Project Inception Report - High Capacity Power Transmission Corridor - Main Report

59
HIGH CAPACITY POWER TRANSMISSION CORRIDOR - PROJECT INCEPTION REPORT Power Grid Corporation of India Ltd. Gurgaon

Transcript of Project Inception Report - High Capacity Power Transmission Corridor - Main Report

Page 1: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

HIGH CAPACITY POWER

TRANSMISSION CORRIDOR

- PROJECT INCEPTION REPORT

Power Grid Corporation of India Ltd.

Gurgaon

Page 2: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 1 of 46

BACKGROUND

1. Pursuant to the introduction of Long Term Open Access (LTOA) in the inter-State

transmission system vide CERC regulations 2004, POWERGRID had received

overwhelming response from the IPP generation developers seeking LTOA for

the new generation projects proposed to be setup under the de-licensed regime.

2. POWERGRID had received 225 nos. of applications amounting to capacity

addition of about 1,98,438 MW. While processing these applications readiness of

generation projects applied for LTOA were assessed through several rounds of

discussions held with the project developers, wherein status of proposed

generation projects with respect to availability of land, fuel & water linkages,

environment and other statutory clearance were examined in association with the

beneficiaries of concerned regions and CEA. Based on the information furnished

by the applicants, group of generation projects who have made progress on

ground were prioritized and considered for grant of Long Term Open Access.

Accordingly, POWERGRID has already processed and granted or in process of

issuance of LTOA to 90 nos. of applications and balance is at different stages of

processing.

3. It has been observed that the generation projects, for which LTOA has been

sought, are mainly concentrated in small pockets in areas like pit-head in Orissa,

Chhattisgarh, Jharkhand or Coastal sites with port facilities in Andhra Pradesh,

Tamil Nadu or hydel sites in Sikkim etc. These projects are likely to add

generation capacity of about 49,323 MW in which LTOA has been sought for

42,108 MW, The LTOA for these projects has been granted/finalized.

4. All the above applications have no firm beneficiaries and accordingly the

transmission system requirement has been worked out on the basis of target

beneficiaries/regions as informed by the applicants.

5. For meeting the evacuation requirement of above LTOA generation projects likely

to be commissioned progressively from 2011 onwards, construction of nine nos.

high capacity transmission corridors shall be necessary on urgent basis at an

estimated cost of Rs. 58,061 Crores. These transmission corridors have been

Page 3: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 2 of 46

evolved and finalized after lot of deliberations with stakeholders in consultation

with CEA at forums including LTOA Meetings, Standing Committee Meetings for

Power System Planning and respective Regional Power Committee meetings.

6. The implementation of finalized transmission system require many pre-

investment project preparation activities like survey, land identification,

preparation of DPR including cost estimates, tendering activity like issuance of

NIT, opening/evaluation of bids etc. which besides incurring cost requires

substantial time. Considering the urgency due to likely commissioning of IPP

projects progressively from 2011 onwards and to enable unhindered

development of transmission system necessary for LTOA projects, POWERGRID

have gone ahead with such activities with the tentative/target beneficiaries given

by the LTOA applicants. In the absence of firm beneficiaries for these generation

projects, the investment of such magnitude would involve high risk. Therefore,

now before initiating physical implementation and making actual investment of

such large magnitude it is necessary to evolve adequate security mechanism to

mitigate the risk involved.

7. In this regard, it may be mentioned that as per para-7.1(4) of the Tariff Policy of

Govt of India published on 6/1/2006, “prior agreement with the beneficiaries

would not be a pre-condition for network expansion. CTU/STU should undertake

network expansion after identifying the requirements in consonance with the

National Electricity Plan and in consultation with stakeholders, and taking up the

execution after due regulatory approvals.”

8. In view of above, POWERGRID vide its petition no. 233/2009 had filed a petition

with the Central Electricity Regulatory Commission (CERC) for grant of regulatory

approval and other relief for execution of evacuation system required in

connection with grant of long-term open access to group of developers. Vide

dated 25/XI/2009, CERC has directed POWERGRID to submit the minutes of the

above meetings and corridor-wise details of the scheme.

9. Accordingly, a Project Inception Report (PIR) covering above mentioned 9 nos of

High Capacity Power Transmission Corridors (HCPTC) have been prepared

which inter-alia comprises of description/justification of each of the corridor in

Page 4: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 3 of 46

different sections. The tentative cost estimate for each of the corridor has been

included as a part of the report. These tentative cost has been worked out based

on the unit cost for different categories of transmission line/substation/associated

bays etc, details of the per unit cost considered is given at Annexure-A. It is

pertinent to mention here that these costs are indicative only and actual cost of

each transmission corridor shall be worked out while preparing Detailed Project

Report while seeking its investment approval. Further, the details of the meetings

where such corridors have been discussed/agreed have also been indicated.

10. The nine nos of High Capacity Power Transmission corridors have been depicted

at Exhibit – 1 and a brief summary of the tentative estimated cost is as given

below:

High Capacity Power Transmission Corridor

(HCPTC) Rs. Crs

Section-I HCPTC – I (Transmission System Associated with Phase-I Generation Projects in Orissa)

8,752

Section-II HCPTC – II (Transmission System Associated with IPP projects in Jharkhand)

5,709

Section-III HCPTC – III (Transmission System Associated with IPP projects in Sikkim)

1,304

Section-IV HCPTC – IV (Transmission System Associated with IPP projects in Bilaspur complex, Chattisgarh & IPPs in Madhya Pradesh)

1,243

Section-V HCPTC – V (Transmission System Associated with IPP projects in Chattisgarh)

28,824

Section-VI HCPTC – VI (Transmission System Associated with IPP projects in Krishnapatnam Area, Andhra Pradesh)

2,065

Section-VII HCPTC – VII (Transmission System Associated with IPP projects in Tuticorin Area, Tamil Nadu)

2,357

Section-VIIII HCPTC – VIII (Transmission System Associated with IPP projects in Srikakulam Area, Andhra Pradesh)

2,986

Section-IX HCPTC – IX (Transmission System Associated with IPP projects in Southern Region for transfer of power to other regions)

4,821

Total 58,061

Page 5: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 4 of 46

Annexure-A

BASE COST

SL. NO. ITEM UNIT COST 1 + 800 kV, 6000 MW HVDC Terminal Rs. in Crores 6600 2 + 800 kV, 6000 MW HVDC line Rs. in Crores/km 3 3 + 600 kV, 4000 MW HVDC Terminal Rs. in Crores 4400 4 + 600 kV, 4000 MW HVDC line Rs. in Crores 2.5 5 Establishment of New 765 kV Substation Rs. in Crores 100 6 765 kV D/c (Hexa Zebra) line Rs. in Crores/km 2.8 7 765 kV S/c (Quad Bersimis) line Rs. in Crores/km 1.7 8 765 kV Substation Bay Rs. in Crores 13 9 765/400 kV, 1500 MVA Transformer Rs. in Crores 80 10 765/400 kV, 1000 MVA Transformer Rs. in Crores 60 11 765 kV, 330 MVAR Reactor Rs. in Crores 30 12 765 kV, 240 MVAR Reactor Rs. in Crores 30 13 Establishment of New 400 kV Substation Rs. in Crores 50 14 Establishment of New 400 kV Substation (GIS) Rs. in Crores 60 15 400 kV D/c (Quad Moose) line Rs. in Crores/km 1.8 16 400 kV D/c (Triple Snowbird) line Rs. in Crores/km 1.5 17 400 kV D/c (Twin Moose) line Rs. in Crores/km 1 18 400 kV Substation Bay Rs. in Crores 5 19 400 kV Substation Bay (GIS) Rs. in Crores 10 20 400/220 kV, 500 MVA Transformer Rs. in Crores 12 21 400/220 kV, 315 MVA Transformer Rs. in Crores 10 22 400 kV, 125 MVAR Reactor Rs. in Crores 8 23 400 kV, 80 MVAR Reactor Rs. in Crores 5 24 400 kV, 63 MVAR Reactor Rs. in Crores 5 25 400 kV, 50 MVAR Reactor Rs. in Crores 5 26 220 kV D/c line Rs. in Crores/km 0.7 27 220 kV bay Rs. in Crores 2 28 220 kV bay (GIS) Rs. in Crores 6 29 132 kV D/c line Rs. in Crores/km 0.55 30 132 kV bay Rs. in Crores 1.5 31 IDC & Centages % 17

** Note : The estimated cost of various corridors has been calculated based upon the above base cost.The above etimated cost are indicative only valid at 3rd qtr 2009 price level. The cost of transmission line may vary depending on various factors viz. Wind zone, type of terrain, availability of right-of-way, number of River/Railway/Road crossing, accesibility of the terrain, Law & Order situation, etc. The cost of sub-station may vary depending on the shape & size of substation land, orientation and layout of the substation etc.

Page 6: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

SECTION – I

Page 7: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 5 of 46

HIGH CAPACITY POWER TRANSMISSION CORRIDOR – I (Transmission System Associated with IPP projects in Orissa)

1.0 DESCRIPTION/OBJECTIVE AND JUSTIFICATION

This transmission corridor has been evolved to evacuate power from the proposed IPP generation projects in the Orissa. In this state, LTOA has been granted to 7 nos of applicants as per the details given below:

Target Beneficiaries LTOA Sought (MW) Sl No.

Generation Developer/ Open Access Applicant

Date of Commissioning

Installed Capacity (MW)

NR WR ER SR Total

1 Sterlite Energy Ltd June, 2009 2400 200 200 - - 400

2 GMR Kamalanga Energy Ltd

September, 2011

1050 600 - - 200 800

3 Navabharat Power Pvt. Ltd

March, 2012 1050 465 255 - - 720

4 Monet Power Company Ltd

June, 2012 1050 300 375 225 - 900

5 Jindal India Thermal Power Ltd

March, 2011 1200 834 210 - - 1044

6 Lanco Babandh Power Pvt Ltd

December, 2013

2640 650 950 - - 1600

7 Ind Barath Energy(Utkal) Ltd

September, 2011

700 266 350 - - 616

Sub-total(Orissa) 10090 3315 2340 225 200 6080 A comprehensive transmission system was planned so as to take care of the evacuation needs of all the future generation projects in Orissa and the same was discussed with generation developers as well as constituents of Eastern, Northern and Western regions during various meetings in the year 2007 and 2008. The comprehensive transmission system was proposed to be implemented in phased manner matching with the program of generation capacity addition. Subsequently, review of progress of generation projects in Orissa was done in various meetings with the project developers between November-2008 to April-2009. Accordingly, the projects mentioned above have been considered under first phase based on the assessment of their actual progress.

