ppt metro
-
Upload
vipul-rathi -
Category
Documents
-
view
186 -
download
4
Transcript of ppt metro
Training underDMRC
About Project:About Project: Jaipur Metro Rail is proposed to be setup on Jaipur Metro Rail is proposed to be setup on
Public Private Partnership (DBFOT) model. The Public Private Partnership (DBFOT) model. The project is going to have two corridors, one project is going to have two corridors, one running from East to West and the other running from East to West and the other running from North to South. The total length is running from North to South. The total length is around 35 Km. around 35 Km.
Major portion of the East West corridor, i.e 9.25 Major portion of the East West corridor, i.e 9.25 Km out of total length of 11.5 Km, is already Km out of total length of 11.5 Km, is already under construction by the Corporation under construction by the Corporation
East-West Corridor - Mansarovar, New East-West Corridor - Mansarovar, New Aatish Market, Vivek Vihar, Shyam Nagar, Aatish Market, Vivek Vihar, Shyam Nagar, Ram Nagar, Civil Lines, Jaipur Railway Ram Nagar, Civil Lines, Jaipur Railway Station, Sindhi Camp Bus Stand, Station, Sindhi Camp Bus Stand, Chandpole, Choti Chaoupar and Badi Chandpole, Choti Chaoupar and Badi Chaoupar.Chaoupar.
East-West Corridor - Mansarovar, New Aatish East-West Corridor - Mansarovar, New Aatish Market, Vivek Vihar, Shyam Nagar, Ram Nagar, Market, Vivek Vihar, Shyam Nagar, Ram Nagar, Civil Lines, Jaipur Railway Station, Sindhi Camp Bus Civil Lines, Jaipur Railway Station, Sindhi Camp Bus Stand, Chandpole, Choti Chaoupar and Badi Stand, Chandpole, Choti Chaoupar and Badi Chaoupar.Chaoupar.
The East-West corridor of the Metro in The East-West corridor of the Metro in Phase 1Phase 1 is is expected to cost Rs expected to cost Rs 1250 crore1250 crore..
East-West Corridor - Mansarovar, New Aatish East-West Corridor - Mansarovar, New Aatish Market, Vivek Vihar, Shyam Nagar, Ram Nagar, Market, Vivek Vihar, Shyam Nagar, Ram Nagar, Civil Lines, Jaipur Railway Station, Sindhi Camp Bus Civil Lines, Jaipur Railway Station, Sindhi Camp Bus Stand, Chandpole, Choti Chaoupar and Badi Stand, Chandpole, Choti Chaoupar and Badi Chaoupar.Chaoupar.
The East-West corridor of the Metro in The East-West corridor of the Metro in Phase 1Phase 1 is is expected to cost Rs expected to cost Rs 1250 crore1250 crore..
The Phase 2 is expected to cost Rs 7000 crore The Phase 2 is expected to cost Rs 7000 crore
Here are some facts about the Jaipur:Here are some facts about the Jaipur:
• • Number of lines in Jaipur Metro Railways: 2Number of lines in Jaipur Metro Railways: 2• Number of stations : 12 (phase 1)• Number of stations : 12 (phase 1)• Daily ridership: roughly 6 lacks (one way).• Daily ridership: roughly 6 lacks (one way).• Operation Began: 2010 (line 1)• Operation Began: 2010 (line 1)• System length: 32.5 kilometers • System length: 32.5 kilometers • Track gauge: 1,435 mm (4 ft 8+1⁄2 in) • Track gauge: 1,435 mm (4 ft 8+1⁄2 in) • Electrification: 25 kV, 50 Hz AC through overhead • Electrification: 25 kV, 50 Hz AC through overhead • Average speed: 33 km/h (21 mph)• Average speed: 33 km/h (21 mph)• Top speed: 80 km/h (50 mph)• Top speed: 80 km/h (50 mph)• • Jaipur metro rail start dateJaipur metro rail start date: Around June 2013.: Around June 2013.
