1 P6.0 Workgroup Meeting #1: Summary Notes RTP Headquarters, 12 Davis Drive, Research Triangle Park Monday, October 15, 2018, 9:30 am – 3:00 pm Attendees Participant Advisory Other Anthony Prinz Karyl Fuller Aldea Coleman Bobby Lewis Austin Chamberlain Matt Day Bobby Walston Brian Gackstetter Beau Mills Neil Burke Brooke Boyle Cat Peele Brian Burch Patrick Flanagan Dan Gurley Jon Arnold Brian Wert Pat Ivey Debbie Collins Julie Lorenz (Facil.) Chris Lukasina Ray McIntyre George Hoops Kai Monast Chris Werner Ronnie Keeter Hanna Cockburn Neil Perry David Wasserman Sarah Lee Jason Gray Rich Denbow (Admin.) Jason Schronce Tristan Winkler Jason Orthner Ron McCollum Joey Hopkins Tyler Meyer John Farley Julie White Vicki Eastland Josh Levy Stephanie Ayers Sterling Baker Van Argabright Welcome/Agenda Review David Wasserman began the meeting at 9:30am by welcoming the attendees. He introduced Julie Lorenz as the new Workgroup facilitator. Julie is with Burns and McDonnell and previously worked for Kansas DOT. Julie also previously facilitated the P2.0 Workgroup. David reviewed the agenda and the desired outcomes for the meeting. Introduction Julie welcomed the meeting attendees. Julie’s primary role as facilitator is to ensure the meeting covers all of the topics on the agenda while providing the Workgroup opportunity for discussion. Workgroup members introduced themselves. Opening Remarks Bobby Lewis welcomed the attendees and emphasized the importance of the Workgroup to the success of STI implementation over the past several years. Under STI, the State’s programming process has evolved to where there is now a fully transparent STIP. The P6.0 process will be especially important to the State as population in North Carolina and neighboring states continues to grow, as vehicle technology advances, and as the state considers new revenue sources and approaches.

Transcript of P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project...

Page 1: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

1  

P6.0 Workgroup Meeting #1:  Summary Notes 

RTP Headquarters, 12 Davis Drive, Research Triangle Park 

Monday, October 15, 2018, 9:30 am – 3:00 pm 

 

Attendees 

Participant  Advisory  Other 

Anthony Prinz  Karyl Fuller  Aldea Coleman  Bobby Lewis 

Austin Chamberlain  Matt Day  Bobby Walston  Brian Gackstetter 

Beau Mills  Neil Burke  Brooke Boyle  Cat Peele 

Brian Burch  Patrick Flanagan  Dan Gurley  Jon Arnold 

Brian Wert  Pat Ivey  Debbie Collins  Julie Lorenz (Facil.) 

Chris Lukasina  Ray McIntyre  George Hoops  Kai Monast 

Chris Werner  Ronnie Keeter  Hanna Cockburn  Neil Perry 

David Wasserman  Sarah Lee  Jason Gray  Rich Denbow (Admin.) 

Jason Schronce  Tristan Winkler  Jason Orthner  Ron McCollum 

Joey Hopkins  Tyler Meyer  John Farley 

Julie White  Vicki Eastland  Josh Levy   

    Stephanie Ayers 

    Sterling Baker   

    Van Argabright   

 

Welcome/Agenda Review 

David Wasserman began the meeting at 9:30am by welcoming the attendees.  He introduced Julie 

Lorenz as the new Workgroup facilitator.  Julie is with Burns and McDonnell and previously worked for 

Kansas DOT.  Julie also previously facilitated the P2.0 Workgroup.  David reviewed the agenda and the 

desired outcomes for the meeting. 

 Introduction 

Julie welcomed the meeting attendees.  Julie’s primary role as facilitator is to ensure the meeting covers 

all of the topics on the agenda while providing the Workgroup opportunity for discussion.  Workgroup 

members introduced themselves.  

 Opening Remarks 

Bobby Lewis welcomed the attendees and emphasized the importance of the Workgroup to the success 

of STI implementation over the past several years.  Under STI, the State’s programming process has 

evolved to where there is now a fully transparent STIP.  The P6.0 process will be especially important to 

the State as population in North Carolina and neighboring states continues to grow, as vehicle 

technology advances, and as the state considers new revenue sources and approaches.  

 

Page 2: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

2  

Roles and Responsibilities 

Julie discussed the roles and responsibilities of the different types of Workgroup members.  She also 

covered the general ground rules for Workgroup meetings, including a clear understanding of operating 

in a consensus‐driven manner.  [See Roles and Responsibilities document for more information.] 

 Overall Schedule and Workgroup Meeting Schedule/Approach 

David summarized transportation project prioritization efforts across the nation.  North Carolina is a 

leader in prioritization and is one of only four states with a mature prioritization process.  North Carolina 

is statutorily required to fund the highest scoring projects based on Prioritization results, which allows 

the state to address critical transportation needs while growing rapidly.  

Based on this mature prioritization process, David introduced the proposed P6.0 Workgroup approach.  

Under this new approach, in order to change something from previous prioritization rounds, the 

Workgroup would need to agree that the issue needs to be addressed in P6.0.  Otherwise, items would 

remain the same as P5.0.  This means consensus is assumed on items that are not raised for discussion.  

This proposed approach would apply to all aspects of scoring, including criteria, weights, measures, data 

usage, local input points, and submittal numbers.  This approach is also supported by responses to the 

recent Workgroup topic survey. 

As part of this proposed approach, David reviewed the proposed schedule for 7 additional Workgroup 

meetings that would take place approximately once a month from November 2018 to (early) June 2019.  

Subcommittees would be established and utilized to address more specific modes and topics of interest, 

such as Bike/Ped, Public Transportation, Aviation, and potentially others.  Subcommittee membership 

will depend on the topic, interest level, and expertise of Workgroup members.  Each subcommittee 

would discuss topics in depth and develop recommendations to bring to the overall Workgroup; the 

overall Workgroup would reach consensus on each topic.  

Consensus is desired on this meeting schedule and approach at the November Workgroup meeting. 

The Workgroup discussed this approach.  A few members expressed concern about assuming there is 

consensus on items that are not raised for discussion.  Issues may arise during the process that are not 

foreseen early on, and there would no longer be an opportunity to address it.  Julie responded that all 

items raised during the Workgroup topic survey will be discussed and voted on today, and the 

Workgroup will identify those that rise to the top as priorities.  Any additional items not addressed in 

survey responses are also open to discussion today.  This approach is simply a way to make the 

Workgroup process more efficient, and items that arise during future Workgroup meetings would 

certainly be open to discussion by the Workgroup if deemed necessary and time allows.  

Julie reiterated that this approach is presented for discussion today but consensus would not desired 

until the next Workgroup meeting.  

 Committed Project Definition 

David started a discussion about Committed Projects.  In previous rounds, numerous programmed 

projects fell out of the STIP between prioritization rounds.  NCDOT’s goal is to create more stability and 

reliability in project delivery.   

 

Page 3: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

3  

David presented options for the Committed Project window:  

1. increase to 8 years, 

2. increase to 7 years, or  

3. keep as 5 years (P5.0 approach). 

Consensus is desired on this topic prior to programming P5.0 Division Needs projects and the release of 

the Draft 2020‐2029 STIP. 

During discussion, it was noted that projects often fall out for good reasons, such as findings from 

additional project studies, input received during public involvement on a project, changing prioritization 

criteria, and better projects coming along.  Many projects that fall out do so due to changing criteria, 

therefore it’s important to maintain stability in the criteria as much as possible between prioritization 

cycles.  However, North Carolina also needs flexibility to stay responsive to rapidly changing needs 

across the State.  Some members suggested considering a 6 or 7 year window (the SPOT office also 

provided data for 6 years).  Others suggested that in order to avoid unintended consequences, the 

Workgroup may also want to leave the window as is and instead address the issue outside of this 

process.  However, there may be fewer unintended consequences if an incremental change is made 

from a 5 year to a 6 year window, versus going from a 5 year to a 7 year or 8 year window.  

Overall, the Workgroup did not seem in favor of an 8 year window.  The SPOT office will bring additional 

information on all options to the next meeting.  The Workgroup was asked to consider this topic, with 

the desire to reach consensus at the next meeting.  

 Topic Gathering Exercise 

The SPOT office led an exercise to identify the priority topics to be addressed in P6.0, which began by 

highlighting prioritization roles established in the STI law.  

Jason Schronce reviewed the summarized results from the topic survey completed by Workgroup 

members about the items that worked well in P5.0 and those that potentially need improvement.  Each 

specific item submitted for potential improvement had been condensed and printed on individual cards 

on a poster board for use during this discussion.  Jason, David, and Sarah Lee reviewed each item and 

clarified with the Workgroup as needed.  Workgroup members also submitted additional topics to the 

boards during the discussion.  [See list of topics and photos of boards for further information.]  

Next, Julie conducted an exercise in which the Workgroup members identified their top priorities.  Each 

participant was given twelve voting dots to place next to the items they believe are priority topics.  [See 

list of topics and photos of boards for further information.]  The results of this exercise will be used by 

the SPOT office to create a tentative schedule of topics for future Workgroup meetings. 

A member asked if the Workgroup will address issues that involve legislative changes.  David replied that 

the Workgroup has not historically done this because it is out of the Workgroup’s purview.  Any 

legislative changes should be suggested or advocated for through the members that are staff to the 

Legislature, or through Workgroup members’ respective organizations.    