As indicated above, the major portion of power from various generation projects of Orissa would have to be exported to power deficit regions like NR & WR. For evacuation and transfer of power from different generation projects in Orissa to NR/WR, a composite high capacity transmission scheme has been planned in view of the Right-of-way problem, so that different generation projects coming up in different time-frame could be integrated. In order to pool power from the generation projects in Orissa, two nos of major 765/400kV pooling substations have been planned at Angul and Jharsuguda. The pooling stations would be interconnected in ring form with 765kV 2xS/c lines. The

Page 8: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 6 of 46

Angul substation would be established vide LILO of one ckt of Talchar-Meramundali 400kV D/c line as well Meramundali-Jeypore 400kV S/c line. The Jharsuguda substation would be established vide LILO of Rourkela-Raigarh 400kV D/c line. These LILOs are required for evacuation of initial power from the generation projects pooled at Angul and Jharsuguda. At a later date, these LILOs may be withdrawn so as to reduce the short circuit levels of these substations.

For transfer of power from Angul/Jharsuguda to WR/NR, a high capacity 765kV AC corridor has been planned to NR via WR. The corridor starts from Jharsuguda in ER, reaches upto Bhiwani in NR via important substations like Dharamjaygarh(WR), Jabalpur(WR), Bina(WR), Gwalior(WR) and Jaipur(NR). The corridor also reaches to Indore in WR via Bhopal(WR) and Jabalpur(WR). In this process, three nos of new 765/400kV substations would be created at Dharamjayagarh, Jabalpur and Bhopal. Dharamjayagarh would be an important power hub where power could be pooled from generation projects of Orissa as well as Jharkhand/Bihar in ER for onward transfer to Western part of WR as well as to NR. This substation would be established through LILO of Ranchi-WR Pooling 765kV S/c line. Jabalpur 765/400KV substation would be an important take off point for diversion of power to WR through Jabalpur-Bhopal-Indore route and to NR via Jabalpur-Bina-Gwalior(WR)-Jaipur(NR)-Bhiwani route. Bhopal is also a new 765/400kV substation on the route from Jabalpur to Indore 765kV corridor. 2.0 SCOPE OF WORK The transmission scheme for above mentioned 7 nos. of projects is to be implemented in three parts. The transmission system covered under this corridor is as given below : Part-A • Angul Pooling Station – Jharsuguda Pooling Station 765kV 2xS/c • LILO of Rourkela – Raigarh 400kV D/c at Jharsuguda Pooling station • LILO of Meramundali – Jeypore 400kV S/c line at Angul pooling station • LILO of one ckt of Talcher - Meramundali 400kV D/c line at Angul pooling station • Establishment of 2x1500 MVA, 765/400kV Pooling Station at Jharsuguda • Establishment of 4x1500MVA, 765/400kV Pooling Station at Angul Part-B • Establishment of 765kV switching station at Dharamjaygarh • Establishment of 2x1500 MVA, 765/400kV Pooling Station at Jabalpur • Jharsuguda Pooling Station – Dharamjaygarh (WR) 765kV D/c • LILO of Ranchi – WR Pooling near Sipat 765kV S/c line at Dharamjaygarh • Dharamjaygarh – Jabalpur Pooling Station 765kV D/c line • Jabalpur Pooling Station – Jabalpur 400 kV D/c (high capacity) line Part-C • Jabalpur Pooling Station – Bina 765kV D/c line • Bina – Gwalior 765kV S/c (3rd circuit) • Gwalior - Jaipur 765kV S/c line • Jaipur - Bhiwani 765kV S/c line

Page 9: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 7 of 46

Part-D (Under Private Sector) • Establishment of 2x1500MVA, 765/400kV Bhopal Pooling Station • Jabalpur Pool – Bhopal – Indore 765kV S/c • Bhopal New substation – Bhopal (M.P.) 400kV D/c (high capacity) 3.0 TENTATIVE ESTIMATED COST The estimated cost of the proposed transmission is as below and Details of transmission element wise cost for POWERGRID scope of works is enclosed at Annexure-1. The proposed transmission system is enclosed at Exhibit-1.

Part-A : About Rs. 2409 Crores Part-B : About Rs. 2992 Crores Part-C : About Rs. 3351 Crores Total : About Rs. 8752 Crores 4.0 TIME FRAME The above transmission system would be implemented in phased manner matching with the progress of the generation projects. Further wherever possible interim/temporary arrangement of transmission system for immediate evacuation shall be implemented to insure evacuation of power. 5.0 CONSENT OF BENEFICIARIES The transmission system for evacuation of power from the above generation projects as well as transfer of power to target beneficiaries in various regions was evolved through load flow studies carried out by considering various alternatives/options based on the transmission needs incident on the system because of these open access requirements. The studies for the evolution of transmission systems were discussed & finalized in consultation with CEA and generation developers and various state utilities as given below. It was agreed that the charges of the transmission system is to be borne by the generation developers till the time beneficiaries are firmed up and agree to bear its transmission charges. Accordingly, it was decided that POWERGRID shall go ahead for implementation of the transmission system based on the assurance of signing the BPTA (Bulk Power Transmission Agreement) by the project developers for sharing the transmission charges.

Meeting North East West Long Term Access Meeting Date

- 8-11-2008 (Bhubaneswar) Appendix-1 17-04-2009 CEA,New Delhi) Appendix-2

-

Standing Committee Meeting No./ Date

27th SCM 30-05-2009 (Nainital) Appendix-3

8-11-2008 (Bhubaneswar) Appendix-4 14-09-2009 (Bhubanewar) Appendix-5

29th / 10.09.2009 / Ahmedabad Appendix-6

Page 10: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 8 of 46

Meeting North East West Regional Power Committee Meeting No./ Date

- Special RPC 30-12-2008 Appendix-7

11th /25.09.09 / Raipur Appendix-11

Page 11: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 9 of 46

Annexure-1

HIGH CAPACITY TRANSMISSION CORRIDOR – I THE TRANSMISSION SYSTEM ASSOCIATED WITH IPPs PROJECTS IN ORISSA

(Transmission System under the Scope of POWERGRID) Sl

No. Transmission System No. / KM. Unit Cost

(Rs. Crore) Total

tentative Cost (Rs.

Crs) A Part-A : 1 Establishment of new 765/400kV sub-station at

Jharsuguda 1 100 100

2 Establishment of new 765/400kV sub-station at Angul

1 100 100

3 Angul - Jharsuguda 765kV 2xS/c 245 1.7 833 4 LILO of Rourkela - Raigarh 400kV D/c at

Jharsuguda 40 1 40

5 LILO of Meramundali – Jeypore 400kV S/c line at Angul

4 1 4

6 LILO of one ckt of Talcher - Meramundali 400kV D/c line at Angul

16 1 16

7 765/400 kV Transformers 6 80 480 8 Reactors (Line/Bus) (765kV) 8 30 240 9 Reactors (Line/Bus) (400kV) 5 5 25 10 Associated bays - line & reactors (765kV) 12 13 156 11 Associated bya - line & reactors (400kV) 13 5 65 Sub-Total 2059 Subtotal with IDC and Centages 2409 B Part-B : 1 Establishment of 765kV station at Dharamjaygarh 1 100 100 2 Jharsuguda Pooling Station – Dharamjaygarh(WR)

765kV D/c 190 2.8 532

3 LILO of one ckt of Ranchi-WR Pool 765kV S/c at Dharamjaygarh

6 2.8 17

4 Dharamjaygarh - Jabalpur 765kV D/c 350 2.8 980 5 Establishment of 765/400kV sub-station at

Jabalpur 1 100 100

6 Jabalpur Pool - Jabalpur 400kV D/c (High Capacity)

14 1.8 25

7 765/400 kV Transformers 2 80 160 8 Reactors (Line/Bus) (765kV) 11 30 330 9 Reactors (Line/Bus) (400kV) 2 5 10 10 Associated bays - line & reactors (765kV) 21 13 273 11 Associated bays - line & reactors (400kV) 6 5 30 Sub-Total 2557 Subtotal with IDC and Centages 2992 C Part-C : 1 Jabalpur Pool - Bina 765kV D/c 250 2.8 700 2 Bina - Gwalior 765kV S/c (3rd circuit) 245 1.7 417 3 Gwalior - Jeypore 765kV S/c 260 1.7 442 4 Jeypore - Bhiwani 765kV S/c 320 1.7 544 5 Associated bays - line & reactors (765kV) 24 13 312

Page 12: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 10 of 46

Sl No.

Transmission System No. / KM. Unit Cost (Rs. Crore)

Total tentative Cost (Rs.

Crs) 6 Associated bays - line & reactors (400kV) 3 5 15 7 Reactors (Line/Bus) (765kV) 14 30 420 8 Reactors (Line/Bus) (400kV) 3 5 15 Sub-Total 2865 Subtotal with IDC and Centages 3351 Total 8752

Page 13: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

SECTION – II

Page 14: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 11 of 46

HIGH CAPACITY TRANSMISSION CORRIDOR – II (Transmission System Associated with IPP projects in Jharkhand)

1.0 DESCRIPTION/OBJECTIVE AND JUSTIFICATION

This transmission corridor has been evolved to evacuate power from the proposed IPP generation projects in the state of Jharkhand and state sector generation projects in West Bengal. In this regard, LTOA has been granted / being granted to 5 nos. of applicants as per the details given below:

Target Beneficiaries Allocation (MW) Sl.

No. Developer/Applicant Time Frame Installed Capacity (MW)

LTOA (MW) NR WR ER Total

1. Adhunik Power & Natural Resources Ltd) March, 2012 1080 850 400 100 350 850

2. Corporate Power Ltd March, 2012 660 594 594 - - 594

3. Essar Power (Jharkhand) Ltd.

December, 2011 1200 1100 400 400 300 1100

4. CESC Ltd.(Dumka) June, 2012 600 540 270 270 - 540

5. West Bengal State Electricity Distribution Compnay Ltd.

Progressively by 2014-15 1000 1000 600 400 - 1000

Subtotal 4540 4084 2264 1170 650 4084

A combined transmission scheme has been evolved for evacuation and transfer of power from above mentioned generation projects in the state of Jharkhand and West Bengal to constituents of Eastern, Northern and Western region. The scheme consists of two parts i.e. immediate evacuation system to be developed by the generation project developer / LTOA applicant and strengthening scheme to be developed by POWERGRID. The scheme includes establishment of new 400kV sub-station near Essar / Corporate generation projects which would be connected to Ranchi and Gaya sub-stations of Eastern region through high capacity 400kV lines. Further, in Northern region, a new 765kV corridor has been proposed through establishment of new 765kV substations at Varanasi and Kanpur. The Varanasi substation is proposed to be established through LILO of Sasaram-Balia 765kV S/c line and from Varanasi 765kV corridors viz. Varanasi-Kanpur-Bareilly/Jhattikalan has been planned. For transfer of power to Western Region, 765kV corridor has been planned from Ranchi to Jabalpur via Dharamjaygarh. Here, it is to mention that 765 kV D/c (2nd) line from Dharamjaygarh to Jabalpur has been proposed for implementation under private sector.

