio (1:6)
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Bricks 525.00 Nos 1200.00 Per 1000 Nos 630.00
Cement 1.30 Bag 230.00 Each 299.00
Sand 9.78 Cft 3.50 P. Cft 34.23
Total 963.23
Contractor's Profit & Overheads 20 Percent 192.65
Total 1,155.88
Labour for 125 Sft
Mason 1.50 No 300.00 P. Day 450.00
Unskilled Cooly 2.00 No 140.00 P. Day 280.00
Bahishti 0.50 No 160.00 P. Day 80.00
Total 810.00
Sundries 10 Percent 81.00
Total 891.00
Contractor's Profit & Overheads 20 Percent 178.20
Total 1,069.20
Item Rates
Labour Rate Per 100 Sft Rs. 855.36 Say 855.35
Labour Rate Per Sqm Rs. 92.04 Say 92.05
Composite Rate Per 100 Sft Rs. 2011.24 Say 2,011.25
Composite Rate Per Sqm Rs. 216.41 Say 216.40
Unit Rate (British System) per 100 Sft
Page 10
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 11/43
DESCRIPTION OF ITEM NO 4: Pacca flat brick, herring bond pitching in cement,
sand mortar laid to lines, grades, shapes and
slopes as per Engineer's Drawing.
a) Ratio (1:3)
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Bricks 350.00 Nos 1200.00 Per 1000 Nos 420.00
Cement 1.50 Bag 230.00 Each 345.00
Sand 5.60 Cft 3.50 P. Cft 19.60
Total 784.60
Contractor's Profit & Overheads 20 Percent 156.92
Total 941.52
Labour for 125 Sft
Mason 0.75 No 300.00 P. Day 225.00
Unskilled Cooly 1.50 No 140.00 P. Day 210.00
Bahishti 0.50 No 160.00 P. Day 80.00
Total 515.00
Sundries 10 Percent 51.50
Total 566.50
Contractor's Profit & Overheads 20 Percent 113.30 Total 679.80
Item Rates
Labour Rate Per 100 Sft Rs. 543.84 Say 543.85
Labour Rate Per Sqm Rs. 58.52 Say 58.50
Composite Rate Per 100 Sft Rs. 1485.36 Say 1,485.35
Composite Rate Per Sqm Rs. 159.82 Say 159.85
Unit Rate (British System) per 100 Sft
Page 11
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 12/43
Item No. 4 Pacca flat brick, herring bond pitching in cement,
sand mortar laid to lines, grades, shapes and
slopes as per Engineer's Drawing.
b) Ratio (1:5)
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Bricks 350.00 Nos 1200.00 Per 1000 Nos 420.00
Cement 1.00 Bag 230.00 Each 230.00
Sand 6.25 Cft 3.50 P. Cft 21.88
Total 671.88
Contractor's Profit & Overheads 20 Percent 134.38
Total 806.25
Labour for 125 Sft
Mason 0.75 No 300.00 P. Day 225.00
Unskilled Cooly 1.50 No 140.00 P. Day 210.00
Bahishti 0.50 No 160.00 P. Day 80.00
Total 515.00
Sundries 10 Percent 51.50
Total 566.50
Contractor's Profit & Overheads 20 Percent 113.30 Total 679.80
Item Rates
Labour Rate Per 100 Sft Rs. 543.84 Say 543.85
Labour Rate Per Sqm Rs. 58.52 Say 58.50
Composite Rate Per 100 Sft Rs. 1350.09 Say 1,350.10
Composite Rate Per Sqm Rs. 145.27 Say 145.25
Unit Rate (British System) per 100 Sft
Page 12
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 13/43
Item No. 4 Pacca flat brick, herring bond pitching in cement,
sand mortar laid to lines, grades, shapes and
slopes as per Engineer's Drawing.
c) Ratio (1:6)
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Bricks 350.00 Nos 1200.00 Per 1000 Nos 420.00
Cement 0.86 Bag 230.00 Each 197.80
Sand 6.40 Cft 3.50 P. Cft 22.40
Total 640.20
Contractor's Profit & Overheads 20 Percent 128.04
Total 768.24
Labour for 125 Sft
Mason 0.75 No 300.00 P. Day 225.00
Unskilled Cooly 1.50 No 140.00 P. Day 210.00
Bahishti 0.50 No 160.00 P. Day 80.00
Total 515.00
Sundries 10 Percent 51.50
Total 566.50
Contractor's Profit & Overheads 20 Percent 113.30 Total 679.80
Item Rates
Labour Rate Per 100 Sft Rs. 543.84 Say 543.85
Labour Rate Per Sqm Rs. 58.52 Say 58.50
Composite Rate Per 100 Sft Rs. 1312.08 Say 1,312.10
Composite Rate Per Sqm Rs. 141.18 Say 141.20
Unit Rate (British System) per 100 Sft
Page 13
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 14/43
DESCRIPTION OF ITEM NO 5: Pacca brick on edge, herring bond pitching in
cement, sand mortar laid to lines, grades, shapes
and slopes as per Engineer's Drawing.