Delhi Metro Rail CorporationDelhi Metro Rail Corporation
INTRODUCTIONINTRODUCTION For implementation and subsequent For implementation and subsequent
operation of Delhi MRTS, a company operation of Delhi MRTS, a company under the name DELHI METRO RAIL under the name DELHI METRO RAIL CORPORATION was registered on 03-CORPORATION was registered on 03-05-95 under the Companies Act, 05-95 under the Companies Act, 1956. DMRC has equal equity 1956. DMRC has equal equity participation from GOI and GNCTD.participation from GOI and GNCTD.
Pile Foundation
Construction of Construction of Pile FoundationPile Foundation of the elevated structure for the of the elevated structure for the
transition of transition of Metro Rail Metro Rail & also for & also for the the Metro StationsMetro Stations..
Indian Standards on PilesIndian Standards on Piles
IS 2911 : Part 1 : Sec 1 : 1979 Driven cast in-situ concrete IS 2911 : Part 1 : Sec 1 : 1979 Driven cast in-situ concrete pilespiles
IS 2911 : Part 1 : Sec 2 : 1979 Bored cast-in-situ pilesIS 2911 : Part 1 : Sec 2 : 1979 Bored cast-in-situ piles IS 2911 : Part 1 : Sec 3 : 1979 Driven precast concrete pilesIS 2911 : Part 1 : Sec 3 : 1979 Driven precast concrete piles IS 2911 : Part 1 : Sec 4 : 1984 Bored precast concrete pilesIS 2911 : Part 1 : Sec 4 : 1984 Bored precast concrete piles IS 2911 : Part 2 : 1980 Timber pilesIS 2911 : Part 2 : 1980 Timber piles IS 2911 : Part 3 : 1980 Under reamed pilesIS 2911 : Part 3 : 1980 Under reamed piles IS 2911 : Part 4 : 1985 Load test on pilesIS 2911 : Part 4 : 1985 Load test on piles
Pile foundations are adopted generally in the Pile foundations are adopted generally in the following situationfollowing situation
• • Low Bearing Capacity of soil.Low Bearing Capacity of soil.
• • Non availability of proper bearing stratum at Non availability of proper bearing stratum at shallow shallow depths. depths.
• • Heavy loads from the super structure for Heavy loads from the super structure for which which shallow foundation may not be shallow foundation may not be economical or economical or feasible. feasible.
Pile Foundations
Classification of Piles :Classification of Piles : Based on material Based on material
ConcreteConcrete SteelSteel TimberTimber
Classification of Piles :Classification of Piles : Based on material Based on material
ConcreteConcrete SteelSteel TimberTimber
Based on method of construction/installation.:Based on method of construction/installation.: Driven /Displacement Pre cast Piles Driven /Displacement Pre cast Piles Driven/Displacement Cast in Situ Piles Driven/Displacement Cast in Situ Piles Bored/ Replacement Pre cast piles Bored/ Replacement Pre cast piles Bored/ Replacement Cast in situ pilesBored/ Replacement Cast in situ piles
Classification of Piles :Classification of Piles : Based on material Based on material
ConcreteConcrete SteelSteel TimberTimber
Based on method of construction/installation.:Based on method of construction/installation.: Driven /Displacement Pre cast Piles Driven /Displacement Pre cast Piles Driven/Displacement Cast in Situ Piles Driven/Displacement Cast in Situ Piles Bored/ Replacement Pre cast piles Bored/ Replacement Pre cast piles Bored/ Replacement Cast in situ pilesBored/ Replacement Cast in situ piles
Based on Load transfer mechanism:Based on Load transfer mechanism: Friction/Floating pilesFriction/Floating piles Bearing cum Friction piles Bearing cum Friction piles
Based on sectional area :Based on sectional area : CircularCircular SquareSquare H ShapeH Shape OctagonalOctagonal TubularTubular
Based on sectional area :Based on sectional area : CircularCircular SquareSquare H ShapeH Shape OctagonalOctagonal TubularTubular
Based on size:Based on size: Micro piles Dia. < 150 mmMicro piles Dia. < 150 mm Small dia. Pile Dia. > 150 mm and Dia. < 600 mmSmall dia. Pile Dia. > 150 mm and Dia. < 600 mm Large Dia. Piles Dia. > 600 mmLarge Dia. Piles Dia. > 600 mm
SOFT SOILPILES
We used Friction Piles in Metro Foundation
If the firm soil is at a considerable depth, it may be very expensive to use end bearing piles. In such situations, the piles are driven through the penetrable soil for some distance. The piles transmit the load of structure to the penetrable soil by means of skin friction between the soil.
