PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE...

45
PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS

Transcript of PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE...

Page 1: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL

PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS

Page 2: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

PURPOSE OF THE PRESENTATION

In terms of Section 55 (2) (b) and Section 56 of the Constitution, the National Assembly must provide mechanisms to maintain oversight of any organ of state and may summon/require any institution to report to it.

The IDT complied with the National Treasury Framework on Strategic and Annual Performance Planning as the 2015/16–19/20 Strategic Plan was:

Approved by the Board of Trustees on 25 February 2015. Lodged with the Executive Authority and National Treasury on 27 February

2015. Approved by the Minister on 6 March 2015 as evidenced by the Foreword,

Official Sign-off and Shareholder Compact, Submitted to Parliament on 11 March 2015.

Therefore the IDT presents the Portfolio Committee on Public Works for consideration and processing:

the 2015/16 - 2019/20 Strategic Plan;

the 2015/16 – 2017/18 Budget; and

the 2015/16 Annual Performance Plan.

1

Page 3: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

1.

BACKGROUND

2

Page 4: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

BACKGROUND & STRATEGIC POSTURE

The IDT positions itself to contribute to national development imperatives through its service offering.

The strategic posture adopted by the IDT Board is aimed at building an IDT which:

i. Has the capacity to deliver a distinctive value proposition which measurably advances the national development policy objectives;

ii. Can address the development gap that has continued to undermine government’s development policy objectives; and,

iii. Is financially viable and organisationally sustainable.

The Cabinet approved the appointment of a new CEO, Mr Coceko Bambihlelo Johan Pakade who will drive the Strategy.

3

Page 5: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

2.

2015/16- 2019/20 STRATEGIC PLAN

4

Page 6: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

STRATEGIC PLAN: (HIGH LEVEL) TABLE OF CONTENTS

1. FOREWORD: EXECUTIVE AUTHORITY

2. OFFICIAL SIGN-OFF

3. STATEMENT: BOARD CHAIRPERSON

4. PART A: STRATEGIC OVERVIEW

5. PART B: STRATEGIC OBJECTIVES

6. PART C: LINK TO OTHER PLANS

7. APPENDICES

5

Page 7: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

FOREWORD: EXECUTIVE AUTHORITY

Asserts that IDT’s Strategic Plan underscores the importance of infrastructure in fostering shared prosperity by all.

Highlights IDT’s role within the mandate of the Department of Public Works

Demonstrates IDT’s value-add to national development effort:

Shows the IDT’s alignment to: The national priority outcome areas; The National Development Plan; The National Infrastructure Plan; The DPW Policy Statement; Minister’s Performance Contract.

Emphasises IDT’s commitment to be a relevant, effective and financial viable development agency that delivers programmes that make meaningful impact on the life of the country’s citizens.

Minister’s support and commitment to remodelling the IDT.

6

Page 8: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

STATEMENT: BOARD CHAIRPERSON

Recaps IDT’s commendable achievements (in terms of delivery) during the 2013/14 financial year.

Acknowledges a qualified audit opinion for the 2013/14 on its regulatory audit which digressed from a potential 11th successive unqualified audit report. An audit action plan has been approved by the Board under the oversight of the Audit and Risk Committee to address the root causes that led to the qualified audit opinion.

Indicates the Board’s resolve to continue working with the Executive Authority to finalise IDT’s mandate which will address among others:

Corporate form;

The business model;

Institutional arrangements; and

Financial sustainability of the organisation..

The Board of Trustees further commits itself to give management total support in the implementation of the Strategic Plan.

7

Page 9: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

INTRODUCTION

The Strategic Plan of the IDT is primarily formulated to support the mandate of the DPW and overall to contribute to the national development effort. The Strategy is prepared in line with the National Treasury Framework on Strategic and Annual Performance Plans (2010) and articulates the following elements :

VISION: To be a leading public sector developmental programme implementation and management agency.

MISSION: The IDT manages and delivers integrated quality social infrastructure programmes on behalf of government on time, cost effectively and through a people centred approach.

OUR APPROACH: The The IDT’s approach to social infrastructure development entails all the necessary facilities and networks required to prepare communities to receive, participate in, own and sustain their own development.

