Project-sheet Blinkwater TSF
1
www.construction.murrob.com BLINKWATER Mokopane, Mogalakwena Mine PROJECT TYPE: EARTHWORKS CLIENT: Anglo Platinum VALUE: R 129 Million CONSULTANTS: None PROJECT DURATION: 36 Months DATE OF PROJECT: January 2013 PROJECT DESCRIPTION: Load & Haul of waste material to construct tailings impoundment dam. Approximate volumes mined for the project:- • Topsoil Stripped 379,254m³ • Dam wall 2,322,515m³ • Interface 580,000m³
-
Upload
gert-buitendach -
Category
Business
-
view
32 -
download
0
description
Opencast Contract Mining, Load, Haul, TSF
Transcript of Project-sheet Blinkwater TSF
www.construction.murrob.com
BLINKWATER Mokopane, Mogalakwena Mine
PROJECT TYPE: EARTHWORKS
CLIENT:
Anglo Platinum
VALUE:
R 129 Million
CONSULTANTS:
None
PROJECT DURATION:
36 Months
DATE OF PROJECT:
January 2013
PROJECT DESCRIPTION:
Load & Haul of waste material to construct
tailings impoundment dam.
Approximate volumes mined for the project:-
• Topsoil Stripped 379,254m³
• Dam wall 2,322,515m³
• Interface 580,000m³