Page 15: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 12 of 46

2.0 SCOPE OF WORK The transmission system covered under this corridor is as given below : • In Eastern Region − Establishment of 400kV Pooling Station (Jharkhand Pool) near Essar and

Corporate generation projects. This will be a switching station without ICTs − Ranchi New (765/400kV S/s) – Jharkhand Pool 400 kV D/c line with Quad

Moose conductor − Jharkhand Pool – Gaya 400 kV D/c line with Quad Moose conductor

• In Northern Region − New 2x1500 MVA, 765/400 kV substation at Varanasi and Kanpur − Gaya – Varanasi 765 kV S/c − LILO of one circuit of Tillaiya – Balia 765 kV D/c line at Varanasi − Varanasi – Kanpur 765 kV D/c − Kanpur – Jhatikalan 765 kV S/c − 400kV connectivity for new 765/400kV S/s at Varanasi & Kanpur Varanasi - Sarnath (UPPCL) 400kV D/c (quad) LILO of Sasaram - Allahabad 400kV line at Varanasi Kanpur (765/400kV) - Kanpur (Existing) 400kV D/c (quad)

• In Western Region − Ranchi New (765/400kV S/s) - Dharamjayagarh 765kV S/c

Common Strengthening Transmission System for Transfer of power from generation projects in Jharkhand to NR/WR under the Scope of Private Sector • In Western Region − Dharamjaygarh – Jabalpur 765kV D/c (2nd line)

Note : Associated 765kV line bays at Dharamjaygarh and Jabalpur sub-station would be under the scope of POWERGRID

3.0 TENTATIVE ESTIMATED COST

Estimated Cost of above transmission system : about Rs 5709 Crs Details of transmission element wise cost for POWERGRID scope of works is enclosed at Annexure-1. The proposed transmission system is enclosed at Exhibit-1. 4.0 TIME FRAME The above transmission system would be implemented in phased manner matching with the progress of the generation projects. Further wherever possible interim/temporary arrangement of transmission system for immediate evacuation shall be implemented to insure evacuation of power.

Page 16: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 13 of 46

5.0 CONSENT OF BENEFICIARIES The transmission system for evacuation of power from the above generation projects as well as transfer of power to target beneficiaries in various regions was evolved through load flow studies carried out by considering various alternatives/options based on the transmission needs incident on the system because of these open access requirements. The studies for the evolution of transmission systems were discussed & finalized in consultation with CEA and generation developers and various state utilities as given below. It was agreed that the charges of the transmission system are to be borne by the generation developers till the time beneficiaries are firmed up and agree to bear its transmission charges. Accordingly, it was decided that POWERGRID shall go ahead for implementation of the transmission system based on the assurance of signing the BPTA (Bulk Power Transmission Agreement) by the project developers for sharing the transmission charges.

Meeting North East West Long Term Access Meeting Date

08-11-2008 Bhubaneswar Appendix-1 26-05-2009 Gurgaon Appendix-8

Standing Committee Meeting No./ Date

27th SCM 30-05-2009 (Nainital) Appendix-3

14-09-2009 Bhubaneswar Appendix-5

29th / 10.09.2009 / Ahmedabad Appendix-6

Regional Power Committee Meeting No./ Date

- To be discussed 11th /25.09.09 / Raipur Appendix-11

Page 17: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 14 of 46

Annexure-1

HIGH CAPACITY TRANSMISSION CORRIDOR – II

THE TRANSMISSION SYSTEM ASSOCIATED WITH IPPs PROJECTS IN JHARKHAND

(Transmission System under the Scope of POWERGRID)

Sl No.

Transmission System No. / KM. Unit Cost (Rs. Crore)

Total tentative Cost (Rs.

Crs) A Strengthening in Eastern / Northern Region 1 Ranchi - Jharkhand pool - Gaya 400kV D/c (quad) 200 1.8 360 2 Gaya - Varanasi 765kV S/c 235 1.7 400 3 LILO of Tillaiyya-Balia 765kV S/c at Varanasi 60 2.8 168 4 Varanasi - Kanpur 765kV D/c 350 2.8 980 5 Kanpur - Jhatikra 765kV S/c 400 1.7 680 6 Varanasi - Sarnath (UPPCL) 400kV D/c (quad) 30 1.8 54 7 LILO of Sasaram - Allahabad 400kV line at

Varanasi 30 1 30

8 Kanpur (765/400kV) - Kanpur (Existing) 400kV D/c (quad)

20 1.8 36

9 Ranchi - Dharamjaygarh 765kV S/c 300 1.7 510 10 New 400kV Jharkhand Pooling Station 1 50 50 11 New 765/400kV sub-station at Varanasi 1 100 100 12 New 765/400kV sub-station at Kanpur 1 100 100 13 765/400 kV Transformers 4 80 320 14 Reactors (Line/Bus) (765kV) 18 30 540 15 Reactors (Line/Bus) (400kV) 2 5 10 16 Associated bays - line & reactors (765kV) 34 13 442 17 Associated bays - line & reactors (400kV) 20 5 100 Sub-Total 4880 Subtotal with IDC and Centages 5709

Page 18: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

SECTION – III

Page 19: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 15 of 46

HIGH CAPACITY TRANSMISSION CORRIDOR – III (Transmission System Associated with IPPs projects in Sikkim)

1.0 DESCRIPTION/OBJECTIVE AND JUSTIFICATION This transmission corridor has been evolved to evacuate power from the proposed IPP generation projects in the State of Sikkim. In this state, LTOA has been granted to 9 nos of applicants as per the details given below: Sl. No

Name of the Developer/ Open Access Applicant

Name of the Generation Plant

Capacity/ Power to be transferred

Target Beneficiaries

Generation expected to Commence from

1 Teesta Urja Ltd. / PTC Teesta-III 200x6 =1200 MW

PSEB-340MW, HPGCL-200MW, UPPCL-200MW, Rajasthan Discom-100MW

Aug., 2011

2 Lanco Energy Pvt. Ltd. Teesta-VI 125x4=500 MW MSEDCL (Maharastra)

Nov, 2012

3 DANS Energy Pvt. Ltd. Jorethang 48x2 = 96 MW NR/WR Dec., 2011 4 JAL Power Corporation Rangit-IV 40x3=120 MW NR/WR June, 2013 5 Shiga Energy Pvt. Ltd. Tashiding 48.5x2 =97 MW NR/WR June, 2012 6 TT Energy Pvt. Ltd. Tingting 49.5x2=99 MW NR/WR March, 2012 7 Madhya Bharat Power

Corporation Ltd. Rongnichu 48x2=96 MW Chhattishgarh March, 2012

8 Gati Infrastructure Ltd Chuzachen 49.5x2=99 MW PSEB, DVB, HSEB, BSEB

March, 2010

9 Gati Infrastructure Bhasmey Power Pvt. Ltd.

Bhasme 25.5x2 = 51 MW NR/WR March, 2012

Total 2358 MW A comprehensive transmission system has been planned so as to take care of the evacuation need of all the future generation projects in Sikkim. The transmission schemes are to be implemented in stages matching with the realistic commissioning of generation projects in consultation with Generating Companies / Beneficiaries. The transmission system for above mentioned 9 nos. of projects is to be implemented in two parts; Part-A for evacuation of 1299MW power from the first two projects i.e. Chujachen (99MW) and Teesta-III (1200MW) and Part-B for evacuation of 1059MW power from balance 7 projects.

The power from various generation projects of Sikkim would have to be exported to power deficit regions like NR & WR. For evacuation of power from different generation projects in Sikkim, a need is felt to evolve a composite high capacity transmission scheme in view of the Right-of-way problem in Sikkim, wherein different generation projects coming up in different time-frame could be integrated. In order to pool power from various generation projects in Sikkim, two nos of major pooling substations have been planned at Mangan and New Melli in the upper and lower part of Sikkim respectively. In addition, one small pooling point substation in lower part of Sikkim i.e. Rangpo has also been planned for pooling of power from the generating stations in the vicinity. In view of the tough hilly terrain and scarcity of land for 400kV

Page 20: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 16 of 46

Air Insulated Switchyard, it is envisaged that all pooling substations in Sikkim shall be Gas Insulated Switchyard (GIS).

The power from all the future projects of Sikkim is to be brought to a new pooling station in Kishanganj in northern part of West Bengal/Bihar. For this, a 400kV high capacity D/c line is planned from the pooling station Mangan to Kishanganj which is to be LILOed at New Melli Substation. Further, Teesta-V – Siliguri 400kV D/c line would also be LILOed at other pooling station New Melli in order to provide evacuation path for initial generation units as well as reliability to the transfer of Sikkim power to Siliguri/Kishanganj.

The Teesta-III generation project is planned to be evacuated through 400kV D/c line upto Mangan pooling station. However, as Teesta-III is the only project in the upper part of Sikkim in the list of Phase-I generation projects, the Mangan pooling substation is not required to be established now. Accordingly, Teesta-III would be evacuated through Teesta-III–Kishanganj 400kV D/c line. This line would be further LILOed at New Melli, so that the Melli-Kishanganj portion of the line is utilized as a common transmission corridor for evacuation of power from all the Phase-I generation projects. Mangan pooling substation would be established at a later date through LILO of Teesta-III–New Melli-Kishanganj 400kV line for evacuation of power from future generation projects in upper part of Sikkim.

Here, it is to mention that Teesta-III – Kishanganj 400kV D/c line is proposed to be constructed by Teesta Valley Power Transmission Ltd. (a Joint Venture between Teesta Urja Ltd. and POWERGRID).

For onward transfer of power from the generation projects in Sikkim pooled at the Kishanganj pooling substation, strong integration of the pooling substation with the regional grid has been planned. For this, both the high capacity 400kV D/c lines between Siliguri and Purnea are planned to be LILOed at Kishanganj. Further, in order to relieve the critical loading of transmission corridors towards northern region i.e. Purnea-Muzaffarpur 400kV D/c line (quad moose) and Purnea-Biharsharif 400kV D/c line (quad moose, under implementation by private sector), a new corridor i.e. Kishanganj-Patna 400kV D/c line with quad moose conductor has been planned. 2.0 SCOPE OF WORK The common transmission system covered under this corridor is as given below: Part-A : Transmission System for development of pooling station at Kishanganj in Northern part of West Bengal/Bihar

LILO of Siliguri (Existing) – Purnea 400kV D/c line(quad) at new pooling station Kishanganj

LILO of Siliguri (Existing) – Purnea 400kV D/c line(on which reconductoring is being carried out) at Kishanganj with the higher capacity(HTLS) conductor

LILO of Siliguri – Dalkhola 220kV D/c line at new pooling station in northern part of West Bengal / Bihar

Page 21: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 17 of 46

LILO of Gangtok-Melli 132kV S/c line upto Rangpo pooling point, where Chuzachen-Rangpo 132kV D/c would be connected so as to form Chuzachen-Gangtok and Chuzachen-Melli 132kV S/c lines.

