Project Management Chapter No 1 97-2003 format
Transcript of Project Management Chapter No 1 97-2003 format
Project ManagementChapter No 1
Chapter Objectives
Define a Project List a project’s characteristics Distinguish a project from a program,
activity and task. Understand the three parameters that
constrains a project Know the importance of defining and using
a project classification rule. Understand the issues around scope creep,
hope creep, effort creep and feature creep.
Define a Project
“A Project is a sequence of unique, complex and connected activities having one goal or purpose and that must be completed by a specific time, within budget and according to specification”.( Taken from Robert K. Wysocki).
Now lets take each part of the Definition separately.
CharactertisticsSequence of Activities
A project comprises a number of activities that must be completed in some specified order, or sequence.(An activity is a defined as chunk of Work).
In order to get the desired objective we have to think in terms of inputs and outputs.
What is needed as input in order to begin working on this activity.
What activities produce those as outputs.
Unique Activities
The activities in a project must be unique.
For each and every project the outputs can be different.
Like in doing of one activity we can have different result and when we repeat the same activity the result can be totally changed.
Now this thing becomes a challenge for the project manager.
Complex Activities
The activities that make up the project are not simple, repetitive acts, such as mowing the lawn, painting the house, washing the car, or loading the delivery truck.
They are complex. For example, designing an intuitive
use interface to an application system is a complex activity.
Connected Activities
Connectedness implies that there is a logical or technical relationship between pairs of activities.
There is an order to the sequence in which the activities that makeup the project must be completed.
They are considered connected because the output from one activity is the input to another.
Connected Activities
For example, we must design the computer program before we can program it.
One Goal
Projects must have a single goal, for example, to design an inner city play ground for families.
However, very large or complex projects may be divided into several subprojects, each of which is a project in its own right.
This division for better management control.
For example, subprojects can be defined at the department , division or geographic level.
Specified Time
Projects have a specified completion date.
This date can be self imposed by management or externally specified by a customer or government agency.
The deadline is beyond the control of anyone working on the project.
The project is over on the specified completion date whether or not the project work has been completed.
Within Budget
Projects also have resources limits, such as a limited amount of people, money or machines that are dedicated to the project.
While these resources can be adjusted up or down by management, they are considered fixed resources to the project manager.
For example, suppose a company has only one web designer at the moment.
That is the fixed resources that is available to project managers.
Project And Program
A Program is a collection of projects. A Project is a to be completed within
specific time and in specific order to make it complete.
Cause program comprises of multiple projects, they are larger in scope than a single project.
For example a space program can that includes several projects.
Project And Program
Unlike projects, program can have many goals.
The NASA space program is such that every launch of a new mission includes several dozen projects in form of scientific experiments.
Project Parameters
Five constraints operate on every project.1) Scope2) Quality3) Cost4) Time 5) Resources These constraints are an interdependent
set. A change in one can cause a change in
another constraint to restore the equilibrium of the project.
Project Parameters
These all constraints or five parameters form a system that must remain in balance for the project to be in balance.
They are so important to success or failure of the project.
1) Scope
Scope is a statement that defines the boundaries of the project.
It tells not only what will be done but also what will not be done.
Scope may also be referred to as a document of understanding , a scoping statement, a project initiation document and a project request form.
Beginning a project on the right is important and so staying on the right foot.
1) Scope
It is no secret that scope can change at any time.
Detecting that change and deciding how to accommodate it in the project plan are major challenges for the project manager.
2) Quality
Two types of quality are part of every product.
The first is product quality. This refers to the quality of the
deliverable form the project. The traditional tools of quality
control are used to ensure product quality.
2) Quality
The second type of quality is the process quality, which is the quality of the project management process itself.
The focus is on how well the project management process works and how can it be improved.
Continuous quality improvement and process quality management are the tools used to measure process quality.
2) Quality
When we are going to make a sound management process plan so just one job gets left over there and that is to monitor the project.
Because if you have a sound plan so everything automatically get adjusted and running smoothly.
3) Cost
The Dollar cost of the project is another variable that defines the project.
The second name can be budget that has been established for the project.
It works like an input when we do project to deliver.
It is the major consideration throughout the project management life cycle.
3) Cost
The customer can simply offer a figure about equal to what customer he or she had in mind for the project.
The figure should be close to the estimate that is already made for the project.
In more formal situations the project managers prepares a proposal for the projected work.
3) Cost
That proposal includes an estimate (perhaps even a quote) of the total cost of the project.
It makes it easy for the customer to decide whether to work on the project with proposed budget or not.
4) Time
The customer specifies a timeframe or deadline date within which the project must be completed.
Basically the time and cost are inversely proportion with each other.
The time a project takes to be completed can be reduced but cost increases as a result.
Time is an interesting resource, it is consumed whether we use it or not.
4) Time
The objective for the project manager is to use the future time allotted to the project in the most effective and productive ways possible.
Future time (time that has not occurred) can be resource to be traded within a project or across projects.
Once a project has begun, the prime resource available to the project manager to keep the project on schedule or get it back on schedule is time.
5) Resources
Resources are assets, such as people, equipment, physical facilities, or inventory, that have limited availabilities, can be scheduled, or can be leased from an outside party.
Some are fixed others are variable only in the long term.
In any case they are central to the scheduling of project activities and the orderly completion of the project.
5) Resources
For system development projects, people are the major resource.
Another valuable resource for systems project is the availability of the computer processing time (mostly for testing purposes), which can present significant problems to the project manager with regard to project scheduling.
