Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER...

40
US Contributions to ITER NRC 12/14/07 Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation Planning Process Washington, DC December 14, 2007 “U.S. Contributions to ITER” Major Item of Equipment project

Transcript of Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER...

Page 1: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Plans for U.S. engagementwith ITER Organization

Ned SauthoffU.S. ITER Project Manager

Committee to Review U.S. ITERScience Participation Planning Process

Washington, DCDecember 14, 2007

“U.S. Contributions to ITER” Major Item of Equipment project

Page 2: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

U.S. Contributions to ITER

• Deliverables, as per ITER Agreement:– In-kind hardware– Cash– Staff for the international ITER Organization

• Some governing policies/procedures for US contributions:– ITER Joint Implementing Agreement– DOE Order 413.3 Project Management Order

(for Major Item of Equipment)– Federal Acquisition Regulations– Department of Energy Acquisition Regulations– Buy American Act

Page 3: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

U.S. 2006 ITER In-kind Hardware Contributions

100% ion cyclotrontransmission lines

100% electron cyclotron transmission lines

15% of port-based diagnostics

7 central solenoid windings

75% cooling for divertor, vacuum vessel, …

20% blanket/shield

pellet injector tokamak exhaust processing system

roughing pumps, standard components

8% of toroidal field conductor

steady-state power supplies

Page 4: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

ITER Procurements in-kind

Page 5: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Major Areas of Cost

ITER Sept 2006 Cost Estimate by WBS($M, fully burdened, escalated w/o contingency)

$167.27$164.08

$117.46

$92.35

$83.69

$58.16$54.48

$46.61 $44.26

$25.82

$11.89

-

25

50

75

100

125

150

175

200

1.1.1 Magnet

Systems

1.7 IT Support 1.2.1 Cooling

Water

Systems

1.1.2 / 1.1.3

First Wall &

Shield

Systems / Port

Limiters

1.5.3

Diagnostics

1.6 Project

Support

1.5.2 Electron

Cyclotron

1.3.1 Vacuum

Pumping &

Fueling System

1.3.2 Tritium

Plant Exhaust

Processing

1.4.1 Electric

Power

Systems

1.5.1 Ion

Cyclotron

System

$M

5

Page 6: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Toroidal Field Coil Conductor

outboard section inboard section

TF CICC, section TF CICC, exploded

“long”double

pancakes

TF coilin case

Exploring:

- Seam-welded (vs. seamless) tube conduit

- Perforated (vs. helical) central cooling tube

Page 7: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Fabrication of TF Conductor

Cablewinch

8-stand tube-forming mill with doubleturks-head for straightening

Page 8: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Central Solenoid Coil

Originally, all JA-supplied Conductor (exploring US supplying initial CS cable)

Exploring alternative supports

Page 9: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

US Scope

Cooling Water System

IN Scope

Page 10: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Tokamak Cooling Water System

Primary Heat Transfer:• Vault• Upper Pipe Chase• Roof• Lower Pipe Chase

Support Systems:• Draining and Refilling

(WBS1.2.1.6)

• Chemical and VolumeControl System(WBS1.2.1.5)

• Drying (WBS1.2.1.7)

Page 11: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Blanket, Port Limiter and Divertor Systems

Page 12: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

Instrumentation is key to science on ITER

Page 13: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/0713

US ITER Diagnostics Scope

Instrumentation Purpose

Upper IR/Visible Cameras monitor for hot spots on outer target surface

Low Field Side Reflectometr y pedestal and SOL density profiles,

fluctuations

Motional Stark Effect safety factor q(R)

Electron Cyclotron Emissio n Te(R), and MHD

Divertor Interferometer line density, several chords across divertor

throats

Toroidal Interferometer/ Polarimeter

line density along tangential chords at

midplane

Residual Gas Analyzer gas composition in pumping ducts

Port Plug s Comments

Upper Ports (U5, U17)

Equatorial Ports (E3, E9)

Lower Port Structures (L8)

Includes design, fabrication, assembly and testing. Also includes integration of both US

and other party’s instruments in US plugs and support for US instruments in plugs provided by other parties. Also includes

integration in interspace and port cell areas.