8

Page 10: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

VALUES & OPERATING PRINCIPLES

VALUES OPERATING PRINCIPLESPEOPLE CENTRED

We improve the lives of people We work together as a team We put people first

 INTEGRITY

We are open and honest in all our communications We believe in the integrity of our data and reports We treat one another with dignity and respect We conduct our business in a lawful, honest and ethical manner

 PROFESSIONALISM

We approach work in a systematic manner Our service complies with best practice We deliver quality results

 ACCOUNTABILITY

We have responsibility to communities, stakeholders and one another for our actions

We are accountable to our clients, stakeholders and one another for our actions

 INNOVATIVE

• We approach our work in a creative manner• We explore and implement innovative solutions to foster

sustainable development practices and outcomes

9

Page 11: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

LEGISLATIVE AND OTHER MANDATES (1)

The 1997 Cabinet mandate is still in place, that is:

“The IDT must be transformed into a government development agency that will implement projects which are commissioned by government departments.”

Integrated into the public service delivery system in 1999 with the promulgation of the PFMA and listed as a Schedule 2 Major Public Entity.

Reports to the Minister of Public Works, Executive Authority and the Shareholder Representative.

The IDT seeks to contribute towards the mandate, vision and strategic objectives of Department of Public Works (DPW), and to advance the:

National Development PlanNational priority outcomesNational Infrastructure PlanNew Growth Path

10

Page 12: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

LEGISLATIVE AND OTHER MANDATES (2)

Shareholder Compact

Relevant Programmes of DPW Programme 1: Administration Programme 2: Immovable Assets Investment Management Programme 3: Expanded Public Works Programme (EPWP)

Contribution to National Strategic Outcomes Outcome 1: Quality basic education; Outcome 2: A long and healthy life for all South Africans; Outcome 4: Decent employment through inclusive growth; Outcome 5: A skilled and capable workforce to support an inclusive growth path; Outcome 7: Vibrant, equitable and sustainable rural communities contributing to food security

for all; Outcome 8: Sustainable human settlements and improved quality of household life; Outcome 10: Protect and enhance our environmental assets and natural resources; and Outcome 12: An efficient, effective and development-oriented public service.

The IDT directly supports DPW in its Medium-Term Strategic Framework (MTSF) priorities for job creation, contractor development and skills development.

11

Page 13: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

SITUATIONAL ANALYSIS: PERFORMANCE ENVIRONMENT

In the last 10 years IDT delivered programmes worth approximately R20.25 bn.; 85-95% was directed at social infrastructure development. R5.6bn and R6.6 bn. worth of programme delivery in 2012/13 and 2013/14 , respectively.

Agency implements integrated social infrastructure and social development programmes whose outputs have long-term development impact.

One of IDT’s key service offering is social facilitation: IDT facilitates for acceptability and ownership of development, programme delivery undertaken with the full participation of communities

IDT committed to making direct contribution to the achievement of Government’s Strategic Outcome 12 which has been translated by the Department of Public Works to mean “SERVICE DELIVERY QUALITY AND ACCESS TO GOVERNMENT SERVICES”.

12

Page 14: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

SITUATIONAL ANALYSIS: OPPORTUNITIES & THREATS

13

Page 15: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

SITUATIONAL ANALYSIS: OPPORTUNITIES & THREATS

14

Page 16: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

SITUATIONAL ANALYSIS: STRENGTHS & WEAKNESSES

15

Page 17: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

SITUATIONAL ANALYSIS: STRENGTHS & WEAKNESSES

16

Page 18: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

SITUATIONAL ANALYSIS: KEY ISSUES

The environmental scan highlighted the following areas as pertinent to the IDT and it thus informed the corporate strategy:

Persistent poverty and inequalityUnemployment, especially amongst out-of-school youth and young adultsSocial Infrastructure backlogs despite massive investments by government.Local government service delivery challenges Rural-to-urban migration, land reform and post-settlement support Changes in and perceived conflicts in instruments meant to promote affirmative action towards empowerment of the previously disadvantagedUneven access to basic services Public fiscus under pressure Need for alternative and creative ways of stretching public investment, deepening and broadening development impact

17

Page 19: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

STRATEGIC PILLARS 18

Page 20: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

PROGRAMME 1: STRATEGIC ARTICULATION

Programme 1 articulates the IDT’s responsibility to promote sustainable development in marginalized areas through delivery of integrated social infrastructure. The institution aims to achieve these Strategic Goals by using resources in a prudent and efficient manner.