Method ForMethod ForThe ConstructionThe Construction OfOf Pile Pile
FoundationFoundation
The following steps were observed in the The following steps were observed in the construction:construction: SETTING OUTSETTING OUT DRIVING OF TEMPORARY CASINGDRIVING OF TEMPORARY CASING BoringBoring REINFORCEMENT CAGE LOWERINGREINFORCEMENT CAGE LOWERING REINFORCEMENT COVER BLOCKREINFORCEMENT COVER BLOCK FLUSHING OPERATIONFLUSHING OPERATION CONCRETINGCONCRETING
S.No. DESCRIPTION TYPE CAPACITY
1. Pilling Rig Mait HR 130 130 KN
2. Crane TATA 320
3. Excavator JCB .25 cum
4. Dumpers TATA/AL 4 cum
5. Batching Plant M1 30 cum/hr
6. Transit Mixers 6/4 cum
7. Welding Generator 400 Amps
8. Tremie Pipe 250 mm dia 25-35 mt
9. Hopper
CONSTRUCTION EQUIPMENTS
Soil BucketSoil Bucket
Light weightLight weight Large storage Large storage
capacitycapacity DurableDurable ReliableReliable
Tremie PipesTremie Pipes
quick disconnect quick disconnect couplings couplings
O ring seals for O ring seals for easy installationeasy installation
leak proof leak proof connectionsconnections
Various lengths Various lengths can be providedcan be provided
METHODOLOGYMETHODOLOGY
SETTING OUT:SETTING OUT: Necessary survey was conducted and Necessary survey was conducted and
pile points were marked. The pile pile points were marked. The pile location was set out with respect to the location was set out with respect to the control points by suitable pin marked at control points by suitable pin marked at location and checked by Engineer’s location and checked by Engineer’s representative.representative.
DRIVING OF TEMPORARY CASING:DRIVING OF TEMPORARY CASING:
• Rotating drilling rig fitted with suitable tool (soil boring tool) to be positioned at the pre-marked pile point and boring was started
• On completion of boring up to about 1m casing pipe was installed in position using special attachment to the rotary head
• Diameter of the cutting tool was diameter of the pile minus 75mm
Material UsedMaterial Used::
Bentonite:Bentonite:
used to stabilize the sides of the used to stabilize the sides of the pile borehole.pile borehole.
Bentonite was saturated for Bentonite was saturated for 24hrs and then used.24hrs and then used.
Frequency test: 24hrs after Frequency test: 24hrs after mixing, prior to concreting.mixing, prior to concreting.
The properties of bentonite slurry The properties of bentonite slurry met at the site were:met at the site were:
S.no. Type of test Required Value
Equipment to be used
1. Mud density 1.05 g/cc Hydrometer
2. Viscosity prior to concrete
30 – 40 second Marsh cone
3. pH value 9.5 to 12 pH meter
4. Sand content 1% Sieve Analysis
5. Liquid limit 400% Casagranda
Concrete:Concrete:
Grade of concrete: M35Grade of concrete: M35 Slump of concrete: 150 to 200 mmSlump of concrete: 150 to 200 mm The maximum size of Coarse aggregate was The maximum size of Coarse aggregate was
20mm20mm The cement used for pilling work as per IS:455 The cement used for pilling work as per IS:455
specification for Portland slag cement.specification for Portland slag cement. Minimum cement content for the design mix Minimum cement content for the design mix
was not kept less than 400kg/mwas not kept less than 400kg/m33
Reinforcement Steel:Reinforcement Steel:
TMT bars were used.TMT bars were used. G.I wires were used for binding reinforcement.G.I wires were used for binding reinforcement. Bending of reinforcement was as per IS: Bending of reinforcement was as per IS:
25021963.25021963. The reinforcement was extended to the full The reinforcement was extended to the full
length of the pile and was projected 60 times length of the pile and was projected 60 times diameter above the cut-off level.diameter above the cut-off level.
