Power Scenario India
Transcript of Power Scenario India
ANIL KUMAR
NPTI, FBD
NPTI
POWER SECTOR-AN OVERVIEW
Electricity - ‘Concurrent Subject’ : joint responsibility of State and Central Governments.
Bulk of transmission and distribution functions with State Utilities.
Private sector - small presence in Distribution and making entry into Transmission.
POWER SECTOR-AN OVERVIEW
Conventional Generation - blend of thermal, hydro and nuclear sources.
Coal based thermal power plants and in some regions hydro power plants - mainstay of electricity generation.
Oil, natural gas and nuclear power accounts for smaller proportion of power.
Emphasis also on non-conventional energy sources i.e. solar, wind, biogas and tidal.
Captive power plants being encouraged to supply surplus power to Grid.
GROWTH OF INSTALLED GENERATING CAPACITY IN INDIA
'47 '55 '61 '66 '74 '80 '85 '90 '95 '02 '03 '04 '06 '07 '12(Projeced)
Thermal Nuclear
Hydro Renewable
1,36
2
2,69
5
4,65
3
9,02
7
16,6
64
28,4
48 42,5
85
81,1
71
63,6
36
1,05
,046
1,07
,877
1,18
,426
1,24
,287
2,24
,907
*
1,32
,329
Source: CEA
(figs. in MW)
* includes Likely capacity Addition of 14000 MW from Renewables during 11th plan period
ALL INDIA PLF (%) OF THERMAL POWER STATIONS(COAL AND LIGNITE BASED)
Source: CEA
56. 555
56. 5
53. 955. 3
57. 1
60
64. 6
67. 369
69. 9
72. 7
74. 374. 8
72. 2
6164. 4 64. 7
53. 2
63
52. 4
76. 878. 6
48
53
58
63
68
73
78
Years
C HA R T : 13
MAJOR LEGISLATIVE / POLICY INITIATIVES
OF GOVERNMENT
1998- Electricity Regulatory Commission Act
1998 - Electricity Laws (Amendment) Act
2001- Electricity Conservation Act
2003- Electricity Act
February ,2005- National Electricity Policy
January 2006- National Tariff Policy
August 23, 2006 - Rural Electrification Policy
August 2006- Integrated Energy Policy.
January 2007- Report submitted by Working Group on Power for 11th Plan constituted by Planning Commission.
August,2007 - National Electricity Plan notified.
• Access to electricity for all households in next 5 years.
• Availability of power on demand to be fully met by 2012
• Energy shortage and peaking shortage to be overcome by providing adequate spinning reserves
• Reliability and quality of power to be supplied in efficient manner .
• Electricity Sector to achieve financial turnaround and commercial viability
• Consumers’ interests to be accorded top priority.
NATIONAL ELECTRICITY POLICY – THE WAY FORWARD
INSTALLED CAPACITY IN THE COUNTRY (as on 31st August, 2008)
TOTAL IC-1,45,627 MW
R.E.S., 12195 8.4%
NUCLEAR 4120 2.8%
THERMAL 93115 64%
HYDRO, 36198, 24.8%
EVOLUTION OF UNIT SIZE OF COAL BASED POWER PLANTS
Largest unit size in 1950-30 MW First re-heat unit of 82.5 MW in 1966 at
Bandel TPS First 200 MW unit at Obra TPS in 1977 First 500 MW unit at Trombay in 1984 Committee constituted by CEA
recommended 800 to 1000 MW unit size in future
In 11th Plan 800/660 MW units planned
CENTRAL ELECTRICITY AUTHORITY
MINISTRY OF POWER
GOVERNMENT OF INDIA
Details of IC of renewable energy sources
(As on 31.03.2008)
Sources / Systems Installed Capacity ( MW)
Wind Power 7666.84Biomass Power & Biomass Gasifiers
1325.63
Small Hydro Power 2034.07Solar power & others 87.87Total 11,125.41
Development of Transmission Voltages Levels
• 132 kV Highest level at the time of Independence
• Introduction of 220 kV in 1960
• 400 kV in 1977
• HVDC back-to-back link in 1989,
• 500kV, HVDC bi-pole line in 1990
• 765 kV transmission line from 2000 onwards.