Page 14: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/0714

Recent Progress and Near-Term Challenges

Co

st

De

sig

n

R&

D

Co

st

De

sig

n

R&

D

Upper Visible/IR Camera assess optical design, central tube concept LLNL C C O

LFS Reflectometer determine optimum frequency bands and polarizations UCLA C

LFS Reflectometer ORNL C

LFS Reflectometer optimize front-end configuration, WG tests ? P

MSE assess usefulness of |B| determination NOVA C C O

MSE performance simulation of conventional polarimetry approach PPPL C

MSE optimization of optical design LLNL C C O

ECE investigate non-thermal issues, use of oblique view PPPL C

ECE review reference design, hot source R&D U.Texas, U. Md, MIT C O

ECE ORNL C

ECE refine front end design ? P

Divertor Interferometer develop conceptual design UCLA/GA C C

Divertor Interferometer refine front-end design ? P

Tang. Interfer./Polarimeter optimize reference design GA/UCLA C C

Tang. Interfer./Polarimeter refine front-end design ? P

RGA develop conceptual design ORNL C C

Neutronics Analysis develop neutronics models for plug integration using ATILLA UCLA C O

First Mirror R&D model erosion/deposition on 1st mirrors ANL C O

Shutter R&D develop candidate shutter concepts PPPL P

C - complete, O - ongoing, P - planned

Phase 2Phase 1

Package Design/R&D Task Summary Institution(s)

• Progress in advancing diagnostics designs comes through broad communityinvolvement in short-term performance assessments, cost studies, & R&D tasks.

• Near-term challenge is to obtain authorization to proceed to detailed design.– Activity presently delayed due to slip in schedule for issuance of diagnostic

procurement arrangements by ITER Organization to July, 2009.– In many areas, scope definition is also incomplete pending PAs.

Page 15: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Electron Cyclotron Transmission Line andMode Control

US ITER ECH Test Facility to develop and qualify T-line componentswith long pulse gyrotrons (140 GHz and 170 GHz)

1 or 2 MW transmission lines from the gyrotrons to the launchers24 lines to the equatorial launcher (EL); 32 lines to the upper launchers (UL)

Page 16: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Likely upgrades to ECH system impactthe Transmission Lines

• Increase sources from 24 to 48 MWsas a substitute for NBI power.

• 2 MWs per line (increased cooling)• Three possible T-line options

Eq. launcher

Up. launchers24-1MW gyrotrons

Transmission lines

20MW

20MW24-1MW gyrotrons

(A)

40MWEq. launcher

Up. launchers48-1MWgyrotrons

Transmission lines

Power combiner

WaveguideSW

(B)

(40MW)

f0

f0+Δf

Eq. launcher

Up. launchers

24-Upgradedgyrotrons

Transmission lines

WaveguideSW

(C)

(greater than 20MW)

greater than 20MWG. Saibene

Page 17: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Ion Cyclotron System

20 MW

Page 18: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

5 or 2.5 MW transmission lines from the sources to the antenna4 or 8 lines feed an ELM tolerant tuning/matching (T/M) system Conjugate T or 3 dB T/M connected to 24 strap antenna array

ICH Transmission lines andTuning/Matching System

Tritium ion heating during DT ops.Minority ion heating with H/D ops.Central current drive for AT ops.