New 2x315 MVA, 400kV sub-station at Kishanganj along with associated bays. Part-B : Transmission System for development of pooling substations within Sikkim and transfer of power to a new pooling station Kishanganj in northern Part of West Bengal/Bihar

LILO of Teesta III – Kishanganj 400kV D/c line(quad) at New Melli Rangpo – New Melli 220kV D/c line (with twin Moose conductor) LILO of Gangtok-Rangit 132kV S/c line at Rangpo and termination of Gangtok-

Rangpo/Chujachen and Melli – Rangpo/Chujachen 132kV lines (constructed under part-A through LILO of Gangtok-Melli 132kV S/c line upto Rangpo) at Rangpo sub-station

LILO of Teesta V – Siliguri 400kV D/c line at New Melli Kishanganj – Patna 400kV D/c (quad) line Establishment of 220/132kV, 3x100MVA Gas Insulated Substation at Rangpo Establishment of 10x167MVA, 1 phase, 400/220kV Gas Insulated substation at

New Melli

3.0 TENTATIVE ESTIMATED COST The estimated cost of the proposed transmission is as below and Details of transmission element wise cost for POWERGRID scope of works is enclosed at Annexure-1. The proposed transmission system is enclosed at Exhibit-1. Part-A : About Rs. 185 Crores Part-B : About Rs. 1127 Crores Total : About Rs. 1304 Crores

4.0 TIME FRAME The above transmission system would be implemented in phased manner matching with the progress of the generation projects. Further wherever possible interim/temporary arrangement of transmission system for immediate evacuation shall be implemented to insure evacuation of power. 5.0 CONSENT OF BENEFICIARIES The transmission system for evacuation of power from the above generation projects as well as transfer of power to target beneficiaries in various regions was evolved through load flow studies carried out by considering various alternatives/options based on the transmission needs incident on the system because of these open access requirements. The studies for the evolution of transmission systems were discussed & finalized in consultation with CEA and generation developers and various state utilities as given below. It was agreed that the charges of the transmission system is to be borne by the generation developers till the time beneficiaries are firmed up and agree to bear its transmission charges. Accordingly, it was decided that POWERGRID shall go ahead for implementation of the

Page 22: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 18 of 46

transmission system based on the assurance of signing the BPTA (Bulk Power Transmission Agreement) by the project developers for sharing the transmission charges.

Meeting North East West Long Term Access Meeting Date

22-04-209 (Gurgaon) Appendix-9

Standing Committee Meeting No./ Date

27th SCM 30-05-2009 (Nainital) Appendix-3

14-09-2009 (Bhubaneswar) Appendix-5

29th / 10.09.2009 / Ahmedabad Appendix-6

Regional Power Committee Meeting No./ Date

- - 11th /25.09.09 / Raipur Appendix-11

Page 23: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 19 of 46

Annexure-1

HIGH CAPACITY TRANSMISSION CORRIDOR – III THE TRANSMISSION SYSTEM ASSOCIATED WITH IPPs PROJECTS IN SIKKIM

Sl

No. Transmission System No. / KM. Unit Cost

(Rs. Crore) Total

tentative Cost (Rs. Crs)

Part-A : Transmission System for development of pooling station at Kishanganj in Northern part of West Bengal/Bihar 1 LILO of Siliguri (Existing) – Purnea 400kV D/c

line(quad) at new pooling station Kishanganj 12 1.8 22

2 LILO of Siliguri (Existing) – Purnea 400kV D/c line(on which reconductoring is being carried out) at Kishanganj with the higher capacity(INVAR) conductor

12 1.8 22

3 LILO of Siliguri – Dalkhola 220kV D/c line at new pooling station in northern part of West Bengal / Bihar

12 0.7 8

4 LILO of Gangtok-Melli 132kV S/c line upto Rangpo, where Chuzachen-Rangpo 132kV D/c would be connected so as to form Chuzachen-Gangtok and Chuzachen-Melli 132kV S/c lines.

10 0.55 6

5 New 400kV sub-station at Kishanganj 1 50 50 6 400/220kV, 315 MVA Transformer 2 10 20 7 Associated bays - line & reactors (400kV) 4 5 20 8 Associated bays - line & reactors (220kV) 4 2 8 9 Associated bays - line & reactors (132kV) 2 1.5 3 Sub-Total (Part-A) 158 Subtotal (Part-A with IDC & Centages) 185

Part-B : Transmission System for development of pooling substations within Sikkim and transfer of power to a new pooling station Kishanganj in northern Part of West Bengal/Bihar

1 LILO of Teesta III – Kishanganj 400kV D/c line at New Melli

4 1.8 7

2 Rangpo – New Melli 220kV D/c line (with twin Moose conductor)

22 0.7 10

3 LILO of Gangtok-Rangit 132kV S/c line at Rangpo and termination of Gangtok-Rangpo and Melli – Rangpo 132kV lines (constructed under part-A through LILO of Gangtok-Melli 132kV S/c line upto Rangpo) at Rangpo sub-station

8 0.35 3

4 LILO of Teesta V – Siliguri 400kV D/c line at New Melli

12 0.9 11

5 Kishanganj – Patna 400kV D/c (quad) line 351 1.8 632 6 Establishment of 220/132kV, 3x100MVA Gas

Insulated Substation at Rangpo 1 100 100

7 Establishment of 10x167MVA, 1 phase, 400/220kV Gas Insulated substation at New Melli

1 200 200

Sub-Total (Part-B) 963 Subtotal (Part-B with IDC & Centages) 1127 Total 1304

Page 24: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

SECTION – IV

Page 25: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 20 of 46

HIGH CAPACITY TRANSMISSION CORRIDOR – IV (Transmission System Associated with IPPs near Bilaspur complex in

Chhattisgarh & MP projects) 1.0 DESCRIPTION/OBJECTIVE AND JUSTIFICATION As per the Long-term Open Access applications received in WR, about 1400 MW capacity (2 nos. IPPs) is coming up near Bilaspur in the State of Chhattisgarh and about 3000 MW capacity (3 nos. IPPs) is coming up near Bina/Satna/Vindhyachal Complex in the State of Madhya Pradesh progressively in next 3-4 years. Keeping this in view, transmission system was evolved to evacuate and transfer of power from following IPP generation projects/applicants in the State of Chhattisgarh/MP: S. No.

Developer Date of Commissioning

Capacity (MW) LTOA Granted (MW)

Target Beneficiaries Allocation (MW)

IPP in Chhattisgarh WR NR 1. Maruti Clean Coal Jun’12 300(1x300) 300 222 78

2. PTC (Dheeru) Sep’12, Dec’12,

Mar’13

600(3x350) - part 600 300 300

3. Dheeru Power Gen Sep’12, Dec’12,

Mar’13

450(3x350) - part 450 367.5 82.5

IPPs in MP 1 Jaiprakash Power

Ventures Ltd.(Nigri) May’13, Nov’13 1320(2x660) 1320 908 412

2 Aryan Coal Benefications

Mar’13, Mar’14,

Dec’14, Mar’15

1200(4x300) 1200 900 300

3. Bina Power Supply Co. Ltd

Sep’11, Dec’11 500 (2x250) 290 145 145

Total 4370 4160 2842.5 1317.5

For projects in Bilaspur complex, dedicated connectivity to 400kV WR Pooling Station (Bilaspur) with generation projects is being considered. Further, for generation projects in Vindhyachal/Satna/Bina Complex, dedicated connectivity to 400kV POWERGRID substations in Vindhyachal-Satna-Bina corridor is being considered.

Power from these projects shall need to be transferred to Western Region as well as Northern Region. For transfer of power from WR Pooling Station(Bilaspur) onwards, high capacity transmission corridors viz. Seoni-Bina-Indore/Gwalior in Northern part of WR as well as Seoni-Wardha-Arunabagabd in Central part of WR are already being developed. Similarly, for transfer of power from Vindhyachal Complex, high capacity transmission corridors viz. Vindhyachal Pool-Satna-Bina/Gwalior is being established. For transfer of power from the above generation projects to NR, 2 (two) nos. high capacity transmission corridors viz. Gwalior-Agra and Gwalior - Jaipur shall effect power transfer requirement. However for transfer of power from these generation projects to WR, system strengthening is required beyond Indore in M.P for which a separate high capacity 765kV transmission corridor from Indore -

Page 26: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 21 of 46

Vadodra, a major load center in Gujarat, along with establishment of new 765/400 kV substation at Vadodra in Gujarat is proposed. 2.0 SCOPE OF WORK Scope of works under transmission System Strengthening associated with IPPs in Chhattisgarh & M.P is as under. Description of transmission system 1) Indore- Vadodra 765kV S/c 2) Vadodra – Pirana 400kV D/c (Quad) 3) Establishment of 765/400kV, 2x1500 MVA substation at Vadodra

The Schematic of the proposed transmission scheme is shown at Exhibit-1. 3.0 TENTATIVE ESTIMATED COST Broad Estimated Cost : Rs 1243 Cr Details of transmission element wise cost for POWERGRID scope of works is enclosed at Annexure-1. 4.0 TIME FRAME The above transmission system would be implemented in phased manner matching with the progress of the generation projects. Further wherever possible interim/temporary arrangement of transmission system for immediate evacuation shall be implemented to insure evacuation of power. 5.0 CONSENT OF BENEFICIARIES The transmission system for evacuation of power from the above generation projects as well as transfer of power to target beneficiaries in various regions was evolved through load flow studies carried out by considering various alternatives/options based on the transmission needs incident on the system because of these open access requirements. The studies for the evolution of transmission systems were discussed & finalized in consultation with CEA and generation developers and various state utilities as given below. It was agreed that the charges of the transmission system is to be borne by the generation developers till the time beneficiaries are firmed up and agree to bear its transmission charges. Accordingly, it was decided that POWERGRID shall go ahead for implementation of the transmission system based on the assurance of signing the BPTA (Bulk Power Transmission Agreement) by the project developers for sharing the transmission charges. Status of approval in this regard is given as under:

Page 27: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 22 of 46

Meeting West Long Term Access Meeting Date

11th LTOA Meet /10.09.09 / Ahmedabad Appendix-10

Standing Committee Meeting No./ Date

29th / 10.09.2009 / Ahmedabad Appendix-6

Regional Power Committee Meeting No./ Date

11th /25.09.09 / Raipur Appendix-11

Page 28: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 23 of 46

Annexure-1

HIGH CAPACITY TRANSMISSION CORRIDOR – IV

THE TRANSMISSION SYSTEM ASSOCIATED WITH IPPs NEAR BILASPUR COMPLEX IN CHHATTISGARH & IPPs M.P PROJECTS

Sl. No.