a) Ratio (1:3)
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Bricks 525.00 Nos 1200.00 Per 1000 Nos 630.00
Cement 2.30 Bag 230.00 Each 529.00
Sand 8.55 Cft 3.50 P. Cft 29.93
Total 1,188.93
Contractor's Profit & Overheads 20 Percent 237.79
Total 1,426.71
Labour for 125 Sft
Mason 1.00 No 300.00 P. Day 300.00
Unskilled Cooly 2.80 Nos 140.00 P. Day 392.00
Bahishti 0.50 No 160.00 P. Day 80.00
Total 772.00
Sundries 10 Percent 77.20
Total 849.20
Contractor's Profit & Overheads 20 Percent 169.84 Total 1,019.04
Item Rates
Labour Rate Per 100 Sft Rs. 815.23 Say 815.25
Labour Rate Per Sqm Rs. 87.72 Say 87.70
Composite Rate Per 100 Sft Rs. 2241.94 Say 2,241.95
Composite Rate Per Sqm Rs. 241.23 Say 241.25
Unit Rate (British System) per 100 Sft
Page 14
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 15/43
Item No. 5 Pacca brick on edge, herring bond pitching in
cement, sand mortar laid to lines, grades, shapes
and slopes as per Engineer's Drawing.
b) Ratio (1:5)
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Bricks 525.00 Nos 1200.00 Per 1000 Nos 630.00
Cement 1.50 Bag 230.00 Each 345.00
Sand 9.50 Cft 3.50 P. Cft 33.25
Total 1,008.25
Contractor's Profit & Overheads 20 Percent 201.65
Total 1,209.90
Labour for 125 Sft
Mason 1.00 No 300.00 P. Day 300.00
Unskilled Cooly 2.80 Nos 140.00 P. Day 392.00
Bahishti 0.50 No 160.00 P. Day 80.00
Total 772.00
Sundries 10 Percent 77.20
Total 849.20
Contractor's Profit & Overheads 20 Percent 169.84 Total 1,019.04
Item Rates
Labour Rate Per 100 Sft Rs. 815.23 Say 815.25
Labour Rate Per Sqm Rs. 87.72 Say 87.70
Composite Rate Per 100 Sft Rs. 2025.13 Say 2,025.15
Composite Rate Per Sqm Rs. 217.90 Say 217.90
Unit Rate (British System) per 100 Sft
Page 15
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 16/43
Item No. 5 Pacca brick on edge, herring bond pitching in
cement, sand mortar laid to lines, grades, shapes
and slopes as per Engineer's Drawing.
c) Ratio (1:6)
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Bricks 525.00 Nos 1200.00 Per 1000 Nos 630.00
Cement 1.30 Bag 230.00 Each 299.00
Sand 9.78 Cft 3.50 P. Cft 34.23
Total 963.23
Contractor's Profit & Overheads 20 Percent 192.65
Total 1,155.88
Labour for 125 Sft
Mason 1.00 No 300.00 P. Day 300.00
Unskilled Cooly 2.80 Nos 140.00 P. Day 392.00
Bahishti 0.50 No 160.00 P. Day 80.00
Total 772.00
Sundries 10 Percent 77.20
Total 849.20
Contractor's Profit & Overheads 20 Percent 169.84 Total 1,019.04
Item Rates
Labour Rate Per 100 Sft Rs. 815.23 Say 815.25
Labour Rate Per Sqm Rs. 87.72 Say 87.70
Composite Rate Per 100 Sft Rs. 1971.11 Say 1,971.10
Composite Rate Per Sqm Rs. 212.09 Say 212.10
Unit Rate (British System) per 100 Sft
Page 16
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 17/43
DESCRIPTION OF ITEM NO 6: Constructing Punjab standard drains of cement
concrete 1:2½:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades, slopes
and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar ¼"(6mm)
thick as per Engineers Drawing (excluding
Excavation).
a) Type I
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
CC 1:6:12
1x100x5/6'x1/6' 13.89 Cft
Say: 13.90 Cft
CC 1:2½:5
1x100x5/6'x11/24' 38.19 Cft
D/D 1x100x22/7x¼x¼x¼x½ 2.45 Cft
D/D 1x100x(6"+10")x½" 2.78 Cft
2 32.96 Cft
Say: 33.00 Cft
Surface Rendering
1x100x22/7x3/12' 78.57 Sft
1x100x(2"+2") 33.33 Sft
12 111.90 Sft
Say: 112 SftMaterial
Cement for.
Cement Concrete 1:6:12 0.90 Bag
Cement Concrete 1:2½:5 4.78 Bag
¼" Cement PLaster 1:1 1.03 Bag
6.71 Bag 230.00 Each 1,543.30
Sand for.
Cement Concrete 1:6:12 6.81 Cft
Cement Concrete 1:2½:5 14.95 Cft
¼" Cement PLaster 1:1 1.29 Cft
23.05 Cft 3.50 P. Cft 80.68
Unit Rate (British System) per Rft
Page 17
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 18/43
a) Type I
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Brick ballast 1:6:12 13.62 Cft 5.60 P. Cft 76.27
Bajri for 1:2½:5 29.70 Cft 18.50 P. Cft 549.45
Total 2,249.70
Contractor's Profit & Overheads 20 Percent 449.94
Total 2,699.64
Labour
Mason 1.50 No 300.00 P. Day 450.00
Unskilled Cooly 3.00 Nos 140.00 P. Day 420.00
Bahishti 0.75 No 160.00 P. Day 120.00
Total 990.00
Sundries 10 Percent 99.00
Total 1,089.00
Contractor's Profit & Overheads 20 Percent 217.80
Total 1,306.80
Item Rates
Labour Rate Per Rft Rs. 13.07 Say 13.05
Labour Rate Per Rm Rs. 42.86 Say 42.85
Composite Rate Per Rft Rs. 40.06 Say 40.05
Composite Rate Per Rm Rs. 131.41 Say 131.40
Unit Rate (British System) per Rft
Page 18
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 19/43
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2½:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar ¼"(6mm)
thick as per Engineers Drawing (excluding
Excavation).
b) Type II
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
CC 1:6:12
1x100x(1'-2½"+1'-8½")x7¼" 88.10 Cft
2
Deduction.