BORINGBORING
Initial Boring of Initial Boring of 1.5 meters was 1.5 meters was done by using done by using augerauger
temporary temporary casing was casing was installed in the installed in the boreholeborehole
Bentonite suspension was then filled in the Bentonite suspension was then filled in the borehole for stabilising sides before starting borehole for stabilising sides before starting boring below bottom of temporary slurryboring below bottom of temporary slurry
The level of bentonite was always kept 1.5 meters The level of bentonite was always kept 1.5 meters above the bottom of casing during grabbingabove the bottom of casing during grabbing
Further boring was done using soil bucket till the Further boring was done using soil bucket till the required depth was reachedrequired depth was reached
Once the bore has depth has reached to the Once the bore has depth has reached to the desired depth, the bottom of the bore was desired depth, the bottom of the bore was cleaned by Bentonite flushingcleaned by Bentonite flushing
REINFORCEMENT CAGE REINFORCEMENT CAGE LOWERINGLOWERING
The reinforcement was cut and bent to The reinforcement was cut and bent to required shape and sizerequired shape and size
The reinforcement cage was fabricated at the fabrication yard The reinforcement cage was fabricated at the fabrication yard and was transported to the siteand was transported to the site
Specified cover blocks were provided to the reinforcement Specified cover blocks were provided to the reinforcement cage for the pilecage for the pile
The cage was lowered in 3 pieces or more depending upon the The cage was lowered in 3 pieces or more depending upon the length of pile.length of pile.
Bottom cage was lowered inside the borehole and temporarily Bottom cage was lowered inside the borehole and temporarily supported on the casing pipe top, keeping the dowel length supported on the casing pipe top, keeping the dowel length projecting above and second cage lifted and lapped by projecting above and second cage lifted and lapped by welding.welding.
The minimum lap length was 60d. Helical was tied more The minimum lap length was 60d. Helical was tied more closely at the welding zone then the whole cage length.closely at the welding zone then the whole cage length.
The whole cage then lowered inside The whole cage then lowered inside the bore hole. the reinforcement was the bore hole. the reinforcement was projected 60 times bar diameter projected 60 times bar diameter above the cut off level.above the cut off level.
REINFORCEMENT COVER REINFORCEMENT COVER BLOCKBLOCK
Circular cover blocks of 150mm Circular cover blocks of 150mm diameter was made with the same diameter was made with the same grade of concrete as that of pile grade of concrete as that of pile concrete and fixed to helical.concrete and fixed to helical.
The cover block was provided at The cover block was provided at approximately 2m intervals and approximately 2m intervals and suitably staggered.suitably staggered.
FLUSHING OPERATIONFLUSHING OPERATION Before concreting the borehole was flushed again with Before concreting the borehole was flushed again with
fresh bentonite suspension. Immediately after lowering of fresh bentonite suspension. Immediately after lowering of the cage.the cage.
Tremie pipes of 250mm diameter of length 1.5m length Tremie pipes of 250mm diameter of length 1.5m length were joined together and lowered into the bore and the were joined together and lowered into the bore and the bentonite was pumped through the pipe.bentonite was pumped through the pipe.
During flushing, contaminated bentonite from bottom of During flushing, contaminated bentonite from bottom of the pile was collected in the tank through Tremie outlet & the pile was collected in the tank through Tremie outlet & fresh bentonite was pumped to maintain the bentonite at fresh bentonite was pumped to maintain the bentonite at required level.required level.
