Program of Works Example

5
Program of Works 0 0 Preliminary's Preliminary's Week Starting Mon Week Starting Mon Input Start Date 1-Sep-09 8-Sep-09 Week Week 1 2 Materials Delivered Pour Concrete #2 NHBC notification F10 submission 1st Conc pour Bricky's CDM consultation Shuttering Foundation Blocks Architect consultationsEngineer consultations Start Steel Fixing brickwork to DPC Drawings Appoint NHBC Reinforcement Commons Delivery Attached House Order Stone/Blocks etc Spoil removal (Cages) Sand/Cement Del Program Schedule Order Dec Cills/Lintols Tree removal Extra Shuttering Wall ties Delivery Order Steel Mesh & Bar Shuttering Order Service Boxes Book Scaffold contact Services Heave protection Order Sand/Cement/Febmix Drainage layout Fencing? Inspections Order Regularised Joist #1&2 Order Templates Order kicker blocks Order Hockey Stick/Box Soil pipes in place Order drainage Order Floor I-Beams+Hangers Order Insulation Blocks/Stone Delivery Excavate for drainage Mark Out, Check Position Order Wall Ties I-beams delivery Fit Drainage for reinforced strip foo Soil pipes positioned Radon Protection DPC's Excavate Footings Inspections General Site Program Schedule

description

hh

Transcript of Program of Works Example

Page 1: Program of Works Example

Program of Works Example0 0 0

Preliminary's Preliminary's Week Starting Mon Week Starting Mon Week Starting MonInput Start Date 1-Sep-09 8-Sep-09 15-Sep-09

Week Week Week1 2 3

Materials Delivered Pour Concrete #2

NHBC notification F10 submission 1st Conc pour Bricky's Bricky'sCDM consultation Shuttering Foundation Blocks Start from DPC

Architect consultations Engineer consultations Start Steel Fixing brickwork to DPC Start Blockwork

Drawings Appoint NHBC Reinforcement Commons Delivery Start Stonework

Attached House Order Stone/Blocks etc Spoil removal (Cages) Sand/Cement Del

Program Schedule Order Dec Cills/Lintols Tree removal Extra Shuttering Wall ties Delivery Fit DPC Membrane

Order Steel Mesh & Bar Shuttering Order Service Boxes Book Scaffold Oversite Concretecontact Services Heave protection Order Sand/Cement/Febmix Drainage layout Radon barrierFencing? Inspections Order Regularised Joist #1&2 Order Templates Insulation Delivery

Order kicker blocks Order Hockey Stick/Box Soil pipes in place Order Floor 2 I-BeamsOrder drainage Order Floor I-Beams+Hangers Order Insulation Blocks/Stone Delivery Order Lintols (struc)

Excavate for drainage Mark Out, Check Position Order Wall Ties I-beams delivery Order Ridge BeamsFit Drainage for reinforced strip footings Soil pipes positioned Radon Protection DPC's

Excavate Footings Inspections

GeneralSiteProgram Schedule

Page 2: Program of Works Example

Program of Works Example0 0 0 0 0 0

Week Starting Mon Week Starting Mon Week Starting Mon Week Starting Mon Week Starting Mon Week Starting Mon22-Sep-09 29-Sep-09 6-Oct-09 13-Oct-09 20-Oct-09 27-Oct-09

Week Week Week Week Week Week4 5 6 7 8 9

Fit Ridge Beam NHBC&REGS Inspected Roo

Scaffold Start 2nd lift, Lintol hight Lintols Roof Structure Started Fit Roof insulation1st lift, Window sills 4th lift, Fit Roof Restraint Straps dormer boarding

Fit Grnd Floor Joist/Beams Trestle Hight internal Fit Padstones Brickwork Fit Cut ups Cav Closers Fit Roof Boarding

Block Infilling Fit Service Boxes Fit Lintols Set Purlins if any Valley's constructed

Temporary Flr Boards Fit Hockey Stick Fit 1st Floor Joist Fit 1st floor Restraint straps Underside netting Fit Soil roof vents

Fit Door Templates Fit Decorative Sills Internal wall build Block Infilling Purlin Positions if any Inspections

Fit Wall Insulation Fit Window Templates Inspections restraint straps Fit Rafters in placeFit Floor Insulation Mullions? Cavity Closers Delivery Slates DeliveredInspections DPC 3rd lift, Roof Materials Del Drainage Delivery

Floor Joist Delivery #2 Order Cavity Closers Order Patio Doors Valley sets Seal all Cavity'sLintols (Struc) Delivery Order Ridge beam Order Windows onsite 5th lift Gables cut ups Cut up's complete

Décor Cills Lintols Del Order PAN Timber Order Roof Materials Fit Restraint StrapsService box Deliivery Order Slates Order Plumbing Mat's