STRATEGIC OUTCOME ORIENTED GOAL 1

THE IDT CONTRIBUTES TO THE STATE’S CAPACITY TO EFFECTIVELY IMPLEMENT DEVELOPMENT PROGRAMMES.

GOAL STATEMENT 1 The IDT provides integrated development programme services in a cost effective manner within time, scope and to the required quality

PROGRAMME NAME : INTEGRATED SERVICE DELIVERYSTRATEGIC OBJECTIVE 1 Deliver quality social infrastructure on time,

within budget and scope OBJECTIVE STATEMENT 1 IDT distinctive developmental approach to

social infrastructure delivery empowers communities to receive, participate in, own and sustain their own development.

19

Page 21: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

PROGRAMME 2: STRATEGIC ARTICULATION

Programme 2 confirms and reasserts IDT’s commitment to continue being a relevant, efficient, effective, sustainable and compliant-driven entity. The IDT commits to strive for the best in terms of Corporate governance practice and prudent leadership and management.

STRATEGIC OUTCOME ORIENTED GOAL 2

AN EFFECTIVE AND EFFICIENT ADMINISTRATION

GOAL STATEMENT THE IDT IS A RELEVANT, EFFECTIVE, EFFICIENT AND SUSTAINABLE ORGANISATION

PROGRAMME NAME: ADMINISTRATIONSTRATEGIC OBJECTIVE 2 A compliant, results-based, efficient and focused

organizationOBJECTIVE STATEMENT 2 Operating a development agency that retains relevance

to the country’s development needs and aspirations, and maintaining a clean administration which is committed to the efficient application of resources, compliance with regulations and legislation and which is accountable.

20

Page 22: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

STRATEGIC VISION IMPLEMENTATION

IDT is a major public entity and development agency which has to:1. Create value in the lives of the people of South Africa. 2. Ensure that it delivers high quality service and sustainable development in

a cost effective way. 3. Remain relevant in the South African development landscape,4. Find innovative and sustainable solutions to the development challenges

facing the country as identified in the National Development Plan and other key policy instruments.

1. The strength of the IDT lies in its ability to deliver quality social infrastructure through its niche in programme management. The results of the scan suggest that the IDT will deliver meaningful value add to government through cost-effective delivery of programmes, in such a manner that key development objectives of job creation, shared prosperity and skills development are an integral part of addressing the social infrastructure and social development backlogs. This will be achieved through the continued application of IDT’s integrated service delivery model.

21

Page 23: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

KEY PERFORMANCE MEASURES & INDICATORS (1)

Corporate Business Plan and the 2015/16 APP reflected in Appendix 2 and 3. Delivery of these pre-determined targets hinges on a number of assumptions and dependencies:

VALUE AND DELIVERY OF BUSINESS PORTFOLIO: The IDT is required to generate its own business portfolio. However, the speed at which agreements are concluded as well as the frequency and values of funds transferred is not entirely within the control of the organisation and delays impact on delivery. Associated indicators and targets assume that agreements are concluded before the start of and or early in the financial year and that clients will transfer funds as stipulated in the agreements.

MANAGEMENT FEE: Is negotiated with clients and stipulated in agreements. . In order to remain a going concern, the minimum average management fee which the IDT can consider is between 6% and 7% in the short term. A level lower than 6% will jeopardise the organisation’s going concern status. If clients do not make the funds available for the IDT to deliver, the organisation will not be able to collect its management fees.

22

Page 24: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

KEY PERFORMANCE MEASURES & INDICATORS (2)

GOING CONCERN: It assumes that the operation will be able to continue trading for a minimum of 12 months. Currently, the going concern base is at 12 months, assuming 100% collection of outstanding management fees. Unforeseen cash flow challenges may jeopardise the organisation and thus could have devastating impact on the delivery of approximately R20bn programmes over the planning period.

