FRONT ELEVATION OVERVIEWACTIVE LEVEL (STRUCTURAL)
FORMWORKS
WETWORKS
DRYWORKS
TOG
1
2
3
4
5
6
789
10
WETWORKS
39TH
38TH
37TH
36TH
PRECAST WALL CHB LAYING(PERIMETER WALL)
DOOR JAMBINSTALLATION
ZOCALLO(T&B)
BOX ALIGNMENT
PLASTERING (PERIMETER)
RUBBED CONCRETE(INTERIOR)
CHB LAYING(PARTITION & T&B WALL)
RUBBED CONCRETE(EXTERIOR)
ALUMINUM DOORS & WINDOW INSTALLATION
(PERIMETER)
WATERPROOFING APPLICATION
(T&B)
PLASTERING(LDK & T7B)
PUNCHLIST
PRIMER PAINTAPPLICATION(EXTERIOR)
SKIMCOAT APPLICATION(PRECAST)
SKIMCOAT APPLICATION(INTERIOR)
ALUMINUM DOORS & WINDOW INSTALLATION
(HALLWAY)
…back to Front Elevation
DRYWORKS
T&B TILES
TOG INSPECTION
789
10
PUNCHLIST (T&B) DRYWALL,CLADDING, CEILING FRAMING
MAIN DOOR HALLWAY WINDOWS
BOXSETTING/ WIRING SKIM COAT (T&B) LDK TILES DRYWALL CLOSURE
INTERMEDIATE PAINT INSTALLATION OF DEVICES BASEBOARD INSTALLATION SPRINKLER HEADS INSTALLATION
…back to Front Elevation
T&B Tiles Installation (DMCI)Status•Manpower: 12 Masons•Productivity: 24 T&B’s per wk/ 9 days per floor•Actual no. of floors from structural – 9 floors•Target no. of floors from structural – 7 floors•Floors delayed: 2 floor •Reason for delayed: Manpower
…back to Front Elevation
Punchlist T&B (Masonry Subcon)Status•Manpower: 2 Masons and 2 Concrete Planer•Productivity: 3 T&Bs per day per subcon•Actual no. of floors from structural – 9 floors•Target no. of floors from structural – 7 floors•Floors delayed: 2 floor •Reason for delayed: Other Trade (T&B Tiles Installation)
…back to Front Elevation
Drywall, Cladding, Ceiling Framing (Estolano)Status•Manpower:
Drywall/Cladding - 6 installersT&B Ceiling – 4 Installers
•Productivity: Drywall/Cladding – 12 units per dayT&B Ceiling Frame – 10 t&b per day
•Actual no. of floors from structural – 10 floors•Target no. of floors from structural – 7 floors•Floors delayed – 3 floors•Reason for delayed – other trades (Rubbed Concrete, Skim Coat and Ext Window)
…back to Front Elevation
Main Door Installation (DMCI)Status•Manpower: 2 Carpenters•Productivity: 6 Doors per day/ 7 days per floor•Actual no. of floors from structural – 9 floors•Target no. of floors structural – 8 floors•Floors delayed – 1 floor•Reason for delayed - Manpower
…back to Front Elevation
Hallway Windows (SPI)Status•Manpower: 2 installers•Productivity: 12 units per day/ 2 days per floor•Actual no. of floors from structural – 10 floors•Target no. of floors structural – 8 floors•Floors delayed – 2 floors•Reason for delayed – Other Trades (Rubbed Concrete)
…back to Front Elevation
Box Setting / Electrical Wiring (Anvic)
Status•Manpower: 4 persons•Productivity: 6 units per day/ 4 days per floor•Actual no. of floors from structural – 10 floors•Target no. of floors structural – 8 floors•Floors delayed – 2 floors•Reason for delayed – Other Trades (Hallway Windows)
…back to Front Elevation
Skim Coat Application T&B Wall (JBLS)Status•Manpower: 7 groups (2 persons each)•Productivity: 1 unit per 2 days/ 8 days per floor•Actual no. of floors from structural – 11 floors•Target no. of floors structural – 8 floors•Floors delayed – 3 floors•Reason for delayed – Other Trades (Masonry Punchlist)
…back to Front Elevation
