PMP05 Project Quality Management

Transcript of Pmp 05 Project Quality Management

Page 1: Pmp 05 Project Quality Management

Project Quality ManagementBased on PMBOK 5th Edition

Abdelrahman Sheta, PMP,ITIL

1PMP - Project Quality Planfacebook.com/Sheta.Page

Page 2: Pmp 05 Project Quality Management

Agenda

PMP - Project Quality Plan 2

Quality Theories

Evolution of Quality Management

8.1 Plan Quality Management

8.2 Perform Quality Assurance

8.3 Control Qualityfacebook.com/Sheta.Page

Page 3: Pmp 05 Project Quality Management

Quality is the degree to which the project fulfills

requirements.

Quality Management

PMP - Project Quality Plan 3

Quality Management includes creatingand following policies and procedures

in order to ensure that a project meets the defined needs it was intended to meet.

facebook.com/Sheta.Page

Page 4: Pmp 05 Project Quality Management

Joseph Juran: 80/20 principle, top management

involvement. Quality is fitness for use.

W. Edwards Deming: 14stepsof total Quality

Management, Plan-Do-Check-Act cycle.

Philip Crosby: Cost of poor quality,

prevention over inspection and zero

defects. Quality is “conformance to

requirements”

Quality Theorists

PMP - Project Quality Plan 4facebook.com/Sheta.Page

Page 5: Pmp 05 Project Quality Management

Customer Satisfaction

Prevention over inspection

Continuous improvement

Management Responsibility

Cost of Quality (COQ)

ISO Compatibility

PMP - Project Quality Plan 5facebook.com/Sheta.Page

Page 6: Pmp 05 Project Quality Management

Quality is:

A. Meeting & exceeding customer needs.

B. Adding extra to make customer happy.

C. Conformance of requirements and fitness of use

D. Conformance to management’s requirements

Quiz:

PMP - Project Quality Plan 6facebook.com/Sheta.Page

Page 7: Pmp 05 Project Quality Management

PMP - Project Quality Plan 7facebook.com/Sheta.Page

Page 8: Pmp 05 Project Quality Management

8.1 Plan Quality Management

• Identifying quality requirement and/or standards

for the project and its deliverables, and

documenting how the project will demonstrate

compliance with the relevant quality requirements.

PMP - Project Quality Plan 8facebook.com/Sheta.Page

Page 9: Pmp 05 Project Quality Management

1. Project Management Plan,

includes but not limited to Scope baseline

Work Breakdown Structure

WBS Dictionary

Schedule baseline

Cost baseline

Other management Plans

Plan Quality: Inputs (1)

PMP - Project Quality Plan 9facebook.com/Sheta.Page

Page 10: Pmp 05 Project Quality Management

2. Stakeholder Register

3. Risk register

4. Requirements Documentation

5. Enterprise environmental factors

6. Organizational process assets

Plan Quality: Inputs (2)

PMP - Project Quality Plan 10facebook.com/Sheta.Page

Page 11: Pmp 05 Project Quality Management

1. Cost-benefit Analysis2. Cost of Quality (COQ)3. Seven Basic Quality

Tools Cause-and-Effect

Diagram Flowcharts Check-sheet Pareto Diagram Histograms Control Charts Scatter Diagram

Plan Quality: T & T

PMP - Project Quality Plan 11facebook.com/Sheta.Page

Page 12: Pmp 05 Project Quality Management

4. Benchmarking5. Design of Experiments6. Statistical Sampling7. Additional Quality Tools

Brainstorming Force field analysis Nominal Group Technique Quality Management and control

tools

8. Meetings

Plan Quality: T & T

PMP - Project Quality Plan 12facebook.com/Sheta.Page

Page 13: Pmp 05 Project Quality Management

The primary benefit of meeting

quality requirements is less

rework, i.e., higher productivity,

lower costs and increased

stakeholder satisfaction.

The primary cost of meeting

quality requirements is the

expenses associated with quality

management activities.

