PERFORMANCE AUDIT REPORT of the AUDITOR GENERAL on …ANTI-RETROVIRAL DRUGS. I have the honour to...
Transcript of PERFORMANCE AUDIT REPORT of the AUDITOR GENERAL on …ANTI-RETROVIRAL DRUGS. I have the honour to...
Our VisionTo be one of the leading
Supreme Audit Institutionsin the world, delivering
professional, excellent, andcost effective auditing
services
REPUBLIC OF GHANA
on the
PERFORMANCE AUDIT REPORT of the
AUDITOR GENERAL
MANAGEMENT AND DISTRIBUTION OF ANTI-RETROVIRAL DRUGS
IN GHANA
This report has been prepared under Section 11
of the Audit Service Act 2000 for presentation
to Parliament in accordance with
Section 20 of the Act.
Richard Quartey
Auditor General
Ghana Audit Service
3 September 2012
This study team comprised:S. A. K. Quist, Minata Diabor, Dennis Agbleze, andSampson Osei Boadu
This report can be found on the Ghana Audit Service
website at www.ghaudit.org
For further information about the
Ghana Audit Service please contact:
The Director, Communication Unit
Ghana Audit Service
Headquarters
Post Office Box MB 96, Accra.
Tel: 0302 664928/29/20
Fax: 0302 662493/675496
E-mail: [email protected]
Location: Ministries Block 'O'
© Ghana Audit Service 2012
Performance audit report of the Auditor-General on management and distribution of Anti-retroviral drugs
TABLE OF CONTENTS
Page
Transmittal Letter i
Executive Summary iii
CHAPTER ONE………………………………………………………... 1
1.0 INTRODUCTION………………………………………............. 1
1.1 Reasons for the audit……………………………………………… 1
1.2 Purpose and scope………………………………………………… 2
1.3 Methods and implementation……………………………………… 3
CHAPTER TWO……………………………………………………… 5
2.0 DESCRIPTIVE CHAPTER ...…………………………………… 5
2.1 Historic background …………………………………………… 5
2.2 Statutory mandate……………………………………………… 5
2.3 Objective……………………………………………………….. 6
2.4 Funding………………………………………………………… 6
2.5 Current development…………………………………………... 6
2.6 Key players and their activities………………………………… 7
2.7 System description……………………………………………… 7
Performance audit report of the Auditor-General on management and distribution of Anti-retroviral drugs
CHAPTER THREE…………………………………………………… 8
3.0 FINDINGS AND RECOMMENDATIONS .…………………….. 8
3.1 Introduction……………………………………………………. 8
3.2 Inadequate supply of ARV drugs…………………………….. 8
3.3 Submission of inaccurate data……………………………….. 11
3.4 Delayed in submission of returns ……………………………… 12
3.5 Failure to supply drugs purchased...…………………………… 13
3.6 ARVs are partially delivered….……………………………… 14
3.7 Delays in clearing of ARVs from Airports…………..………… 16
3.8 Monies collected from PLHIV are not accounted for properly…… 18
Appendices
A Key stakeholders interviewed……………………………………… 20
B Documents reviewed…..…………………………………………… 21
C Key players and their activities……………………………………… 22
D NACP system description…………………………………………… 23
E Analysis of responses of treatment sites to questions asked……… 24
F Amount of money collected by sites visited as at the time of the audit… 25
G Treatment sites with buffer stock……………………………………… 26
H Air-conditioning at treatment sites…………………………………… 27
I Total amount of revenue collected from all the sites in the country… 28
J List of abbreviations…………...…………………………………… 29
Performance audit report of the Auditor-General on management and distribution of Anti-retroviral drugs i i
TRANSMITTAL LETTER
Ref. No. AG.01/102/Vol.2/57
Office of the Auditor-General
Ministries Block “O”
P. O. Box MB 96
Accra
Tel. (021) 662493
Fax (021) 662493
3 September 2012
Dear Madam,
PERFORMANCE AUDIT REPORT OF THE AUDITOR-GENERAL
ON MANAGEMENT AND DISTRIBUTION OF
ANTI-RETROVIRAL DRUGS
I have the honour to submit to you a performance audit report on Management
and Distribution of Anti-Retroviral Drugs in Ghana in accordance with my
mandate under Section 187(2) of the 1992 Constitution of Ghana and Section
13(e) of the Audit Service Act which requires me to carry out performance
audits.
2. The purpose of the audit was to determine whether PLHIV have access to
ARVs at all times at affordable prices and close to the location where they live
throughout the country. The audit covered the period 2005 to 2009 and was
carried out at 24 treatment sites in five regions.
3. The audit found that NACP has made huge progress in providing ARV
drugs to PLHIV and setting up and managing 117 treatment sites throughout the
country. There were however shortages in supply of ARV drugs as a result of
which drugs were rationed to patients.
Performance audit report of the Auditor-General on management and distribution of Anti-retroviral drugs ii
4. The shortages were caused by delays in receiving data from treatment
sites to inform forecasting of drug requirement to purchase the right quantity of
drugs and delays in clearing the ARV drugs from the Airport on their arrival.
5. This has defeated the goal of providing PLHIV with ARV drugs at all
times to improve their life expectancy. We however made appropriate
recommendations to address the challenges noted in the management and
distribution of anti-retroviral drugs to enable the project achieve the desired
goal.
6. The audit was undertaken by the Performance and Special Audit
Department under the supervision of Jacob Essilfie, Lawrence Ayagiba all
Assistant Auditors-General and Yaw Agyei Sifah, Deputy Auditor-General.
7. I would like to thank my staff for their assistance in preparing this report,
the management and staff of NACP, the Central and Regional Medical Stores
and the treatment sites visited for their assistance and cooperation during the
audit.
8. I trust that this report will meet the approval of Parliament.
Yours faithfully,
AUDITOR-GENERAL
THE RIGHT HON. SPEAKER
OFFICE OF PARLIAMENT
PARLIAMENT HOUSE
ACCRA
Performance audit report of the Auditor-General on management and distribution of Anti-retroviral drugs iii
PERFORMANCE AUDIT REPORT OF THE AUDITOR-GENERAL
ON MANAGEMENT OF ANTI-RETROVIRAL DRUGS IN GHANA
EXECUTIVE SUMMARY
The National AIDS/STI Control Programme (NACP) was set up in 2003 to
provide care and support to People Living with HIV (PLHIV) by ensuring that
they have access to anti-retroviral drugs (ARVs) all the time. Between 2005 and
2009, the NACP has with donor support procured ARVs worth US$22,156,890
and opened 117 treatment sites where PLHIV could receive ARV drugs.