CERTAINTY OF MANDATE AND LONG-TERM SUSTAINABILITY: The Shareholder has undertaken to formally consider and provide certainty on the organisation’s mandate and long-term sustainability. The uncertainty, which had prevailed for a number of years, negatively impacts client confidence, organisational culture and staff morale, which in turn is reflected in business generation, productivity and delivery capacity.

ATTRACT AND RETAIN RIGHT SKILLS: The on-going uncertainly has increased the risk of flight of skills resulting in a high vacancy rate of 20% in 2014/15. This impacts the organisation’s ability to recruit and retain appropriate skills. Client confidence is enhanced by the organisation’s ability to deploy appropriate competencies to manage programmes.

23

Page 25: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

GOVERNANCE STRUCTURES

SHAREHOLDER COMPACT: Between the Executive Authority and Accounting Authority

BOARD OF TRUSTEES AND ITS COMMITTEES: Strategic Planning and Programmes Committee Human Resources and Corporate Services Committee Audit and Risk Committee Finance Committee Board EXCO (acts as Remuneration Committee )

EXECUTIVE MANAGEMENT: Comprising Executive Heads mostly reporting to the Chief Executive Officer (CEO), providing leadership to Operations (Ops) Development Services Unit (DSU) Corporate Services Unit (CSU) Financial Services Unit (FSU) Office of the CEO (OCEO)

24

Page 26: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

AN OVERVIEW: FINANCIAL CHALLENGES & RISKS

The major challenge that faces the IDT is the uncertainty surrounding the financial sustainability of the organisation.

Treasury has allocated R50m per year for the 2015/16 financial year. The funds have been allocated on condition that “the Independent Development Trust will develop and submit a restructuring plan to the National Treasury…”.

The Business Case (the plan referred to by Treasury) is being prepared in conjunction with the Department of Public Works. The plan will address, inter alia, the issues of:

The structure, form and resourcing required for the organisation in order for it to become self-sustainable over the MTEF period;

The clearly identified target market for the organisation;

The management fees structure required to provide for the funding of the organisation.

25

Page 27: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

Strategic Risk (1) Management: Litigation

Contributory factors

Implications Current Controls Mitigation Plans (Tasks)

Delays in programme funds transfers resulting in late payments to the service providers

Project failure

Competition between contractors when tenders are allocated

Damage to reputation

Exorbitant litigation cost

Unproductive time.

Prolonged delays in service delivery

Attachment of the trust and trustees property

Signed Contracts in place

Consultants provide project supervision

Monitoring of payment turnaround times

Investigate and look into a contingency plan to have funds available to be used in circumstances where there are delays in funds transfer .

Improve adherence to programme and project management process.

Improve contracts management capacity.

Recruitment of in-house professionals for technical validation and evaluation

26

Page 28: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

Strategic Risk (2) Management: Financial Insecurity

Contributory factors Implications Current Controls Mitigation Plans (Tasks) Existence of

previous contractual arrangement affecting revenue

General fiscal tightening in public sector

Low cost recovery rate

Non recovery of management fees due to disputes with clients department

Internal financial reporting and billing systems.

 

Impaired financial sustainability

Impaired organisational performance

Failure to achieve mandate

Poor reputation

Staff insecurity and low morale

Risk of reckless trading

Loss of skills

Continued draw down on investment

Cost recovery drive

Management fee annual structure review

Cost containment measures

Tight Programme Implementation Agreements (PIAs)

Enhanced service provision

Client engagements to negotiate for management fees as per treasury instruction note

Management to develop an organisational refocus and streamlining strategy and plan in order to safeguard short term financial viability and improve service offering.

Monitor management fees collection

Continue cost containment

Continuation of monitoring projects contracts

Capacitating FSU to enable speedy production of programmes recons.