 Wrap Up/Next Steps 

David thanked the Workgroup for their participation and input.  In scanning the topic items on the 

boards, he noted that the Workgroup can address some of the issues that were raised but may not be 

Page 4: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

4  

able to address all.  He did note that SPOT On!ine will still be used for P6.0 (rather than move to the new 

TOP3S application).  

The first subcommittee meeting for Bike/Ped and Public Transportation will take place on Thursday, 

October 18th, and the first subcommittee meeting for Aviation will be on Friday, October 19th. 

Sarah reminded the Workgroup that a Workgroup website has been created and is where all 

documentation will be available. The URL is: 

https://connect.ncdot.gov/resources/PrioritizationWorkgroup/Pages/default.aspx 

David noted that the next meeting will focus on reaching consensus on the Workgroup meeting 

schedule and approach, as well as the Committed Project window.  It will also include a potential 

schedule of the topics to address in P6.0, based on today’s discussions and exercise.  

 Next Meeting 

The next Workgroup meeting will take place on Monday, November 5, 2018 at RTP Headquarters. 

Page 5: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

1  

P6.0 Workgroup Meeting #2:  Summary Notes  

RTP Headquarters, 12 Davis Drive, Research Triangle Park 

Monday, November 5, 2018, 9:30 am – 3:00 pm 

 

Attendees 

Participant  Advisory  Other 

Amber Harris  Karyl Fuller  Amanda Hayden  Julie Lorenz (Facil.) 

Anthony Prinz  Matt Day  Brooke Boyle  Rich Denbow (Admin.) 

Austin Chamberlain  Neil Burke  Dan Gurley  Ron McCollum 

Beau Mills  Patrick Flanagan  Dana Magliola   

Brian Burch  Pat Ivey  George Hoops   

Brian Wert  Randi Gates  Hanna Cockburn   

Bryant Buck  Ray McIntyre  John Farley   

Chris Werner  Ronnie Keeter  Lisa Hollowell   

David Wasserman  Sarah Lee     

Jason Schronce  Tristan Winkler   

Joey Hopkins  Tyler Meyer     

Julie White  Vicki Eastland     

 

Welcome/Agenda Review 

David Wasserman began the meeting at 9:30 am by welcoming the attendees.  He provided a recap of 

the previous Workgroup meeting and reviewed the agenda and the desired outcomes for this meeting. 

Subcommittee Updates 

Sarah Lee provided an update on Subcommittee membership and activities.  The Bike/Ped, Transit, and 

Aviation Subcommittees each met in October to review P5.0 scoring and discuss potential 

improvements for their respective modes.   

 

Jason Schronce asked for a show of hands from those who are interested in participating in the Highway 

Subcommittee.  The SPOT Office will schedule the first Highway Subcommittee meeting to be held in 

late November.  

 

P6.0 Overall Schedule and Workgroup Meeting Schedule/Approach 

The SPOT Office reviewed the proposed P6.0 overall schedule, including the requested change from the 

last meeting to extend the Regional Impact point assignment window from 3 to 4 months.  Some 

Workgroup members stated that the timeframe for Local Input Points does not necessarily need to be 4 

months in length, but that this period usually ends up being completed in July instead of June.  They 

emphasized that developing project costs takes a significant amount of time, and some would prefer the 

extra month to be during the scoring and data review period in order to allow additional time for QA/QC 

of costs.  SPOT Office staff asked Division Engineers if 3 months is enough time to complete their point 

assignments, including the coordination with POs and the public comment period.  The MPO and RPO 

meeting schedules usually drive this part of the process, so it would depend on when PO meetings are 

Page 6: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

2  

held.  The number of POs in a Division is also a factor.  The Workgroup tabled this discussion until the 

end of the meeting in order to allow time for David to check with other Division Engineers on the 3 

month time period.  

 

The SPOT Office reviewed the proposed Workgroup meeting schedule and approach.  RTP Headquarters 

had been confirmed for the location of the 2019 meetings.  The Workgroup briefly discussed the 

approach, with the understanding that additional topics will be addressed by the Workgroup as needed, 

and all P6.0 components would be viewed as a “package” (as would be presented to the Board of 

Transportation) toward the end of Workgroup.  This would prevent consensus from being assumed on 

any item not discussed in detail by the Workgroup.  As part of this package, it was noted that the P5.0 

method would be the default unless there is consensus to change.  It was also noted that subcommittee 

recommendations would be open for discussion in the Workgroup and not assumed as automatic 

consensus.  The Workgroup reached consensus on the Workgroup meeting schedule and approach. 

 

The Workgroup revisited the P6.0 overall schedule at the end of the meeting.  David reported that the 

Division Engineers replied that 3 months would be workable.  The Workgroup reached consensus on 

the proposed P6.0 overall schedule, with the following changes: 

Extend scoring and data review period from 5 to 6 months 

The SPOT office will release quantitative scores at the end of April 2020 instead of March 

2020 

Regional Impact point assignment window will be 3 months, from the beginning of May 2020 

to the end of July 2020.  

 

Committed Project Definition 

The Workgroup discussed options for changing the Committed Projects window.  NCDOT has a goal of 

creating additional stability and reliability for project delivery while still allowing for flexibility and new 

projects to get funded through STI.  The SPOT office presented an analysis of Statewide, Regional, and 

Division projects funded in P4.0 that had to recompete in P5.0, and the outcome of these projects after 

P5.0 scoring.  The funding line shift appears to be the factor that made the biggest difference.  In 

addition, many projects continue to receive cost increases.  Most P5.0 projects funded in Statewide, and 

many Regional and Division projects, will likely have to recompete in P6.0 with the current 5 year 

committed project window.  

 

The Workgroup discussed pros and cons of changing the Committed Projects window from 5 to 6 years.  

Some were concerned that going to a longer window would commit most of the overall STIP budget, 

which may limit flexibility to fund important projects in the future.  Others said the focus should be on 

committing more projects, and the longer window will help.  

 

During the discussion, a few members noted that there was an infusion of funds during the previous 

round that we won’t have for P6.0, therefore outcomes may be different after this round.  It was 

suggested that at some point the caps on each mode should be considered for adjustment.  A few 

members suggested there may be a problem with how committed projects are communicated to the 

public.  The communication issue was placed in the parking lot for future discussion.   

 

Page 7: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

3  

The Workgroup reached consensus to increase the Committed Projects window from 5 to 6 years for 

P6.0.  As a note, this definition applies to the 2020‐2029 STIP (resulting from P5.0) currently under 

development.  The length of the committed window may be revisited in P7.0 Workgroup discussions. 

 

Items in Motion (Since P5.0 Workgroup Ended) 

The SPOT Office reviewed items that are already in motion from P5.0.  [See presentation slides for the 

list of items.]  Some Workgroup members requested information about NCDOT’s approach to PeakADT 

Factors Statewide Update.  NCDOT will send the scope to the Workgroup.  

 

Draft P6.0 Topic Schedule 

The SPOT Office presented a draft P6.0 topic schedule, with desired consensus items and topics for each 

meeting.  Sarah asked the Workgroup to provide feedback to the SPOT Office on the schedule.  

 

Future Interstate Completion Factor 

The SPOT Office led a discussion of scoring in P5.0 for the Future Interstate Completion Factor (FICF).  

The sense of the Workgroup is that the FICF is accomplishing its intended purpose, which is to identify 

projects that improve the movement of freight across North Carolina.  The Workgroup reached 

consensus on the continued use of the Future Interstate Completion Factor in P6.0.  

 

Local Input Points 

The SPOT Office led a brainstorming exercise on how to improve the Local Input Points (LIP) process.  

Austin Chamberlain provided a history of LIP in each prioritization round and discussed LIP issues that 

were identified by Workgroup members in survey responses.  The Workgroup discussed how POs and 

Divisions allocate LIPs and initial ideas to improve the process, including adjusting the number of points 

and/or linking the points to project cost.     

 

A subcommittee was formed to identify and discuss ideas and will meet before the next Workgroup 

meeting.  Subcommittee members asked the SPOT Office to provide data about how POs and Divisions 

have allocated points in previous prioritization rounds and to what modes.  

 

Wrap Up/Next Steps 

Jason asked the Workgroup for clarification on a few Highway topics that were identified in the October 

15, 2018 Workgroup meeting: 

Resiliency – the Workgroup is interested in not only the evacuation component of resiliency but 

also the ability to respond after an event to reach those who did not evacuate and need 

services.  This could be addressed as part of modernization or perhaps by using an impedance 

factor.  

Safety benefit calculations – a Workgroup member pointed out that highway widening projects 

do not receive safety points but highway median projects do.  This is something that could be 

addressed. 

Linking Prioritization to federal performance measures – the Workgroup will discuss this topic at 

a future meeting. 

David thanked the Workgroup for their participation and input.  

Page 8: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

4  

 

Next Meeting 

The next Workgroup meeting will take place on Monday, December 3, 2018 at RTP Headquarters. 

 

Action Items: 

Provide Peak ADT scope 

Provide Draft Topic Schedule 

Provide data on LIP assignment to subcommittee 

Page 9: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

1  

P6.0 Workgroup Meeting #3:  Summary Notes  

RTP Headquarters, 12 Davis Drive, Research Triangle Park 

Monday, December 3, 2018, 9:30 am – 3:00 pm 

 

Attendees 

Participant  Advisory  Other 

Anthony Prinz  Karyl Fuller  Aldea Coleman  Julie Lorenz (Facil.) 

Austin Chamberlain  Matt Day  Brooke Boyle  Neil Perry 

Beau Mills  Neil Burke  Dana Magliola  Rich Denbow (Admin.) 