Page 19: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

40-55 MHz High Power, Long Pulse, facilityused to develop and qualify components

High power resonant ring and shorted T-line cantest components to > 5 MWs for full pulse length

Page 20: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

ITER Pumping and Fueling Systems

LeakDetectionSystem

RGADiagnostics

Page 21: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Tritium Processing System

Tokamak

Vacuum

Tokamak

Exhaust

Processing

Isotope

Separation

System

Storage and

DeliveryFueling

Atmosphere

Detritiation

Water

Detritiation

Automated

Control

System

Analytical

System

Q2

Water

Methane

Inerts

Q2

Water

Methane

Inerts

Q2

Trace-tritium gases (water ,

methane, inerts

D, TD, TDTH

Air /

Gases

EffluentH2OHTO

T

Tritium Plant

US

KA

EU EU, JA

EU

Central

Fund

Central

Fund

Note: Q = H, D or T

Page 22: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Roughing Pump SystemLeak Detection System• Roughing pump sets - 4 identical pump assemblies

Piston pumps, Blowers, glove box assemblies with associated valves,instrumentation and controls. Needs to be tritium compatible.

Roughing Pump Set AssemblyChange Over Valve Box Assembly

• Leak Detection System - Mass spectrometers and RGAs,conventional vacuum hardware, all need to be tritium compatible.Some assemblies in glove boxes.

Mass Spectrometer LD Type 1

Page 23: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

• Pellet injection to achieveefficient core tritium fueling

Pellet Fueling of ITER

Pellet Path

Hydrogen, Deuterium andTritium Pellets @ 14° Kelvin

Page 24: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

ITER Gas Gun Pellet Injection System R&Dand Design underway

Roots + Screw BlowerPropellant Compressor

Pellet Injector

V1V2

Pellets CryocoolerCompressor

DT Supply

VacuumMicrowave

Cavity

Prototype extruderis being tested

Page 25: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Control of Type 1 ELMs Is a Pressing Issue for ITER

Loarte et al., Nuclear Fusion, ITER Physics Basis,Chapter 4

Reducing the energy loss to <1MJ using ~ 40 Hz pellet pacinghas been proposedWould require at least 2 additional injectors to provide highthroughput of pacing pellets

Minimum AcceptableValue (?)

Pellet pacing to trigger ELMs

Page 26: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

• A “golf ball size” pellet made withD2 or combination of D2 and Ne orother impurity is an option tomitigate disruptions.

• A 10 cm3 pellet with 10,000 torr-Lis entirely possible.

• A reliable single stage gas guncan accelerate the pellet to 1 km/sspeed.

• A “V” groove guide tube toproduce quasi-liquid jet lookspromising.

Killer pellets have been proposed forDisruption Mitigation

1115 m/s350 m/s 581 m/s

Page 27: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Standard Vacuum Components

• Standard components consists of – ICRF vacuum system - 64 getter pumps and 32 valves– ECH vacuum system - 130 sputter ion pumps, 10 TMPs,

10 dry pumps & 220 valves– Guard and service vacuum system - 86 cryo pumps, 2 dry pumps and

1738 valves

Page 28: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Steady-state Electric Power Scope

HV Switchgear

HV Transformers

MV Switchgear

MV Transformers

LV Load Centers

LV Distribution Boards

75% by US~ $20Mequipment

25% by EU

• 140MVA AC Substation & Power Distribution• Design, installation, commissioning by EU• Procurements shared by EU and US

Page 29: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Steady State ElectricPower

Steady State Electric Power Network Pulsed Electric Power Network400kV

Magnets Heating & Current Drive

~=

~= P,Q

Control

500MW400MVAR650MVAPulsed

EU + China

120MW50MVAR130MVAContinuous

Class III (Safety):8MW

~

Class IV:CWS 37MWCryo 27MWOther 50MW

EU + US

Host(EU)

Similar toauxiliaryelectricalsystem of

nuclear powerplant

except higherpower level

Page 30: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Support of the Resolution of Design Issues

• The USIPO provided support for communityparticipation in the “Design Review”– The Burning Plasma Organization

was a major contributor, particularlyin Working Group 1

– The Virtual Laboratory for Technologycontributed in the areas of expertise

– The USIPO team participated in theUS design areas and in general areas

• The remaining issues are being addressed by the ITER Organization,Domestic Agencies, and the fusion communities of the ITER parties– International and domestic processes being developed– Target resolution by Spring 2008

Page 31: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Design Issues for Resolution