27

Page 29: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

Strategic Risk (3) Management: Delays in Programme Funds Transfers & Payments

Contributory factors Implications Current Controls Mitigation Plans (Tasks) Departments utilising

funds initially budgeted for projects for other matters, resulting in non payments and or failure to transfer funds to IDT

Inadequate reporting

Poor client relations management

Clients contesting management fees due to existing contracts

Delays on programme reconciliation

 

Litigations by contractors

 

Bad media publicity

 

Service delivery protests

 

• Failure to complete projects

 

• Attachment of trust and trustees property

• SLA'S, MOU, Approach planning

 

Continuous client management relations

 

Provision of programme financial reconciliations

 

Second level verification of progress reports by National team

Formally inform the clients departments in writing on the risks associated with failure to pay,.

 

Continuously review IDT service level agreements with Clients to close loop holes

 • Where necessary

request political principals to intervene to speed up/resolve funds transfer challenges

28

Page 30: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

Strategic Risk (4) Management: Loss of Business Portfolio

Contributory factors Implications Current Controls Mitigation Plans (Tasks) Lack of continuity

within the regions with regards to political engagements and stakeholder Management

 

Projects awarded to contractors from other Regions resulting in conflicts on empowerments and outcry from the local contractors

 

Shortcomings in programme management capacity

Withdrawal of business by clients departments.

 

Financial loss/ reduction in income.

 

Relocation of Regional staff

 

• Closure of Regional operations and offices

• Retrenchment of staff

 

Dented corporate image

Client relations management

 

Effective SCM processes and procedures.

 

Committed programme management team.

 

• Effective leadership response to challenges.

• Stakeholder engagement process to address concerns from the clients and provincial leadership.

 

• Dedicated stakeholder management support to support regions by Executives and Board.

 

Improve SCM processes to strengthen local contractor empowerment.

 

Secure Board support in business development and client relations management.

29

Page 31: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

BUDGET 2015/16 & FORECAST2015/16 – 2017/18 Budget

The Business Plan for the financial years 2015/16 to 2017/18 shows steady growth in its programme delivery as opposed to the quantum growth rate of the past 3 years.

Between the 2010/11 and 2013/14 programme delivery grew from R 2.2 billion to R 6.63 billion

Growth is predicted to reach R 7 billion to R 8 bn. over the next three years .

Increase in level of management fees to ensure longer-term financial viability. However this action has met resistance from a number of client departments, hence the Practice Note issued by the National Treasury.

Late transfer of programme funds – from which management fees are drawn - exacerbate the financial situation of the IDT.

Cost containment strategy implemented to closely monitor and contain costs.

30

Page 32: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

INCOME

THE IDT HAS TWO SOURCES OF INCOME:THE IDT HAS TWO SOURCES OF INCOME:

MANAGEMENT FEES:MANAGEMENT FEES:

Management fees charged to client departments constitutes the major source of its income. The level of fees budgeted/projected at 6% during the 2014/15 financial year and management has implemented a process to increase the average level of fees to 6.3% over the budget year. The level of fees will be further increased over the outer years.

INVESTMENT INCOME: INVESTMENT INCOME:

Earned from interest on investment fund.

The Fund has declined over years as it has been used to fund the IDT’s operational costs; and,

The reduction in the level of interest rates together with the decrease in the capital invested has resulted in the investment income being reduced significantly over the past few years.

31

Page 33: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

HUMAN RESOURCES STRATEGY

The HR Strategy aims to facilitate that the IDT can at all times attract, retain and develop the best available skills such that it is able to deliver on its mandate.

Staff establishment: 441. Staff occupancy: 80%.

The IDT plans to embark on a refocus and streamlining process to improve the service offering of the organization and safeguarding performance on obligations to clients. This process includes a structure review aimed at achieving among other, the following goals:

To increase the built environment technical capacity in order to strengthen social infrastructure programme management while reducing the social and community development staff contingent as part of de-investment in functional areas not aligned with the new mandate

To bring about a healthy balance in the ratio of core and support staff through increasing the total direct programme staff while reducing staff in administration, corporate services and governance positions

To increase capacity at regional level and reduce staff at head office, thus address the top heavy concern visible in the existing structure

