SP Manufacturing Confidential 1

PT SP Manufacturing

Fire Drill 2014

Prepared By

Fahrizal Nasution

25th-Nov-14

IPC-610-D

ComplianceIPC/WHMA-A-620

Page 2: PTM Fire drill exercise 25-Nov-2014 (2) [Read-Only] [Compatibility Mode]

SP Manufacturing Confidential 2

Fire Drill on 25th Nov 2014Fire Drill on 25th Nov 2014

Before fire drills implemented, already done outage refresher training to allmembers of the firefighting team + PTM trainer on November 17th, 2014.Before fire drills implemented, already done outage refresher training to allmembers of the firefighting team + PTM trainer on November 17th, 2014.

Page 3: PTM Fire drill exercise 25-Nov-2014 (2) [Read-Only] [Compatibility Mode]

SP Manufacturing Confidential 3

Fire Drill on 25th Nov 2014Fire Drill on 25th Nov 2014

Attendance Record.Attendance Record.

Materials of Training (syllabus):

� Cause of the fire triangle.

� Type of material /Flammable materials.

� Type of fire extinguishers.

� Classification of fire.

� How to use a fire extinguishers.

� Principles against fire.

� Fire Emergencies procedure

Trainer by: Safety Officer PT. SP Manufacturing.

Materials of Training (syllabus):

� Cause of the fire triangle.

� Type of material /Flammable materials.

� Type of fire extinguishers.

� Classification of fire.

� How to use a fire extinguishers.

� Principles against fire.

� Fire Emergencies procedure

Trainer by: Safety Officer PT. SP Manufacturing.

Page 4: PTM Fire drill exercise 25-Nov-2014 (2) [Read-Only] [Compatibility Mode]

SP Manufacturing Confidential 4

Start

Fire alarm(Duration ±3mins)

-be alert and stay calm

-Lock up valuable

- Don't Panic

Evacuation Announcement

& Evacuate> Evacuate building using the nearest

EXIT and Staircase immediately> Do Not Use Lift> Do not Take Personal belonging

Assembly Point> Proceed to the evacuation assembly

area in orderly manner.> Assemble for roll call.> Do not Re-enter the building until

clear instruction is given by Fire representative / Officer

END

Fire Drill on 25th Nov 2014Fire Drill on 25th Nov 2014

PT. SP Manufacturing

FIRE DRILL FLOW

PT. SP Manufacturing

FIRE DRILL FLOW

Page 5: PTM Fire drill exercise 25-Nov-2014 (2) [Read-Only] [Compatibility Mode]

SP Manufacturing Confidential 5

1. PTM annual fire drill exercise was conducted on 25th Nov start from 11.00am,end at 11.25am which involved all employees.

2. The exercise was carried out as plan and employees moved to the assemblypoint orderly and smoothly.

3. Evacuation time cycle was 2.15 minutes, compared with 2.4 minutes year 2014.

4. Firefighting demonstration and Safety briefing also carried out.

1. PTM annual fire drill exercise was conducted on 25th Nov start from 11.00am,end at 11.25am which involved all employees.

2. The exercise was carried out as plan and employees moved to the assemblypoint orderly and smoothly.

3. Evacuation time cycle was 2.15 minutes, compared with 2.4 minutes year 2014.

4. Firefighting demonstration and Safety briefing also carried out.

Fire Drill on 25th Nov 2014Fire Drill on 25th Nov 2014

The evacuation Process#1 The evacuation Process#2

Page 6: PTM Fire drill exercise 25-Nov-2014 (2) [Read-Only] [Compatibility Mode]

SP Manufacturing Confidential 6

Fire Drill on 25th Nov 2014Fire Drill on 25th Nov 2014

At Assembly point#1 At Assembly point#2

At Assembly point#3 At Assembly point#4 At Assembly point#5

HR/AdminHR/Admin QAQA Wire HarnessWire Harness

Page 7: PTM Fire drill exercise 25-Nov-2014 (2) [Read-Only] [Compatibility Mode]

SP Manufacturing Confidential 7

Fire Drill on 25th Nov 2014Fire Drill on 25th Nov 2014

At Assembly point#6

Test / PCBA Eng’gTest / PCBA Eng’g

At Assembly point#7

PCBA Prod.PCBA Prod.

At Assembly point#8

PPIC-Store/FacilityPPIC-Store/Facility

Page 8: PTM Fire drill exercise 25-Nov-2014 (2) [Read-Only] [Compatibility Mode]

SP Manufacturing Confidential 8

Fire Drill on 25th Nov 2014Fire Drill on 25th Nov 2014

Safety Briefing by Safety officer#1 Safety Briefing by Safety officer#2

Safety Briefing by PTM Director#1 Safety Briefing by PTM Director#2

Page 9: PTM Fire drill exercise 25-Nov-2014 (2) [Read-Only] [Compatibility Mode]

SP Manufacturing Confidential 9

Fire Drill on 25th Nov 2014Fire Drill on 25th Nov 2014

Preparation of fire Drills Practical show#1

Practical show#2 Practical show#3

Page 10: PTM Fire drill exercise 25-Nov-2014 (2) [Read-Only] [Compatibility Mode]

SP Manufacturing Confidential 10

Fire Drill on 25th Nov 2014Fire Drill on 25th Nov 2014

Practical show#4 Practical show#5

Practical show#6 Practical show#7

Page 11: PTM Fire drill exercise 25-Nov-2014 (2) [Read-Only] [Compatibility Mode]

SP Manufacturing Confidential 11

Fire Drill on 25th Nov 2014Fire Drill on 25th Nov 2014

Dissolution fire drill exercise

Thank You…Thank You…

Back To WorkBack To WorkBack To WorkBack To WorkBack To WorkBack To WorkBack To WorkBack To Work