• Vertical Stability• Shape Control / Poloidal Field Coils• Flux swing in Ohmic Operation and CS• ELM control• Remote Handling• Blanket Manifold RH• First Wall (C/W) strategy• Capacity for 17MA discharge• Coil cold tests• Vacuum Vessel• Other issues

– TBM strategy– Hot cell Design– Buildings/ integrated logisitcs– Heating and current drive strategy related to research plan

Page 32: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

The U.S. ITER Project Office (USIPO)

Legend:LLC Limited Liability CompanyORO Oak Ridge OfficePSO Princeton Site OfficeORNL Oak Ridge National LaboratoryPPPL Princeton Plasma Physics LaboratorySRNL Savannah River National LaboratorySROO Savannah River Operations Office

Page 33: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

33

U.S. Contributions to ITER Project

Page 34: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US ITER In-kind Hardware Contributions

100% Ion Cyclotrontransmission lines

100% Electron Cyclotron transmission lines

15% of port-based diagnostics

7 Central Solenoid windings

75% Cooling for divertor, vacuum vessel, …

20% Blanket/Shield

pellet injector Tokamak exhaust processing system

Roughing pumps [swap w/ EU?], standard components

8% of Toroidal Field conductor

Steady-state power supplies

ORNLORNL

ORNL

ORNL

ORNLORNLORNL

ORNL

PPPL

PPPL

SRNL

Page 35: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Procurement Procedures

• U.S. ITER procurements are governed by Department ofEnergy Acquisition Regulations (DEAR) as well as theFederal Acquisition Regulations (FAR)

• These DOE regulations are flowed down to the nationallaboratories through their contracts with DOE

• ITER Agreement terms also flow down through contracts

• Partner labs PPPL and SRNL will manage their owncontracts with USIPO oversight

Page 36: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

US ITER Procurement Practices

• USIPO and IO jointly perform R&D, design andProcurement Agreements

• USIPO completes enabling work and defines scopes forsuppliers

• We expect detailed design, manufacturing design andfabrication to be done mostly by industry

• USIPO will be the contact with the suppliers for US scope

• We have the ability to offer incentives in contracts tomotivate schedule performance

• USIPO provides information to the IO on milestones

Page 37: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015

ITER IOLICENSE TOCONSTRUCT

TOKAMAKASSEMBLY STARTS

FIRSTPLASMA

BidContract

EXCAVATETOKAMAK BUILDING

OTHER BUILDINGS

TOKAMAK ASSEMBLY

COMMISSIONING

MAGNET

VESSEL

Bid Vendor’s Design

Bid

Installcryostat

First sector Complete VVComplete blanket/divertor

PFC Install CS

First sector Last sector

Last CSLast TFCCSPFC TFCfabrication start

Contract

Contract

2016

Construction License Process

Current Official Project Schedule

Page 38: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

US ITER Budget Request ($M),summing to $1.122B

Procurements ~$600M

Page 39: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Interfaces with the research community

• The US is a strong participant in the International TokamakPhysics Activity (ITPA)

• The Burning Plasma Organization and the Virtual Laboratoryfor Technology engage the US community in burning plasmascience and engineering-science/technology research– US ITER’s chief scientist is the director of the BPO– US ITER’s chief technologist is the director of the VLT

• The IO-led Research Planning involves 3 US participants– Engaging the US community in planning ITER research is

key

• ITER issues are major foci of the US facilities’ researchprograms

Page 40: Plans for U.S. engagement with ITER Organization · Plans for U.S. engagement with ITER Organization Ned Sauthoff U.S. ITER Project Manager Committee to Review U.S. ITER Science Participation

US Contributions to ITER NRC 12/14/07

Summary

The U.S. Contributions to ITER project is:• established and functioning, with a tightly integrated

DOE/contractor team

• working with the ITER Organization and the other DomesticAgencies to plan, position, and act

• finishing design-related R&D, performing design work, andpreparing for procurements

• engaging the US fusion community in addressing keyITER- design issues