32

Page 34: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

HIGH-LEVEL ORGANOGRAM

CHIEF EXECUTIVE OFFICER

COMPANY

SECRETARY

HEAD OF INTERNAL AUDIT

EXECUTIVE HEAD: OFFICE OF THE CEO

CHIEF OPERATIONS OFFICER

EXECUTIVE HEAD: CSU

CHIEF FINANCIAL OFFICER

EXECUTIVE HEAD: DEVELOPMENT SERVICES UNIT

EXECUTIVE: REGIONAL

OPERATIONS

REGIONAL HEADS X 9

GM: PROGRAMME MANAGEMENT OFFICE

GM: LEARNING AND INNOVATION

DEPUTY CHIEF FINANCIAL OFFICER

GM: SUPPLY CHAIN MANAGEMENT

GM: HUMAN RESOURCES

GM: STRATEGY AND POLICY

GM: INFORMATION

MANAGEMENT

GM: COMMUNICATIONS & STAKEHOLDER

MANAGEMENT

GM: COMPLIANCE AND RISK

BOARD

GM: SPECIAL PROJECTS

33

Page 35: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

OTHER CRITICAL PLANS AND STRATEGY

Risk Management Plan

Fraud Prevention Plan

Materiality and Significance Framework

Environmental Plan

Communication Plan

IT Management Plan

Corporate Knowledge Strategy

Monitoring and Evaluation Framework

34

Page 36: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

CORPORATE PROGRAMME WEIGHTING

In the quest of transforming the IDT from a government funding dependent agency into a self-sustaining organisation based on revenue generated from its service offering, the IDT has instituted a targeted operational refocus placing a significant amount of effort on institutional and financial sustainability aspects. This has necessitated the review of weighting on its Corporate programmes and related strategic goals resulting in the prominence of financial and institutional sustainability matters as provided under Programme 2 in 2015/16 and a gradual shift towards the service delivery-oriented Programme 1 in subsequent years.

Corporate programmes weighting over the planning period

Refer to Hand-out: Corporate Business Plan

  2015/16 2016/17 2017/18 2018/19 2019/20Prog. 1 50% 60% 70% 70% 70%Prog. 2 50% 40% 30% 30% 30%Total 100% 100% 100% 100% 100%

35

Page 37: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

PROGRAMME 1 (SERVICE OFFERING) KPA KPI WEIGH

TBASELINE

2015/16 TARGET

 PROGRAMME DELIVERY

No. of government departments supported 10%  40 40Value of programme spend 20% R6.63bn  R7bn.No. of new/replacement schools completed 5% 22 30

 COMMUNITY MOBILISATION AND EMPOWERMENT

No. of work opportunities created through IDT portfolio

7.5% 26 937 20 000

No. of EPWP-NSS work opportunities created 5% 48 920 50 000No. of EPWP cooperatives, NPO’s and CBOs supported

5% 330 350

 ENTERPRISE AND SUPPLIER DEVELOPMENT 

% of Weighted BBBEE spend 15% Approx. 65%

65%(R4.550bn)

Value of programme spend on contracts awarded to women contractors as a percentage of programme spend

7.5% 17%(R1.15bn)

20%(R1.4bn)

Value of programme spend on contracts awarded to youth contractors as a percentage of programme spend.

10% Approx. 15%

15%(R1.05bn)

% of women contractors participating in the contractor development programme

5% 67% 65%

Value of contracts awarded to contractor development participants as a percentage of programme spend

10% 4%(R280m)

 5%(R350m)

 

36

Page 38: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

PROGRAMME 2 (ORGANISATIONAL EFFICACY)

KPA KPI WEIGHT BASELINE 2015/16 TARGET

CORPORATE

GOVERNANCE

Effective

financial and

non-financial

compliance

15%Financial audit outcome:

qualified for 2013/14

Financial audit outcome:

unqualified

10%Performance audit outcome:

unqualified for 2013/14

Performance audit outcome:

unqualified

RISK

MANAGEMENT

Effective risk

management 10%

Enterprise risk management

strategy and plan in place and

implemented.

Enterprise risk management

strategy and plan in place

and implemented.

HUMAN

CAPITAL

MANAGEMENT

Effective

human capital

management

 

5%

HR Strategy partially

operationalised. Targeted

recruitment effected.