Brian Burch  Patrick Flanagan  George Hoops   

Brian Wert  Pat Ivey  Stephanie Ayers   

Bryant Buck  Ray McIntyre     

Chris Lukasina  Ronnie Keeter     

David Wasserman  Sarah Lee     

Jason Schronce  Tristan Winkler     

Joey Hopkins  Tyler Meyer   

Julie White  Vicki Eastland     

 

Welcome/Agenda Review 

David Wasserman began the meeting at 9:30am by welcoming the attendees.  He provided a recap of 

items the Workgroup reached consensus on at the previous Workgroup meeting:  P6.0 Workgroup 

meeting schedule and approach, P6.0 overall schedule, Committed projects definition, and Future 

Interstate Completion Factor.  

 

David announced that Jason Schronce had accepted the position as SPOT manager and is now Chair of 

the P6.0 Workgroup.  Jason reviewed the agenda and the desired outcomes for this meeting. 

 

Subcommittee Updates 

Sarah Lee and Jason Schronce provided an update on recent subcommittee activities.  [See Workgroup 

presentation slides for more information.]  The Bike/Ped, Transit, Aviation, Highway, and Local Input 

Points (LIP) subcommittees each met in November.  While reviewing the concept of a Highway resiliency 

factor, one Workgroup member pointed out that some of the approaches the subcommittee discussed 

to use resiliency as a factor would involve a significant amount of effort.  The subcommittee may want 

to consider other approaches that could be done more quickly.  The Workgroup raised the possibility of 

analyzing network segments rather than using the Statewide Model.  The Highway subcommittee will 

continue to discuss the resiliency topic at future meetings.  

 

Page 10: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

2  

Local Input Points 

The SPOT Office led a discussion to get input on the full range of issues and observations related to LIP 

for P6.0 and whether changing LIP is the solution to address the known issues, in order to either reach 

consensus or provide the LIP subcommittee with more direction.  Sarah reviewed the known LIP issues 

that had been identified and potential solutions to address the issues.  She presented data showing the 

number and percentage of submittals by mode vs. the percentage of total points by mode, as well as 

LIPs assigned by cost percentile by mode.  [See Workgroup presentation slides for more information.] 

 

A Workgroup member noted that the data indicates there is a high level of desire for bike and ped 

projects but an identified lack of available resources for the projects, which is reflected in the points 

allocated.  Another member pointed out that the ability to match and administer these projects locally is 

a hurdle.  A few members said that the Workgroup should recognize and state that LIP issues are more 

of a reflection of local governance, local funding constraints, and/or specific LIP methodologies rather 

than a result of problems with the STI process and LIPs.  This point could be noted in an after‐action 

report that summarizes the data trends and discusses the possible reasons behind the trends.  The 

Workgroup also discussed the potential to bundle low‐cost projects with other projects (either within 

jurisdictions or across the state, and both within a mode and across multiple modes) in order to 

encourage more LIPs to be assigned to these.   

 

With regard to the education and awareness of local governments on the lack of funding and value of 

projects in various project modes, some Workgroup members suggested that a round of exercises 

across the state similar to the Investment Strategy Summits offered by the SPOT Office many years ago 

could potentially be helpful.  It was noted that this type of exercise may already be part of the State’s 

long range transportation plan update (NC Moves 2050), but there is value in doing it at the local level as 

well.  

 

The SPOT Office also reviewed the results of the LIP topic discussion from the P5.0 Workgroup, and 

noted that many of the issues and conclusions are similar to those currently being discussed. 

 

After presenting all the data and concluding the discussions, the SPOT Office asked the Workgroup for 

direction for the subcommittee or if they were ready for consensus.  It was requested to have the 

subcommittee analyze the current allocation of Regional points (if there are too many) as well as the 

concept of pooling Regional and Division points into one allocation per organization.  It was also 

suggested to look at the ratio of projects to points at the Division level.   

 

Lastly, it was suggested that if an after‐action report is developed, it should identify the types of projects 

that potentially could do better outside of STI (ex. rural Public Transportation vehicle requests).  

 

Peak ADT 

Jason provided details about NCDOT’s Peak ADT update.  The approach calls for 50 counties to be 

updated for P7.0 and all 100 counties updated for P8.0.  The Highway subcommittee recommends 

continuing the use of Peak ADT in P6.0 as it was done in P5.0.  A few Workgroup members asked if the 

approach will address the issue of navigation apps redirecting drivers to alternate routes during periods 

of congestion.  Jason said this could be considered during development of sampling plans.  The 

consultant doing the Peak ADT update is reaching out to MPOs and RPOs.  If they are aware of instances 

Page 11: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

3  

where this is occurring, they can raise it to be addressed in the sampling plan.  A Workgroup member 

asked that NCDOT share count locations once they are identified.  The Workgroup reached consensus 

to continue the use of Peak ADT in P6.0 as it was used in P5.0 scoring. 

 

Bicycle/Pedestrian Improvements 

Sarah provided a detailed update of Bike/Ped subcommittee activities and reviewed the current 

recommendations.  The subcommittee reviewed project scoring statistics in both prioritization rounds 

by bicycle vs. pedestrian, but also requested to further examine the data broken down by Specific 

Improvement Type (SIT).  Their primary topics of discussion were Specific Improvement Types, Safety 

criteria, Cost Effectiveness criteria, and project costs.  Recommendations from these discussions are as 

follows: 

Specific Improvement Types – remove route designations from SIT 1, as long as scoring finds 

another way to reward the project for improving these routes 

Specific Improvement Types – clarification to include bridges/tunnels over rivers and physical 

barriers 

Specific Improvement Types – further examine some intersection improvements that could 

move from SIT 5 to SIT 4 (or 3) 

Safety – remove the lookup table for Speed Limit scoring and scale based on the raw speed 

limit 

Safety – continue using bike/ped crash data 

Cost Effectiveness – convert to Benefit/Cost by implementing economic data as a benefit 

 

The subcommittee also discussed project cost and ways to bundle projects in order to increase project 

cost (and attractiveness for LIP), as well as the consideration of a Multimodal factor in the benefit (of 

Benefit/Cost) to offset the potential additional cost of multimodal/bundled projects.  The subcommittee 

will continue to discuss these items and bring recommendations to the full Workgroup for discussion 

and consensus.  

 

Multimodal Benefits 

Sarah reported that the Bike/Ped and Transit subcommittees discussed issues and ideas for encouraging 

and rewarding the submittal of projects with multimodal elements.  She presented the Benefit/Cost and 

Cost Effectiveness formulas for each mode and how multimodal factors could be implemented.  

Workgroup members understood the potential benefit of incorporating a multimodal element into 

scoring, but noted that it would be difficult to come up with a one‐size‐fits‐all approach that applies to 

all projects and modes.  A multimodal factor could perhaps be considered only for certain applicable 

modes.  A “hold harmless” solution to remove project cost increases from scoring due to multimodal 

elements was also suggested as an alternative to a factor that rewards projects for those elements.  And 

finally, it was discussed that if the NCDOT Complete Streets committee moves towards the idea of 

Complete Streets being “business as usual”, then a multimodal factor would not be needed, as these 

elements should be included in all projects as applicable. 

 

The Workgroup was interested in continuing the discussion at the subcommittee level.  NCDOT 

Complete Streets committee staff will also be involved in the discussions.   

 

 

Page 12: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

4  

Aviation Improvements 

Sarah briefly discussed the introductory list of topics the Aviation subcommittee is working on.  [See 

Workgroup presentation slides for more information.]   

 

Area‐Specific Weights vs. Default Weights 

The Spot Office conducted an analysis of the use of Area‐Specific Criteria Weights by each applicable 

Region and Division in P5.0.  The analysis shows that the Regions and Divisions generally benefited by 

using area‐specific weights.  A Workgroup member suggested it would be useful to do the analysis by 

SIT, which could indicate whether Divisions were aiming to benefit certain projects.  The Workgroup 

would like to see more data about the breakdown by SIT and a similar analysis for prior Prioritization 

cycles.  

 

Mobility vs. Modernization Weights 

Jason asked the Workgroup if there is interest in looking into using different weights for mobility 

projects vs. modernization projects (SIT 16 and SIT 17).  The Workgroup expressed interest in looking at 

this topic further.  The Workgroup mentioned that Prioritization 2.0 used a similar method.  One 

member said that if the Workgroup decides to treat modernization as essentially a separate mode, 

other factors such as resiliency can also be addressed here. 

 

Project with Multiple Cross Sections  

Jason raised the topic of addressing projects that have multiple cross sections.  One potential approach 

is to enter a project multiple times into SPOT Online with the applicable cross sections.  The SPOT office 

would then analyze the projects separately by cross section and factor the final score by length of each 

cross‐section.  Jason asked the Workgroup if this is a common issue and one that should be addressed in 

P6.0.  The Workgroup said this would be a nice enhancement, but it is not common enough to be critical 

to P6.0 scoring.   

 

Draft P6.0 Topic Schedule 

Sarah reviewed the anticipated topics for the upcoming Workgroup meetings.  

 

Wrap Up/Next Steps 

Sarah highlighted the Consensus Tracker document that can be accessed on the P6.0 Workgroup 

website.  The SPOT Office also added all Workgroup and subcommittee meetings to the calendar.  The 

Workgroup requested that SPOT Office presentations to the Board of Transportation also be added to 

the calendar.   

 

Jason thanked the Workgroup for their participation.  

 

Next Meeting 

The next Workgroup meeting will take place on Monday, January 7, 2019 at RTP Headquarters. 