1x100x(8"+11½")x4¼" 28.77 Cft
2
Net Total 59.33 Cft
CC 1:2½:51x100x(11½"+8")x4¼" 28.77 Cft
2
1x100x(1-8½")x4" 56.94 Cft
Total 85.71 Cft
Deduction.
1x100x0.82 8.20 Cft
1x100(7 3/8"+10") 2 1/8" 17.34 Cft
2
1x100(10"+1"-8½")x0.87 4.21 Cft
2 Total 29.75 Cft
85.71 - 29.75 Net Total 55.96 Cft
Surface Rendering
With Cement Sand Mortar1:1of¼" thick 220.00 Sft
Material
Cement for.
Cement Concrete 1:6:12 3.84 Bags
Cement Concrete 1:2½:5 5.62 Bags
¼" Cement PLaster 1:1 2.27 Bags
11.73 Bags 230.00 Each 2,697.90 Sand for.
Cement Concrete 1:6:12 28.86 Cft
Cement Concrete 1:2½:5 17.54 Cft
¼" Cement PLaster 1:1 2.86 Cft
49.26 Cft 3.50 P. Cft 172.41
Unit Rate (British System) per Rft
Page 19
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 20/43
b) Type II
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Brick ballast for 1:6:12 57.70 Cft 5.60 P. Cft 323.12
Bajri for 1:2½:5 35.10 Cft 18.50 P. Cft 649.35
Total 3,842.78 Contractor's Profit & Overheads 20 Percent 768.56
Total 4,611.34
Labour
Mason 3.00 Nos 300.00 P. Day 900.00
Unskilled Cooly 6.00 Nos 140.00 P. Day 840.00
Bahishti 1.50 No 160.00 P. Day 240.00
Total 1,980.00
Sundries 10 Percent 198.00
Total 2,178.00
Contractor's Profit & Overheads 20 Percent 435.60
Total 2,613.60
Item Rates
Labour Rate Per Rft Rs. 26.14 Say 26.15
Labour Rate Per Rm Rs. 85.73 Say 85.75
Composite Rate Per Rft Rs. 72.25 Say 72.25
Composite Rate Per Rm Rs. 236.98 Say 237.00
Unit Rate (British System) per Rft
Page 20
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 21/43
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2½:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar ¼"(6mm)
thick as per Engineers Drawing (excluding
Excavation).
c) Type III
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
CC 1:6:12
1x100(1'-3 5/8"+1'-11") 117.33 Cft
2
2'x100'x4½"x1½" 9.38 Cft
Total 126.71 Cft
Deduction.1x100x(8"+1'-½"
)x5¾" 40.93 Cft
2
Net Total 85.78 Cft
CC 1:2½:5
1x100(8"+1'-2") 5¾" 43.92 Cft
2
1x100x1'-11"x4" 63.89 Cft
Total 107.81 Cft
Deduction.
1x100x.082 8.20 Cft
1x100(7-3/8"+1'-½")6" 41.40 Cft
2
1x100(1'-½"+1'-11")x¾" 9.24 Cft
2
Total 58.84 Cft
107.81 - 58.84 Net Total 48.97 Cft
Surface Rendering.
Surface Area.
1x9.4'x100 78.33 Sft
12
2x6½"x100 108.33 Sft
12
Unit Rate (British System) per Rft
Page 21
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 22/43
c) Type III
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
2x5¼"x100 87.50 Sft
12
274.16 Sft
Material Required. Say: 274.20 Sft
Cement for.
Cement Concrete 1:6:12 5.57 Bags
Cement Concrete 1:2½:5 7.10 Bags
Cement for Surface rendering 2.52 Bags
15.19 Bags
Say 15.00 230.00 Each 3,450.00
Sand for.
Sand for 1:6:12 40.00 Cft
Sand for 1:2½:5 22.00 Cft
Sand for Surface rendering 3.00 Cft
65.00 Cft 3.50 P. Cft 227.50
Brick ballast for 1:6:12 84.00 Cft 5.60 P. Cft 470.40
Bajri for 1:2½:5 44.07 Cft 18.50 P. Cft 815.30
Total 4,963.20
Contractor's Profit & Overheads 20 Percent 992.64
Total 5,955.83
Labour
Mason 2.75 Nos 300.00 P. Day 825.00
Unskilled Cooly 10.00 Nos 140.00 P. Day 1,400.00
Bahishti 1.30 Nos 160.00 P. Day 208.00
Total 2,433.00
Sundries 10 Percent 243.30
Total 2,676.30
Contractor's Profit & Overheads 20 Percent 535.26
Total 3,211.56
Item Rates
Labour Rate Per Rft Rs. 32.12 Say 32.10
Labour Rate Per Rm Rs. 105.34 Say 105.35
Composite Rate Per Rft Rs. 91.67 Say 91.65
Composite Rate Per Rm Rs. 300.69 Say 300.70
Unit Rate (British System) per Rft
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 23/43
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2½:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar ¼"(6mm)
thick as per Engineers Drawing (excluding
Excavation).
d) Type IV
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
CC 1:6:12
1x100(1'-3 ¾"+2'-1½")x11½" 164.73 Cft
2
2x100x4½"x1½" 9.38 Cft
Total 174.11 Cft
Deduction.