2. The purpose of the audit was to determine whether PLHIV have access to
ARVs at all times at affordable prices and close to the location where they live
throughout the country. The audit covered the period 2005 to 2009 and was
carried out at 24 treatment sites in five regions. We used interviews, documentary
reviews, observations and administration of questionnaires to obtain our audit
evidence.
3. The audit found that high prevalence rate, high population density and the
farther away of treatment sites and Regional Medical Stores (RMSs) from Central
Medical Store (CMS) did not affect the accessibility of ARVs by PLHIV. Rather,
there was the problem of inadequate supply of ARVs which has led to rationing of
the drugs to the treatment sites.
4. CMS is required to distribute enough drugs to the RMSs and RMSs in turn
to treatment sites to enable the sites keep a buffer stock of three months.
Treatment sites were however given drugs that will last for one to two weeks, and
as a result the few available drugs were rationed to PLHIV.
Performance audit report of the Auditor-General on management and distribution of Anti-retroviral drugs iv
5. The shortages resulted from the following factors:
failure to supply all the ARVs purchased
partial delivery of drugs
delays in submitting returns
submission of inaccurate data
delays in clearing drugs from the airport, and
improper accounting for monies collected.
Failure to supply all ARV drugs purchased
6. Two contracts for the supply of ARV drugs costing US$222,764.00 which
were awarded in 2008 and 2009 respectively had not been delivered at the time of
the audit in November 2010.
Recommendation
NACP should ensure that they procure the required quantity of ARVs to
enable CMS, RMS and treatment sites maintain the required buffer stock.
Ensure the supply of the drugs by the defaulting firms or initiate steps to
recover the amount involved.
NACP through the Ministry of Health should impress on government to
buy ARVs from local manufacturers like DANADAMS now that Global
Fund will not finance the drug any longer.
Returns from treatment sites were delayed
7. Treatment sites are to report drug consumption returns to RMSs by 5th day
of each month while the RMSs should forward same to NACP by the 12th day.
Treatment sites delay in sending their consumption returns to RMSs and as a
result, RMSs also delay sending their returns to NACP.
Performance audit report of the Auditor-General on management and distribution of Anti-retroviral drugs v
Recommendation
NACP should ensure that treatment sites and RMSs submit their returns
by due date and that they submit the right data for the required ARVs to
be acquired.
NACP should provide needy sites with computers and accessories and
urgently repair or replace unserviceable computers.
Drugs arriving at the airport are not cleared on time
8. GSCL does not clear ARVs within eight days on arrival at the port as the
air waybills were written in the names of the Banks issuing the letters of credit
instead of MoH/PU. The name change takes between two and eight weeks to
complete.
Recommendation
Procurement Unit of MoH should provide all the necessary documents
to GSCL on time to facilitate the clearing of ARVs at the airport.
Monies collected were not properly accounted for
9. Total monies collected of GH¢594,091.30 by the treatment centres were not
lodged in the prescribed bank accounts.
Recommendation
NACP should retrieve monies collected by individual staff members and
those invested in private accounts with the accrued interest and sanction
staff members who have violated directives from the Director General
of GHS to lodge funds collected in the hospital account.
Performance audit report of the Auditor-General on management and distribution of Anti-retroviral drugs vi
NACP should inform the treatment sites to bank the revenue collected in
the certified bank account and educate patients on the need to pay
GH¢5 fee per visit.
NACP through MoH should liaise with National Health Insurance
Scheme (NHIS) to include the treatment of AIDS patients in the
scheme.
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 1
CHAPTER ONE
1.0 INTRODUCTION
1.1 Reasons for the audit
National AIDS/STI Control Programme (NACP) is responsible for
coordinating and managing HIV and AIDS issues of the Ghana Health Sector
Strategic Framework. According to the NACP annual reports for 2005 and
2006 respectively and the 2009 HIV Sentinel report, the number of reported
AIDS cases, AIDS related deaths and children orphaned by AIDS has kept
rising.
2. According to the Sentinel report, the number of People Living with HIV
(PLHIV) increased from 104,995 in 2005 to 267,069 in 2009, an increase of
162,074 (154%). The disease has also affected the most productive citizens
constituting the work force of the country and falling in the age group of 20 to
49 years. In 2005 and 2006 respectively, this age group constituted 81% of
PLHIV.
3. In 2003, NACP was mandated to provide care and support including
anti retroviral drugs (ARVs) to keep PLHIV healthy and productive. NACP
procured ARVs for 2,000 patients in 2003 and has so far opened 117 treatment
sites where PLHIV could receive ARVs. NACP procures and stores ARVs to
ensure that PLHIV have constant supply of the drug at affordable prices and
close to the location where they live.
4. Despite these interventions, statistics available indicate that not all
PLHIV have access to ARVs and there are problems with the provision of the
drugs. In an interview on myjoyonline.com of 15 December 2009, the Acting
Director General of Ghana AIDS Commission stated that Ghana is about 70%
deficient in the supply of anti retroviral drugs to over 230,000 PLHIV and that,
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 2
at the time, treatment covered about 37% of PLHIV. This means that 85,100
PLHIV are on treatment. Out of this figure, 40,000 are on ARVs while 45,100
are on adherence counselling and drugs to take care of opportunistic diseases
like TB and skin diseases. In January 2010, PLHIV went on a demonstration
because there was shortage of anti retroviral drugs in Ghana.
5. The Auditor-General in line with Section 13(e) of Act 584 of 2000
commissioned performance audit into the management of ARV to determine
whether the procurement, revenue, storage and distribution of ARV are
managed in a way that enable PLHIV have access to the drugs at all times.