Page 13: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

1  

P6.0 Workgroup Meeting #4:  Summary Notes 

RTP Headquarters, 12 Davis Drive, Research Triangle Park 

Monday, January 7, 2019, 9:30 am – 3:00 pm 

 

Attendees 

Participant  Advisory  Other 

Anthony Prinz  Karyl Fuller  Aldea Coleman  Brian Gackstetter 

Austin Chamberlain  Matt Day  Brooke Boyle  Brittany Gaustad (ITRE) 

Beau Mills  Neil Burke  Dana Magliola  David Crest (Timmons) 

Brian Burch  Pat Ivey  George Hoops Heather Hildebrandt 

(NCDOT) 

Brian Wert  Patrick Flanagan  Hanna Cockburn  Jim Reed (Timmons) 

Bryant Buck  Ray McIntyre  Stephanie Ayers  Kai Monast (ITRE) 

Chris Lukasina  Ronnie Keeter  Van Argabright  LaToya Caldwell 

Chris Werner  Sarah Lee    Rich Denbow (Admin.) 

David Wasserman  Tristan Winkler    Sean Diehl (Timmons) 

Jason Schronce  Tyler Meyer    Stacy Cook (Facil.) 

Joey Hopkins  Vicki Eastland    Waugh Wright (ITRE) 

Julie White       

 

Welcome/Agenda Review 

Jason Schronce started the meeting at 9:30 by welcoming the attendees.  He briefly summarized the 

previous Workgroup meeting, at which the Workgroup reached consensus to continue the use of Peak 

ADT in P6.0 as it was used in P5.0 scoring.  Jason reviewed the agenda and desired outcomes for this 

meeting and announced that Stacy Cook from Cambridge Systematics will serve as our facilitator for this 

meeting in place of Julie Lorenz.  

Subcommittee Updates 

Sarah Lee and Jason provided an update of recent subcommittee activities.  The Highway, Bike/Ped, 

Transit, Aviation, and LIP subcommittees each met in December.  [See Workgroup presentation slides 

for more information.]  Many of the items discussed in the subcommittee meetings are on today’s 

agenda for Workgroup discussion and feedback.  

Local Input Points 

The SPOT Office led a discussion about potential changes to LIP for P6.0.  Sarah summarized discussions 

that have taken place during recent LIP subcommittee meetings, particularly those around flexing LIP 

points and number of points.  [See Workgroup presentation slides for more information.]  The 

Workgroup first addressed the topic of flexing LIP points.  The LIP subcommittee discussed the option to 

flex up to 50% of an organization’s points between the Regional and Division categories.  This would 

provide more flexibility to address varying needs of different areas in each category.  Flexing would be 

Page 14: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

2  

optional, and each organization’s decision to potentially use flexing would need to be part of the 

approved LIP methodology.   

Several Workgroup members expressed support for this approach.  There was discussion around the 

50% value.  One possible drawback is that large Divisions may gain an unfair advantage over smaller 

Divisions by flexing 50% of a larger number of allocated points, especially in Regional Impact.  The 

Workgroup discussed whether the percent should be lower, or perhaps a set number or a not‐to‐exceed 

amount.  The Workgroup concluded that because this is new territory, 50% of an organization’s entire 

point allocation is too high, and a low number should be chosen to start with.  The Workgroup reached 

consensus to allow each organization the option of flexing of up to 500 points (50% of the base 

allotment) between the Regional Impact and Divisional Needs categories. 

The Workgroup then discussed the number of points allocated to each organization.  Jason summarized 

the subcommittee’s discussions, which reflect a feeling by some that there are too many points overall.  

However, in more detail, there are too many Regional points for some areas, but too many Division 

points in other areas.  In addition, funding has traditionally run out before points, and the calculation 

method of the number of points allocated to each organization has not changed since P3.0.  The 

subcommittee proposed to round population values up to the next 50,000 value instead of the nearest 

value when applying the LIP calculation formula.  Jason showed LIP point allocations by PO and Division 

using both rounding methods, both of which used the updated census data.  

Jason asked the Workgroup if the number of points is an issue that should be addressed or left as‐is.  

Some members agreed there are too many points, and it would make sense from a technical perspective 

to reduce the overall number, but doing so would mean many organizations that currently have a small 

number of points could actually decrease further.  In addition, proportionality between the population 

differences and number of points among various areas is also becoming a concern.  A more sensible 

time to reduce points could be when new census designations are released after the 2020 census.  In 

general, members thought that allowing flexing may address the issue, and it was suggested to keep the 

process changes incremental in order to understand the effects.  The Workgroup reached consensus to 

apply the LIP formula used in P5.0, with the change to always round populations up to the next 

50,000. 

Bicycle/Pedestrian Improvements 

The SPOT Office provided more detail about the Bike/Ped subcommittee’s activities.  The subcommittee 

requested project statistics broken down by Specific Improvement Type (SIT) and possibly by criteria.  

Sarah presented this data.  [See Workgroup presentation slides for more information.]  The key 

takeaway from this analysis is that most quantitative scores decreased slightly from P4.0 to P5.0.  The 

primary reason for the decrease appears to be Connectivity criteria scoring corrections.  

Sarah summarized the subcommittee’s discussions about Access and Connectivity criteria and asked for 

feedback from the Workgroup.  The Workgroup discussed how Connectivity is defined.  The original goal 

of connectivity was aimed at filling in gaps in existing networks, but it does not address or reward a goal 

of creating new networks where there is a need or making connections between points of interest 

(destinations).  The Workgroup discussed combining Access and Connectivity to cover connecting origins 

and destinations as well as enhancing or beginning new networks.  It was suggested to provide more 

Page 15: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

3  

statistical analysis of where Connectivity is not working as it should, such as projects that begin new 

networks.  

The Workgroup also discussed why “residential” was previously taken out as a destination in the Access 

criteria.  Reasons include lack of a good definition of residential, and almost every project has some sort 

of access to residential.  The subcommittee will discuss whether residential should be added back in as a 

destination.  It could be qualified and varied by considering the density of residential.  One member 

noted that it presents a disadvantage in rural areas because bike/ped projects are partially funded in a 

statewide competition.  Another member followed up by requesting that this issue of statewide 

competition for bike/ped projects be added to the subcommittee’s list of topics to discuss. 

Transportation Disadvantage 

Brittany Gaustad and Waugh Wright, ITRE, gave a presentation titled “Assessing Measures of 

Transportation Disadvantage for Public Transportation Project Prioritization.”  [See Workgroup 

presentation slides for more information.]  The presentation summarized research conducted to 

evaluate measures of transportation disadvantage (TD) and recommend metrics to be included in P6.0 

for public transportation scoring (and potentially bike/ped scoring).  The researchers discussed 

conclusions and recommendations and asked Workgroup members for feedback.  

As part of the discussion, Sarah noted that the subcommittee heard this same information in the last 

meeting and therefore has not spent much time discussing TD yet.  It likely will not be its own criteria, in 

order to avoid assigning zero points to projects where TD is not applicable.  One way to address this 

across the board is to apply it as a factor, potentially to the trips value used in scoring.  Workgroup 

members asked how this topic is connected to the Bike/Ped subcommittee discussions about Access and 

Connectivity.  These are related efforts, and the TD presentations and discussion are being shared with 

both groups.  A TD measure may potentially apply to bike/ped projects.  Some members emphasized 

that a TD measure should be quantitative rather than a yes/no measure.  Another member suggested to 

keep in mind that there are technical concerns with the available data and analysis methods – the 

analysis methods work well for fixed route service but may not work well for demand response service.  

Lastly, a member requested to know what data is available for the metrics, at what geography it is 

available, and what it would it look like when it is applied. 

Sarah said the subcommittee will continue to discuss this topic to determine what can be addressed in 

P6.0.  She asked the Workgroup to review the ITRE research materials for further discussion at the next 

subcommittee meeting.  

Resiliency Factor 

The SPOT Office led a discussion on resiliency to seek agreement on the definition of resiliency and 

provide guidance to the SPOT Office on what needs to improve, what kind of projects should be 

promoted, and if there are known locations.  Jason provided two definitions of resiliency – one used by 

CDM Smith for the North Carolina Statewide Travel Model (NCSTM) and another from FHWA.  He asked 

Workgroup members if there are any other definitions that should be considered.  The Highway 

subcommittee would like guidance from the Workgroup on what the definition should be for 

prioritization purposes. 

Page 16: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

4  

The ports define resiliency as the ability to recover port services after events (e.g., weather‐related) as 

well as redundancy and building/enhancing facilities to be more resilient.  Others said a risk‐based 

approach that considers the importance of a facility to the system is important.  Some members said 

that because resiliency means different things to different people, it may not be possible to develop a 

factor that can be used in P6.0 in any meaningful way.  If there was a map of critical facilities across the 

State, a priority factor could be added to improvement projects on these facilities.  Similarly, resiliency 

could be addressed as part of a modernization factor.  

The Workgroup discussed resiliency‐related cost issues.  Projects with components that make them 

more resilient will have a higher cost.  The way these projects are scored should reflect the additional 

resiliency‐related benefits in addition to the higher cost.  One member suggested that factoring 

resiliency into the benefit‐cost evaluation in this manner may be the preferred way to address resiliency 

rather than with a separate resiliency factor.  

After much discussion, Austin Chamberlain noted there is little agreement on a definition and approach 

for resiliency, and there seems to be a sense among the Workgroup that this issue is bigger than what 

can be addressed in the prioritization process.  As a result, it was proposed that the Workgroup not 

pursue a resiliency factor for P6.0.  The Workgroup is willing to address this issue, but it needs more 

direction to do so.  The Workgroup asked that the SPOT Office obtain more information from NCDOT 

leadership on how resiliency is being addressed by the Department, as a starting point for future 

conversations.  The Workgroup also emphasized that the SPOT Office should communicate to those who 

are working on the 2050 Plan that resiliency is an essential topic that should be addressed in the plan. 