1x100x(8"+1-3½")x8½" 69.35 Cft
2
Net Total 104.76 Cft
CC 1:2½:5
1x100(8"+1'-4¼") 8½" 71.60 Cft
2
1x100x2'-1¼"x4" 70.14 Cft
Total 141.74 Cft
Deduction.1x100x0.082 8.20 Cft
1x100(7'-3/8"+1'-2¾")x8¾" 67.20 Cft
2
1x100(1'-2¾"+2'-1¼")x¾" 10.42 Cft
2
Total 85.82 Cft
141.74 - 85.82 Net Total 55.92 Cft
Surface Rendering.
1x9.4/1x100 78.33 Sft
122x5¼x100 87.50 Sft
12
2x9½x100 158.33 Sft
12 324.16 Sft
Say: 324.16 Sft
Unit Rate (British System) per Rft
Page 23
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 24/43
d) Type IV
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material Required.
Cement for.
Cement for 1:6:12 6.81 Bags
Cement for 1:2½:5 8.11 Bags
Cement for Surface rendering 2.98 Bags
17.90 Bags 230.00 Each 4,117.00
Sand for.
Sand for 1:6:12 51.33 Cft
Sand for 1:2½:5 25.33 Cft
Sand for Surface rendering 3.73 Cft
80.39 Cft 3.50 P. Cft 281.37
Brick ballast for 1:6:12 102.66 Cft 5.60 P. Cft 574.90
Stone Bajri for 1:2½:5 50.33 Cft 18.50 P. Cft 931.11
Total 5,904.37
Contractor's Profit & Overheads 20 Percent 1,180.87
Total 7,085.24
Labour
Mason 3.25 Nos 300.00 P. Day 975.00
Unskilled Cooly 11.83 Nos 140.00 P. Day 1,656.20
Bahishti 1.67 Nos 160.00 P. Day 267.20
Total 2,898.40
Sundries 10 Percent 289.84 Total 3,188.24
Contractor's Profit & Overheads 20 Percent 637.65
Total 3,825.89
Item Rates
Labour Rate Per Rft Rs. 38.26 Say 38.25
Labour Rate Per Rm Rs. 125.49 Say 125.50
Composite Rate Per Rft Rs. 109.11 Say 109.10
Composite Rate Per Rm Rs. 357.88 Say 357.90
Unit Rate (British System) per Rft
Page 24
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 25/43
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2½:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar ¼"(6mm)
thick as per Engineers Drawing (excluding
Excavation).
e) Type V
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
CC 1:6:12
1x100(1'-7"+2'-3¾")x10½" 170.44 Cft
2
2x100x(6½"x4½")5½" 44.01 Cft
2Total 214.45 Cft
Deduction.
1x100x(8"+1'-2¾")x7½" 59.24 Cft
2
Net Total 155.21 Cft
CC 1:2½:5
1x100(8"+1'-6¾")x1'-1" 120.75 Cft
2
1x100x2'-3¾"x4" 77.08 CftTotal 197.83 Cft
Deduction.
1x100x0.082 8.20 Cft
1x100(7-3/8"+1'-5¼")x11¾" 100.48 Cft
2
1x100(1-5¼"+2'-3¾")x¾" 11.72 Cft
2
Total 120.40 Cft
197.83 - 120.40 Net Total 77.43 Cft
Surface Rendering with 1:1 C/S.
Mortor ¼" thick.
1x9.4"x100 78.33 Sft
12
Unit Rate (British System) per Rft
Page 25
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 26/43
e) Type V
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
2x5¼"x100 87.50 Sft
12
2x1'-1"x100 216.66 Sft
Total 382.49 SftMaterial Required. Say: 382.50 Sft
Cement for.
Cement for 1:6:12 9.96 Bags
Cement for 1:2½:5 11.22 Bags
Cement for Surface rendering 3.52 Bags
24.70 Bags 230.00 Each 5,681.00
Sand for.
Sand for 1:6:12 75.00 Cft
Sand for 1:2½:5 35.00 Cft
Sand for Surface rendering 4.40 Cft
114.40 Cft 3.50 P. Cft 400.40
Brick ballast for 1:6:12 150.15 Cft 5.60 P. Cft 840.84
Stone Bajri for 1:2½:5 69.70 Cft 18.50 P. Cft 1,289.45
Total 8,211.69
Contractor's Profit & Overheads 20 Percent 1,642.34
Total 9,854.03
Labour
Mason 4.00 Nos 300.00 P. Day 1,200.00
Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00 Bahishti 2.20 No 160.00 P. Day 352.00
Total 3,792.00
Sundries 10 Percent 379.20
Total 4,171.20
Contractor's Profit & Overheads 20 Percent 834.24
Total 5,005.44
Item Rates
Labour Rate Per Rft Rs. 50.05 Say 50.05 Labour Rate Per Rm Rs. 164.18 Say 164.20
Composite Rate Per Rft Rs. 148.59 Say 148.60
Composite Rate Per Rm Rs. 487.39 Say 487.40
Unit Rate (British System) per Rft
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 27/43
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2½:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar ¼"(6mm)
thick as per Engineers Drawing (excluding
Excavation).
f) Type VI
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
CC 1:6:12
1x100(1'-7"+2'-6½")x1-1½" 230.25 Cft
2
2x100x(6½"x4½")5½" 42.01 Cft
2
Total 272.26 CftDeduction.
