Copyright of Royal Dutch Shell plc., 2015 Please contact Ronald Gatbonton for more information for underlying data. A B E F H D PROJECTS OPERATED PTP/O Highlights July 2015 A – Norway Nyhamna Expansion: Turnaround successfully completed in July, and milestone for pull-in of the Polarled pipeline achieved F - Nigeria GU Ph2A: Execution ongoing. Compressors have arrived at site and pipelay (pictured left), is in progress Bacton Norg UGS Expansion Laila Development F14: Achieved first gas ahead of GIP and below budget. I - Malaysia Laila: First Oil Delivery achieved, completed Final Acceptance and handed over to Asset. C - Onegas Bacton: First systems (instrument air and first reboiler) have been handed over. 450 days TRCF free achieved. F14 Development PTP/O HSSE Performance YTD 1 st July 2015 Operated Non- Operated Gamba Export Sealine Nyhamna Expansion Majnoon FCP Sweet Gas G - Iraq Majnoon FCP Sweet Gas: Progress on Trains 1 & 2, including glycol regeneration unit installation. J J – Philippines Malampaya MP3: Turnaround completed after installation of new depletion compression platform. Malampaya Depletion Compression G H – Brunei (NOV) CWF B23: Topside, bridges and helideck sailed away to Champion field for installation. Champion Waterflood B2 B3 HSSE performance similar to 2014 (not improved) D - Netherlands Norg: Expansion projects successfully started up and in operation. E - Gabon Gamba Export Sealine: Offshore pipelay complete – now installing onshore facilities C B – United Kingdom Clair Ph2 (NOV): The three modules have been installed on the LQ jacket and hook-up has started Clair Ph2 Brent Decommissioning Brent Decom: The Brent Delta topsides removal programme has received Government approval. Under-deck lift points for the single lift are being installed Malikai: Topsides superlift successfully completed; this is an industry first for lift and skid at height. Offshore pipelay is in progress I Gumusut: Annual oil production ahead of target. First water injection achieved on 9 th June, and turn- around completed on 27 th July ahead of operating plan Gumusut-Kakap Gbaran Ubie infill G - Iraq (NOV) Basra Gas – Khor al-Zubair (KAZ): Power plant started up at the gas plant to supply site power and free grid power for local use. Basra Gas – KAZ Power Malikai

description

PTPO

Transcript of PTPO Poster 2015 Q2v5

Page 1: PTPO Poster 2015 Q2v5

Copyright of Royal Dutch Shell plc., 2015 Please contact Ronald Gatbonton for more information for underlying data.

A

B

E

F H

D

PROJECTS OPERATED PTP/O Highlights July 2015A – NorwayNyhamna Expansion: Turnaround successfully completed in July, and milestone for pull-in of the Polarled pipeline achieved

F - NigeriaGU Ph2A: Execution ongoing. Compressors have arrived at site and pipelay (pictured left), is in progress

Bacton

Norg UGS Expansion

Laila Development

F14: Achieved first gas ahead of GIP and below budget.

I - MalaysiaLaila: First Oil Delivery achieved, completed Final Acceptance and handed over to Asset.

C - OnegasBacton: First systems (instrument air and first reboiler) have been handed over. 450 days TRCF free achieved.

F14 Development

PTP/O HSSE Performance YTD 1st July 2015

Operated Non- Operated

Gamba Export Sealine

Nyhamna Expansion

Majnoon FCP Sweet Gas

G - Iraq Majnoon FCP Sweet Gas: Progress on Trains 1 & 2, including glycol regeneration unit installation.

J

J – PhilippinesMalampaya MP3: Turnaround completed after installation of new depletion compression platform.

Malampaya Depletion Compression

G

H – Brunei (NOV)CWF B23: Topside, bridges and helideck sailed away to Champion field for installation.

Champion Waterflood B2 B3

HSSE performance similar to 2014 (not improved)

D - NetherlandsNorg: Expansion projects successfully started up and in operation.

E - GabonGamba Export Sealine: Offshore pipelaycomplete – now installing onshore facilities

C

B – United KingdomClair Ph2 (NOV): The three modules have been installed on the LQ jacket and hook-up has started

Clair Ph2

Brent Decommissioning

Brent Decom: The Brent Delta topsides removal programme has received Government approval. Under-deck lift points for the single lift are being installed

Malikai: Topsides superlift successfully completed; this is an industry first for lift and skid at height. Offshore pipelay is in progress

I

Gumusut: Annual oil production ahead of target. First water injection achieved on 9th June, and turn-around completed on 27th July ahead of operating plan

Gumusut-Kakap

Gbaran Ubie infill

G - Iraq (NOV)Basra Gas – Khor al-Zubair(KAZ): Power plant started up at the gas plant to supply site power and free grid power for local use.

Basra Gas – KAZ Power

Malikai