1.2 Purpose and scope
6. The purpose of the audit was to determine whether the funding,
procurement, storage and distribution of ARVs are managed in a way that
PLHIV have access to the drugs at all times. The team examined the following
in carrying out the audit:
funding of ARVs
procurement of anti- retroviral drugs
use of Electronic Logistic Management Information System (E-
LMIS) in gathering data for quantification and forecasting of ARV,
and
management of revenue collected from PLHIV.
7. The audit covered the period 2005 to 2009 and was carried out from
April 2010 to October 2010. The team visited the Central Medical Store
(CMS), five Regional Medical Stores (RMS) and 29 treatment sites in five
regions (Greater Accra, Eastern, Ashanti, Northern and Upper East). The
choice of the regions was based on HIV prevalence rate (areas with high rate of
PLHIV), population density (high populated area) and distance from CMS.
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 3
8. The team went to Eastern Region because of its high prevalence rate of
4.2% to ascertain whether quantity of ARV drugs matched the prevalence rate.
In Ashanti, the team ascertained whether the population density of 3,187,607
out of the total population of 18,412,247 (17.3%) had any bearing on
accessibility of ARVs by patients while in the Northern and Upper East the
team assessed whether the distance (Tema to Northern Region: 458 Km; Tema
to Upper East: 606 Km) from CMS which is the main depot for ARVs had any
bearing on the availability of the drugs in the regions.
1.3 Methods and implementation
9. We used interviews, document review questionnaire administration and
inspection of facilities to obtain audit evidence to inform our finding and
conclusions.
Interviews
10. The audit team interviewed key stakeholders of the programme, as
listed in Appendix A. The interviews were to enable the audit team obtain data
on funding, procurement, storage and distribution of anti-retroviral drugs to
conclude on our findings.
Documents review
11. We reviewed annual reports, laws, rules and regulations governing the
operations of NACP. Details of documents reviewed and information gathered
from them are listed as Appendix B. We reviewed the documents to ascertain
and confirm information gathered during interviews on the management of
ARVs.
Questionnaires
12. We administered questionnaires to management of NACP, HIV
Coordinators, pharmacists and accounts officers of the various sites visited.
The questionnaires captured information on the Electronic Logistic
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 4
Management Information System (E-LMIS) which is used to gather
returns/data from the treatment sites for quantification and forecasting, monies
paid by PLHIV per visit, procurement and storage facilities.
13. We analysed the information obtained from the sites visited to enable us
ascertain whether NACP is managing anti- retroviral drugs effectively.
Inspection
14. We inspected treatment sites, storage facilities (size of stores, cabinet,
shelves, etc.) and computers and printers for generating returns. The purpose
was to find how drugs were stored to ensure their efficacy at all times and
whether sites and RMSs were able to generate timely returns.
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 5
CHAPTER TWO
2.0 DESCRIPTIVE CHAPTER
2.1 Historical background
15. NACP started as the National Technical Committee on AIDS and later
became National Advisory Council on HIV and AIDS in 1985. The first case of
HIV was reported in Ghana in 1986 and there after, there has been a rapid rise
in HIV cases in Ghana. To ensure a systematic approach and response to the
spread of HIV and AIDS, the Government in1987 tasked NACP under the
Disease Control and Prevention Department of the Public Health Directorate of
the Ghana Health Service (GHS), to coordinate and manage all HIV related
activities: funding, procuring, distributing and storage of ARVs and managing
treatment sites and RMSs.
16. The treatment of PLHIV and the management of ARVs started as a pilot
programme in Ghana beginning in Manya Krobo and Yilo Krobo districts
between 2003 and 2004 with 2000 patients. The lessons learnt led to the
expansion of anti-retroviral therapy at Korle-Bu Teaching Hospital and Komfo
Anokye Teaching Hospital by February 2004 to serve the southern and
northern sectors of Ghana respectively. NACP has since opened 117 treatment
sites where PLHIV could receive ARV drugs and adherence counseling
throughout the country.
2.2 Statutory Mandate
17. NACP draws it authority from the mandate of GHS, which is a “Public
Service body established under Act 525 of 1996 as required by the 1992
constitution. It is an autonomous Executive Agency responsible for
implementing national policies under the control of the Minister for Health
through its governing Council - the Ghana Health Service Council.”
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 6
2.3 Objective
18. The objective of the programme is to provide care and support services
for PLHIV.
2.4 Funding
19. The ARVs are mainly paid for by Global Fund (90%) and Government
of Ghana (10%). Government of Ghana’s contribution is in the form of
training and capacity building. Management of NACP was not able to provide
the details of government’s contribution which according to them, comes in
various forms from different sources. Table 1 shows the amount of money
NACP spent on procuring ARVs per year, totalling US$22,156,890 for the
audit period.
Table 1: Sources of funding for ARVs from 2005 to 2009
Year/source
2005
US$
2006
US$
2007
US$
2008
US$
2009
US$
Total
US$
Global Fund 3,053,989 2,813,167 6,418,658 1,161,095 4,534,828 17,981,737
TAP 1,300,000 1,618,674 - 1,201,391 - 4,120,065
GoG - - - -
DFID - 55,088 - - - 55,088
Total 4,353,989 4,486,929 6,418,658 2,362,486 4,534,828 22,156,890
Source: NACP
2.5 Current Development
20. NACP failed to win Global Fund’s bid (Round 10) for financial support
to procure ARVs for PLHIV for the period between 2012 to 2015. According
to the Programme Manager, they were seeking an amount of $1billion between
the period of 2012 to 2015 to fund the programme. This means that the
government of Ghana will have to finance the procurement of ARVs from its
own budget.
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 7
2.6 Key players and their activities
21. The key players of NACP and their activities are shown in Appendix C.
2.7 System Description
22. A chart showing the main activities undertaken by NACP and its key
players in assessing the needs of the treatment sites, initiating procurement
process, storing, supplying and distributing anti retroviral drugs can be found
at Appendix D.
23. Treatment sites gather data on the consumption of ARVs by PLHIV
which is sent to NACP through RMSs for planning (quantification) and
forecasting to procure ARVs to last for a period of two years. NACP
subsequently sends the processed data to Procurement Unit where World
Health Organisation (WHO) pre-qualified suppliers are invited to bid and
supply ARVs. When the drugs have been supplied, they are sent to Central
Medical Stores (CMS) from where ARVs are distributed to various RMSs or
treatment sites according to the quantity requisitioned for dispensing to PLHIV.