1x100x(8"+1-5 1/8")x10½" 91.58 Cft
2
Net Total 180.68 Cft
CC 1:2½:5
1x100(8"+1'-9 1/8")x1'-4" 161.81 Cft
2
1x100x2'-6-1/8"x4" 83.68 Cft
Total 245.49 Cft
Deduction.1x100(7'-3/8"+1'-7 5/8")x1'-2¾" 138.28 Cft
2
1x100(1'-7 5/8"+2'-6 1/8")x0.75" 12.96 Cft
2
1x100x0.082 8.20 Cft
Total 159.44 Cft
245.49 - 159.44 Net Total 86.05 Cft
Surface Rendering.
1x9.4x100 78.33 Sft
122x5¼"x100 87.50 Sft
12
2x1'-4/12"x100 266.66 Sft
Total 432.49 Sft
Say: 432.50 Sft
Unit Rate (British System) per Rft
Page 27
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 28/43
f) Type VI
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material Required.
Cement for.
Cement for 1:6:12 11.74 Bags
Cement for 1:2½:5 12.48 BagsCement for Surface rendering 3.98 Bags
28.20 Bags 230.00 Each 6,486.00
Sand for.
Sand for 1:6:12 88.53 Cft
Sand for 1:2½:5 38.98 Cft
Sand for Surface rendering 4.97 Cft
132.48 Cft 3.50 P. Cft 463.68
Brick ballast for 1:6:12 177.07 Cft 5.60 P. Cft 991.59
Stone Bajri for 1:2½:5 77.45 Cft 18.50 P. Cft 1,432.83
Total 9,374.10 Contractor's Profit & Overheads 20 Percent 1,874.82
Total 11,248.92
Labour
Mason 4.55 Nos 300.00 P. Day 1,365.00
Unskilled Cooly 18.50 Nos 140.00 P. Day 2,590.00
Bahishti 2.50 Nos 160.00 P. Day 400.00
Total 4,355.00
Sundries 10 Percent 435.50
Total 4,790.50
Contractor's Profit & Overheads 20 Percent 958.10
Total 5,748.60
Item Rates
Labour Rate Per Rft Rs. 57.49 Say 57.50
Labour Rate Per Rm Rs. 188.55 Say 188.55
Composite Rate Per Rft Rs. 169.98 Say 170.00
Composite Rate Per Rm Rs. 557.52 Say 557.50
Unit Rate (British System) per Rft
Page 28
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 29/43
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2½:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar ¼"(6mm)
thick as per Engineers Drawing (excluding
Excavation).
g) Type VII
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
CC 1:6:12
1x100(1'-7"+2'-8½")x1-4 3/8" 292.82 Cft
2
2x100x(6½"x4½")5¼" 40.10 Cft
2Total 332.92 Cft
Deduction.
1x100x(8"+9'-7½")1'-1 3/8" 127.71 Cft
2
Net Total 205.21 Cft
CC 1:2½:5
1x100(8"+1'-11½")1'-6.5/8" 203.71 Cft
2
1x100x2'-8½"x4" 90.28 CftTotal 293.99 Cft
Deduction.
1x100x0.082 8.20 Cft
1x100(7 3/9"+1'-10")1'-5½" 178.52 Cft
2
1x100(1'-10"+2'-8½")x7/8" 16.56 Cft
2
Total 203.28 Cft
293.99 - 203.28 Net Total 90.71 Cft
Surface Rendering with 1:1 CS mortor.
1x9.4x100 78.33 Sft
12
Unit Rate (British System) per Rft
Page 29
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 30/43
g) Type VII
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
2x5¼"x100 87.50 Sft
12
2x1'-7/12"x100 316.66 Sft
482.49 Sft
Material Required. Say: 482.50 Sft
Cement for.
Cement for 1:6:12 13.34 Bags
Cement for 1:2½:5 13.15 Bags
Cement for Surface rendering 4.44 Bags
30.93 Bags 230.00 Each 7,113.90
Sand for.
Sand for 1:6:12 100.55 Cft
Sand for 1:2½:5 41.09 Cft
Sand for Surface rendering 5.55 Cft147.19 Cft 3.50 P. Cft 515.16
Brick ballast for 1:6:12 201.00 Cft 6.50 P. Cft 1,306.50
Stone Bajri for 1:2½:5 81.64 Cft 18.50 P. Cft 1,510.34
Total 10,445.90
Contractor's Profit & Overheads 20 Percent 2,089.18
Total 12,535.08
Labour
Mason 5.04 Nos 300.00 P. Day 1,512.00 Unskilled Cooly 20.50 Nos 140.00 P. Day 2,870.00
Bahishti 2.78 Nos 160.00 P. Day 444.80
Total 4,826.80
Sundries 10 Percent 482.68
Total 5,309.48
Contractor's Profit & Overheads 20 Percent 1,061.90
Total 6,371.38
Item Rates
Labour Rate Per Rft Rs. 63.71 Say 63.70
Labour Rate Per Rm Rs. 208.98 Say 209.00
Composite Rate Per Rft Rs. 189.06 Say 189.05
Composite Rate Per Rm Rs. 620.13 Say 620.15
Unit Rate (British System) per Rft
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 31/43
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2½:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar ¼"(6mm)
thick as per Engineers Drawing (excluding
Excavation).
h) Type VIII
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
CC 1:6:12
1x100(1'-7"+2'-10 7/8")1' 7" 355.43 Cft
2x100x(6½"+4½")5¼" 40.10 Cft
2
Total 395.53 Cft
Deduction.
