TMALL 0143 Presentation engelsk v 1.0 Project ALEX (Automatic LX) New Level Crossing Control System Status in March 2016

Transcript of Project ALEX - Trafikverket · 2016-03-24 · • The following pages describe the system that...

Page 1: Project ALEX - Trafikverket · 2016-03-24 · • The following pages describe the system that project ALEX now specifies • All information is subject to change before the RFQ is

TM

ALL 0

143 P

resenta

tio

n e

ngels

k v

1.0

Project ALEX(Automatic LX)

New Level Crossing

Control System

Status in March 2016

Page 2: Project ALEX - Trafikverket · 2016-03-24 · • The following pages describe the system that project ALEX now specifies • All information is subject to change before the RFQ is

2 2016-03-23

Trafikverket,

Swedish Transport Administration

• 16 500 track km in Sweden

• Trafikverket manages 14 700 km

• 80 % electrified

• 8 900 single track km

• 6 500 LX

Page 3: Project ALEX - Trafikverket · 2016-03-24 · • The following pages describe the system that project ALEX now specifies • All information is subject to change before the RFQ is

3 2016-03-23

Level Crossing Protection

Protection at our 6475 LX

Full barrier 19%

Half barrier 15%

Light and sound 12%

Passive protection 20%

No protection 34%

Source: Plk-webb 2014-01-17

Page 4: Project ALEX - Trafikverket · 2016-03-24 · • The following pages describe the system that project ALEX now specifies • All information is subject to change before the RFQ is

4 2016-03-23

2770 LX have active protection

-

20

40

60

80

100

120

140

160

An

tal i

nst

alle

rad

e

Year

Maintenance DebtHalf is more than 25 years old!

Page 5: Project ALEX - Trafikverket · 2016-03-24 · • The following pages describe the system that project ALEX now specifies • All information is subject to change before the RFQ is

5 2016-03-23

LX control systems in Sweden

• 1948, Sweden was among the first to build automatic LX

• Today Trafikverket has one of Europe's oldest automatic

LX control systems with 65-85 year old technology

Skånebanan 2014

Our latest solution was introduced

in 1967 when Sweden changed to

right-hand traffic.

JRK relays, produced 1952-today

Page 6: Project ALEX - Trafikverket · 2016-03-24 · • The following pages describe the system that project ALEX now specifies • All information is subject to change before the RFQ is

6 2016-03-23

Project ALEX – procure new LX control systems

• The Director General has approved the ALEX Procurement strategy

and Supply plan

• There are many suppliers of modern solutions in the EU

• Several products meet the requirements

• Trafikverket announced at the annual National Suppliers Day 2015:

• We have problems obtaining spare parts for our LX installations

• We need to replace 70-100 LX / year

• Framework agreements will be signed with two suppliers

• It includes four pilot installations per supplier

• Cost: 10–30 M€ / year

• Procurement information, see http://www.trafikverket.se/for-dig-i-

branschen/upphandling/Planerade-upphandlingar, search for

“Vägskyddsanläggningar” and http://www.trafikverket.se/for-dig-i-

branschen/teknik/anlaggningsteknik/vagskyddsanlaggningar/alex/

Page 7: Project ALEX - Trafikverket · 2016-03-24 · • The following pages describe the system that project ALEX now specifies • All information is subject to change before the RFQ is

7 2016-03-23

Preliminary time schedule

Serial installations - 2019

Approvals by NSA and Trafikverket – December 2018

Probationary period of in-service operation – 6 to 12 months

Pilot installations – Q4 2017

Contracts signed – December 2016

Procurement – RFQ released June 30 2016

Requirements specification - Ongoing

Supply and Procurement strategy- Approved

Page 8: Project ALEX - Trafikverket · 2016-03-24 · • The following pages describe the system that project ALEX now specifies • All information is subject to change before the RFQ is

8 2016-03-23

• The following pages describe the system that project ALEX now

specifies

• All information is subject to change before the RFQ is released in

June, 2016

• Trafikverket is still in a silent period regarding ALEX and is unable to

answer any questions

Status in March 2016

Page 9: Project ALEX - Trafikverket · 2016-03-24 · • The following pages describe the system that project ALEX now specifies • All information is subject to change before the RFQ is

9 2016-03-23

Page 10: Project ALEX - Trafikverket · 2016-03-24 · • The following pages describe the system that project ALEX now specifies • All information is subject to change before the RFQ is