Number of Submittals 

The SPOT Office announced that the Draft 2020‐2029 STIP will be released next week.  If needed, the 

plan is to transition the LIP subcommittee into the Submittals subcommittee.  Jason asked the 

Workgroup to provide direction to the Submittals subcommittee on what issues exist or what items 

need to be discussed.  The Workgroup requested that the subcommittee examine the data after the 

Draft STIP is released and the estimated number of Carryover projects are known. 

CMAQ Process 

Heather Hildebrandt gave a presentation on the Congestion Mitigation and Air Quality Improvement 

program (CMAQ).  [See Workgroup presentation slides for more information.]  CMAQ projects are not 

subject to prioritization.  They undergo a separate application and selection process.  NCDOT is looking 

at changing the way they operate the CMAQ program in order to level the playing field among POs, fund 

good CMAQ projects that align with new federal performance measures requirements, and encourage 

selection of projects that are shovel‐ready.  Delays in CMAQ project delivery puts CMAQ funding at the 

risk of rescission of federal funds.  NCDOT will be putting together a workgroup to discuss these 

changes. 

Topic Schedule / Wrap Up / Next Steps 

The SPOT Office reviewed the anticipated topics for the upcoming Workgroup meetings.  

Next Meeting 

The next Workgroup meeting will take place on Monday, February 4, 2019 at RTP Headquarters. 

Page 17: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

1  

P6.0 Workgroup Meeting #5:  Summary Notes 

RTP Headquarters, 12 Davis Drive, Research Triangle Park 

Monday, February 4, 2019, 9:30 am – 3:00 pm 

 

Attendees 

Participant  Advisory  Other 

Anthony Prinz  Julie White  Aldea Coleman  Alpesh Patel 

Austin Chamberlain  Mike Stanley  Brooke Boyle  Amber Harris 

Beau Mills  Karyl Fuller  Dan Gurley  Brian Gackstetter 

Brian Alligood  Matt Day  Hanna Cockburn  Don Voelker 

Brian Burch  Neil Burke  Lisa Hollowell  James Bridges 

Brian Wert  Pat Ivey    Jim Reed 

Bryant Buck  Patrick Flanagan    LaToya Caldwell 

Chris Lukasina  Ronnie Keeter    Mark Johnston 

Dana Magliola  Sarah Lee    Neil Perry 

David Wasserman  Tristan Winkler    Rich Denbow (Admin) 

Jason Gray  Tyler Meyer    Stacy Cook (Facil.) 

Joey Hopkins  Vicki Eastland   Vanthaphone 

Phongsavath 

 

Welcome/Agenda Review 

David Wasserman opened the meeting at 9:30 and welcomed attendees.  He recognized Jason Gray 

from the NC Rural Center and Dana Magliola from the NCDOT Logistics and Freight Division, who are 

now official P6.0 Workgroup Participants.  He also welcomed Brian Alligood from the NC Association of 

County Commissioners (replacing Amber Harris).  Stacy Cook reviewed the agenda and desired meeting 

outcomes.  

Subcommittee Updates 

The SPOT Office provided an update on recent activities of the Highway, Bike/Ped, Transit, and Aviation 

Subcommittees.  [See Workgroup presentation slides for more information.]  Many of the items 

discussed in recent subcommittee meetings were also on the Workgroup meeting agenda for further 

discussion.   

Draft STIP, P6.0 Normalization, P6.0 Database including Submittals 

Draft STIP 

David discussed the Draft 2020‐2029 STIP that was recently released.  He summarized the number of 

projects and dollar amounts for projects evaluated through STI and projects programmed, funding 

distribution by Region and Division, adjustments to project schedules, and project cost increases.  He 

also summarized initial ideas for improving cost estimation.  [See Workgroup presentation slides for 

more information.]   

Page 18: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

2  

A member asked David if it was possible to overlay the pre‐STI distribution of funds with the distribution 

under STI to compare the two.  Chris Lukasina noted that CAMPO has looked at this in the past and 

found the distributions to be fairly consistent.  

The Workgroup discussed cost increases of funded projects and cost estimation issues.  Members would 

like to have a better idea of available funding for each upcoming prioritization round.  They also 

requested data on amounts available for programming in previous prioritization rounds.  

David discussed schedule adjustments in the STIP.  A total of 260 projects were affected due to changes 

in funding availability, resulting primarily from project cost increases.  Reasons for cost increases include 

projects being developed much quicker and cost estimates coming in more often.  Many projects lacked 

information when they were submitted in P3.0 and P4.0.  Their costs increased as more information 

became available. 

David discussed approaches underway to improve cost estimation, including developing better project 

scopes.  A member noted that most of the projects in CTPs across the state do not have well‐defined 

scopes.  David noted that for P6.0, a purpose and need statement will be required for each project 

submitted; the specific details for this requirement are still being worked on and will be provided once 

ready.  These purpose and need statements will assist in developing cost estimates and help streamline 

the project delivery process.  One member encouraged NCDOT to not consider dropping the bike/ped 

components of projects that have experienced cost increases.  

Normalization 

David led a discussion about Normalization.  [See Workgroup presentation slides for more information.]  

David reviewed how normalization was set up in P5.0 and how it was applied in the Draft STIP.  He 

reminded the Workgroup that Normalization is applied over the entire 10‐year STIP period.  He 

presented a recommendation from the STIP unit that the same percentages continue to be applied, with 

a change to the Division Needs non‐highway allocation being all 4% competition within each Division.  

The Workgroup discussed the recommendation.  There was a sense that more non‐highway projects 

could potentially be funded with this change, and that this approach is more straightforward and easier 

to explain to local decision makers and the public.  The Workgroup reached consensus to change the 

Division Needs 4% non‐highway allocation to all Division competition.   

P6.0 Database (Including Submittals) 

Sarah Lee led a discussion of the P6.0 Database and discussed Carryover projects.  [See Workgroup 

presentation slides for more information.]  There are approximately 250 Carryovers for P6.0, although 

siblings and projects with planning underway/complete are yet not finalized, so this number could 

change slightly.  Sarah presented the number of Carryovers by PO and by Division.  The SPOT Office will 

send a final list within about two weeks.  

Sarah also discussed P6.0 Project Submittals.  She presented the expected number of P6.0 submittals by 

PO and by Division if the P5.0 definition was used (with updated 2017 populations), and asked the 

Workgroup for thoughts on the number of submittals.  Some members believe the number of submittals 

should not be limited, as submitters are encouraged to segment some types of projects before 

Page 19: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

3  

submitting.  Some members like the ability to submit projects to test how they score with different 

scopes.  Other members were skeptical that more submittals are needed, believing submitters should 

do more work upfront to submit the best project they can.  Some suggested options were to place a cap 

on the number that can be submitted for screening‐type calculations and another cap on the number 

for full submittal, or to have an off‐cycle window of time to submit projects for screening calculations.  

David noted that an increase in the number of projects submitted will require additional resources for 

evaluation, and there are already constraints on these resources.   

After much discussion, the Workgroup reached consensus to continue using the P5.0 formula for the 

number of project submittals in P6.0.  The SPOT Office will confirm the final number of centerline miles 

used in the formula and provide the final list of submittal numbers at the next Workgroup meeting.  

NC Turnpike Authority Handbook 

Alpesh Patel and Don Voelker provided an overview of a current effort to create an NC Toll Project 

Development Handbook.  The handbook will include suggestions to facilitate enhanced toll project 

scoring in P6.0.  Development of the handbook is a partnership between NCDOT and several partners.  

The presenters requested input from the Workgroup to help shape handbook topics and next steps.  

[See Workgroup presentation slides for more information.]  One member requested that the NCDOT Rail 

team be involved in this effort.  

Rail Improvements 

Neil Perry presented changes to the STI legislation that will be requested by the Rail Division in to allow 

additional rail lines to become eligible for STI.  Currently, highway routes on the Strategic Highway 

Network (STRAHNET) are eligible by law for STI.  The Rail Division is requesting a change to allow all NC 

railroads designated as Strategic Rail Corridor Network (STRACNET) and military‐owned or controlled 

railroads to become eligible for STI.  

The Workgroup asked for information on the reasoning behind the proposed change.  Neil noted that 

the issue was identified during an assessment of threats to strategic ports.  If a Class I railroad sold a 

portion of its track to a shortline railroad, that section would currently no longer be eligible for funding 

under STI, causing the port to lose its classification as a strategic port in the future.  The Rail Division felt 

that the importance of STRAHNET routes in the Highway mode should be mirrored in the law by 

including STRACNET rail corridors as well.  A member noted that changes to the STI law are typically 

presented as a package and asked if this change would be part of a package or requested separately.  

Other members requested a map to show STI‐eligible rail corridors today compared to what would be 

eligible under this proposed change.  The Rail Division will bring this information back to the Workgroup 

at their next meeting.  

Highway – Mobility vs. Modernization 

Austin Chamberlain summarized Highway Subcommittee discussions about criteria and weights for 

Mobility vs. Modernization projects.  The Subcommittee developed an option for revised Modernization 

weights for Statewide, Regional, and Division categories and now needs Workgroup input.  Some 

members would like to see Freight included in all three categories.  One current challenge is funding 

modernization projects on SR routes only eligible in the Division Needs category.  After much discussion, 

Page 20: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

4  

the Workgroup agreed that it will be difficult to develop an approach that will address all projects and 

cases.  The Subcommittee will continue to address this issue.  