1x100x(8"+1'-9 7/8")1'-4" 165.97 Cft
2
Net Total 229.56 Cft
CC 1:2½:5
1x100(8"+2-1 7/8")1'-9¼" 249.95 Cft
2
1x100(2'-10 7/8")4" 96.88 Cft
Total 346.83 Cft
Deduction.
1x100x0.082 8.20 Cft
1x100(7 3/8"+2'-3/8")1'-8¼" 223.42 Cft
2
1x100(2'-3/8"+2'-10 7/8")x¾" 15.43 Cft
2
Total 247.05 Cft
346.83 - 247.05 Net Total 99.78 Cft
Surface Rendering with 1:1 CS mortor.
1x9.4/x100 78.33 Sft
12
Unit Rate (British System) per Rft
Page 31
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 32/43
h) Type VIII
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
2x5¼"x100 87.50 Sft
12
2x1'-10.1/12"x100 375.00 Sft
540.83 Sft
Material Required. Say : 540.85 Sft
Cement for.
Cement for 1:6:12 14.92 Bags
Cement for 1:2½:5 14.50 Bags
Cement for Surface rendering 4.98 Bags
34.40 Bags 230.00 Each 7,912.00
Sand for.
Sand for 1:6:12 112.48 Cft
Sand for 1:2½:5 45.30 Cft
Sand for Surface rendering 6.22 Cft
164.00 Cft 3.50 P. Cft 574.00
Brick ballast for 1:6:12 250.00 Cft 5.60 P. Cft 1,400.00
Stone Bajri for 1:2½:5 90.00 Cft 18.50 P. Cft 1,665.00
Total 11,551.00
Contractor's Profit & Overheads 20 Percent 2,310.20
Total 13,861.20
Labour
Mason 5.63 Nos 300.00 P. Day 1,689.00 Unskilled Cooly 22.90 Nos 140.00 P. Day 3,206.00
Bahishti 3.10 Nos 160.00 P. Day 496.00
Total 5,391.00
Sundries 10 Percent 539.10
Total 5,930.10
Contractor's Profit & Overheads 20 Percent 1,186.02
Total 7,116.12
Item Rates
Labour Rate Per Rft Rs. 71.16 Say 71.15
Labour Rate Per Rm Rs. 233.41 Say 233.40
Composite Rate Per Rft Rs. 209.77 Say 209.75
Composite Rate Per Rm Rs. 688.06 Say 688.05
Unit Rate (British System) per Rft
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 33/43
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2½:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar ¼"(6mm)
thick as per Engineers Drawing (excluding
Excavation).
i) Type IX
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
CC 1:6:12
1x100(1'-10 3/8"+3'-3¼")x1'-8" 427.99 Cft
2
2x100x(7"+4½")9¼" 80.30 Cft
2Total 508.29 Cft
Deduction.
1x100x(9 3/8"+1'-11¼")x1'-4" 181.22 Cft
2
Net Total 327.07 Cft
CC 1:2½:5
1x100(9 3/8"+2'-6¼")x2'-1¼" 347.45 Cft
2
1x100(3'-3¼")4½" 122.66 Cft
Total 470.11 Cft
Deduction.
1x100x0.082 8.20 Cft
1x100(7 3/8"+2'-11/2")x2'-¼" 278.41 Cft
2
1x100(2'-2¾"+3'-3¼")x¾" 17.19 Cft
2
Total 303.80 Cft
470.11 - 303.80 Net Total 166.31 Cft
Surface Rendering with (1:) C/S Mortar.1x9.4/x100 78.33 Sft
12
2x6¼x100 104.17 Sft
12
Unit Rate (British System) per Rft
Page 33
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 34/43
i) Type IX
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
2x1'-10.1/12"x100 375.00 Sft
557.50 Sft
Material Required.
Cement for.Cement for 1:6:12 21.26 Bags
Cement for 1:2½:5 24.11 Bags
Cement for Surface rendering 5.13 Bags
50.50 Bags 230.00 Each 11,615.00
Sand for.
Sand for 1:6:12 160.26 Cft
Sand for 1:2½:5 75.34 Cft
Sand for Surface rendering 6.41 Cft
242.01 Cft 3.50 P. Cft 847.04
Brick ballast for 1:6:12 320.53 Cft 5.60 P. Cft 1,794.97
Stone Bajri for 1:2½:5 149.68 Cft 18.50 P. Cft 2,769.08
Total 17,026.08
Contractor's Profit & Overheads 20 Percent 3,405.22
Total 20,431.30
Labour
Mason 6.66 Nos 300.00 P. Day 1,998.00
Unskilled Cooly 31.91 Nos 140.00 P. Day 4,467.40
Bahishti 4.03 Nos 160.00 P. Day 644.80
Total 7,110.20
Sundries 10 Percent 711.02
Total 7,821.22
Contractor's Profit & Overheads 20 Percent 1,564.24
Total 9,385.46
Item Rates
Labour Rate Per Rft Rs. 93.85 Say 93.85
Labour Rate Per Rm Rs. 307.84 Say 307.85
Composite Rate Per Rft Rs. 298.17 Say 298.15
Composite Rate Per Rm Rs. 977.99 Say 978.00
Unit Rate (British System) per Rft
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 35/43
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2½:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar ¼"(6mm)
thick as per Engineers Drawing (excluding
Excavation).
j) Type X
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
CC 1:6:12
1x100(1'-10¾"+3'-5¾")x1'-10½" 503.91 Cft
2
2x100x(8"+4½")9½" 82.47 Cft2
Total 586.38 Cft
Deduction.