Human capital plan

approved and implemented

5%Vacancy rate as of Q3

2014/15 20%

Vacancy rate for funded

positions less than 15%

37

Page 39: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

PROGRAMME 2 (ORGANISATIONAL EFFICACY)

KPA KPI WEIGHT BASELINE 2015/16 TARGET

ORGANISATIONA

L

SUSTAINABILITY

Average

management

fee billed and

collected

10%

Annual average management

fee billed: 6.1%

Annual average

management fee billed:

6.3%

20%Annual Management Fee

collection rate of appro. 70%

Annual management fee

collection rate: 90%

Cost- and

service-

effective

structure

5%

Internal reforms initiated

and awaiting confirmation of

mandate and approval of

structure

Refocus Organizational

Structure developed and

approved.

38

Page 40: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

STRATEGIC OBJECTIVE 2 (ORGANISATIONAL EFFICACY)

KPA KPI WEIGHT BASELINE 2015/16 TARGET

OPERATIONAL

EFFICIENCY

% Corporate

Efficiency

Ratio

10%

Annual Corporate

Efficiency Ratio: 5.5%

Annual Corporate Efficiency

Ratio: 6%

COMMUNICATIO

NS

Effective

Communicati

ons and

Stakeholder

Management

Strategy

5%

Targeted delivery of the

Communications Strategy

Corporate communication

plan approved and

implemented.

5%

No profile building

campaign implemented.

At least 3 EXCO approved

comprehensive profile

building corporate media

campaigns undertaken in

electronic and print media.

39

Page 41: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

3.

IMPLICATIONS AND

RECOMMENDATIONS

40

Page 42: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

IMPLICATIONS OF AND ON THE STRATEGY

In considering the 2015/16 – 2019/20 Strategic Plan, the Portfolio Committee on Public Works is requested to note:

That the Strategy, Budget and Annual Performance Plan in question have been prepared on the basis of the status quo with adjustments being made where appropriate and as informed by the environmental scan findings and the strategic direction given by the Board. A review will be undertaken by the Board on confirmation by the Shareholder of the appointment of the CEO and/or mandate of the organization.

The financial vulnerability faced by the organization as highlighted in the 2015/16 budget arising from among other retention of personnel in operational areas not supported by the refocus and streamlining objectives and challenges relating to charging and collection of management fees.

That the tight fiscal position of government as evidenced by budget cuts in public spend has dual and adverse impact in programme portfolio payments and income of the IDT as presented in the Corporate Plan.

41

Page 43: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

IMPLICATIONS OF AND ON THE STRATEGY

In considering the 2015/16 – 2019/20 Strategic Plan, the Portfolio Committee on Public Works is requested to note:

4.The weights allocated to key performance indicators and targets in the Corporate Plan as a basis for directing organizational strategies and operational focus and thus informing corporate performance evaluation.

5.The financial sustainability challenge that has faced the IDT as it impacts on the Organisation’s ability to delivery on its mandate.

6.The value of programme implementation agency agreements (PIA) or memoranda of agreements (MOA) signed for future implementation is currently in excess of R 20 billion over the next three years. This would represent a significant risk to the relevant departments and service delivery to communities should the IDT not be able to implement their programmes.

42

Page 44: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

RECOMMENDATIONS

It is therefore recommended that the Portfolio Committee on Public Works:

Recommends the IDT’s 2015/16 - 2019/20 Strategic Plan, 2015/16 Annual Performance Plan and 2015/16 – 2017/18 Budget to Parliament; and

Sustains its support for the long-term sustainability of the IDT such that the organisation can maintain and accelerate its distinctive role in delivering social infrastructure in the most marginalised communities on behalf of government.

43

Page 45: PRESENTATION OF THE IDT 2015/16 – 2019/20 STRATEGIC PLAN & 2015/16 ANNUAL PERFORMANCE PLAN TO THE PORTFOLIO COMMITTEE ON PUBLIC WORKS.

THANK YOU!SIYABONGA!

ENKOSI!DANKIE!

KE A LEBOHA!

44