Elements Length (kms)/ Nos

Unit Cost (Rs. Crs)

Total tentative Cost

(Rs. Crs) 1 Indore(PG)- Vadodra 765kV S/c 310 1.7 527

2 Vadodra - Pirana(PG) 400kV D/c (Quad) 50 1.8 90

3 Establishment of 765/400kV S/s at Vadodra 1 100 100 4 765/400 kV Transformers 2 80 160 5 Associated bays-line & reactors (765kV) 5 13 65 6 Associated bays-line & reactors (400kV) 6 5 30 7 Reactors (Line/Bus) (765kV) 3 30 90 Sub Total 1062 Total with IDC and Centages 1243

Page 29: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

SECTION – V

Page 30: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 24 of 46

HIGH CAPACITY TRANSMISSION CORRIDOR – V (Transmission System Associated with Chhattisgarh IPP projects)

1.0 DESCRIPTION/OBJECTIVE AND JUSTIFICATION A number of IPPs (about 55 nos. with 58000 MW generation capacity) have proposed coal based generation projects in the State of Chhattisgarh which are mainly located near Raigarh and Champa-Janjgir area. Review of progress of IPPs projects in Chhattisgarh was made in various meetings, wherein it emerged that transmission system for transfer of power from the generation projects under advanced stage with commissioning schedule by the end of 11th Plan/early 12th plan may be considered for implementation progressively as Phase-1 transmission project. Keeping this in view, transmission system was evolved to evacuate and transfer of power from following IPP generation projects/applicants in the State of Chhattisgarh: S. no

Developer Comm. Schedule

Capacity (MW)

LTOA (MW)

Target Beneficiaries Quantum (MW)

RAIGARH COMPLEX

WR NR SR Total 1 RKM Powergen

Ltd.(4x360) Mar'11,Jun'11, Sep'11,Dec'11

1440 936 469 167 300 936

2 Athena Chhattisgarh Power Ltd.(2x600)

Mar'12, Aug'12

1200 780 535 245 780

3 Jindal Power Ltd.(4x600) Mar'12,Jul'12, Nov'12, Mar'13

2400 1560 1047 513 1560

4 Jindal Power Ltd.(2x250) Existing 500 500 500 500 5 SKS Ispat & Power

Ltd.(4x300) Nov'11,Dec'11,Mar'12, Mar'12

1200 780 520 260 780

6 Korba West Power Co. Ltd.(1x600)

Jul'12 600 390 390 390

7 DB Power Ltd.(2x600) Nov'11,Feb'12 1200 780 532 248 780 sub-total 8540 5726 3993 1433 300 5726

JANJGIR-CHAMPA COMPLEX

1 Wardha Power Co. Ltd (6x600)

Feb'12, Jun'12,Oct'12,Feb'13, Jun'13,Oct'13

3600 2340 2340 2340

2 BALCO(4x300) Jun'10, Sep'10, Dec'10, Mar'11

1200 585 293 292 585

3 Vandana Vidyut Ltd.(2x135+1x270)

Apr'11,Dec'11,Mar'12

540 351 286 65 351

4 Lanco Amarkantak Power Pvt. Ltd.(2x660)

Mar'12,Jun'12 1320 858 300 558 858

5 Chhattisgarh Steel & Power Ltd.(1x35+1x250)

Existing, Dec'11

285 185 130 55 185

Page 31: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 25 of 46

S. no

Developer Comm. Schedule

Capacity (MW)

LTOA (MW)

Target Beneficiaries Quantum (MW)

sub-total 6945 4319 3349 970 0 4319 1 Chhattisgarh State Power

Tr. Co. Ltd** 5140 3801 1339 5140

Total 15485 15185 11143 3742 300 15185

** Chhattisgarh Allocation @35% on a/c of First Right of Refusal As per review on the preparedness of generation projects, it is estimated that about 15,000MW capacity (12 IPPs) may come up in Chhattisgarh (in phase-1 development) progressively in next 3-4 years. Power from these projects need to be transferred to target regions as WR/NR. For evacuation and transfer of power from these different generation projects in Chhattisgarh to NR/WR, there is a need to evolve a composite high capacity transmission scheme in view of the Right-of-way problem, wherein different generation projects coming up in different time-frame could be integrated. However, considering the quantum of power transfer requirement as well as progressive commissioning of generation projects, the entire scheme is proposed for implementation in four nos. different stages. Considering that generation projects are proposed in clusters, it is prudent to pool the power from such clusters at suitable locations. Accordingly, three nos. of 765/400kV pooling substations have been planned namely at Raigarh(Near Kotra), Raigarh(Near Tamnar) and Champa. Power from various generation projects is proposed to be pooled at the above pooling stations through 400kV dedicated transmission lines.

In order to provide interconnections between pooling stations, high capacity 765kV lines are proposed. Towards this, pooling stations at Raigarh (Near Kotra) and Raigarh (Near Tanmar) would be interconnected through 765kV D/c line and Raigarh(Near Kotra) and Champa Pooling station through a 765kV S/c line. For onward transfer of power, it is proposed to further pool power from above pooling station through another pooling station at Raipur. Raigarh Pooling station (Near Kotra) would be connected to Raipur pooling station through 765kV D/c line, similarly Champa would also be connected to Raipur through 765kV D/c lines. However, keeping in view the initial power transfer requirement, above 765kV lines are proposed to be operated at 400kV. In addition to above AC corridors, two nos. high capacity HVDC corridors viz. Raigarh Pool(Near Kotra) to Dhule in WR as well as Champa Pool(WR) to Kurukshetra in NR is also proposed to effect transfer of power to the target regions.

For transfer of power beyond Raipur, a high capacity corridor between eastern and western part of WR namely Raipur-Wardha-Aurangabad 765kV D/c line is proposed which shall be operated at 400kV level initially. Beyond Aurangabad, power is proposed to be transferred through high capacity Aurangabad-Khargar 400 kV D/C (quad) lines. In order to facilitate charging of above pooling stations, 400kV interconnections between Raigarh Pooling Station(near Kotra) and Raigarh(existing) S/s as well as Raipur Pooling station and Raipur(existing) S/s is proposed. However,

Page 32: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 26 of 46

these interconnections shall be opened at a later date to avoid high loading on the underlying 400kV system.

2.0 SCOPE OF WORK Scope of works under transmission System Strengthening associated with IPPs in Chhattisgarh IPP (POWERGRID Scope as well as scope under tariff based competitive bidding) is as under.

Transmission System Strengthening (1) Common transmission system strengthening to be implemented by POWERGRID • Raigarh Pooling Station (Near Kotra) – Raipur Pooling Station 765kV D/c (Initially

to be operated at 400kV) • Champa Pooling Station – Dharamjaygarh Pooling Station 765kV S/c • Champa Pooling Station – Raipur Pooling Station 765kV D/c (Initially to be

operated at 400kV) • Raigarh Pooling Station(Near Kotra) – Champa Pooling Station 765kV S/c • Raigarh Pooling Station (Near Tamnar) – Raigarh Pooling Station(near Kotra)

765kV D/c (Initially to be operated at 400kV) • Raigarh Pooling Station(Near Kotra) – Raigarh(PG) 400kV D/c(to be opened at

later date) • Raipur Pooling Station – Raipur (PG)400kV D/c (to be opened at later date) • Raipur Pooling Station – Wardha 765kV 2xD/c (Initially 1st D/c line to be operated

at 400kV) • Wardha – Aurangabad (PG) 765kV 2xD/c (Initially 1st D/c line to be operated at

400kV) • Aurangabad(PG) – Padghe(PG) 765kV D/c • Aurangabad(PG) – Khargar(MSTECL) 400kV D/c(Quad) • Padghe(PG)- Padghe(MSTECL) 400kV D/c(Quad) • ±600kV, 4000MW HVDC bipole between Raigarh Pooling Station(Near Kotra) –

Dhule(PG) • Vadodara – Asoj(GETCO) 400kV D/c(Quad) • ±800kV, 3000MW HVDC bipole between Champa Pooling Station

Kurukshehtra(NR) with provision to upgrade to 6000MW at a later date • Dhule(PG) – Dhule(New) 400kV 2xD/c(Quad) • Establishment of 765/400kV 4x1500MVA Raigarh Pooling Station(near Kotra)

(the Pooling station shall be initially at 400kV and later upgraded to 765kV with indicated transformation capacity)

• Establishment of 765/400kV Raigarh Pooling Station(near Tamnar) (the Pooling station shall be initially at 400kV and later upgraded to 765kV level)

• Establishment of 765/400kV 3x1500MVA Champa Pooling Station(the Pooling station shall be initially at 400kV and later upgraded to 765kV with indicated transformation capacity)

• Establishment of 765/400kV 1x1500MVA Raipur Pooling Station(the Pooling station shall be initially at 400kV and later upgraded to 765kV with indicated transformation capacity)

Page 33: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 27 of 46

• Establishment of 4000MW 600KV HVDC bipole terminal each at Raigarh Pooling station(near Kotra) and Dhule(PG) respectively.

• Establishment of 3000MW 800KV HVDC bipole terminal each at Champa Pooling station and Kurukshetra(NR) respectively (provision to upgrade the terminals at 6000MW at a later date).

• Establishment of 765/400kV 2x1500MVA Padghe(PG) S/s • Establishment of 765/400kV 2x1500MVA Aurangabad(PG) S/s • Strengthening in Northern region

Kurukshetra(NR) - Jallandhar 400kV D/c(Quad) one ckt. via 400/220kV Nakodar S/s

LILO of Abdullapur – Sonepat 400kV D/c(triple) at Kurukshetra Establishment of 400/220kV 2x500 MVA S/s at Kurukshetra

(2) Common transmission system strengthening under tariff based

competitive bidding • Aurangabad(PG) – Dhule (New) 765kV S/c • Dhule (New) – Vadodara 765kV S/c • Establishment of 765/400kV, 2x1500MVA Dhule(New) S/s • Dhule (New)-Dhule (MSETCL) 400kV D/c (Quad) • Dhule(New) – Malegaon (MSETCL) 400kV D/c(Quad) • Dhule(New) – Nasik(MSETCL) 400kV D/c(Quad) 3.0 TENTATIVE ESTIMATED COST Broad Estimated Cost of Tr. System under scope POWERGRID : Rs 28,824 Crore Details of transmission element wise cost for POWERGRID scope of works is enclosed at Annexure-1.

4.0 TIME FRAME The above transmission system would be implemented in phased manner matching with the progress of the generation projects. Further wherever possible interim/temporary arrangement of transmission system for immediate evacuation shall be implemented to insure evacuation of power. 5.0 CONSENT OF BENEFICIARIES The transmission system for evacuation of power from the above generation projects as well as transfer of power to target beneficiaries in various regions was evolved through load flow studies carried out by considering various alternatives/options based on the transmission needs incident on the system because of these open access requirements. The studies for the evolution of transmission systems were discussed & finalized in consultation with CEA and generation developers and various state utilities as given below. It was agreed that the charges of the transmission system is to be borne by the generation developers till the time beneficiaries are firmed up and agree to bear its transmission charges. Accordingly, it was decided that POWERGRID shall go ahead for implementation of the

Page 34: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 28 of 46

transmission system based on the assurance of signing the BPTA (Bulk Power Transmission Agreement) by the project developers for sharing the transmission charges.