1x100x(9½"+2'-1¾")1'-6½" 226.43 Cft
2
Net Total 359.95 Cft
CC 1:2½:5
1x100(9½"+2'-8¾")2'-4" 410.76 Cft
21x100x3'-5¾"4½" 130.47 Cft
Total 541.23 Cft
Deduction.
1x100x0.082 8.20 Cft
1x100(7' 3/8"+2'-5¼")2'-2¼" 333.86 Cft
1x100(2'-5¼"+3'-5¾"
)x¾" 18.43 Cft
2
Total 360.49 Cft
541.23 - 360.49 Net Total 180.74 Cft
Surface Rendering with (1:1) Cement
Sand Mortar. 620.00 Sft
Unit Rate (British System) per Rft
Page 35
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 36/43
j) Type X
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material Required.
Cement for.
Cement for 1:6:12 23.40 Bags
Cement for 1:2½:5 26.20 BagsCement for Surface rendering 5.70 Bags
55.30 Bags 230.00 Each 12,719.00
Sand for.
Sand for 1:6:12 176.37 Cft
Sand for 1:2½:5 81.85 Cft
Sand for Surface rendering 7.13 Cft
265.35 Cft 3.50 P. Cft 928.73
Brick ballast for 1:6:12 352.75 Cft 5.60 P. Cft 1,975.40
Stone Bajri for 1:2½:5 162.61 Cft 18.50 P. Cft 3,008.29
Total 18,631.41 Contractor's Profit & Overheads 20 Percent 3,726.28
Total 22,357.69
Labour
Mason 7.35 Nos 300.00 P. Day 2,205.00
Unskilled Cooly 35.00 Nos 140.00 P. Day 4,900.00
Bahishti 4.43 Nos 160.00 P. Day 708.80
Total 7,813.80
Sundries 10 Percent 781.38 Total 8,595.18
Contractor's Profit & Overheads 20 Percent 1,719.04
Total 10,314.22
Item Rates
Labour Rate Per Rft Rs. 103.14 Say 103.15
Labour Rate Per Rm Rs. 338.31 Say 338.30
Composite Rate Per Rft Rs. 326.72 Say 326.70
Composite Rate Per Rm Rs. 1071.64 Say 1,071.65
Unit Rate (British System) per Rft
Page 36
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 37/43
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2½:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar ¼"(6mm)
thick as per Engineers Drawing (excluding
Excavation).
k) Type XI
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
CC 1:6:12
1x100(1'-10¾"+3'-8¼")x2'-1 3/8" 599.05 Cft
2
2x100x(8"+4½")9½" 82.47 Cft2
Total 681.52 Cft
Deduction.
1x100x(9½"+2'-4¼")1'-9¾" 285.09 Cft
2
Net Total 396.43 Cft
CC 1:2½:5
1x100(9½"+2'-11¾")2'-7¼" 490.99 Cft
1x100x3'-8¼"x4½" 138.28 Cft
Total 629.27 Cft
Deduction.
1x100x0.082 8.20 Cft
1x100(7' 3/8"+2'-7¾")2'-5½" 400.71 Cft
2
1x100(2'-7¾"+3'-8¼")x¾" 19.79 Cft
2
Total 428.70 Cft
629.27 - 428.70 Net Total 200.57 Cft
Surface Rendering with (1:1) Cement
Sand Mortar. 711.70 Sft
Unit Rate (British System) per Rft
Page 37
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 38/43
k) Type XI
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material Required.
Cement for.
Cement for 1:6:12 25.77 Bags
Cement for 1:2½:5 29.08 BagsCement for Surface rendering 6.55 Bags
61.40 Bags 230.00 Each 14,122.00
Sand for.
Sand for 1:6:12 194.25 Cft
Sand for 1:2½:5 91.12 Cft
Sand for Surface rendering 8.18 Cft
293.55 Cft 3.50 P. Cft 1,027.43
Brick ballast for 1:6:12 388.50 Cft 5.60 P. Cft 2,175.60
Stone Bajri for 1:2½:5 180.51 Cft 18.50 P. Cft 3,339.44
Total 20,664.46 Contractor's Profit & Overheads 20 Percent 4,132.89
Total 24,797.35
Labour
Mason 8.34 Nos 300.00 P. Day 2,502.00
Unskilled Cooly 38.94 Nos 140.00 P. Day 5,451.60
Bahishti 4.96 Nos 160.00 P. Day 793.60
Total 8,747.20
Sundries 10 Percent 874.72
Total 9,621.92
Contractor's Profit & Overheads 20 Percent 1,924.38
Total 11,546.30
Item Rates
Labour Rate Per Rft Rs. 115.46 Say 115.45
Labour Rate Per Rm Rs. 378.72 Say 378.70
Composite Rate Per Rft Rs. 363.44 Say 363.45
Composite Rate Per Rm Rs. 1192.07 Say 1,192.05
Unit Rate (British System) per Rft
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 39/43
Item No. 6 Constructing Punjab standard drains of cement
concrete 1:2½:5 with cement concrete bedding
ratio 1:6:12 complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of
concrete with 1:1 cement sand mortar ¼"(6mm)
thick as per Engineers Drawing (excluding
Excavation).
l) Type XII
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
CC 1:6:12
1x100(1'-10¾"+3'-10¾")x2'-4¼" 681.72 Cft
2
2x100x(8"+4½")9¾" 84.63 Cft2
Total 766.35 Cft
Deduction.