Flushing was continued till the density of the return mud Flushing was continued till the density of the return mud was less then 1.2gm/cc.was less then 1.2gm/cc.
CONCRETINGCONCRETING
• The concrete was placed in the bore through the tremie pipe.• The bottom of the tremie was 300mm above the bottom of the bore.• During concreting the care was taken to keep the tremie pipe 1.5m embedded in the concrete.
On completion of concreting to the On completion of concreting to the required level elevation, temporary required level elevation, temporary casing was withdrawn either by the casing was withdrawn either by the crane or drilling rig.crane or drilling rig.
The grade of concrete used in the The grade of concrete used in the pile was M35.pile was M35.
Workability of concrete and concrete Workability of concrete and concrete cubes were prepared to check the cubes were prepared to check the strength of concrete after 7 and 28 strength of concrete after 7 and 28 days.days.
Cast in Situ Replacement Cast in Situ Replacement PilePile
Advantage Disadvantages Less noise or vibration problem Concrete cannot be inspected after
installation
Equipment can break up practically all kinds of obstructions
Liable to squeezing or necking
Can be installed in a very long length Raking bored pile are difficult to construct
No ground heave Drilling a number of pile groups may cause ground loss and settlement of adjacent structures
Depth and diameter can varied easily Cannot be extended above ground level without special adaptation
UNDERGROUND METRO UNDERGROUND METRO STATION AT CHANDPOLESTATION AT CHANDPOLE
GENERAL ABOUT THE PROJECT GENERAL ABOUT THE PROJECT FOR UNDERGROUND METRO FOR UNDERGROUND METRO
STATIONSTATION SCOPE- Construction of guide wall, trench SCOPE- Construction of guide wall, trench excavation under bentonite, placing of excavation under bentonite, placing of reinforcement cage and concreting of reinforcement cage and concreting of diaphragm wall.diaphragm wall.
OWNER- DMRCOWNER- DMRC
CONTRACTOR- ITD Cementation India Ltd.CONTRACTOR- ITD Cementation India Ltd.
TOTAL COST- 102Cr(approx)TOTAL COST- 102Cr(approx)
LIST OF MAJOR PLANTS AND LIST OF MAJOR PLANTS AND EQUIPMENTSEQUIPMENTS
S NO.
Plant/Equipment Type Number
1. 75t Capacity Crawler Excavation Crane/(Service)
2
2. Hydraulic and/or Rope Grabs 1
3. Bentonite Facility and Equipment 1(set)
4. Stopend System As required
Continue …Continue …
S NO. Plant/Equipment
Type
Number
5. Stopend Chisel As required
6. Tremie Pipe System(250mmdia) inc Hopper
2
7. Welding Sets 4
METHODOLOGY FOR THE METHODOLOGY FOR THE CONSTRUCTION OF DIAPHRAGM CONSTRUCTION OF DIAPHRAGM
WALLWALL
The following steps were observed in the The following steps were observed in the construction:construction:
1.1.Guide WallGuide Wall
2.2.Bentonite MixingBentonite Mixing
3.3.ExcavationExcavation
CONTINUE …CONTINUE …
4.4. Installation Of Stopened And Installation Of Stopened And WaterstopenedWaterstopened
5.5. Reinforcement & ConcretingReinforcement & Concreting
GUIDE WALLGUIDE WALL
It is temporary structure constructed It is temporary structure constructed priorprior
to excavation of diaphragm wall.to excavation of diaphragm wall.
Purpose of guide wall:Purpose of guide wall: To ensure the stability and prevent To ensure the stability and prevent
the collapsing of the soil strata.the collapsing of the soil strata. To provide temporary support for To provide temporary support for
the reinforcement cage.the reinforcement cage. To provide the supports to Stopend.To provide the supports to Stopend.