Bicycle/Pedestrian Improvements and Public Transportation Improvements 

Sarah provided an update of Bike/Ped Subcommittee activities.  Recent discussion topics include Specific 

Improvement Types, bundling projects, and Transportation Disadvantage.  [See Workgroup presentation 

slides for more information.]  Due to data quality issues, the Subcommittee had determined that it 

would be difficult to apply Transportation Disadvantage metrics across the state for P6.0 as currently 

proposed.   

Sarah also provided an update on Transit Subcommittee activities.  In addition to Transportation 

Disadvantage, the Subcommittee discussed bundling projects and Demand Response eligibility.  [See 

Workgroup presentation slides for more information.]  Because no new potential data or scoring metrics 

are currently available, and in light of NCDOT internal changes to the Public Transportation and 

Bicycle/Pedestrian Divisions, the current direction of the Subcommittee is to keep P6.0 Transit scoring 

the same as P5.0.  

Aviation Improvements 

Bobby Walston provided a report from the Aviation Work Group.  Bobby discussed issues the Aviation 

Work Group is addressing and expected actions as they move forward.  [See Workgroup presentation 

slides for more information.]   

Workgroup members support the Aviation Work Group’s consideration of the project prescreening 

process.  Improving this process is important not only for Aviation but for all modes.  Putting forth 

projects that meet Purpose and Need will strengthen the implementation process.  Workgroup 

members also asked for a list of Division of Aviation contacts. 

Topic Schedule / Wrap Up / Next Steps 

The SPOT Office reviewed the anticipated topics for the upcoming Workgroup meetings.  

Next Meeting 

The next Workgroup meeting will take place on Monday, March 4, 2019 at RTP Headquarters. 

Page 21: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

1  

P6.0 Workgroup Meeting #6:  Summary Notes 

RTP Headquarters, 12 Davis Drive, Research Triangle Park 

Monday, March 4, 2019, 9:30 am – 3:00 pm 

 

Attendees 

Participant  Advisory  Other 

Amber Harris  Joey Hopkins  Aldea Coleman  Brian Gackstetter 

Austin Chamberlain  Julie White Bill Marley (for George 

Hoops) James Bridges 

Beau Mills  Karyl Fuller  Brooke Boyle  Jim Reed 

Brian Burch  Matt Day  Dan Gurley  LaToya Caldwell 

Brian Wert  Neil Burke  Hanna Cockburn  Neil Perry 

Bryant Buck  Pat Ivey    Rich Denbow (Admin.) 

Chris Lukasina  Patrick Flanagan    Stacy Cook (Facil.) 

Chris Werner  Sarah Lee     

Dana Magliola  Tristan Winkler     

David Wasserman  Tyler Meyer     

Jason Gray  Vicki Eastland     

Jason Schronce       

Jimmy Eatmon (for 

Ronnie Keeter)      

 

Welcome/Agenda Review 

Jason Schronce opened the meeting and welcomed attendees.  He summarized the consensus items 

from the previous Workgroup meeting, then reviewed the agenda and desired meeting outcomes. 

Subcommittee Updates 

The SPOT Office provided an update on activities of the Highway, Bike/Ped, Transit, and Aviation 

subcommittees.  [See Workgroup presentation slides for more information.]  Many of the items being 

addressed by the subcommittees were on the Workgroup meeting agenda and to be discussed 

throughout the meeting.  Sarah provided an update on the potential Rail eligibility changes that were 

presented at the previous Workgroup meeting.  At this time, NCDOT is not pursuing a legislative change 

to allow NC railroads designated as Strategic Rail Corridor Network (STRACNET) and military‐owned or 

controlled railroads to become eligible for STI. 

P6.0 Carryovers and Submittals 

Carryovers 

Jason provided an update on projects that automatically carry over from P5.0 for evaluation in P6.0.  The 

SPOT Office is working on a definition of “active NEPA” with NCDOT Technical Services.  The Workgroup 

discussed concepts of how to define when a project becomes active in the NEPA process.  The unofficial 

definition generally used is when the project scoping meeting is held.  The Workgroup was in favor of 

Page 22: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

2  

using this in the prioritization process, and specific projects that have work started without meeting this 

definition will be evaluated on an individual basis.  The SPOT Office will finish compiling the full 

carryover project list and provide to all partners for use in submittal coordination meetings.  Partners 

may also flag projects that should potentially be Carryovers for SPOT to review. 

P6.0 Submittals 

Sarah Lee presented the final number of P6.0 Project Submittals by PO and Division, using final 2017 

population and 2019 centerline miles, as an informational item.  This information will also be provided 

to all partners. 

Bicycle/Pedestrian Improvements 

Sarah provided an overview of Bike/Ped subcommittee discussions.  To meet the deadline for SPOT 

On!ine improvements, Workgroup consensus is needed for any changes that will affect the system, such 

as Specific Improvement Types (SIT), new data, and any new scoring process. 

The Workgroup discussed Transportation Disadvantage.  As reported in the previous Workgroup 

meeting, the subcommittee had determined that it would be difficult to incorporate Transportation 

Disadvantage within the structure of STI and current scoring criteria.  SPOT and the subcommittee will 

continue working on what information is needed for addressing this topic in P7.0 scoring. 

The topic of bundling Bike/Ped projects across geographies and varying project types was discussed at 

length in subcommittee meetings.  Sarah summarized the bundling changes that were discussed and put 

forward to the Workgroup for consensus.  [See Workgroup presentation slides for a list of bundling 

changes discussed.]  The Workgroup reached consensus on the Bike/Ped project bundling changes. 

Sarah summarized the subcommittee’s recommended SIT changes.  [See Workgroup presentation slides 

for a list of recommended SIT changes.]  The Workgroup reached consensus on the SIT changes.  Sarah 

noted that the subcommittee was still discussing ways to incorporate National/State/Regional bike 

routes into another criteria. 

Sarah also summarized the subcommittee’s discussions about Safety.  The subcommittee recommended 

removing the Speed Limit measure and replacing it with ATLAS Safety Risk Analysis data, and creating 

new Safety Benefit groupings that are not based on SIT.  The Workgroup discussed the changes and the 

data used in ATLAS.  The Workgroup reached consensus to remove the Speed Limit measure and 

replace with ATLAS Safety Risk Analysis, and to create new Safety Benefit groupings not based on SIT.  

The subcommittee will continue to discuss ATLAS Safety Risk inputs / final output as well as the Safety 

Benefit table specifics/groupings. 

Sarah summarized the subcommittee’s discussion about combining Access and Connectivity criteria and 

automating data where possible, with the proposal to use ATLAS points of interest (POI) to buffer for the 

Access portion and the ATLAS Pedestrian Bicycle Infrastructure Network (PBIN) as a reference layer in 

SPOT On!ine to assist in Connection Point entry.  The proposal also included the transition of manual 

Connection Point options from infrastructure‐based to options of “Existing”, “Committed”, or “In a 

Plan”.  [See Workgroup presentation slides for more information.]  The subcommittee discussed various 

options for scoring combined Access and Connectivity criteria.  The Workgroup reached consensus on 

the structure of using the ATLAS POI, ATLAS PBIN as a reference layer, and the structure of new 

Connection Point options.  The subcommittee will continue to work on how to score the combined 

Page 23: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

3  

criteria, a possible POI cap, POI final categories, and connection point values.  It was also noted that the 

subcommittee needs to discuss the scaling of lookup tables.  

Highway Topics 

Mobility vs. Modernization Weights 

Jason summarized Highway subcommittee discussions regarding Mobility and Modernization scoring 

and default weights.  [See Workgroup presentation slides for more information.]  The subcommittee had 

discussed the criteria that are potentially important at the Statewide, Regional, and Division categories 

but did not bring a recommendation on weights.  The SPOT Office asked for input from the Workgroup 

on criteria and weights across all categories.   

During discussion, a Workgroup member expressed interest in developing a method to consider 

mobility‐type issues within Modernization scoring, such as the functionality of a road and how it is used.  

Some members recommended dropping Benefit/Cost because, as currently defined, it addresses travel 

time savings, and there may be better ways to account for benefits.  Members also felt that Congestion 

can be a differentiator but should not have a high weighting.  The Workgroup discussed Pavement 

Condition and felt that there might be a better measure that looks at pavement condition rating versus 

the need for total roadway reconstruction.  The SPOT Office will discuss internally with pavement 

experts about other potential measures that address this concern.  There was a suggestion to combine 

Lane Width and Shoulder Width into one criteria.  There was also a suggestion to give Freight more 

weight, and to consider whether Economic Competitiveness should be added for considering future 

interstates.   

After discussion, the Workgroup decided more time is needed to look into this topic.  The Highway 

subcommittee will continue to discuss it before bringing a recommendation back to the Workgroup.  In 

the meantime, the SPOT Office will perform an analysis of Mobility and Modernization project scores 

from P5.0 using the suggested weights from the Workgroup discussions.  

Multiple Intersection SIT 

The SPOT Office discussed a suggested technical correction to how multiple intersection improvements 

along a corridor were scored in P5.0.  With this new approach, a new specific improvement type (SIT 25) 

would be created.  In SPOT On!ine, the submitter would select the entire corridor and list out the 

intersections being improved.  A new safety benefit factor is being developed, and travel time savings 

would be scored using the CALC method.  The Workgroup stated their support for this approach.  