1x100x(9½"+2'-6¾")2'-¼" 338.91 Cft
2
Total 427.44 Cft
CC 1:2½:5
1x100(9½"+3'-1¾")2'-10" 557.81 Cft
1x100x3'-10¾"x4½" 146.09 CftTotal 703.90 Cft
Deduction.
1x100x0.082 8.20 Cft
1x100(7' 3/8"+2'-10¼")2'-8¼" 466.17 Cft
2
1x100(2'-10¼"+3'-10¾")x¾" 21.61 Cft
2
Total 495.98 Cft
703.90 - 495.98 Net Total 207.92 Cft
Surface Rendering with (1:1) Cement
Sand Mortar. 765.82 Sft
Unit Rate (British System) per Rft
Page 39
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 40/43
l) Type XII
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material Required.
Cement for.
Cement for 1:6:12 27.78 Bags
Cement for 1:2½:5 30.15 BagsCement for Surface rendering 7.05 Bags
64.98 Bags 230.00 Each 14,945.40
Sand for.
Sand for 1:6:12 209.45 Cft
Sand for 1:2½:5 94.19 Cft
Sand for Surface rendering 7.05 Cft
310.69 Cft 3.50 P. Cft 1,087.42
Brick ballast for 1:6:12 418.90 Cft 5.60 P. Cft 2,345.84
Stone Bajri for 1:2½:5 187.12 Cft 18.50 P. Cft 3,461.72
Total 21,840.38
Contractor's Profit & Overheads 20 Percent 4,368.08
Total 26,208.45
Labour
Mason 8.89 Nos 300.00 P. Day 2,667.00
Cooly 41.50 Nos 140.00 P. Day 5,810.00
Bahishti 5.30 Nos 160.00 P. Day 848.00
Total 9,325.00 Sundries 10 Percent 932.50
Total 10,257.50
Contractor's Profit & Overheads 20 Percent 2,051.50
Total 12,309.00
Item Rates
Labour Rate Per Rft Rs. 123.09 Say 123.10
Labour Rate Per Rm Rs. 403.74 Say 403.75
Composite Rate Per Rft Rs. 385.17 Say 385.20 Composite Rate Per Rm Rs. 1263.37 Say 1,263.35
Unit Rate (British System) per Rft
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 41/43
DESCRIPTION OF ITEM NO 7: Laying RC hume pipes in positions, including
jointing.
a) 6" to 12" (150 to 300mm) Dia.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Cement 0.25 Bags 230.00 Each 57.50
Sand 1.20 Cft 3.50 P. Cft 4.20
Total 61.70
Contractor's Profit & Overheads 20 Percent 12.34
Total 74.04
Labour for 50 Lft
Mason 1.00 No 300.00 P. Day 300.00
Unskilled Cooly 4.00 Nos 140.00 P. Day 560.00
Total 860.00
Sundries 10 Percent 86.00
Total 946.00
Contractor's Profit & Overheads 20 Percent 189.20
Total 1,135.20
Item Rates
Labour Rate Per Rft Rs. 22.70 Say 22.70
Labour Rate Per Rm Rs. 74.47 Say 74.45
Composite Rate Per Rft Rs. 24.18 Say 24.20
Composite Rate Per Rm Rs. 79.33 Say 79.35
Unit Rate (British System) per Rft/Assumed for 40 Rft
Page 41
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 42/43
Item No. 7 Laying RC hume pipes in positions, including
jointing.
b) 12" to 24" (300 to 600mm) Dia.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Cement 0.50 Bags 230.00 Each 115.00
Sand 2.40 Cft 3.50 P. Cft 8.40
Total 123.40
Contractor's Profit & Overheads 20 Percent 24.68
Total 148.08
Labour for 50 Lft
Mason 1.00 No 300.00 P. Day 300.00
Unskilled Cooly 7.00 Nos 140.00 P. Day 980.00
Total 1,280.00
Sundries 10 Percent 128.00
Total 1,408.00
Contractor's Profit & Overheads 20 Percent 281.60
Total 1,689.60
Item Rates
Labour Rate Per Rft Rs. 33.79 Say 33.80
Labour Rate Per Rm Rs. 110.84 Say 110.85
Composite Rate Per Rft Rs. 36.75 Say 36.75
Composite Rate Per Rm Rs. 120.55 Say 120.55
Unit Rate (British System) per Rft/Assumed for 40 Rft
Page 42
8/9/2019 Rate analsis Chapter No. 20 (Surface Drainage)
http://slidepdf.com/reader/full/rate-analsis-chapter-no-20-surface-drainage 43/43
Item No. 7 Laying RC hume pipes in positions, including
jointing.
c) 24" to 36" (600 to 900mm) Dia.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material
Cement 0.75 Bags 230.00 Each 172.50
Sand 3.75 Cft 3.50 P. Cft 13.13
Total 185.63
Contractor's Profit & Overheads 20 Percent 37.13
Total 222.75
Labour for 50 Lft
Mason 2.00 No 300.00 P. Day 600.00
Unskilled Cooly 8.00 Nos 140.00 P. Day 1,120.00
Total 1,720.00
Sundries 10 Percent 172.00
Total 1,892.00
Contractor's Profit & Overheads 20 Percent 378.40
Total 2,270.40
Item Rates
Labour Rate Per Rft Rs. 45.41 Say 45.40
Labour Rate Per Rm Rs. 148.94 Say 148.95
Composite Rate Per Rft Rs. 49.86 Say 49.85
Composite Rate Per Rm Rs. 163.55 Say 163.55
Unit Rate (British System) per Rft/Assumed for 40 Rft