PER CAPITA CONSUMPTION OF ELECTRICITY IN INDIA
Source: CEA
176
348
559632 672 704
1000
613
1980-81
1990-91
2000-01
2004-05
2005-06
2006-07
2007-08
2011-12
kWh/year
(Projected)
As per UN Methodology (Gross Electrical Energy Availability / Population)
Growth Pattern
ACTUAL POWER SUPPLY POSITION OF THE COUNTRY (April,08-August,08)
Peak (MW) Energy (MU)
Requirement 1,06,922 3,18,813
Availability 91,363 2,84,861
(-)Shortage/
(+)Surplus
(-) 15,559 (-)33,952
(%) (-) 14.6 (-) 10.6
10TH PLAN –TARGET AND ACTUAL CAPACITY ADDITION
6
(MW)
Original Target 41,110
Capacity Slipped / Dropped 21,281
Net Capacity Addition from Original Target 19,829
Additional Projects identified during the Plan 8,320
Capacity Slipping from additional projects 6,969
Net Capacity Addition from additional Projects 1,351
Net Capacity added during 10TH Plan 21,180*
* Thermal -12,114 MW, Hydro – 7,886 MW, Nuclear – 1180 MW
POWER GENERATION - STRATEGY
• Large emphasis on hydro development. Constraints restricting progress are large gestation period, high capital cost, Issues such as R&R, law & order etc. New Hydro Policy to encourage private participation in hydro power generation.
• Limited dependability on gas based capacity - Availability of gas at reasonable rates being a constraint for gas based projects. During 11th Plan only about 6,843 MW gas based capacity envisaged.
• Active steps to harness Nuclear energy on a larger scale being taken but contribution minor as yet.
• Renewables.
POWER GENERATION - STRATEGY
CENTRAL ELECTRICITY AUTHORITY
MINISTRY OF POWER
GOVERNMENT OF INDIA
POWER GENERATION - STRATEGY
• Renewable energy sources to be made economically viable- At present can play dominant role in meeting remote located demands where not economic to extend the grid.
• Coal based power projects expected to be main stay of Indian Power Sector for next 50-70 years. Continuous efforts directed at generating maximum energy from each tonne of coal with minimum effect on environment
POWER GENERATION - STRATEGY
CENTRAL ELECTRICITY AUTHORITY
MINISTRY OF POWER
GOVERNMENT OF INDIA
Development of Hydro Power projects
Plan Period Hydro Capacity Addition (MW)
Total Hydro Capacity at the end of plan (MW)
11th Plan (2007-08 to 2011 - 12)
15627 50280
12th Plan (2012-13 to 2016-17)
30000 80280
13th Plan (2017 - 18 to 2021-22)
31000 111280
14th Plan (2022-23 to 2026 - 27)
36494 147774
DEMAND AND CAPACITY REQUIREMENT
Year Energy Requirement
(BU)
Peak Demand
(MW)
Proposed Capacity Addition during 5 year plan (MW)
Generation growth rate (CAGR)
2011-12 1038 1,52,000 77,070*
( 11th Plan)
9.5% (over 2006-07)
2016-17 1470 2,18,209 94,000
(12th Plan)
7.4% (over 2011-12)
* Feasible capacity as per latest assessment
26,783 MW36,874 MW
15,043 MW
CENTRAL SECTORSTATE SECTOR
PVT SECTOR
47%(34%)
(19%)
Total 78,700 MW
CAPACITY ADDITION TARGETTED FOR 11th PLAN (SECTORWISE)
INTERNATIONAL CONCLAVE ON KEY
INPUTS
On 4th-5th July,2007 organized by CBIP/MoP/CEA.
Purpose-To discuss issues to be addressed to ensure timely Implementation of projects during 11th Plan and beyond .
11th Plan tentative targets for grid interactive renewable power
(Figures in MW)
Sources / Systems Target for 11th plan
Wind Power 10,500
Biomass Power Baggasse Co-generation Biomass Gasifiers
2,100
Small Hydro (up to 25 MW) 1400
Total 14,000
Targets for 12th Plan likely to be at least 14,000 MW
Village Electrification
Number of villages electrified increased from 3061 in 1950 to about 4,88,655 in 2008 (as on 31.07.08, 82.3% village electrification).
Renewable Energy Sources during 12th Plan
• Capacity addition during 12th Plan expected to be more than 11th Plan due to incentives by MNRE for setting up of Solar and Wind power plants
• Considering at least 14,000 MW during 12th Plan also, by 12th Plan end about 38,000 MW Renewable power expected.
• Assuming PLF of 20 %, generation about 67 BU.
• This energy considered while planning for 12th Plan
12th Plan Tentative Capacity Addition • Demand as per 17th EPS – Energy Requirement – 13,92,066
BU; Peak Demand- 2,18,209 MW• Spinning Reserve – 5% as per National Electricity Policy.