Tiling LDK (DMCI)Status•Manpower: 5 groups (2 tilers each, 1 solo)•Productivity: 1 unit per 1.5 days/ 8 days per floor•Actual no. of floors from structural – 10 floors•Target no. of floors structural – 8 floors•Floors delayed – 2 floors•Reason for delayed – Other Trades (Masonry Punchlist)
…back to Front Elevation
Drywall, Cladding and Ceiling Closure (Estolano)Status•Manpower: 20 persons (6 installers, 14 jointers )•Productivity:
Drywall/ Cladding Closure – 1 unit/2days
Jointer – 2 units/day•Actual no. of floors from structural – 11 floors•Target no. of floors structural – 8 floors•Floors delayed – 3 floors•Reason for delayed – Other Trades (Box Setting)
…back to Front Elevation
Intermediate Paint (JBLS)Actual•Manpower: 10 groups ( 2 persons each)•Productivity: 2.5 days per unit•Actual no. of floors from structural – 11 floors•Target no. of floors structural – 9 floors•Floors delayed – 2 floors•Reason for delayed – Other Trades
…back to Front Elevation
Installation of Devices (Anvic)Status•Manpower: 4 persons•Productivity: 20 units per week•Actual no. of floors from structural – 11 floors•Target no. of floors structural – 9 floors•Floors delayed – 2 floors•Reason for delayed – Other Trades (Intermediate Paint)
…back to Front Elevation
Baseboard Installation (DMCI)Status•Manpower: 5 Carpenters•Productivity: 20 units per week•Actual no. of floors from structural – 11 floors•Target no. of floors structural – 9 floors•Floors delayed – 2 floors•Reason for delayed – Other Trades (Intermediate Paint)
…back to Front Elevation
Sprinkler Heads (Alpa)Status•Manpower: 1 Installer•Productivity: 20 units per week•Actual no. of floors from structural – 11 floors•Target no. of floors structural – 9 floors•Floors delayed – 2 floors•Reason for delayed – Other Trades (Intermediate Paint)
…back to Front Elevation
TOG INSPECTION
Status•Productivity: 20 units per week•Actual no. of floors from structural – 11 floors•Target no. of floors structural – 10 floors•Floors delayed – 1 floor
•Total Accepted – 338 units•Total Balance – 659 units•Projected end of turnover 20 units per week
- July 18, 2014…back to Front Elevation
PRECAST WALL
PRECAST WALL FABRICATION
Status : 24th floor
•Manpower: 2 carpenters•Productivity: 6 panels per day•Gap on Structural: 4 floors
PRECAST WALL INSTALLATION
Status : 24th floor
•Manpower: 2 carpenters•Productivity: 5 panels per day•Gap on Structural: 4 floors
•Target productivity: 10 panels per day•Additional manpower: 2 Carpenters
…back to Front Elevation
RUBBED CONCRETE(EXTERIOR)
Status: 21st Floor
•Manpower: 18 mason•Productivity: 10 days/floor•Gap from Structural: 7 Floors
•Target Productivity: 8 days/Floor•Additional manpower: 6 masons
…back to Front Elevation
CHB LAYING(EXTERIOR)
Status: 24TH Floor
•Manpower: 3 mason & 3 labor•Productivity: 3 days/floor•Gap from Structural: 4 Floors
…back to Front Elevation
DOOR JAMBINSTALLATION
Status: 24TH Floor
•Manpower: 2 Carpenters•Productivity: 8 Jambs/day•Gap from Structural: 4 Floors
…back to Front Elevation
ZOCALLO FORMWORKSINSTALLATION
(T&B)
Status: 24TH Floor
•Manpower: 1 Carpenter•Productivity: 4 units/day•Gap from Structural: 4 Floors