Freight Routes 

The subcommittee has discussed developing a Freight Network Improvement Factor that would 

consider items important to freight movement.  [See Workgroup presentation slides for more 

information.]  The subcommittee requested feedback on whether a second factor (in addition to the 

Future Interstate Completion Factor) in the Freight criteria is a proper addition for P6.0 scoring.   

During discussion, Workgroup members noted that using distance in the denominator does not have the 

same importance to freight network improvements as it does to improvements that help to complete 

the Future Interstate network.  There may be a better way to account for improvements on the freight 

network.  Some members were interested in knowing more about the data available for each of the 4 

items (from the presentation slides) important to freight movement.  The SPOT Office noted that 

because of the IT deadline for incorporating this into SPOT On!ine, the determination must be made 

soon on using this approach in P6.0 or addressing it in P7.0 scoring.  The Workgroup felt that good 

Page 24: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

4  

progress had been made on this issue, so it was beneficial not to shelve it for P6.0 if possible.  If it is not 

used, a distance component in the factor could be incorporated as a manual adjustment rather than 

through SPOT On!ine.  In the meantime, the subcommittee will look at the freight data that is currently 

available.  

P6.0 Updates – Items in Motion 

Mass Email Updates to Submitters 

The SPOT Office will send several emails to submitters in the near term, including a status of 

Committed/Carryover/Holding Tank projects from P5.0, a final Number of Submittals table, and Highway 

Cross Sections to be loaded into P6.0 for scoring (in addition to items in the next few discussions).  

Letters of Support 

Letters of support will be required by April 30, 2019 for all local funds on P5.0 non‐highway projects in 

the draft 2020‐2029 STIP.  POs can provide copies of previous letters if they are applicable.  Guidance 

will request that if any local governments are facing challenges meeting the required Bicycle/Pedestrian 

match, they discuss the issues with NCDOT before requesting that the project be removed from the 

STIP. 

Cost Estimation Tool Changes 

Jason discussed changes that are being made to the Highway cost estimation tool in SPOT On!ine, 

including updates to typical cross‐sections and per‐mile cost estimates.  [See Workgroup presentation 

slides for more information.]  He cautioned that the cost estimates from the new tool may differ 

significantly from estimates with the current tool because the changes involve looking at costs much 

more closely.  

Bike/Ped Cost Estimation Tool Updates 

The SPOT Office reported that the Bike/Ped Cost Estimation Tool is being updated.  It is anticipated to be 

easier to use, more transparent, easier to maintain, and produce improved estimates.  It will be ready 

for use by June 15, 2019 for P6.0 project submittals.  

P6.0 Submittal Training 

Sarah discussed a planned P6.0 Submittal training schedule. [See Workgroup presentation slides for 

more information.]  Training will begin in late May/early June and go through August.  

P6.0 Schedule 

Sarah reviewed the P6.0 schedule and pointed out key dates.  [See Workgroup presentation slides for 

more information.] 

Purpose and Need (Identified Need Statements) 

The SPOT Office reported that NCDOT is establishing guidance and templates on what Identified Need 

statements should look like as a requirement for each P6.0 project submittal.  NCDOT Corridor 

Development Engineers will have a key role in developing statements, where applicable.  The goal is to 

capture key project concepts and the problem being addressed by the project.  For example, why is the 

project needed?  Is the project a long term solution or a temporary fix?  This will improve project 

Page 25: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

5  

knowledge transfer between NCDOT business units and guide NEPA document creation.  A Workgroup 

member asked what multi‐modal information is needed for developing guidance and templates.  The 

SPOT Office will sit down with the modes to discuss this future requirement.  

Review Topic List and Schedule 

The SPOT Office reviewed the items to be addressed by the P6.0 Workgroup that were identified and 

prioritized in the first Workgroup meeting.  The Workgroup requested examples of how POs and 

Divisions are approaching public involvement for projects, including how the coordination takes place 

between POs and Divisions.  The SPOT Office will put together some information for the next meeting in 

response.  

Next Meeting 

The next Workgroup meeting will take place on Monday, April 1, 2019 at RTP Headquarters. 

 

Page 26: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

1  

P6.0 Workgroup Meeting #7:  Summary Notes 

RTP Headquarters, 12 Davis Drive, Research Triangle Park 

Monday, April 1, 2019, 9:30 am – 3:00 pm 

 

Attendees 

Participant  Advisory  Other 

Anthony Prinz  Joey Hopkins  Aldea Coleman  Brian Murphy 

Austin Chamberlain  Julie White  Bobby Walston Daniela Waltersdorfer 

(Admin.) 

Beau Mills  Karyl Fuller  Brooke Boyle  James Bridges 

Brian Alligood  Matt Day  Dan Gurley  Jim Reed 

Brian Burch  Neil Burke  George Hoops  LaToya Caldwell 

Brian Wert  Pat Ivey  Hanna Cockburn  Neil Perry 

Bryant Buck  Patrick Flanagan  Stephanie Ayers  Rich Denbow (Facil.) 

Chris Lukasina  Ray McIntyre    Ron McCollum 

Dana Magliola  Sarah Lee    Tolga Cankurtaran 

David Wasserman  Tristan Winkler     

Jason Gray  Tyler Meyer     

Jason Schronce  Vicki Eastland     

 

Welcome/Agenda Review 

Jason Schronce opened the meeting and welcomed attendees.  He summarized the consensus items 

from the previous Workgroup meeting and reviewed the agenda and desired meeting outcomes. 

Subcommittee Updates 

The SPOT Office provided an update on recent activities of the Highway, Bike/Ped, and Aviation 

subcommittees.  [See Workgroup presentation slides for more information.]  Jason discussed the 

potential need to hold an additional Highway subcommittee meeting in April to address the Priority 

Freight Network and Pavement Condition Rating adjustments.  A Workgroup member expressed interest 

in further discussion about port criteria and a discussion on Multimodal measures. 

Safety Benefit Factors Update 

Brian Murphy from the NCDOT Safety Planning Group provided an update on safety‐related activities in 

support of P6.0 scoring.  Changes in the STI Crash Data Feed are being made after consideration of how 

scaling is performed in the prioritization process.  Previously, roadway section crash data was grouped 

before providing it to the SPOT Office.  Now, data provided to SPOT Online will be the raw severity, 

density, and critical crash rate values.  Scaling will take place on the actual values, leading to more 

variability in the scoring process.   

Page 27: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

2  

Brian discussed recommended additions to safety benefit factors for widening existing urban roadways.  

The suggested changes for P6.0 are based on evaluation of specific Crash Modification Factors and 

NCDOT crash rate comparisons.      

Brian also discussed research to be conducted later in 2019 that will aid in developing safety benefit 

factors for new location and urban widening projects.  The P6.0 recommended safety benefit factors for 

urban widening are subject to change based on findings from this research.  Jason added that the 

research findings will be applied to developing potential changes for P7.0 scoring. 

Highway Modernization Default Weights 

Jason summarized Highway subcommittee discussions about Modernization project default weights at 

the Statewide, Regional, and Division categories.  The SPOT Office conducted an analysis of 

Modernization project scores from P5.0 using potential changes to weights suggested by the 

subcommittee.  Jason summarized the results of the analysis.  The Workgroup discussed the results and 

the suggested weights.  Some members of the Workgroup wanted to assign a weight to Congestion at 

the Regional Impact category as a way to reflect usage levels of facilities.  Other members felt that 

applying a weight to Congestion could hurt some Modernization projects on facilities that are not 

typically congested, such as two‐lane state routes.  Members also expressed an interest in assigning 

weight to Freight at the Division Needs category.  A suggestion was made to include freight counts from 

freight hubs in the scaling process.  The Workgroup decided to continue to discuss Modernization 

default weights with the Highway subcommittee.  

Scaling Lookup Tables 

Sarah Lee provided background information on the practice of scaling lookup tables, and provided 

examples of how scaling can affect lookup table values in different ways.  The Bike/Ped subcommittee 

proposed changing the overall approach to remove the 0‐100 point values and the stated separation 

between values and replace with a straight ranking system (i.e.: 1, 2, 3, 4…) that would still be scaled.  

The proposed method would not change the results of scaling, as both the current and proposed 

methods both rank the projects before scaling.  The two remaining lookup tables this change would 

affect are Rail Multimodal and Public Transportation Facility Efficiency.  The Workgroup questioned if 

the Efficiency table for Passenger Facilities in Public Transportation could be changed to be scaled based 

on actual trips, instead of a lookup table.  Sarah will examine P5.0 notes and project values, and 

determine if this could work.  (Efficiency table for Administrative/Maintenance facilities would need to 

remain a lookup table due to its “ideal size” point assignment method.) 

Since this is just a messaging change in how lookup tables are scaled, the Workgroup agreed to the 

proposed approach for scaling lookup tables.  Sarah noted that she would make sure the Rail and Public 

Transportation teams were aware of the change. 

Bicycle/Pedestrian Improvements 

Sarah summarized Bike/Ped subcommittee discussions and the consensus points previously reached by 

the Workgroup.  [See Workgroup presentation slides for more information.]  The subcommittee has 

continued to discuss several specific issues related to these consensus points that still need to be 

finalized.  

Page 28: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

3  

Sarah summarized proposed categories and approaches for ATLAS Points of Interest (POI) and a 

proposed Accessibility/Connectivity score.  The subcommittee and the Workgroup need to decide on 

POI category definitions, regardless of ATLAS availability.  Some categories could be added manually by 

the project submitter.  The subcommittee also discussed connection point options and point values, 

with a tiered point approach that gives more points to projects that connect to existing bike/ped 

facilities over those that are only committed or in a plan.  More points would also be assigned for 

projects that improve or connect to a national, state, or regional bike route.   