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 8
CHAPTER THREE
3.0 FINDINGS
3.1 Introduction
24. NACP was set up to provide care and support to PLHIV by ensuring
that they have access to ARV drugs at all times. Between 2005 and 2009,
NACP in collaboration with donor partners have procured ARV drugs worth
GH¢32,127,491 ($22,156,8901) and opened 117 treatment sites where PLHIV
could receive a constant supply of ARV drugs at affordable prices and close to
location to where they live throughout the country.
25. Despite the achievements made in ensuring the provision of ARVs at the
treatment sites throughout the country, NACP is saddled with the following
challenges which have resulted in rationing ARV drugs to PLHIV:
inadeqate supply of ARV drugs
failure to supply all drugs purchased
partial delivery of ARVs
delays in submission of returns
delays in clearing of ARVs from airports, and
improper accounting for monies collected.
3.2 Inadequate supply of ARV drugs
26. The National policy for the treatment of PLHIV is to provide patients
with ARVs to last for three months at a time before the next supply. This is to
ensure that there is enough time to procure and re-stock by the MoH so as to
maintain a sustained supply of the drug to patients. The policy is also designed
to reduce the burden of patients having to travel frequently for treatment.
Therefore, to ensure that ARVs are in constant supply and patients are provided
with the needed drugs at all times, NACP is required to collate information on
1 Exchange rate of $1.45.
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 9
ARVs and to ensure that the quantities required are procured and supplied by
MoH to the CMS.
27. In addition, NACP is to ensure that CMS distributes to all RMS and
treatment sites enough ARVs to enable them keep the following buffer stocks:
CMS - a buffer stock of nine months
RMSs - a buffer stock of six months, and
Treatment Sites- a buffer stock of three months.
28. PLHIV were reluctant to speak to the audit team, and as a result, only 48
of them availed themselves to be interviewed at the 24 treatment sites visited.
We found through the interviews that drugs given to patients to last for three
months actually lasted for not more than two weeks. Interviews with
pharmacists at the 24 sites revealed that there were shortages of ARVs at the
treatment sites, so they have no alternative but to ration the drugs or give
substitutes in order to make sure that all patients were supplied the drugs.
29. The team reviewed requisition forms and inspected the stores and found
that, the stores did not have enough ARVs in stock. The reason given by the
pharmacists was that they do not get all ARVs they request from CMS or
RMSs.
30. Further review of requisition forms of treatment sites showed that
between 2005 and 2007, the sites received ARVs they requested. The issue of
sites not receiving the required quantity of ARVs started in 2008 and became
pronounced in 2009. The Programme Manager of NACP confirmed this
through interview that there was a break in procurement process due to change
of government in 2008. He further explained that the new minister who came in
2009 needed time to study the procurement process and that resulted in the
delay of procurement of ARVs.
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 10
31. Table 2 shows requisitions of ARVs made by some sites and the
quantities supplied. While some ARVs supplied were less than the quantity
requested, others were not supplied at all.
Table 2: Quantity of ARVs requisitioned, supplied and shortage
Date Treatment site ARV Quantity
requisitioned
Quantity
supplied
Shortage
4/06/08 Mampong
District
Hospital
Tb. Dauvir 300/50mg
Nevirapine 200mg
Efaveraz 600mg
Stavudine 300mg
6,000
6,000
3,000
6.000
2,940
1,560
1,050
420
3,060
4,440
1,950
5,580
28/07/0
9
15/5/09
Bekwai
Municipal
Hospital
‘’
Tb. Nevirapine
Syr. Zidovudine
Tb. Combivur
Syr. Nevirapin
5,280
1,800
6.780
3,000
3,000
Nil
600
Nil
2,280
Nil
6,180
Nil
14/4/09 Kdua. Reg.
Hospital
Syr. Nevir.
Efavir.600mg
Zidovu.syr.
Lamido. Oral
Stavudine syr.
15
47,520
21
90
216
Nil
5,400
8
32
15
15
42, 120
13
58
201
16/6/09 RMS Bolga Tb. Fluconazole
Syr. Nevir.
6,270
150
Nil
90
6, 270
60
28/09/09 War Memorial
Hospital
Tb. Combiviv
Nevirapine 200mg
Efavirenz 600mg
Lamivudine sp
12,000
9,000
3,000
9,000
1,200
6,450
900
6,000
10,800
2,550
2,100
3,000
28/09/09 Walewale
Municipal
Hospital
Efavirenz
Zidovudine
9,000
3,000
6,480
900
2,520
2,100
1/10/09 Tamale Central
Hospital
Tb.Combivur
Tb. Nivirapine 200mg
Tb. Multivate
6,000
14,460
20,000
4,320
6,000
Nil
1,680
8.460
Nil
16/11/09 St. Patrick
Hospital, A/R
Tb. Lamivudine
Tb. Aluvia
Tb. Nevirapine 200mg
16,200
1,800
20,000
Nil
Nil
18,000
16,200
Nil
2,000
Source: GAS compilation
32. Further analysis of annual reports of NACP revealed that the shortage of
ARVs at treatment sites, leading to their being rationed was caused by the
submission of inaccurate and delayed data from the treatment sites to estimate
the right quantities of ARVs to be bought. Additionally, there were other
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 11
causes like the failure to fully supply all ARVs bought, piecemeal delivery of
ARVs and delays in clearing ARVs from the airport.
3.3 Submission of inaccurate data
33. For NACP to procure the right quantity of ARVs, it requires data on
PLHIV who need the drug from the treatment sites. This is collated using a
customised software called an Electronic Management Information System (E-
LMIS) introduced by NACP. This upgraded version of the manual system or
Excel application package is expected to be used by all treatment sites. The E-
LMIS has been programmed to capture the required combination and dosage of
ARVs both for children and adults. It also records consumption levels and
automatically updates inventory.
34. With the E-LMIS, officers at the sites are able to check the minimum
stock levels and make requisition for the right combination or quantity of
ARVs to replenish stock. By entering the right data, the system will
automatically generate the required quantities of the ARVs needed to be
procured by NACP.