Meeting West North Long Term Access Meeting Date

11th LTOA/ 10.09.09 / Ahmedabad Appendix-10

Standing Committee Meeting No./ Date

29th / 10.09.2009 / Ahmedabad Appendix-6

27th SCM 30-05-2009 (Nainital) Appendix-3

Regional Power Committee Meeting No./ Date

11th WRPC/ 25.09.09 / Raipur Appendix-11

-

Page 35: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 29 of 46

Annexure-1

HIGH CAPACITY TRANSMISSION CORRIDOR – V

THE TRANSMISSION ASSOCIATED WITH CHHATTISGARH IPP PROJECTS

Sl. No.

Elements Length (kms)/ Nos

Unit Cost (Rs. Crs/km)

Total tentative Cost (Rs. Crs)

1 Raigarh Pooling Station (Near Kotra) – Raipur Pooling Station 765kV D/c (Initially to be operated at 400kV)

250 2.8 700

2 Champa Pooling Station – Dharamjaygarh Pooling Station 765kV S/c

85 1.7 144.5

3 Champa Pooling Station – Raipur Pooling Station 765kV D/c (Initially to be operated at 400kV)

150 2.8 420

4 Raigarh Pooling Station(Near Kotra) – Champa Pooling Station 765kV S/c

90 1.7 153

5 Raigarh Pooling Station (Near Tamnar) – Raigarh Pooling Station(near Kotra) 765kV D/c (Initially to be operated at 400kV)

50 2.8 140

6 Raigarh Pooling Station(Near Kotra) – Raigarh(PG) 400kV D/c(to be opened at later date)

6 1 6

7 Raipur Pooling Station – Raipur (PG)400kV D/c (to be opened at later date)

30 1 30

8 Raipur Pooling Station – Wardha 765kV 2xD/c (Initially 1st D/c line to be operated at 400kV)

740 2.8 2072

9 Wardha – Aurangabad (PG) 765kV 2xD/c (Initially 1st

D/c line to be operated at 400kV) 700 2.8 1960

10 Aurangabad(PG) – Padghe(PG) 765kV D/c 260 2.8 728 11 Aurangabad(PG) – Khargar(MSTECL) 400kV

D/c(Quad) 317 1.8 570.6

12 Padghe(PG)- Padghe(MSTECL) 400kV D/c(Quad) 40 1.8 72 13 ±600kV, 4000MW HVDC bipole between Raigarh

Pooling Station(Near Kotra) – Dhule(PG) 1000 2.5 2500

14 Vadodara – Asoj(GETCO) 400kV D/c(Quad) 40 1.8 72 15 ±800kV, 3000MW HVDC bipole between Champa

Pooling Station Kurukshehtra(NR) with provision to upgrade to 6000MW at a later date

1200 3 3600

16 Dhule(PG) – Dhule(New) 400kV 2xD/c(Quad) 80 1.8 144 17 Establishment of 765/400kV 4x1500MVA Raigarh

Pooling Station(near Kotra) (the Pooling station shall be initially at 400kV and later upgraded to 765kV with indicated transformation capacity)

1 100 100

18 Establishment of 765/400kV Raigarh Pooling Station(near Tamnar) (the Pooling station shall be initially at 400kV and later upgraded to 765kV level)

1 100 100

Page 36: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 30 of 46

Sl. No.

Elements Length (kms)/ Nos

Unit Cost (Rs. Crs/km)

Total tentative Cost (Rs. Crs)

19 Establishment of 765/400kV 3x1500MVA Champa Pooling Station(the Pooling station shall be initially at 400kV and later upgraded to 765kV with indicated transformation capacity)

1 100 100

20 Establishment of 765/400kV 1x1500MVA Raipur Pooling Station(the Pooling station shall be initially at 400kV and later upgraded to 765kV with indicated transformation capacity)

1 100 100

21 Establishment of 4000MW 600KV HVDC bipole terminal each at Raigarh Pooling station(near Kotra) and Dhule(PG) respectively

1 4400 4400

22 Establishment of 3000MW 800KV HVDC bipole terminal each at Champa Pooling station and Kurukshetra(NR) respectively (provision to upgrade the terminals at 6000MW at a later date)

1 3300 3300

23 Establishment of 765/400kV 2x1500MVA Padghe(PG) [GIS] S/s

1 100 100

24 Establishment of 765/400kV 2x1500MVA Aurangabad(PG) S/s

1 100 100

Strengthening in northern region Kurukshetra(NR) - Jallandhar 400kV D/c(Quad)

one ckt. via 400/220kV Nakodar S/s 150 1.8 270

LILO of Abdullapur – Sonepat 400kV D/c(triple) at Kurukshetra

40 1.5 60

25

Establishment of 400/220kV 2x500 MVA S/s at Kurukshetra

1 50 50

26 765/400 kV Transformers 12 80 960 27 400/220 kV Transformers 2 10 20 28 Associated bays-line & reactors (765kV) 55 13 715 29 Associated bays-line & reactors (400kV) 78 5 390 30 Associated bays-line (220kV) 2 2 4 31 Reactors (Line/Bus) (765kV) 16 30 480 32 Reactors (Line/Bus) (400kV) 15 5 75 Sub Total 24636 Total with IDC and Centages 28824

Page 37: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

SECTION – VI

Page 38: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 31 of 46

HIGH CAPACITY TRANSMISSION CORRIDOR – VI (Transmision System Associated with IPPs in Krishnapatnam Area, Andhra

Pradesh) 1.0 DESCRIPTION/OBJECTIVE AND JUSTIFICATION

This transmission corridor has been evolved to evacuate power from the proposed IPP generation projects in the Krishnapatnam area of Andhra Pradesh. In the Krishnapatnam area, LTOA has been granted to 4 nos. of applicants as per the details given below:

Target Beneficiaries (MW)

Sl. No.

Generation Developer

Date of Commissioning

Installed Capacity (MW)

LTOA Applied(MW) SR WR NR

1 Simhapuri Energy Private Limited (SEPL)

August, 2010 540 491 311 135 0

2 Meenakshi Energy Private Limited (MEPL)

September, 2010 600 546 186 177 183

3 Andhra Pradesh Power Development Company Limited (APPDCL)

June, 2012 1600 175 0 0 175

4 Krishnapatnam Power Corporation Limited (KPCL)

December, 2012 1860 1860 360 600 900

Total 4600 3072 857 912 1258 From the above it may be seen that besides SR substantial quantum of power for which long term open access has been sought involves transfer of power to constituents of WR and NR. Therefore, the transmission system required for facilitating long term open access shall include; (i) strengthening of the system in Southern region to facilitate immediate evacuation as well as further dispersal of power in SR grid and (ii) strengthening of WR and NR grids including inter-regional links for transmission of power to the target beneficiaries. The present corridor covers the requirement (i) as mentioned above, the requirement (II) has been covered in the separate corridor - IX. The generation projects under Long-Term Open Access in Krishnapatnam area, as mentioned above in the table are proposed to be materialized in two different time frames i.e. 2010-11 & 2012-13. Further major portion of power from these generation projects are allocated outside Southern region and is to be to be exported to power deficit regions like NR & WR. Apart from above, Krishnapatnam UMPP 4000 MW has been proposed in the same vicinity which is likely to be commissioned in 2013-15 time frame. The transmission system associated with Krishnapatnam UMPP has already been finalized under which two transmission corridors viz. Kurnool and Gooty have been envisaged. Therefore a composite high capacity transmission system was evolved for the LTOA generations corresponding 2012-13 time frame when all the projects in the vicinity shall be available. Further the transmission system has been verified for its

Page 39: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 32 of 46

suitability for the 2013-15 time frame when Krishnapatnam UMPP and its transmission system is likely to be available. Accordingly, phasing of transmission system is made to evolve the minimum transmission system that should be available in the intermediate time frame of 2010-11 for meeting the evacuation requirement of Simhapuri and Meenakshi projects which is to be implemented by the project developers. For evacuation and transfer of power from the above generation projects in Andhra Pradesh to NR/WR, following composite high capacity transmission scheme in view of the Right-of-way problem have been evolved, wherein different generation projects coming up in Andhra Pradesh & Tamil Nadu in different time-frame could also be integrated. As mentioned above composite high capacity transmission scheme was evolved for the generation project developer in Krishnapatnam area, Andhra Pradesh. In order to pool power from above generation projects in Andhra Pradesh, a 765/400 kV pooling substation has been planned at Nellore. The Nellore Pooling station would be interconnected by LILO of both circuits of 400 kV D/c (quad) SEPL - Nellore line. For transfer of power from Nellore to constituents of Southern Region, 765 kV AC corridor has been planned to Kurnool/Raichur. For transferring power to NR and WR, inter-regional transmission system has been planned alongwith other generation projects of Southern Region having share in Northern & Western Regions.

2.0 SCOPE OF WORK

The transmission system covered under this corridor shall include the following elements a. Establishment of 765/400 kV, 2x1500 MVA pooling station at Nellore by LILO of

Simhapuri-Nellore 400 kV D/c quad line b. Nellore Pooling station – Kurnool 765 kV 2xS/c line c. Kurnool – Raichur 2nd 765 kV S/c line d. Associated 765 kV & 400 kV bays at Nellore Pooling station, Kurnool and Raichur

stations.

The Schematic of the proposed transmission scheme is shown at Exhibit-1. 3.0 TENTATIVE ESTIMATED COST Estimated Cost of above transmission system : about Rs 2065 Crs Details of transmission element wise cost for POWERGRID scope of works is enclosed at Annexure-1.

4.0 TIME FRAME The above transmission system would be implemented in phased manner matching with the progress of the generation projects. Further wherever possible interim/temporary arrangement of transmission system for immediate evacuation shall be implemented to insure evacuation of power.

Page 40: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 33 of 46

5.0 CONSENT OF BENEFICIARIES The transmission system for evacuation of power from the above generation projects as well as transfer of power to target beneficiaries in various regions was evolved through load flow studies carried out by considering various alternatives/options based on the transmission needs incident on the system because of these open access requirements. The studies for the evolution of transmission systems were discussed & finalized in consultation with CEA and generation developers and various state utilities as given below. It was agreed that the charges of the transmission system is to be borne by the generation developers till the time beneficiaries are firmed up and agree to bear its transmission charges. Accordingly, it was decided that POWERGRID shall go ahead for implementation of the transmission system based on the assurance of signing the BPTA (Bulk Power Transmission Agreement) by the project developers for sharing the transmission charges.

Meeting North West South Long Term Access Meeting Date

13.06.2008 / Hyderabad Appendix-12

Standing Committee Meeting No./ Date

27th SCM 30-05-2009 (Nainital) Appendix-3

29th / 10.09.2009 / Ahmedabad Appendix-6

26th / 13.06.2008 / Hyderabad Appendix-13

Regional Power Committee Meeting No./ Date

- 11th WRPC/ 25.09.09 / Raipur Appendix-11

11th / 17.09.2009 / Bangalore Appendix-14

Page 41: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 34 of 46

Annexure-1

HIGH CAPACITY TRANSMISSION CORRIDOR – VI

THE TRANSMISION SYSTEM ASSOCIATED WITH KRISHNAPATNAM AREA IPP PROJECTS

Sl. No.