Capacity corresponding to 3000 MW and 1600 MW also worked out
• 25,000 MW Hydro and 8,500 MW Nuclear as must run stations.• As result of studies 12th Plan total Generating capacity 94,431
which includes 61,171 MW thermal.(28,190 MW PH, 15,495 MW LC, 14,800 MW Coastal)
• Capacity with 1600 MW S.R.- 81,570 MW; 3000MW S.R. – 82,970 MW
• Fuel consumption(2016-17) – Coal 815 MT, Lignite 60 MT• All India Studies for 5% S.R: LOLP – 0.18%; ENS – 0.00%
(Norms – LOLP-1% & ENS- 0.15%)
13th Plan Tentative Capacity Expansion
ASSUMPTIONS• 17th EPS Demand – Energy Requirement- 19,14,508
MU; Peak Demand- 2,98,253 MW • Spinning Reserve - 5% .• Beginning of 13th Plan 37,014 MW Coal & Lignite
based capacity more than 27 yrs old. (5,634 MW capacity upto 100 MW unit size and 31,380 MW capacity greater than 100 MW unit
size) • Studies indicate 13th Plan capacity addition-1,05,060
MW (Hydro-34,500 MW, Nuclear -8,000 MW, Thermal -62,560 MW including 6000 MW gas)
• LOLP-0.18 % and ENS-0.007 %, Reliability Criteria met.
Strategies/ Initiatives for GHG Mitigation
• Clean Coal technologies Supercritical Technology – 2% efficiency gain possible Ultra Supercritical Technology –additional efficiency 0.75% over
800 MW supercritical Integrated Gasification Technology – higher efficiency of 40-
45%
• Reduction in T & D losses – All India T&D losses- 28.65% in 2006-07. Aim to bring down to 15%
• R & M of old thermal power stations – Benefits of CDM to be extended to overcome fund constraints
• Energy Efficiency improvement
TECHNOLOGIES USED AT COMBUSTION STAGE
• Adoption of Supercritical technology• Ultra supercritical (USC) and advanced USC
technology• Circulating Fluidized Bed Combustion ( CFBC)• Pressurized Fluidized Bed Combustion (PFBC)• Integrated Gasification Combined Cycle (IGCC)• In-Situ gasification• Low NOx burners• Oxy-fuel combustion
Clean coal technologies( CCT) – have pollution abatement in energy conversion process so external environmental control equipments not required
CENTRAL ELECTRICITY AUTHORITY
MINISTRY OF POWER
GOVERNMENT OF INDIA
Sub-critical units in 10th, 11th , 12th, 13th & 14th Plans
600 MW
(nos)
500 MW
(nos)
250/300/330 MW
(nos)
200/210 MW
(nos)
125/135 MW
(nos)
Total Subcritical
MW
10TH Plan 0 11 7 9 4 9620
11TH Plan 8 42 62 6 14 45470
12th Plan 7 20 12 0 2 18270
13TH Plan 0 8 0 0 0 4000
14th Plan 0 0 0 0 0 0
Super-critical units in 10th , 11th , 12th , 13th & 14th Plans
Total Sub critical
MW
660 MW
(nos)
800 MW
(nos)
Total
Super critical MW
Total MW
10TH Plan 9620 0 0 0 9620
11TH Plan 45470 7 1 5420 50890
12th Plan 18270 25 33 42,900 61,170
13TH Plan 4000 36 36 52,560 56,560
14th Plan 0 45 52 71,300 71,300
ALL INDIA EFFICIENCY AND EMISSION RATES
• All India thermal efficiency – 32.44% (2006-07)
(coal & lignite based plants)
• Present weighted average CO2 emission rate (t CO2 /MWh) (including imports) : 0.80 (2006-07)
Likely Coal Based Capacity Addition & Expected Emission
End of The Plan
CoalBasedCapaci
tyAdditio
n(MW)
Cumulative
Coal Base
dCapacity
(MW)
Total Generation from Coal
Based Plants
(BU)
CoalConsumpt
ion(MT)
Co2 Emissio
n(MT)
Co2 Emissio
n per unit of
Thermal Generat
ion
Expected Thermal
Efficiency
Total Ash Generation
(MT)
11th Plan 50240 116610 708 492 722 1.02 35.3 182
12th Plan 58485 175095 1164 785 1152 0.99 36.4 278
13th Plan 56500 231595 1542 1028 1507 0.97 36.85 363
14th Plan 72000 303595 2033 1337 1961 0.96 37.3 471