35. The audit team’s analysis of data collected from the sites shows that 20
out of the 24 sites visited were still using either the manual or the excel
application package. The use of manual leads to delay in sending returns to
NACP thereby delaying the procurement process.
36. Interviews with Programme Manager of NACP revealed that the
shortages of ARVs occur because some treatment sites send inaccurate data of
the number of patients who actually need ARVs. For example, the pharmacist
at Zebilla stated through questionnaire that he found it difficult to generate
accurate ARVs and Opportunistic Infection reports.
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 12
37. The effect is that NACP is not able to procure the right quantity of
ARVs to cater for all existing PLHIV and new patients. According to
pharmacists at the various treatment sites visited, patients who travel long
distances to sites to avoid stigma find it difficult to be regular on clinic days
because of the cost of transportation and as a result develop resistance to the
drugs.
Recommendation
38. NACP should ensure that sites and RMSs submit the right data for the
required quantities of ARVs to be purchased. In addition, NACP should
provide needy sites with computer and accessories, and repair or replace the
unserviceable computers, and train site managers in the use of the E-LMIS
software.
Management responses
39. Management of NACP disclosed that they give ARVs to PLHIV for a
period of three months, however, it is only the newly initiated clients and those
with adverse drugs reactions who are given drugs for two weeks. The
programme manager also stated that ARVs would continue to be rationed
because of the shortages of some drugs. According to the programme manager,
shortages of ARVs is a serious issue, especially now that Ghana has lost the bid
for support of Global Fund to sponsor the programme for the next round ( 2012
and 2015).
3.4 Delays in submission of returns
40. Treatment sites are required to report drug consumption returns by the
fifth day of each month to the RMSs who in turn should forward them to
NACP by the 12th day. This is to enable NACP forecast and quantify the
required ARVs to avoid any shortages.
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 13
41. We noted during the audit that the treatment sites delay in sending their
consumption returns to the RMSs and consequently, RMSs delayed in sending
their returns to NACP. The audit found that the consumption of 15 out of the
24 treatment sites visited were sent between the sixth and 15th day of each
month. A review of consumption returns at Bongo District Hospital showed
that, returns were sent after three months. While five out of the 24 (21%)
treatment sites sent their consumption returns by the fifth day of each month,
three had not sent their request at the time of the audit in October 2010.
42. The audit also revealed that all the RMSs visited sent their returns to
NACP between the 15th and 20th of the month. According to the programme
manager of NACP, submission of returns after the 12th affects the procurement
process by a month because the date for submission to NACP is the 12th of
each month and any submission after the 12th will have to be deferred to the
following month.
43. According to the officials of the treatment sites visited, the reasons for
delay in sending data to RMSs are that the personnel see the task as an
additional responsibility and some sites also have to wait for preparation of
other reports to RMSs. Delay in sending returns to NACP leads to late
submission of the data to Procurement Unit of the MoH for procurement of
ARVs.
Recommendation
44. NACP must ensure that sites and RMs submit their returns on due dates
to facilitate planning and forecasting ARVs requirements.
3.5 Failure to supply drugs purchased
45. We also found that not all drugs procured were delivered by suppliers.
According to the Programme Manager of NACP and officials of the
Procurement Unit of MoH, contracts are awarded for drugs and are supposed to
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 14
be honoured within 90 days. A list of contracts and expected date of delivery is
sent by the MoH/ Procurement Unit to the CMS to confirm that a contract has
been entered into. Any supplier who fails to supply within the 90 days is given
a grace period of 30 days. If after the grace period the supplier fails to supply
the ARVs, then the contract is abrogated.
46. All supplies of ARV drugs procured by the Procurement Unit of MoH
must first be received at the Central Medical Stores. On the contrary, our
review of data on ARVs at Central Medical Stores revealed that between 2008
and 2009, two contracts (MoH/2008/RT/B.2.1/06/CO4 and
MoH/2009/SHP/B.2.1/01/C20) amounting to GH¢323,009.00 (equivalent to
$222,764.00) were not delivered by the suppliers as at the time of audit in
November 2010.
47. The effect is that there will be shortages of ARVs forcing pharmacists to
ration drugs to patients.
Recommendation
48. The Procurement Unit of MoH should provide all the necessary
documents to GSCL on time to facilitate the clearing of AVRs at the airport.
Additionally, NACP should prevail on suppliers to use Airlines that would
carry the consignments en bloc.
Management response
49. The Programme Manager of NACP confirmed that the two contracts
have not been delivered but did not give reasons why they were not delivered.
3.6 ARVs are partially delivered
50. Our interviews with the officials of GSCL revealed that another cause of
delay is short landing of ARVs, that is, when ARVs arrive at the airport in bits
or small consignments or quantities. This occurs because certain airlines do not
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 15
ship all the consignment at the same time. They explained that when the first
consignment of ARVs is shipped, it comes with the original documents
covering the whole consignment. This document is used to clear the first
consignment at the airport. When the earlier consignment has been cleared, the
documents are removed from the computer system of Custom Excise and
Preventive Service (CEPS).
51. Thus when the remaining consignment arrives, it becomes difficult to
trace the original documents covering the entire consignment, thereby
contributing to delays in clearing the subsequent consignment. As shown in
Table 4, a consignment of 7,331 kgs of ARVs was to arrive on the 20 August
2010, but as at 4 September 2010, 6,385kgs had been received in six
consignments. Officials of GSCL confirmed that this was not an isolated case
and that it was a matter of concern.
Table 4: Partial delivery of ARVs in 2010
Master air
waybill
Expected
date of
arrival
Confirmed
date of
arrival
Days
delayed
Landed
weight/kg
Total
weight/kg
Expected
7,331
70622145410 20/8/10 20/8/10 - 177
“ 24/8/10 4 1963
“ 25/8/10 5 1478
“ 26/8/10 6 2436
“ 27/8/10 7 47
“ 4/9/10 15 284
Total weight/kg
collected
6,385
Difference yet
to arrive
946
Source: Audit Service compilation
52. Thus, three months after the confirmed date of arrival of the total
consignment of 7,331kgs, 946 kgs was yet to arrive at the time of the audit in
December 2010. The effect is that NACP does not receive the full complement
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 16
of the required quantity of ARVs to be supplied to the treatment sites for use
by PLHIV at the right time, thereby creating shortages.