Elements Length (kms)/ Nos

Unit Cost (Rs. Crs)

Total tentative Cost (Rs. Crs)

1 LILO of Simhapuri-Nellore 400 kV D/c quad line at Nellore Pooling Station

10 1.8 18

2 Nellore Pooling station – Kurnool 765 kV 2xS/c line 300 1.7 1020 3 Kurnool – Raichur 2nd 765 kV S/c line 100 1.7 170 4 Establishment of 765/400 kV pooling station at

Nellore 1 100 100

5 765/400 kV Transformers 2 80 160 6 Associated bays-line, & reactors (765kV) 9 13 117 7 Associated bays-line, & reactors (400kV) 6 5 30 8 Reactors (Line/Bus) (765kV) 5 30 150 Total 1765 Total with IDC and Centages 2065

Page 42: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

SECTION – VII

Page 43: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 35 of 46

HIGH CAPACITY TRANSMISSION CORRIDOR – VII (Transmission System Associated with IPP projects in Tuticorin Area, Tamil

Nadu)

1.0 DESCRIPTION/OBJECTIVE AND JUSTIFICATION This transmission corridor has been evolved to evacuate power from the proposed IPP generation projects in the Tuticorin area. In the Tuticorin area, LTOA has been granted to 2 nos of applicants as per the details given below:

Target Beneficiaries (MW)

Sl. No.

Generation Developer Date of Commissioning

Installed Capacity

(MW)

LTOA Applied

(MW) SR WR NR 1 Coastal Energen

Private Limited (CEPL) December, 2011 1200 1100 820 280 0

2 Ind-Barath Power (Madras) Limited (IBPML)

December, 2011 1400 945 284 236 425

Total 2600 2045 1104 516 425 From the above it may be seen that besides SR substantial quantum of power for which long term open access has been sought involves transfer of power to constituents of WR and NR. Therefore, the transmission system required for facilitating long term open access shall include; (i) strengthening of the system in Southern region to facilitate immediate evacuation as well as further dispersal of power in SR grid and (ii) strengthening of WR and NR grids including inter-regional links for transmission of power to the target beneficiaries. The present corridor covers the requirement (i) as mentioned above, the requirement (II) has been covered in the separate corridor – IX. In the Tuticorin area, apart from the two IPP generation projects mentioned above another generation project under central sector viz. Tuticorin JV TPS (2x500 MW) is under implementation which is likely to be commissioned by February 2012. The transmission system comprising of Tutiocorin – Madurai 400 kV (Quad) D/c line associated with Tuticorin JV has already been finalized and is under implementation. Further, Nuclear Power Corporation of India Ltd. have indicated expansion of their under construction Kudankulam APP (2x1000 MW) by 4 more units of 1000 MW each. Therefore it would be prudent that the transmission corridor constructed from Tuticorin area northwards should be 765 kV to accommodate future requirement. Accordingly composite high capacity transmission corridor is required to be evolved looking into the Right-of-way problems for immediate evacuation as well as for supply of power to target beneficiaries. Keeping above in view, establishment of pooling station has been envisaged at Tuticorin where power from the IPPs project shall be pooled through dedicated transmission lines from their respective switchyard at their own cost. The power so pooled at Tuticorin shall be transmitted upto Madhugiri near Bangalore through high capacity 765 kV transmission lines (initially operated at 400 kV level) via intermediate 765 kV station at Salem. These lines shall be operated at rated 765 kV

Page 44: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 36 of 46

level alongwith the Kudankulam Stage-II or any other large capacity generation project materializing in the same vicinity. 2.0 SCOPE OF WORK The transmission system covered under this corridor shall include the following elements

a. Establishment of 765 kV pooling station in Tuticorin and Salem (initially charged

at 400 kV) b. LILO of both circuits of Tuticorin JV – Madurai 400 kV D/c (quad) line at Tuticorin

Pooling Station c. Tuticorin Pooling station – Salem Pooling station 765 kV D/c line initially charged

at 400 kV. d. Interconnection of Salem pooling station with existing Salem 400/230 kV

substation through 400 kV D/c (quad) line. e. Salem pooling station – Madhugiri pooling station 765 kV S/c initially charged at

400 kV.

The Schematic of the proposed transmission scheme is shown at Exhibit-1. 3.0 TENTATIVE ESTIMATED COST Estimated Cost of above transmission system : about Rs 2357 Crs Details of transmission element wise cost for POWERGRID scope of works is enclosed at Annexure-1. 4.0 TIME FRAME The above transmission system would be implemented in phased manner matching with the progress of the generation projects. Further wherever possible interim/temporary arrangement of transmission system for immediate evacuation shall be implemented to insure evacuation of power. 5.0 CONSENT OF BENEFICIARIES The transmission system for evacuation of power from the above generation projects as well as transfer of power to target beneficiaries in various regions was evolved through load flow studies carried out by considering various alternatives/options based on the transmission needs incident on the system because of these open access requirements. The studies for the evolution of transmission systems were discussed & finalized in consultation with CEA and generation developers and various state utilities as given below. It was agreed that the charges of the transmission system is to be borne by the generation developers till the time beneficiaries are firmed up and agree to bear its transmission charges. Accordingly, it was decided that POWERGRID shall go ahead for implementation of the transmission system based on the assurance of signing the BPTA (Bulk Power Transmission Agreement) by the project developers for sharing the transmission charges.

Page 45: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 37 of 46

Meeting North West South Long Term Access Meeting Date

27.08.2009 / Hyderabad Appendix-15

Standing Committee Meeting No./ Date

To be discussed in next meeting

29th / 10.09.2009 / Ahmedabad Appendix-6

29th / 27.08.2009 / Hyderabad Appendix-16

Regional Power Committee Meeting No./ Date

- 11th WRPC/ 25.09.09 / Raipur Appendix-11

11th / 17.09.2009 / Bangalore Appendix-14

Page 46: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 38 of 46

Annexure-1

HIGH CAPACITY TRANSMISSION CORRIDOR – VII

THE TRANSMISSION SYSTEM ASSOCIATED WITH TUTICORIN AREA IPP PROJECTS

Sl. No.

Elements Length (kms)/ Nos

Unit Cost (Rs. Crs)

Total tentative Cost (Rs.

Crs) 1 LILO of both circuits of Tuticorin JV – Madurai 400

kV D/c (quad) line at Tuticorin Pooling Station 80 1.8 144

2 Tuticorin Pooling station – Salem Pooling station 765 kV D/c line (initially charged at 400 kV)

325 2.8 910

3 Interconnection of Salem pooling station with existing Salem 400/230 kV substation through 400 kV D/c (quad) line.

60 1.8 108

4 Salem pooling station – Madhugiri pooling station 765 kV S/c (initially charged at 400 kV)

325 1.7 552.5

5 Establishment of 765 kV pooling stations at Tuticorin & Salem.

2 100 200

6 Associated bays-line, & reactors (400kV) 14 5 70 7 Reactors (Line/Bus) (400kV) 6 5 30 Sub-total 2015 Total with IDC and Centages 2357

Page 47: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

SECTION – VIII

Page 48: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 39 of 46

HIGH CAPACITY TRANSMISSION CORRIDOR – VIII (Transmission System Associated with IPP projects in Srikakulam Area,

Andhra Pradesh) 1.0 DESCRIPTION/OBJECTIVE AND JUSTIFICATION

This transmission corridor has been evolved to evacuate power from the proposed IPP generation projects in the Srikakulam area of Andhra Pradesh. In the Srikakulam area, LTOA has been granted to 2 nos. of applicants as per the details given below:

Target Beneficiaries (MW)Sl. No.

Generation Developer

Date of Commissioning

Installed Capacity

(MW)

LTOA Applied

(MW) SR WR NR

1 East Coast Energy Private Limited (ECEPL)

March, 2012 2640 2440 1940 500 0

2 NCC Power Projects Limited (NCC)

December, 2011 1320 1320 500 500 320

Total 3960 3760 2440 1000 320 The above generation projects are located at the Orissa border in Eastern region and close to the routing of 400 kV D/c line from Behrampur to Gazuwaka in Eastern Region which it to be implemented under Private Sector. These generation projects shall further increase the surplus power of Southern region which to be transferred to WR/NR, therefore, these projects shall be synchronized to Eastern Region for onwards dispersal of power to WR/NR. It may be seen from the above table that Southern Region has share of about 2440 MW and balance power is for Western and Northern regions. The transmission system required for facilitating long term open access shall include; (i) strengthening of the system in Southern region to facilitate immediate evacuation as well as further dispersal of power in SR grid and (ii) strengthening of WR and NR grids including inter-regional links for transmission of power to the target beneficiaries. The present corridor covers the requirement (i) as mentioned above, the requirement (II) has been covered in the separate corridor – IX. The generation projects under Long-Term Open Access in Srikakulam area, as mentioned above in the table are proposed to be materialized in same time frame i.e by end of 12th plan (2011-12). In this time frame Southern region is in surplus and this shall further enhance the surplus power. Out of this surplus power about 5000MW is allocated as target beneficiaries outside SR and is to be exported to power deficit regions like NR & WR. However large number of IPP projects envisaged in Southern region with allocation to WR and NR, the power flow requirement from the East Coast project to SR shall not be there and share of SR from their project shall be displaced by the share of WR/NR in other IPP project located in southern part of SR. Therefore a composite high capacity transmission system was evolved for the LTOA generations corresponding 2011-12 time frame when both the above projects in the

Page 49: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 40 of 46

vicinity shall be available. Further phasing of the transmission system has been done for implementation purpose in such a way that evacuation of power of the generation project shall be independent on the materialization of other generation project. As mentioned above composite high capacity transmission scheme was evolved for the generation project developer in Srikakulam area, Andhra Pradesh towards Angul pooling station. Further for transfer of power beyond Angul pooling station to wards NR a high capacity corridor Angul – Jharsuguda – Dharamjaigarh 765kV D/c line has been planned. 2.0 SCOPE OF WORK The transmission system covered under this corridor shall include the following elements

a. Establishment of 765/400 kV 2x1500MVA at East Coast TPS b. Establishment of 765/400 kV 1x1500MVA at NCC TPS c. East Coast TPS – Angul 765 kV D/c (one circuit via NCC TPS) d. Angul – Jharsuguda 765 kV D/c line e. Jharsuguda – Dharamjaigarh 765 kV D/c line

The Schematic of the proposed transmission scheme is shown at Exhibit-1. 3.0 TENTATIVE ESTIMATED COST Estimated Cost of above transmission system : about Rs. 2986 Crs Details of transmission element wise cost for POWERGRID scope of works is enclosed at Annexure-1. 4.0 TIME FRAME The above transmission system would be implemented in phased manner matching with the progress of the generation projects. Further wherever possible interim/temporary arrangement of transmission system for immediate evacuation shall be implemented to insure evacuation of power. 5.0 CONSENT OF BENEFICIARIES The transmission system for evacuation of power from the above generation projects as well as transfer of power to target beneficiaries in various regions was evolved through load flow studies carried out by considering various alternatives/options based on the transmission needs incident on the system because of these open access requirements. The studies for the evolution of transmission systems were discussed & finalized in consultation with CEA and generation developers and various state utilities as given below. It was agreed that the charges of the transmission system is to be borne by the generation developers till the time beneficiaries are firmed up and agree to bear its transmission charges. Accordingly, it was decided that POWERGRID shall go ahead for implementation of the

Page 50: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 41 of 46

transmission system based on the assurance of signing the BPTA (Bulk Power Transmission Agreement) by the project developers for sharing the transmission charges.