Cost-benefit Analysis

PMP - Project Quality Plan 13facebook.com/Sheta.Page

Page 14: Pmp 05 Project Quality Management

Cost of Quality

PMP - Project Quality Plan 14facebook.com/Sheta.Page

Page 15: Pmp 05 Project Quality Management

Cost of Quality

PMP - Project Quality Plan 15facebook.com/Sheta.Page

Page 16: Pmp 05 Project Quality Management

Cause and Effect DiagramTrace the problem’s source back to its

“actionable root cause”

PMP - Project Quality Plan 16facebook.com/Sheta.Page

Page 17: Pmp 05 Project Quality Management

FlowchartingA graphical representation of a process showing the

relationships among process steps.

PMP - Project Quality Plan 17facebook.com/Sheta.Page

Page 18: Pmp 05 Project Quality Management

Tally Sheets

PMP - Project Quality Plan 18facebook.com/Sheta.Page

Page 19: Pmp 05 Project Quality Management

Pareto Diagram

PMP - Project Quality Plan 19facebook.com/Sheta.Page

Page 20: Pmp 05 Project Quality Management

Histogram

PMP - Project Quality Plan 20facebook.com/Sheta.Page

Page 21: Pmp 05 Project Quality Management

Graphic displays of the results, over time, of a process; used to assess whether the process is “in control”

Rule of Seven – Run of seven points toward upper or lower control limit may indicate that process is out of control

Assignable causes – Variations may be caused by differences in machines, workers overtime, etc. Identify the root cause.

Control Charts

PMP - Project Quality Plan 21facebook.com/Sheta.Page

Page 22: Pmp 05 Project Quality Management

Control Chart – contd.

PMP - Project Quality Plan 22facebook.com/Sheta.Page

Page 23: Pmp 05 Project Quality Management

Scatter Diagram

PMP - Project Quality Plan 23facebook.com/Sheta.Page

Page 24: Pmp 05 Project Quality Management

Benchmarking involves comparing actual

or planned project practices to those of

other projects in order to generate ideas

for improvement and to provide a

standard by which to measure

performance.

These other projects may be within the

performing organization or outside of it,

and may be within the same or in another

application area.

Benchmarking

PMP - Project Quality Plan 24facebook.com/Sheta.Page

Page 25: Pmp 05 Project Quality Management

Design of Experiment

• Design of experiments is a statistical method

• that helps identify which factors might

influence specific variables. It also plays a role

in the optimization of products or processes.

PMP - Project Quality Plan 25facebook.com/Sheta.Page

Page 26: Pmp 05 Project Quality Management

Statistical sampling involves choosing part of a population of interest for inspection (e.g., selecting 10 samples of 75 electronic components).

Appropriate sampling can often reduce the cost ofquality control.

There is a substantial body of knowledge on statistical sampling; in some application areas, it is necessary for the project management team to be familiar with a variety of sampling techniques.

Statistical Sampling

PMP - Project Quality Plan 26facebook.com/Sheta.Page

Page 27: Pmp 05 Project Quality Management

1. Quality Management Plan

2. Process Improvement Plan Process Boundaries

Process Configuration

Process Metrics

Targets for Improved Performance

3. Quality Metrics

4. Quality Checklist

5. Project Documents Updates

Plan Quality Management: Outputs

PMP - Project Quality Plan 27facebook.com/Sheta.Page

Page 28: Pmp 05 Project Quality Management

Training costs are part of:

A. Prevention costs

B. Appraisal costs.

C. Internal failure costs.

D. External failure costs.

Quiz:

PMP - Project Quality Plan 28facebook.com/Sheta.Page

Page 29: Pmp 05 Project Quality Management

1. Auditing the quality requirements and the

results from quality control measurement

to ensure that appropriate quality

standards and operational definitions are

used.

