projectmanagementusingmsproject-140520232125-phpapp02
-
Upload
muhammad-noor -
Category
Documents
-
view
213 -
download
0
description
Transcript of projectmanagementusingmsproject-140520232125-phpapp02
PowerPoint Presentation
Project Management Basic conceptswith Microsoft Project 2010By: Abdul Ghaffar [email protected]+923434017209ObjectiveProjects Management BasicsWhat is a ProjectProject ConstraintsProject Planning, Monitoring & controlWBSGetting started with MS Project (General Schedule Settings and Currency)Creating Project in MS ProjectProject CalendarTask ListTask NotesDurationLinking Tasks6/19/2015By : Abdul Ghaffar, PMP3Objective Lead & LagMileStoneNetwork DiagramCritical PathAdding Resource and its costCreating BaselineCustom FieldsTracking ProjectOther Views and Reports
6/19/2015By : Abdul Ghaffar, PMP4What is a Project?A project is a temporary endeavor that helps to accomplish some specific objective by utilizing definite interconnected tasks and the effective utilization of resources.
To achieve an objectiveOne Time (Start and finish dates)Constraints of time, cost and resourcesPerformed by People Single or GroupCoordinated and controlled activitiesSpecific DeliverablesProgressive Elaboration
6/19/2015By : Abdul Ghaffar, PMP5Major Constraint on Project
6/19/2015By : Abdul Ghaffar, PMP6Project Process Groups
6/19/2015By : Abdul Ghaffar, PMP7
PMBOK 56/19/2015By : Abdul Ghaffar, PMP8WBS for MS Project Training6/19/2015By : Abdul Ghaffar, PMP9Starting With MS Project 2010File->options-> Display6/19/2015By : Abdul Ghaffar, PMP10
Starting With MS Project 2010File->options-> Schedule
6/19/2015By : Abdul Ghaffar, PMP11MS Project 2010
6/19/2015By : Abdul Ghaffar, PMP12Task List
6/19/2015By : Abdul Ghaffar, PMP13Task Duration
6/19/2015By : Abdul Ghaffar, PMP14WBS Code
6/19/2015By : Abdul Ghaffar, PMP15Sub Task
6/19/2015By : Abdul Ghaffar, PMP16Link Task..Finish to Start (FS), where the first must be finished before the next begins.Start to Start (SS), where 2 tasks must start at the same time.Finish to Finish (FF), where 2 tasks must end at the same time.Start to Finish (SF) , where the start of the first is linked to the completion of the second (with a lag time specified as well. 6/19/2015By : Abdul Ghaffar, PMP17Link Task
6/19/2015By : Abdul Ghaffar, PMP18Predecessors
6/19/2015By : Abdul Ghaffar, PMP19Lead & Lag TimeLead time causes a successor task to overlap a predecessor even though they are linked finish to start (FS). Lag time allows you to add a delay between the start of the successor and the end of the predecessor. Simply specify lead or lag time in the Predecessor column. Lead time is represented with a minus sign (-)Lag time is represented with a plus sign (+).
6/19/2015By : Abdul Ghaffar, PMP20Lead and Lag
6/19/2015By : Abdul Ghaffar, PMP21Calendar
6/19/2015By : Abdul Ghaffar, PMP22MileStone
Milestones let you gauge your progress through the project.Its good practice to include a Start and Finish Milestone for each division/part of your WBS.
6/19/2015By : Abdul Ghaffar, PMP23Resource
6/19/2015By : Abdul Ghaffar, PMP24Assign Resources to Tasks
6/19/2015By : Abdul Ghaffar, PMP25The Critical PathThe Critical path is the flow of tasks, of which, a delay in any one of these tasks will cause a delay to the project.
It is the longest path through the project network diagram and the shortest possible time to complete the project6/19/2015By : Abdul Ghaffar, PMP26Critical Path
6/19/2015By : Abdul Ghaffar, PMP27Critical Path..
6/19/2015By : Abdul Ghaffar, PMP28Slack
6/19/2015By : Abdul Ghaffar, PMP29Slackis the amount of time that a task can slip before it affects another task or the project's finish date.Custom Field6/19/2015By : Abdul Ghaffar, PMP30
Tracking ProjectTo control the variations from actual plan (baseline) we need to track project and continuously check the health of the project.
EVM is a financial measurement tool that combines the conflicting aspects of scope, schedule and cost into a unified set of metrics.These metrics can be used for measuring, monitoring, reporting and forecasting project performance. It can be used through all the phases of a project, from initiation to closure.
6/19/2015By : Abdul Ghaffar, PMP31Earned Value
6/19/2015By : Abdul Ghaffar, PMP32ExampleYou have a project to build a new fence. the fence is four sided as shown.Each side is to take one day to build and is budgeted for $1000 per side.The sides are planed to be completed one after the other.Today is the end of day three.
Calculate AC, BAC, CV, CPI,SV, SPI, EAC etc.
6/19/2015By : Abdul Ghaffar, PMP33Plan Tasks
6/19/2015By : Abdul Ghaffar, PMP34Set Baseline
6/19/2015By : Abdul Ghaffar, PMP35 Actual Status
6/19/2015By : Abdul Ghaffar, PMP36
Check Status
6/19/2015By : Abdul Ghaffar, PMP37Status Summary6/19/2015By : Abdul Ghaffar, PMP38
Calendar View
6/19/2015By : Abdul Ghaffar, PMP39Network Diagram
6/19/2015By : Abdul Ghaffar, PMP40Other Reports
6/19/2015By : Abdul Ghaffar, PMP41THANKS6/19/2015By : Abdul Ghaffar, PMP42