•Target Productivity: 8 units/day•Additional manpower: 1 Carpenter
…back to Front Elevation
BOX ALIGNMENT
Status: 24TH Floor
•Manpower: 2 PAX•Productivity: 5 days/floor•Gap from Structural: 4 Floors
…back to Front Elevation
PLASTERING(PERIMETER WALL)
Status: 23TH Floor
•Manpower: 5 Mason & 5 Labor•Productivity: 2 days/floor•Gap from Structural: 5 Floors
…back to Front Elevation
Punchlist(Exterior)
Status: 19TH Floor
•Manpower: 1 Mason (subcon)2 masons (dmci)
•Productivity: 3 days/floor•Gap from Structural: 9 Floors
…back to Front Elevation
RUBBED CONCRETE(INTERIOR)
Status: 18TH Floor
•Manpower: 24 Mason•Productivity: 10 days/floor•Gap from Structural: 10 Floors
•Target gap: 4 floors•Target productivity: 7 days/floor•Cause of delay: lack of manpower•Additional manpower needed: 24 masons until 3rd week of January
…back to Front Elevation
CHB LAYING(PARTITION & T&B)
Status: 23RD Floor
•Manpower: 15 Mason & 15 Labor•Productivity: 7 days/floor•Gap from Structural: 5 Floors
…back to Front Elevation
WATERPROOFINGAPPLICATION
(T&B))
Status: 20TH Floor
•Manpower: 3 pax•Productivity: 6 days/floor•Gap from Structural: 7 Floors
•Target Productivity: 3 days/floor•Target gap: 5 floors•Cause of delay: lack of manpower•Additional manpower needed: 4 pax
…back to Front Elevation
PLASTERING WORKS
PLASTERING (LDK)
Status : 22ND floor
•Manpower: 21 Mason & 21 Labor•Productivity: 7 days/floor•Gap on Structural: 6 floors
PLASTERING (T&B)
Status : 19th floor
•Manpower: 9 Mason & 9 Labor•Productivity: 7 days/floor•Gap on Structural: 9 floors
•Cause of Delay: Waterproofing application
…back to Front Elevation
PUNCHLIST
PUNCHLIST (LDK)
Status : 17TH & 18TH floor
•Manpower: 2 Mason & 2 Labor•Productivity: 7 days/floor•Gap on Structural: 9 floors
•Target Productivity: 4 days/floor•Target gap: 6 floors•Cause of delay: lack of manpower•Additional Manpower: 1 mason & 1 labor
PUNCHLIST (T&B)
Status : 17th floor
•Manpower: 3 Mason & 2 Labor•Productivity: 7 days/floor•Gap on Structural: 10 floors
•Taret Productivity: 4 days/floor•Target gap: 7 floors•Cause of Delay: tiling works•Additional Manpower: 1 Mason & 1 Labor
…back to Front Elevation
PRIMER PAINTAPPLICATION(perimeter)
Status: 20TH Floor
•Manpower: 1 Pax•Productivity: 3 days/floor•Gap from Structural: 7 Floors
•Target Productivity: 2 days/floor•Target gap: 5 floors•Cause of delay: Exterior Rubbed Concrete, punchlist
…back to Front Elevation
SKIMCOAT APPLICATION(perimeter)
Status: 18TH Floor
•Manpower: 1 Pax•Productivity: 5 days/floor•Gap from Structural: 9 Floors
•Target Productivity: 2 days/floor•Target gap: 5 floors•Cause of delay: Punchlist
…back to Front Elevation
ALUMINUM DOORS& WINDOWS(perimeter)
Status: 18TH Floor
•Manpower: 7 Pax•Productivity: 7 days/floor•Gap from Structural: 9 Floors
•Target Productivity: 3 days/floor•Target gap: 5 floors•Cause of delay: Skimcoat Application
…back to Front Elevation
SKIMCOAT APPLICATION
(interior)
Status: 17TH Floor
•Manpower: 14 Pax•Productivity: 7 days/floor•Gap from Structural: 10 Floors
•Target Productivity: 5 days/floor•Target gap: 6 floors•Cause of delay: Interior rubbed Concrete, Punchlist
…back to Front Elevation