2. The key benefit of this process is that it

facilitates the improvement of quality

processes

8.2 Perform Quality Assurance

PMP - Project Quality Plan 29facebook.com/Sheta.Page

Page 30: Pmp 05 Project Quality Management

PMP - Project Quality Plan 30facebook.com/Sheta.Page

Page 31: Pmp 05 Project Quality Management

1. Quality Management Plan

2. Process Improvement Plan

3. Quality Metrics

4. Quality Control Measurements

5. Project Documents

Perform Quality Assurance: Input

PMP - Project Quality Plan 31facebook.com/Sheta.Page

Page 32: Pmp 05 Project Quality Management

1. Quality Management and Control Tools

Affinity Diagrams Process Decision Program Charts Interrelationship Digraphs Tree Diagrams Prioritization Matrices Activity Network Diagram Matrix Diagrams

2. Quality Audits

3. Process Analysis

Perform Quality Assurance: T & T

PMP - Project Quality Plan 32facebook.com/Sheta.Page

Page 33: Pmp 05 Project Quality Management

Affinity Diagrams

PMP - Project Quality Plan 33facebook.com/Sheta.Page

Page 34: Pmp 05 Project Quality Management

Process Decision Program Charts (PDPC)

PMP - Project Quality Plan 34facebook.com/Sheta.Page

Page 35: Pmp 05 Project Quality Management

Interrelationship

Digraph

Tree Diagrams

PMP - Project Quality Plan 35facebook.com/Sheta.Page

Page 36: Pmp 05 Project Quality Management

PMP - Project Quality Plan 36facebook.com/Sheta.Page

Page 37: Pmp 05 Project Quality Management

1. Change Requests

2. Project Management Plan Updates

3. Project Documents Updates

4. Organizational Process Assets

Perform Quality Assurance: Output

PMP - Project Quality Plan 37facebook.com/Sheta.Page

Page 38: Pmp 05 Project Quality Management

Who is responsible of the quality

management in the project:

A. Project Quality Manager.

B. Project Manager

C. Project Team members.

D. Quality Assurance Department.

Quiz:

PMP - Project Quality Plan 38facebook.com/Sheta.Page

Page 39: Pmp 05 Project Quality Management

Perform Quality Control is the process of

monitoring and recording results of

executing the quality activities to assess

performance and recommend necessary

changes

The key benefits of this process include

Identifying the causes of poor quality

Validating that project deliverables and

work meet the requirements

8.3 Control Quality (1)

PMP - Project Quality Plan 39facebook.com/Sheta.Page

Page 40: Pmp 05 Project Quality Management

Important Quality terms

Prevention (Keeping errors out of the

process) vs. Inspection (Keeping errors out

of the hands of the customer).

Attribute sampling (either conform or doesn't) vs.

Variables sampling (degree of conformity)

Tolerance (range of acceptable results) and control

limits (thresholds which may indicate out of control)

8.3 Control Quality (2)

PMP - Project Quality Plan 40facebook.com/Sheta.Page

Page 41: Pmp 05 Project Quality Management

PMP - Project Quality Plan 41facebook.com/Sheta.Page

Page 42: Pmp 05 Project Quality Management

1. Project Management Plan

2. Quality Metrics

3. Quality checklists

4. Work Performance Data

5. Approved Change Requests

6. Deliverables

7. Project Documents

8. Organizational Process Assets

Control Quality: Input

PMP - Project Quality Plan 42facebook.com/Sheta.Page

Page 43: Pmp 05 Project Quality Management

1. Seven Basic Quality Tools

2. Statistical Sampling

3. Inspection

4. Approved Change Request Reviews

Control Quality: T & T

PMP - Project Quality Plan 43facebook.com/Sheta.Page

Page 44: Pmp 05 Project Quality Management

1. Quality Control Measurements

2. Validated Changes

3. Verified Deliverables

4. Work Performance Information

5. Change Requests

6. Project Management Plan Updates

7. Project Document Updates

8. Organizational Process Assets Updates (Completed

checklists, lessons learned documentation, etc.)

Control Quality: Output

PMP - Project Quality Plan 44facebook.com/Sheta.Page

Page 45: Pmp 05 Project Quality Management

Quiz:

• When a process considered to be in control, it:

A. Should not be adjusted

B. May not be changed to provideimprovements.

C. Shows differences caused by expected causes.

D. Should not be inspected or reworked for any reason.