Recommendation
53. The Procurement Unit of MoH should provide all the necessary
documents to GSCL on time to facilitate the clearing of ARVs at the airport;
and ensure that the suppliers of ARVs use more reliable Airlines to carry the
drugs at once.
Management response
54. The Progamme Manager stated that this is a normal practice with the
shipping of ARVs and that it is an arrangement between the supplier and the
airlines as to how much quantity can be shipped at a point in time. However, he
gave assurance that they would insist on full delivery instead of short landing.
3.7 Delays in clearing of ARV drugs from Airports
55. Ghana Supply Company Ltd. (GSCL), the main clearing agent for MoH,
is required to clear the ARVs within eight days on arrival at the Kotoka
International Airport. Failure to clear ARVs within the eight days leads to the
payment of demurrage of GH¢ 0.10 per kilo per day. The Procurement Unit
(PU) of MoH should notify GSCL through correspondence or telephone of the
arrival of drugs at the airport and provide the necessary documents to enable
the company clear the goods.
56. Our interviews with the manager of GSCL at the airport disclosed that
the Procurement Unit does not notify GSCL when ARVs arrive at the airport.
The manager also complained that, the air-waybills are written in the name of
the Banks that issued the letters of credit to the suppliers instead of MoH/PU.
Therefore the name must be changed from ‘Bank’ to ‘Procurement Unit’ which
takes between two and eight weeks. This situation makes it difficult for GSCL
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 17
to clear the ARVs from the Airport on time. Table 3 shows how long it took to
clear ARVs in November/December 2009.
Table 3: Delay in the clearing of ARVs
Air-
waybill
No.
Flight
no.
Arrival
date
Date
ARVS
were
collected
or leared
at the
airport
No. of
days
taken
to
clear
ARVs
Time
to
clear
goods
from
air
port
Days
delay
ed
Weig
ht/kg
Cha
rge
kg/
day
Total
Amount
charge to
NACP
GH¢
1 125
80724033
BA081 20/11/09 11/12/09 21 8 13 3,199 0.10 4,158.70
2 125
80724136
“ 21/11/09 15/12/09 24 8 16 2,773 0.10 4,436.80
3 125
80724136
“ 22/11/09 15/12/09 23 8 15 2,591 0.10 3,886.50
4 125
80724136A
BA081 23/11/09 15/12/09 22 8 14 8,621 0.10 12,069.40
Total 24,551.40
Source: Audit Service compilation
57. It could be seen in Table 3 that four consignments of ARVs which
arrived between 20 and 23 November 2009 were eventually cleared from the
airport on 11 and 15 December, 2009. The team interviewed clearing agents at
the airport and collaborated by Custom Officers, that goods of this nature that
have clearance from the MoH should take one day to clear. As Table 3 shows,
for the four consignments of November/December 2009, NACP paid
demurrage of GH¢24,551.40 because it took an average of 22 days (instead of
8 days) to clear the ARVs which could have been used to purchase more drugs.
Recommendation
58. The Procurement Unit must ensure that the airway bills are written in
the name of MoH. Additionally, it should provide all the necessary documents
to GSCL on time to facilitate the clearing of ARVs at the airport.
Management response
59. The Programme Manager of NACP said that adequate notice in the form
of airway bill is always given to GSCL to facilitate clearing of ARVs at the
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 18
airport. But, the manager of GSCL at airport insisted that they do not receive
adequate information in terms of correspondence to enable them clear ARVs
on time.
3.8 Monies collected from PLHIV are not accounted for properly
60. PLHIV are required to pay a fee of GH¢5 per month. This is for
comprehensive care comprising consultation, a month’s supply of ARVs and
medicines for opportunistic infections, half yearly CD4 assays2, laboratory
investigations and viral load monitoring. NACP policy is that monies collected
are to be banked in the facility drug account and patients who do not have the
money are not turned away. They are treated, given the drugs and asked to pay
on their next visit. Although this amount does not cover the total cost of
treatment which is between $250 - $300 per visit, the intention is to have funds
available for drugs in case of emergency.
61. Accounting practice requires that such funds are entered in a cash book
and put into specified bank accounts to keep track and control of the usage of
the monies. Financial Administration Regulation (FAR) also requires that such
fund must be banked in whole within 24 hours according to Regulation 15(1)
of the FAR, 2004.
62. We observed on the contrary that three out of the 24 treatment sites
visited did not pay the monies into any bank account. For example, at Sandema
and KNUST hospitals, an amount of ¢2,075.00 collected were being kept at the
offices, while at Yendi the revenue officer kept the money collected in his
personal account. The revenue officer was however not available at the time
the audit team visited the treatment site.
63. The account officer at Holy Family Hospital at Nkawkaw had invested
the monies in a fixed deposit in a bank for the hospital. Review of the cash
2 CD4 assay is a measure of the number of helper CD4 cells per cubic millimeter of blood used to analyse the prognosis of
patients
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 19
book and bank statement showed that the principal and the accrued interest
amounted to ¢40, 829.48 as at October 2009. The rest of the treatment sites
kept the monies in their drugs account and gave the assurance that although the
monies are used, they can be refunded when the need arises. As at the time of
the team’s visit in November 2010 the 24 treatment sites had between them
collected a total of GH¢594,091.30 as detailed in Appendix D.
64. The team found through interviews that NACP is aware of the issues
with managing moneys collected at the sites but have not taken any steps to
address them. In the absence of a clear directive from NACP, the risk exists
for abuse and embezzlement of the money thereby, defeating and undermining
the effort to build up capital in case Global Fund withdraws its support
Recommendation
65. NACP should retrieve monies collected by individual staff members and
those invested in private accounts with the accrued interest and sanction staff
members who are found to have violated directives from the Director General
of GHS to lodge funds collected in the hospital account. Additionally, NACP
should direct the treatment sites to bank the revenue collected in a certified
bank account and educate patients on the need to pay GH¢5 fee per visit.
66. NACP through MoH should liaise with National Health Insurance
Scheme (NHIS) to include the treatment of AIDS patients in the scheme.
Management response
67. The Programme Manager of NACP disclosed that a letter from the
Director-General of GHS was sent to all treatment sites to lodge funds
collected in the hospital account and generate ledgers to track collections. He
further indicated that they would enforce this directive.