STRUCTURAL DETAILS OF STRUCTURAL DETAILS OF GUIDE WALLGUIDE WALL
Grade of concrete- M15Grade of concrete- M15
Thickness of Guide wall- 150mmThickness of Guide wall- 150mm
Depth of Guide wall- 1500mmDepth of Guide wall- 1500mm
Continue…Continue…
Clear cover- 25mmClear cover- 25mm
Dia. of steel used- 10mm & 8 mm at a Dia. of steel used- 10mm & 8 mm at a distance of 250mm center to center.distance of 250mm center to center.
Clear distance between inner faces of Clear distance between inner faces of guide wall-600mm(diaphragm wall)guide wall-600mm(diaphragm wall)+50mm+50mm
Guide wall Guide wall
BENTONITE MIXINGBENTONITE MIXING
Mixing unit was erected on impermeable Mixing unit was erected on impermeable base to check spillage.base to check spillage.
Kept in storage tank for 24hrs to hydrate.Kept in storage tank for 24hrs to hydrate.
Continuously agitated using vertical pump.Continuously agitated using vertical pump.
Daily bentonite test that were conducted-Daily bentonite test that were conducted- 1. ph- 8.91. ph- 8.9 (9to11.5 as IS code9556-1980)(9to11.5 as IS code9556-1980)
2. Density- 1.112. Density- 1.11 (1.06to1.12 as Is code 9556-1980)(1.06to1.12 as Is code 9556-1980)
Bentonite Bentonite 3. Sand 3. Sand
Content-Content-fresh(2%) & fresh(2%) & contaminatcontaminated(3%){7% ed(3%){7% as per Is as per Is code 9556-code 9556-1980}1980}
4. Viscosity- 4. Viscosity- 45sec(32-45sec(32-90 sec as 90 sec as per Is code-per Is code-9556-1980)9556-1980)
Mixing Tank for Bentonite
DIAPHRGAM WALL DIAPHRGAM WALL EXCAVATIONEXCAVATION
Wall is located between Guide wall.Wall is located between Guide wall. The trench was excavated using The trench was excavated using
Hydraulic Drilling Rig .Hydraulic Drilling Rig . Stopened with water stopened was Stopened with water stopened was
then lowered into the trench.then lowered into the trench. Excavation was done in three Excavation was done in three
panel(primary, secondary & closing).panel(primary, secondary & closing). Excavation was done with bentonite Excavation was done with bentonite
filled to top level.filled to top level.
Diaphrgam wallDiaphrgam wall
REINFORCEMENT & REINFORCEMENT & CONCRETINGCONCRETING
Grade of steel- Fe500Grade of steel- Fe500
Grade of concrete- M35Grade of concrete- M35
Dia of steels used- 35mm & Dia of steels used- 35mm & 25mm25mm
Continue …Continue …
Minimum clear cover- 75mmMinimum clear cover- 75mm
Shape of cover blocks- CircularShape of cover blocks- Circular
Horizontal distance of cover blocks- Horizontal distance of cover blocks- 1500mm1500mm
• Vertical distance of cover blocks-2000mm
• Dia of tremie pipe- 250mm
• Length to which pipe was dipped inside the concrete- 2m
• Concreting was done to 1m above the cut off level.
Concreting of Diaphrgam wallConcreting of Diaphrgam wall
Slump Test Slump Test
The test is an empirical test that The test is an empirical test that measures the workability of fresh measures the workability of fresh concrete. More specifically, it measures concrete. More specifically, it measures consistency between batches. The test is consistency between batches. The test is popular due to the simplicity of popular due to the simplicity of apparatus used and simple procedure. apparatus used and simple procedure. The slump test is used to ensure The slump test is used to ensure uniformity for different batches of similar uniformity for different batches of similar concrete under field conditions.concrete under field conditions.
Types of slumpTypes of slump
Continue…Continue…
Collapse Shear True
In a collapse slump the concrete collapses completely. [2]
In a shear slump the top portion of the concrete shears off and slips sideways.[2]
In a true slump the concrete simply subsides, keeping more or less to shape.[2]
Slump TestSlump Test
Thank you…Thank you…