Meeting North West South Long Term Access Meeting Date

- - 27.08.2009 / Hyderabad Appendix-15

Standing Committee Meeting No./ Date

To be discussed in the next meeting

29th / 10.09.2009 / Ahmedabad Appendix-6

29th / 27.08.2009 / Hyderabad Appendix-16

Regional Power Committee Meeting No./ Date

- 11th WRPC/ 25.09.09 / Raipur Appendix-11

11th / 17.09.2009 / Bangalore Appendix-14

Page 51: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 42 of 46

Annexure-1

HIGH CAPACITY TRANSMISSION CORRIDOR – VIII

THE TRANSMISSION SYSTEM ASSOCIATED WITH SRIKAKULAM AREA IPP PROJECTS

Sl. No.

Elements Length (kms) / Nos

Unit Cost (Rs. Crs)

Total tentative Cost (Rs. Crs)

1 East Coast TPS – Angul 765 kV D/c (one circuit via NCC TPS)

340 2.8 952

2 Angul – Jharsuguda 765 kV D/c line 180 2.8 504 3 Jharsuguda – Dharamjaigarh 765 kV D/c line 125 2.8 350 4 Establishment of 765/400 kV at NCC TPS 1 100 100 5 Establishment of 765/400 kV at East Coast TPS 1 100 100 6 765/400 kV Transformers 3 80 240 7 Reactors (Line/Bus) (765kV) 4 30 120 8 Associated bays-line, & reactors (765kV) 12 13 156 9 Associated bays-line, & reactors (400kV) 6 5 30 Total 2552 Total with IDC and Centages 2986

Page 52: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

SECTION – IX

Page 53: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 43 of 46

HIGH CAPACITY TRANSMISSION CORRIDOR – IX (Transmission System Associated with IPP projects in Southern Region, for

transfer of power to other regions) 1.0 DESCRIPTION/OBJECTIVE AND JUSTIFICATION

This transmission corridor has been evolved to supply allocated power to constituents of WR & NR from the proposed IPP generation projects in Southern region which includes LTOA applications in Krishnapatnam, Tuticorin and Srikakulam area. In these areas, LTOA has been granted to 9 nos. of applicants as per the details given below:

Target Beneficiaries (MW)

Sl. No.

Generation Developer

Date of Commissioning

Installed Capacity

(MW)

LTOA Applied

(MW) SR WR NR 1 Lanco Kondapalli

Power Private Ltd. June, 2009 366 350 0 200 150

2 Simhapuri Energy Private Limited (SEPL)

August, 2010 540 491 311 135 0

3 Meenakshi Energy Private Limited (MEPL)

September, 2010 600 546 186 177 183

4 Andhra Pradesh Power Development Company Limited (APPDCL)

June, 2012 1600 175 0 0 175

5 Krishnapatnam Power Corporation Limited (KPCL)

December, 2012 1860 1860 360 600 900

6 Coastal Energen Private Limited (CEPL)

December, 2011 1200 1100 820 280 0

7 Ind-Barath Power (Madras) Limited (IBPML)

December, 2011 1400 945 284 236 425

8 East Coast Energy Private Limited (ECEPL)

March, 2012 2640 2440 1940 500 0

9 NCC Power Projects Limited (NCC)

December, 2011 1320 1320 500 500 320

Total 11526 9227 4401 2628 2153 The above power projects are based on coastal sites located on Eastern cost of Southern region spread out starting from Andhra Pradesh to Tamil Nadu. These coastal sites are suitable for establishment of imported coal based power projects, therefore, in addition to above generation projects we are observing overwhelming response from private developers for setting up power projects.

Keeping all the IPP generation projects in Southern region which has been granted / shortly to be granted Long Term Open Access, it is seen that during 2012-15 and beyond SR shall be having surplus power of the order of 16,500-18,000 MW during

Page 54: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 44 of 46

peak conditions and about 28,000 MW during off-peak conditions. Here, it is to be mentioned that above surplus includes 14,000 MW of firm power allocated to beneficiaries outside SR. Further this allocation shall increase as some of the IPP generation projects have not indicated their target beneficiaries. Therefore, inter-regional capacity of the order of 16,000-18,000 MW atleast shall be required for catering to the system requirement.

Further the generation additions in SR during 12th plan period under central sector is yet to be finalized which shall further increase the surplus power and SR shall continue to be huge surplus of power. Therefore, the transmission system required for facilitating long term open access shall include; (i) strengthening of the system in Southern region to facilitate immediate evacuation as well as further dispersal of power in SR grid and (ii) strengthening of WR and NR grids including inter-regional links for transmission of power to the target beneficiaries.

The present corridor covers the requirement (ii) as mentioned above, the requirement (i) has been covered in the separate corridor for respective areas. Therefore a composite high capacity transmission system was evolved for the LTOA generations corresponding to 2012-13 time frames when all the generation projects in Southern region which has been granted LTOA shall be available. Further the transmission system has been verified for its suitability for the 2013-15 time frame when Krishnapatnam UMPP and its transmission system is likely to be available. As mentioned above composite high capacity transmission scheme was evolved for the generation project developer in Southern region to facilitate transfer of power to Western region and beyond towards Northern region. 2.0 SCOPE OF WORK The transmission system covered under this corridor shall include the following elements.

a. Sholapur – Pune 765 kV 2nd S/c (1st circuit already covered under transmission

associated with Krishnapatnam UMPP). b. Establishment of 2x1000MVA 765/400 kV station at Orai by LILO of one circuit of

Satna – Gwalior 765 kV line. c. Establishment of 2x1500MVA 765/400 kV station at Bulandshahar by LILO of

Agra – Meerut 765 kV line. d. Establishment of 2x1500MVA 765/400 kV station at Sonipat by LILO of Bhiwani –

Meerut 765 kV line. e. Jabalpur Pooling station – Orai 765 kV S/c line. f. Orai – Bulandshahar – Sonipat 765 kV S/c line. g. Orai-Orai (UPPCL) 400kV D/c Quad – 20 km h. Sonipat-Kurushetra 400kV D/c (Quad)- 120 km i. Sonipat (New) - Sonipat (Under Construction) 400kV D/c (Quad )– 20 km j. Bulandshahr - Hapur (UPPCL) 400kV D/c (Quad) - 40 km

The Schematic of the proposed transmission scheme is shown at Exhibit-1.

Page 55: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 45 of 46

3.0 TENTATIVE ESTIMATED COST Estimated Cost of above transmission system : about Rs 4821 Crs Details of transmission element wise cost for POWERGRID scope of works is enclosed at Annexure-I. 4.0 TIME FRAME The above transmission system would be implemented in phased manner matching with the progress of the generation projects. Further wherever possible interim/temporary arrangement of transmission system for immediate evacuation shall be implemented to insure evacuation of power. 5.0 CONSENT OF BENEFICIARIES The transmission system for evacuation of power from the above generation projects as well as transfer of power to target beneficiaries in various regions was evolved through load flow studies carried out by considering various alternatives/options based on the transmission needs incident on the system because of these open access requirements. The studies for the evolution of transmission systems were discussed & finalized in consultation with CEA and generation developers and various state utilities as given below. It was agreed that the charges of the transmission system is to be borne by the generation developers till the time beneficiaries are firmed up and agree to bear its transmission charges. Accordingly, it was decided that POWERGRID shall go ahead for implementation of the transmission system based on the assurance of signing the BPTA (Bulk Power Transmission Agreement) by the project developers for sharing the transmission charges.

Meeting North West South Long Term Access Meeting Date/ Place

27.08.2009 / Hyderabad Appendix-15

Standing Committee Meeting No./ Date/ Place

To be discussed in next meeting

29th / 10.09.2009 / Ahmedabad Appendix-6

29th / 27.08.2009 / Hyderabad Appendix-16

Regional Power Committee Meeting No./ Date/ Place

- 11th / 25.09.09 / Raipur Appendix-11

11th / 17.09.2009 / Bangalore Appendix-14

Page 56: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

High Capacity Power Transmission Corridor

Page 46 of 46

Annexure-1

HIGH CAPACITY TRANSMISSION CORRIDOR – IX

THE TRANSMISSION SYSTEM ASSOCIATED WITH SOUTHERN REGION IPP PROJECTS

Sl. No.

Elements Length (kms)/ Nos

Unit Cost (Rs. Crs)

Total tentative Cost (Rs.

Crs) 1 Sholapur – Pune 765 kV S/c line (1st already

covered under transmission associated with Krishnapatnam UMPP)

265 1.7 450.5

2 Jabalpur Pooling station – Orai 765 kV S/c line 350 1.7 595 3 Orai – Bulandshahar – Sonipat 765 kV S/c line 500 1.7 850 4 LILO of one circuit of Satna – Gwalior 765 kV line

at Orai 40 2.8 112

5 LILO of Agra – Meerut 765 kV line at Bulandshahar 40 2.8 112 6 LILO of Bhiwani – Meerut 765 kV line at Sonepat 40 2.8 112 7 Establishment of 765 kV station at Orai 1 100 100 8 Establishment of 765 kV station at Buland shahar 1 100 100 9 Establishment of 765 kV station at Sonepat 1 100 100

10 Orai-Orai (UPPCL) 400kV D/c Quad 20 1.8 36 11 Sonipat-Kurushetra 400kV D/c (Quad) line 120 1.8 216 12 Sonipat (New)- Sonipat (Under Construction)

400kV D/c (Quad ) line 20 1.8 36

13 Bulnadshahr- Hapur (UPPCL) 400kV D/c (Quad) line

40 1.8 72

14 765/400 kV Transformers 6 80 480 15 Reactors (Line/Bus) (765kV) 12 30 360 16 Associated bays-line & reactors (765kV) 23 13 299 17 Associated bays-line & reactors (400kV) 18 5 90 Total 4121 Total with IDC and Centages 4821

Page 57: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

EXHIBIT

Page 58: Project Inception Report - High Capacity Power Transmission Corridor - Main Report
01178
Typewritten Text
EXHIBIT - I
Page 59: Project Inception Report - High Capacity Power Transmission Corridor - Main Report

APPENDIX