Classification By Project Characteristics
Many organizations have chosen to define a classification of projects based on such project characteristics as these:
Risk Establish levels of risk (high, medium ,low)
Business Value Establish levels (High, Medium ,low)
Length Establish several categories (i.e , 3 Months, 3 to 6 Months, 6 to 12 Months , etc.)
Classification By Project Characteristics
Complexity Establish categories (High, Medium, Low)
Technology Used Establish several categories (well Established, Used Somewhat, Basic familiarity, unknown, etc)
Number of Departments Affected Establish some categories (One, Few, Several, all).
Cost
Classification By Project Characteristics
The project profile determines the classification of the project.
The classification defines the extent to which the project management methodology is to be used.
Types of Projects
Types A Project: Project of Type A are the high business value, high complexity project.
They are the most challenging projects the organization undertakes.
Type A projects use the latest technology, which, when coupled with high complexity, causes risk to be high also.
To maximize the probability of success, the organization requires that these projects utilize all the methods and tools available in their project management methodology.
Types of Projects
Types A Project: An example of a Type A project is the
introduction of a new technology into an existing product that has been very profitable for the company.
Types of Projects
Type B Projects: Projects of Type B are shorter in
length, yet they still are significant projects for the organization.
All of the methods and tools in the project management process are probably required.
The projects generally have good business value and are technologically challenging.
Types of Projects
Type B Projects: Many product development projects
fall in this category.
Types of Projects
Type C Projects: Projects of Type C are the projects occurring
most frequently in an organization. They are short by comparison and use
establish technology. Many are projects that deal with the
infrastructure of the organization. A typical project team consists of five
people, the project lasts six month, and the project is based on a less than adequate scope statement.
Types of Projects
Type C Projects: Many of the methods and tools are
not required for these projects. The project manager uses those
tools, which are optional, if he or she sees value in their use.
Types of Project
Type D Project: Projects of type D just meet the
definition of a project and may require only a scope statement and a few scheduling pieces of information.
A typical type D project involves making a minor change in an exclusive process or procedure or revising a course in the trianing curriculum.
Table Supporting Types of Project
The figure lists the methods and tools that are required and optional given the the type of project
Table Supporting Types of Project
Project Management Process
Project Classification
A B C D
Define
Conditions of Satisfaction R R O O
Project Overview Statement R R R R
Approval for Request R R R R
Plan
Conduct Planning Session R R O O
Prepare Project Proposal R R R R
Approval of Proposal R R R R
Table Supporting Types of Project
Project Management Process
Project Classification
A B C D
Launch
Kick Off Meeting R R O O
Activity Schedule R R R R
Resource Assignment R R R O
Statement of Working R O O O
Monitor/Control
Status Reporting R R R R
Project Team Meeting R R O O
Approval of Deliverables R R R R
Table Supporting Types of Project
Project Management Process
Project Classification
A B C D
Closure
Post Implementation Audit R R R R
Project Notebook R R O O
R=REQUIRED O=OPTIONAL
Examples Project Classes And Definitions
CLASS
DURATION
RISK COMPLEXITY
TECHNOLOGY
LIKELIHOOD OF PROBLEMS
Type A
>18 months
High High Breakthrough
Certain
Type B
9-18 Months
Medium
Medium Current Likely
Type C
3-9 Months
Low Low Best of Breed
Some
Type D
<3 Months
Very low
Very Low Practical None
Creeps
Scope Creep: Scope creep is the term that has
come to mean any change in the project that was not in the original plan.
Change is constant. Changes occur for several reasons
that have nothing to do with the ability or foresight of the customer or the project manager.
Creeps
Scope Creep: Market conditions are dynamic. The competition can introduce or
announce an upcoming new version of its product.
Your management might decide that getting to the market before the competition is necessary.
Your job as project manager is to figure out how these changes can be accommodated.
Creeps
Scope Creep: Tough job, but somebody has to do
it. Regardless of how these changes
occur, it is your job as project manager to figure out how, if at all, you can accommodate the change.
Creeps
Hope Creep: Hope creep is the result of a project team
member’s getting behind schedule, reporting that he or she is on schedule, but hoping to get on schedule by the next report date.
Hope creep is a real problem for the present manager.
There will be several activity managers within your project, team members who manage a chunk of work.
Creeps
Hope Creep: They don’t want to give you bad
news, so they are prone to tell you that their work is proceeding according to schedule when, in fact, it is not.
It is their hope that they will catch up by the next report period, so they mislead you into thinking that they are on schedule.
Creeps
Hope Creep: The activity managers hope that
they will catch up by completing some work ahead of schedule to make up the slippage.
The project manager must verify the accuracy of the status reports received from the team members.
This does not mean that the project manager has to check into the details of every report.
Creeps
Random checks can be used effectively.
Creeps
Effort Creep: Effort creep is the result of the team
member’s working but not making progress proportionate to the expended.
Everyone of us has worked on a project that always seems to be 95 percent complete no matter how much effort is expended to complete it.
Creeps
Effort Creep: Each week the status report records
progress, but the amount of work remaining doesn’t seem to decrease proportionately.
Other than random checks, the only effective thing that the project manager can do is to increase the frequency of status reporting by those team members who seem to suffer from effort creep.
Creeps
Features Creep: Closely related to scope creep is
feature creep. Feature creep results when the team
members arbitrarily add features and functions to the deliverable that they think the customer would want to have.
The problem is that the customer didn’t specify the feature, probably for good reason.
Creeps
Features Creep: If the team members has strong
feelings about the need for this new feature, formal change management procedures can be employed.