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 20
Appendix A
Key Stakeholders interviewed
1 Programme Manager of NACP
2 Monitoring and Evaluation Officer of NACP
3 HIV Coordinators in the Five regions visited
4 Pharmacists at the Central Medical Stores (RMSs)
5 Manager, Procurement Unit (MoH)
6 Officer in charge of ARVs at the Ghana Supply Company Ltd.
7 The five pharmacists at the five Regional Medical Stores visited
8 Twenty pharmacist, senior nurses and account officers at the
treatment sites visited
9 48 PLHIV
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 21
Appendix B
Documents Reviewed
Source: GAS Compilation
1 NACP Annual Report 2005, 2006, 2007 2008 & 2009
2 NACP Logistic Management Information System (LMIS) Manual
3 Public Procurement ACT ( 663) 2003
4 NACP Transitional Guide 2008,
5 Audit of USAID/GHANA’S HIV/AIDS PROGRAM, 2010
6 HIV Sentinel Survey Report 2008
7 Contract Documents of ARVs
8 Air -waybills of ARVs
9 Guidelines for Antiretroviral Therapy in Ghana September 2008
10 Bank statements of treatment sites
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 22
Appendix C
Key Players and their activities
No. Key Players/Stakeholders Activities
1 NACP Tasked with the responsibility to provide support to PLHIV by
ensuring that ARVs are available at all times for their use. Collates
data on PLHIV and submits information on quantities of ARV
required to the Procurement Unit of MoH for procurement.
2 Ministry of Health (MoH) Formulates policy for the health sector including HIV –AIDS
3 Ghana Health Service (GHS) Implements policy decisions taken by MoH relating to HIV-AIDS
4 Ghana AIDS Commission
(GAC)
Implement policy of the HIV-AIDS related aspects of the Ghana
Health sector strategic framework
5 Procurement unit (MoH) Procures ARVs for NACP.
6 Central Medical Stores (MoH) Implement and monitor ARVs supply plans. Store ARV buffer stock
and supply ARVs to RMSs.
7 Regional Medical Stores Manage ARVs and supply to the treatment sites in the regions.
Collate ARV usage from treatment sites and supply information to
CMS for planning and procurement.
8 DFID/World Bank Provides technical support
9 Global Fund/World Bank(TAP) Provides funding and budgetary support.
10 UNDP (UNAIDS)-Ghana Collaborates with AIDS agencies like NACP to fight HIV prevalence
in Ghana.
11 USAID (Deliver JSI) Provides technical support and advice on HIV-AIDS.
12 WHO Provides technical support to NACP.
13 Treatment Sites Treatment of HIV infection & AIDS using ARVs. Stores and
provides data on usage of ARVs to NACP
14 Ghana Supply Company Ltd. Clearing of ARVs at the airport
15 PLHIV Beneficiaries of the ARVs.
Source: Ghana Audit Service compilation
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 23
Appendix D
NACP system description
Source: GAS Compilation
Arrows going upwards signify submission of data/ information from treatment sites to
NACP, through RMSs for quantification and forecasting of ARVs
Arrows pointing downwards signify how RMSs and sites receive ARVs CMS
Procurement Unit – for procurement of ARVs
receives quantification and forecasting data /drug estimates
from the NACP
advertises for WHO pre-qualified Pharmaceutical
companies to bid.
receives ARVs from receives quantification and forecasting
data /drug estimates from the NACP
advertises for WHO pre-qualified Pharmaceutical
companies to bid.
evaluate and award contract
1.0 award contracts to WHO pre-qualified suppliers
2.0 CP
1.0 ies of RMSs and treatment sites
3.0 y Ltd who clears the drugs
4.0 supplies or distributes drugs to the various regional Medical
Stores and some sites designated as regions
5.0 receives ARVs from receives quantification and forecasting data
/drug estimates from the NACP
6.0 advertises for WHO pre-qualified Pharmaceutical companies to
bid.
7.0 evaluate and award contract
8.0 award contracts to WHO pre-qualified suppliers
9.0 CP
2.0 ies of RMSs and treatment sites
10.0 y Ltd who clears the drugs
11.0 supplies or distributes drugs to the various regional Medical
Stores and some sites designated as regions
and award contract
award contracts to WHO pre-qualified suppliers
Regional Medical Stores
receive ARV’s from CMS
supplies treatment sites with ARVs
receives monthly reports on ARVs from sites
sends quarterly reports from treatment sites to NACP
NACP – quantification and forecasting for ARVs
estimate the needed ARVs –using morbidity and
consumption data methods
forward estimates to the procurement unit
NACP establishes letters of credit for purchase of ARVs
monitors activities of RMSs and treatment sites
Central Medical Stores receives ARVs from airport through Ghana
Supply Company Ltd who clears the drugs
supplies or distributes drugs to the various
regional Medical Stores and some sites
designated as regions
Treatment sites
send monthly returns/ data to NACP RMS for quantification
and forecasting
receive ARVs from RMSs and CMS
supply ARVs to PLHIV
provide adherence counseling to PLHIV
Supplier /Manufacturer of ARVS
bids for contracts to supply ARVs
supplies ARVs to NACP/CMS
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 24
Appendix E
Analysis of responses of treatment sites to questions asked
No. Hospital Which
software
do you use
Has staff
been
trained?
Do you have
the necessary
equipment?
By which date of the
month are returns
sent to RMS?