Pan fitted Velux positioned

Page 3: Program of Works Example

Program of Works Example

Week Starting Mon Week Starting Mon Week Starting Mon Week Starting Mon Week Starting Mon Week Starting Mon3-Nov-09 10-Nov-09 17-Nov-09 24-Nov-09 1-Dec-09 8-Dec-09

Week Week Week Week Week Week10 11 12 13 14 15

NHBC&REGS Inspected RooFit Facia Boards Fit Slates to Rear Roof Fan Holes Cut Order Plasterboards Elec& Plumb finish 1st fix

Fire stops (Party wall) Fit Down Pipes Plumb 1st fix Fit Plumbing Tails Plaster boards Del Ceiling Plaster SkimFit Barge Boards Fit soil & Vent Pipes Fit Flooring (Both Flrs) Fit Floor Insulation PlasterBoard Ceilings

Order Floor Insulation Bat Fit Slates to Front Roof Fit Internal stud work Glass Delivery Path Materials Delivery

Heating pipes B.Boxs Elec Materials Delivered Fit initial Pipe runs Fit Door Frames Fit Window Frames Fit Glazing

Tile or slate dormers Elec first fix Fit Drainage outlets Patios Delivered Garage ConstructionFit Chimney Vent Fit initial Cable runs Stairs Delivery Window Frames del Fit Stairs Order Skirts/Architrave

Fit Rainware Fit Alarm Cables/Video/TV Noggs for Pendants Fit Glazing Mark out Drive/pathsAerial fitted Order Decking for Floors Fit Door Cav Closers 1st Paint Windows Clear Base around hsFit Lat & Felt Flooring Materials del Order for Paths etc Plumb Preasure Test Boxing Pipework Fit Window Sills

Order Stud Timber Order Doors+ Front dr+Fr Start Access Court Prep Fit Front DoorFit Lead work Order Stairs Paint Facias Order Door Frames Window Sills Delivery Footpath Prep

Order Stairs Back boxes mounted Lead work complete Final paint Windows Landscaping FrontFit Soffits (enclosed) Finish all under floor work Fit Patio Cav Closers Remove Scaffold Order Kitchen

Fit Patio Doors Stone Delivery Order Boiler & RADS

Order Sewer & M.Holes pi Dropped Curbs Delivery Order Electrical, Cable, BoxesOrder Dropped Curbs Sewer Pipes Materials Del Water pipes layed

Garage Prep Sewerage Connection start Gas Sleaves layed

Lay Cross Drainage Electric Sleave layed

Sevice trenches dug Storm trench dug Bt Sleave LayedInspections Sewerage trench dug InspectionsDrives and Paths Marked Sewerage Pipe layed Services to Detached

Storm pipe layed Order TurfInspections Order Paving/Drive Materia

Fit Drop Curbs

Page 4: Program of Works Example

Program of Works Example

Week Starting Mon Week Starting Mon Week Starting Mon Week Starting Mon Week Starting Mon Week Starting Mon15-Dec-09 22-Dec-09 29-Dec-09 5-Jan-10 12-Jan-10 19-Jan-10

Week Week Week Week Week Week16 17 18 19 20 21

Tiling

Fit Wall Plaster Boards Plaster boarding snags Elec & Plumbing 2nd Appliances Decorating snags ViewingsGas/Water/Elec/BT Fit Internal Doors Fit Baths/Showers cub Fixtures & Fittings Landscaping Completed

Joinery 2nd fix Decorating WC/sinks fitted Fit/Test Boiler Fit Curtain rails

Order Garage Door Fit Skirts/Architraves Radiators mounted Tiling Completed Footpaths finished

Garage Construction Book Painters Lay Rear Paths Fit lights/switches/Soc Fit Taps,toilet seats Fit Garden Fences

Wall Plasterboard SkImOrder Tiling Fit Worktops Garage Doors Fitted Cleaning

Landscape Rear Fit Kitchen Units Fit Door Hardware Fit Laminate Flooring DressingInspections Laminate Delivery Rear Fences mounted Heating Tested Final ChecksSkirt/Architrave Delivery Inspections Electrical Testing complete Skip for clearanceLay Front Paths WC's/Sinks/Bath DeliveryTurfing RearOrder WC's/Sinks/Bath Elec 2nd fix Mat Del. Garage Doors Delivery Inspections

Lay Outdoor Cables forRads Delivered Boiler Delivery Regs/NHBC Final InspectionOrder Laminate Turf Delivery Turfing Front Lawn

Kitchen Delivery

Order Electrical, Cable, BoxesSewer connection Driveways Started

Services Connected Access Court detail

Elec/Water/BT/Gas? Landscaping Lay Block Paving

Garden Fence Delivery Sand Bed Landscaping Bndry Fence Delivery Hardcore Court Driveways CompletePaint Delivered Whacker Hardcore Bndry Fence ErectionDriveway Materials Del Order Bndry Fence

Order Paving/Drive Materia Lower Cables in Footpat Order Garden FenceOrder for Paths etc