10 2016-03-23

• AA, LX control system

– The LX supplier will be responsible for

• Assembly of all components in the cabinet unless other component contracts

(SG-SL) prevent this

• Delivery to LX site

• Installation of cabinet at LX site

– Trafikverket will be responsible for

• installation of external objects (FE-FN and AD) at pilot LX sites

– Once the system has received type approval, the LX supplier can offer installation

work in future site specific contracts

• AD, Train velocity sensor

– Not a safety component (the safety is ensured by track circuits)

– Relay interface to existing signal cables

– Existing power supply (24 V) can be reused

– Must detect trains above a specific velocity

– RAM requirements are the same as for other subsystems

– Estimated need is 800 units

• FP, Logging & Diagnostic

– The data will be transferred to TH (ALEX web service)

Comments to the system architecture

Page 11: Project ALEX - Trafikverket · 2016-03-24 · • The following pages describe the system that project ALEX now specifies • All information is subject to change before the RFQ is

11 2016-03-23

• SB, Power

– Power components will be sourced from separate frame agreements

• SC, Obstacle detection

– Obstacle detection will be sourced from a separate frame agreement

– Purchased 2013

• SG, Train detection

– Already installed track circuits will be used for detecting approaching trains

Continued

Page 12: Project ALEX - Trafikverket · 2016-03-24 · • The following pages describe the system that project ALEX now specifies • All information is subject to change before the RFQ is

12 2016-03-23

Comparison with the functions of today

To improve railway safety we add

– Logging and Diagnostics

To improve road safety we add

– Acoustic signals adjusted to the

ambient needs

– Improved protection against

trespassing ("barrier skirts")

To reduce maintenance costs we add

– IP/MPLS communication via optic

fiber or GSM-R

– ALEX web services for

maintenance personnel

• Status, log and diagnosis via

web interface

• Alarm on error

Page 13: Project ALEX - Trafikverket · 2016-03-24 · • The following pages describe the system that project ALEX now specifies • All information is subject to change before the RFQ is

13 2016-03-23

• Industrial 19 inch racks

• A low cabinet to provide road users a good visibility along the track

• Modular, one door per function

• ALEX is one of several modules

Proposal for new cabinet

An example of a cabinet;

Toll road equipment in

Gothenburg

Page 14: Project ALEX - Trafikverket · 2016-03-24 · • The following pages describe the system that project ALEX now specifies • All information is subject to change before the RFQ is

14 2016-03-23

Modules/functions

• POWER

– Surge protection

– Rectifiers

– Batteries for 10 h

– Connection of alternative power supply

– Climate control

• IT

– IP/MPLS network via optic fiber or GSM-R

– Access control

– UPS service (power surveillance)

– ALEX web service for maintenance

personnel

• SIGNAL

– Interfaces to adjacent signaling

• Interlocking/ERTMS

• Track circuit (separate power, NiCd)

• Line Block

• ATC

• Disable Adjacent LX

• Common Distant signal toward trains

– ALEX, LX control system

– HEKTOR, Obstacle Detector system

The example cabinet including doors

The example cabinet excluding doors

Page 15: Project ALEX - Trafikverket · 2016-03-24 · • The following pages describe the system that project ALEX now specifies • All information is subject to change before the RFQ is

15 2016-03-23

• Training Center personnel are

assembling the prototype

• The prototype is used to

– Optimize space

– Dimension of the batteries

– Find interface requirements

– Receive feedback from maintenance

personnel and suppliers

• Photos and descriptions will be

released in April 2016

• During the tender period, a transQ

(category 1.3.5 Level Crossing)

qualified supplier can make an

appointment for a closer look at the

prototype

A cabinet prototype is built at the

Railway Training CenterALEX is one of several

possible modules in the

cabinet

Page 16: Project ALEX - Trafikverket · 2016-03-24 · • The following pages describe the system that project ALEX now specifies • All information is subject to change before the RFQ is

16 2016-03-23

• Project ALEX must conduct in-service operation with the 4 future LX

protection options to validate all interfaces

1. Full barrier

interfaces to interlocking and obstacle detector

2. Half barrier

interface to track circuits; automatic on a line

3. Walkway, bicycle path and platform

Optical signals and signs in half size, barrier skirts and barrier

machines without moving counter weights (risk of causing crushing

injuries will not be accepted)

4. User-worked road barrier (Operated with mechanical key with chip for

authentication). Mainly a “one user” solution for farm/forest crossings.

• All 4 pilot installation must undergo probationary period of in-service

operation (6-12 months) to be approved by the National Safety

Authority

• When all 4 pilot installations are NSA approved Trafikverket can issue

a type approval for the LX control system and serial installations can

begin

4 pilot installations per supplier

Page 17: Project ALEX - Trafikverket · 2016-03-24 · • The following pages describe the system that project ALEX now specifies • All information is subject to change before the RFQ is

17 2016-03-23