1 Regional Hospital, Koforidua E-LMIS Y Y 10th
2 Suhum Gov’t Hospital E-LMIS N Received in
Sept 2010
3 St Joseph Hosp, Koforidua Manually Y N
4 Holy Family Hospital Manually Y Y 5th
5 Akuse Gov’t Hospital Excel N N From the 8th
6 Atua Gov’t Hospital Excel Y N 10th
7 Komfo Anokye Teach Hosp Excel N N After 15th
8 Suntreso Gov’t Hospital Excel Y Y 4th
9 Obuasi Gov’t Hospital Excel Y Y 7th
10 KNUST Excel Y N 15th
11 Bekwai Excel Y Y 5th
12 St Patrick’s Hospital, Offinso E-LMIS Y Y
13 Juaben Gov’t Hospital Excel N Y First Wed
14 Mampong Municipal Hosp Excel Y Y 10th
15 Bawku Hospital Manually Y Y
16 Zebilla District Hosp Excel Y Y After 5th
17 Sandema Hospital Excel Y Y Do not know when to
send returns
18 Bongo District Hospital Manually N Y After three months
19 War Memorial Hospital E-LMIS Y Y Defaults sometimes
20 Bolgatanga Reg. Hospital Excel Y Y 5th
21 Tamale Teaching Hospital Excel N Y
22 Central Hosp Tamale Manually Y Y (not in use
because of
lack of space)
23 Yendi Municipal Hosp Excel N Y
24 Walewale District Hosp Manually Y N-not
functional
Do not send returns
because the computer
has crashed Source: GAS Compilation
Y=sites which responded yes to questionnaire
N= sites which responded no to questionnaire
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 25
Appendix F
Amount of money collected by sites visited as at the time of the audit
No. Hospital Amount of revenue
GH¢
1 Regional Hospital, Koforidua 21,728.00
2 Suhum Gov’t Hospital
3 St Joseph Hosp, Koforidua 3,725.00
4 Holy Family Hospital 40,829.00
5 Akuse Gov’t Hospital 411.00
6 Atua Gov’t Hospital 116,775.00
7 Komfo Anokye Teach Hosp 317,458.00
8 Suntreso Govt Hospital 21, 021.50
9 Obuasi Govt Hospital 8,349.00
10 KNUST 550.00
11 Bekwai 4,271.00
12 St Patrick’s Hospital, Offinso 6,817.00
13 Juaben Gov’t Hospital 1,930.00
14 Mampong Municipal Hosp 12,444.00
15 Bawku Hospital 4,479.00
16 Zebilla District Hosp 1,081.00
17 Sandema Hospital 1,525.00
18 Bongo District Hospital 710.00
19 War Memorial Hospital 2,388.00
20 Bolgatanga Reg. Hospital 17,660.90
21 Tamale Teaching Hospital 3,969.90
22 Central Hosp Tamale 1,840.00
23 Yendi Municipal Hosp 3,609.00
24 Walewale District Hosp 520.00
Total 594,091.30
Source: GAS Compilation
***** = Newly created site and yet to start operation
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 26
Appendix G
Treatment sites with buffer stock
No. Hospital Buffer stock
1 Regional Hospital, Koforidua N
2 Suhum Govt Hospital Y
3 St Joseph Hosp, Koforidua N
4 Holy Family Hospital Y
5 Akuse Govt Hospital Y
6 Atua Govt Hospital Y
7 Komfo Anokye Teach Hosp Sometimes
8 Suntreso Govt Hospital N
9 Obuasi Govt Hospital Sometimes
10 KNUST N
11 Bekwai Y
12 St Patrick’s Hospital, Offinso Y
13 Juaben Gov’t Hospital Y
14 Mampong Municipal Hosp N
15 Bawku Hospital N
16 Zebilla District Hosp N
17 Sandema Hospital Y
18 Bongo District Hospital Y
19 War Memorial Hospital Sometimes
20 Bolgatanga Reg Hospital N
21 Tamale Teaching Hospital N
22 Central Hosp Tamale N
23 Yendi Municipal Hosp N
24 Walewale District Hosp N
Source: GAS Compilation
Y = those who responded yes to questionnaires
N = those who responded no to questionnaires
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 27
Appendix H
Air-conditioning at treatment sites
No. Hospital Air-conditioners Generator
1 Regional Hospital, Koforidua Y Y
2 Suhum Govt Hospital Y Y /not strong to
power air-con
3 St Joseph Hosp, Koforidua Y Y
4 Holy Family Hospital Y Y
5 Akuse Govt Hospital Y Y
6 Atua Govt Hospital Y Y
7 Komfo Anokye Teach Hosp Y N
8 Suntreso Govt Hospital Y Y
9 Obuasi Govt Hospital Y Y
10 KNUST Y Y
11 Bekwai Y Y
12 St Patrick’s Hospital, Offinso Y Y
13 Juaben Govt Hospital Y Y
14 Mampong Municipal Hosp Y Y
15 Bawku Hospital N N
16 Zebilla District Hosp Y N
17 Sandema Hospital Y N
18 Bongo District Hospital Y /not functioning N
19 War Memorial Hospital Y N
20 Bolgatanga Reg Hospital Y N
21 Tamale Teaching Hospital Y N
22 Central Hosp Tamale Y N
23 Yendi Municipal Hosp Yes Y
24 Walewale District Hosp Yes/breaks down often N
Source: GAS
Y = those who responded yes to questionnaires
N = those who responded no to questionnaires
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 28
Appendix I
Total amount of revenue collected from all the sites in the country as at June
2009
Region Amount collected
(GH¢)
Military Hospital 10,620.00
KATH 122,281.00
Ashanti 21,496.40
Upper East 27,474.40
Brong Ahafo 21,974.00
Eastern 270,632.50
Greater Accra 66,232.00
KBTH( 2008, Half year 2009) PAED 120,659.91
Northern Region 35,702.00
Upper West Region 16,227.00
Western Region 8,113.00
Police Hospital 5,040.00
Volta Region 28,901.50
Total 755,353.71
Source: NACP
Performance audit report of the Auditor-General on management and distribution ofAnti-retroviral drugs 29
Appendix J
List of abbreviations
ARVs ----------------------- Anti retroviral
CMS ----------------------- Central Medical Stores
GH¢ ------------------------ Ghana Cedis
GOG ----------------------- Government of Ghana
GHS ------------------------ Ghana Health Service
LMIS ------------------------ Logistic Management Information System
MOH ----------------------- Ministry of Health
NACP ---------------------- National AIDS Control Programme
PLHIV----------------------- People Living with HIV
RMS ----------------------- Regional Medical Stores
GSCL ----------------------- Ghana Supply Company Limited
PU ------------------------ Procurement Unit
Mission
Statement
The Ghana Audit Service exists
To promote
good governance in the areas of transparency,
accountability and probity in the public financial
management system of Ghana
By auditing
to recognized international auditing standards the
management of public resources
And
reporting to Parliament