The subcommittee also discussed (and will continue to discuss) adjusting the input factor percentages 

toward the final output layer of values for the ATLAS Safety Risk Analysis data.  

Sarah introduced the proposed Safety Benefit concept, which would be grouped by either safety ratings 

or by actual facilities based on assumed benefit to the safety of users.  Grouping by facilities would lead 

to further discussion on how to define them for the lookup tables.  The Workgroup asked the 

subcommittee to continue to work on grouping options.   

Lastly, the Workgroup discussed proposed changes to bike/ped criteria weights, which remove weight 

from the old Connectivity and add it to Safety and the new Accessibility/Connectivity.  The Workgroup 

reached consensus on using the proposed bike/ped criteria weights for P6.0.  

Public Transportation Improvements and Criteria/Weights 

Sarah reviewed changes discussed by the Transit subcommittee regarding bundling projects and the 

previously discussed recommendation to maintain the existing Public Transportation criteria and 

weights for P6.0.  [See Workgroup presentation slides for more information.]  The Workgroup reached 

consensus on the changes for bundling projects.  The Workgroup also agreed to use the existing Public 

Transportation criteria/weights for P6.0. 

One caveat to note from during the meeting is the possibility of the Efficiency lookup table for Passenger 

facilities changing to use the actual trip values.  This will be a discussion in the next Workgroup meeting, 

and if changed, would be reflected by a technical correction to this topic. 

Aviation Improvements 

Bobby Walston provided an update from the Aviation Work Group.  As previously presented, he 

reviewed issues the group is addressing and recommendations to address each issue.  He also presented 

the Aviation Work Group’s recommended scoring for P6.0, including a change in the Benefit/Cost 

criteria and a new Constructability Index criteria.  [See Workgroup presentation slides for more 

information.]  The Work Group will continue to address remaining issues and bring a full scoring 

recommendation to the next P6.0 Workgroup meeting for discussion and consensus.  

Rail Criteria/Weights 

Sarah reviewed scoring for Rail projects.  The Workgroup agreed to use the existing Rail criteria and 

weights for P6.0.   

One member requested the SPOT Office to review the effect of the Multimodal measure within the Rail 

criteria, in case it could be removed to help not use lookup tables where possible.  These results will be 

available at the next Workgroup meeting. 

Page 29: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

4  

Ferry Criteria/Weights 

Sarah reviewed scoring for Ferry projects.  The Workgroup agreed to use the existing Ferry criteria and 

weights for P6.0.   

Highway Reliability Project Update 

Jason provided an update on the Highway Reliability effort.  There is not enough time remaining to 

validate the reliability data for use in P6.0, so the consultant will continue working with the data for 

anticipated use in P7.0.  The SPOT Office suggested the idea of creating a “pre‐workgroup” 

subcommittee to examine/refine the data and recommend it for use in P7.0.  The Workgroup expressed 

support for this approach, and several volunteers signed up to serve on the subcommittee.  A suggestion 

was made to include weekend travel data to account for Reliability in regions that experience issues 

outside of the typical weekday peak periods.  

Highway Mobility Default Weights 

Jason presented proposed Highway Mobility default weights for use in P6.0.  [See Workgroup 

presentation slides for more information.]  Jason opened the floor for Workgroup members to review 

the weights and voice any concerns.  The Workgroup reached consensus on using the proposed 

Highway Mobility default weights for P6.0.  

NCDOT Complete Streets 2.0 

As a follow‐up to earlier conversations during the meeting on Modernization projects, Aldea Coleman, 

NCDOT Deputy Chief Secretary’s Office, presented on the status of NCDOT Complete Streets 2.0.  [See 

Workgroup presentation slides for more information.]  Workgroup members shared ideas on who Aldea 

could contact to help NCDOT understand the needs of different municipalities throughout the state.  

Members also suggested that Aldea’s team would be the ideal group to create recommendations on 

how to improve the Highway Multimodal criteria for P7.0.   

Aldea said that key recommendations and findings from the Complete Streets 2.0 effort should be 

available by the end of April. 

Next Meeting 

The next Workgroup meeting will take place on Monday, April 29, 2019 at RTP Headquarters.  Jason 

noted that this will likely be the last Workgroup meeting, as the status of most topics is wrapping up and 

should conclude then.  Therefore, the scheduled June meeting could be canceled. 

 

Page 30: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

1  

P6.0 Workgroup Meeting #8:  Summary Notes  

RTP Headquarters, 12 Davis Drive, Research Triangle Park 

Monday, April 29th, 2019, 9:30 am – 3:00 pm 

 

Attendees 

Participant  Advisory  Other 

Anthony Prinz  Julie White  Aldea Coleman  Brooke Boyle 

Austin Chamberlain  Justin Green  Bill Marley Daniela Waltersdorfer 

(Admin.) 

Beau Mills  Karyl Fuller  Bobby Walston  Jim Reed 

Brian Burch  Matt Day  Stephanie Ayers  LaToya Caldwell 

Brian Alligood  Pat Ivey    Neil Perry 

Brian Wert  Patrick Flanagan    Rich Denbow (Facil.) 

Bryant Buck  Ray McIntyre      

Chris Lukasina  Ronnie Keeter     

Dana Magliola  Sarah Lee     

David Wasserman  Tristan Winkler     

Jason Gray  Tyler Meyer     

Jason Schronce  Vicki Eastland     

Joel Strickland (for Neil 

Burke)      

Joey Hopkins       

Welcome/Agenda Review 

Jason Schronce opened the meeting by welcoming the attendees.  He summarized the consensus items from the previous Workgroup meeting and reviewed the agenda and desired meeting outcomes. 

Subcommittee Updates 

The SPOT Office provided an update on the Highway, Bike/Ped, and Aviation subcommittees.  [See 

Workgroup presentation slides for more information.]   

Sarah Lee also provided an update on Rail scoring.  The SPOT Office tested P5.0 projects to determine 

the effect of removing the Multimodal measure, as requested in the previous meeting.  This change had 

a significant effect on the resulting order of projects.  The SPOT Office also discussed this with the Rail 

Division, and both units agreed on the need to keep the measure in P6.0 scoring.  

Sarah also gave an update on scaling lookup tables, as a follow‐up to the consensus item from the 

previous meeting.  The new lookup values for Rail Multimodal and Public Transportation Facilities were 

shown to the Workgroup.  Regarding a previous question about the removal of the Passenger Facilities 

lookup table (and using actual trip values), Sarah showed how this table could not be removed due to 

the way all Facility scores are scaled together, including Administrative and Maintenance facilities. 

Page 31: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

2  

Aviation Improvements and Criteria/Weights 

Bobby Walston summarized the issues and recommendations the Aviation Work Group developed for 

P6.0.  [See Workgroup presentation slides for more information.]  Workgroup members suggested 

changing the step of requiring an approval letter from the Division of Aviation for each project to simply 

an eligibility determination letter, to avoid setting a precedent that a project needs to be pre‐approved 

before submittal – the intent of this step is that the Airport Project Managers are involved in order to 

help make each project the best it can be.  

During the discussion around Constructability Index, it was also noted that while each airport has 

runway designations to note which runway is primary, secondary, or tertiary, the data in this criteria will 

always be sourced from the primary runway.  This will take place regardless of which runway a project 

may be on, since the intent of this criteria is to assess the airport and its overall safety.  Bobby closed by 

summarizing the recommendations, which include revising the criteria weights of the FAA Airport 

Capital Improvement Plan Rating and Constructability Index (in the criteria slot formally used by the 

Non‐State Contribution Index) in the Statewide Mobility and Regional Impact categories.  The 

Workgroup reached consensus on the proposed Aviation scoring changes for P6.0. 

Bobby also noted that the final Risk Assessment (used in the Constructability Index) will be complete by 

the end of this fiscal year, then can be shared with the Workgroup.  A draft will be complete by the end 

of the week, and SPOT will obtain a copy to share with the Workgroup. 

Highway Modernization Default Weights 

Jason summarized Highway subcommittee discussions about Modernization weights and reiterated that 

the SPOT office is looking for consensus on changes to the default weights.  He presented a summary of 

project scoring results using P5.0 projects and different weights for Congestion and Shoulder Width at 

the Regional Impact level, as well as Freight and Pavement Condition at the Division Needs level.  The 

Workgroup discussed the results and proposed changes, with most of the discussion centered around 

varying opinions on the Congestion weight.  The Workgroup discussed whether the Congestion criteria is 

an appropriate way to account for the usage of a facility and discussed various potential changes that 

could be made in order to reach agreement.  It was noted that without consensus, scoring would revert 

back to a single set of default weights for all Highway projects.  The Workgroup generally agreed this 

was not ideal, and the SPOT Office conducted additional analysis based on further discussion.  The 

Workgroup reached consensus on Highway Modernization weights for P6.0 as follows:  

  

Page 32: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

3  

Highway Criteria Weights 

Jason summarized the Highway criteria and weights for both Mobility projects and Modernization 

projects that have been discussed by the P6.0 Workgroup to date (including the earlier discussion and 

consensus on Modernization weights).  [See Workgroup presentation slides for more information.]  The 

Workgroup agreed to the Highway criteria and weights for P6.0 as shown. 

Bicycle/Pedestrian Improvements and Criteria Weights 

Sarah presented a final update on bicycle/pedestrian scoring improvements for P6.0.  [See Workgroup 

presentation slides for more information.]  Workgroup members had questions about some of the 

ranges used in the Crash/Safety Risk factors, and it was established that the ranges were preset by 

ATLAS and based on research – SPOT will obtain a breakdown of the factor scores and provide to the 

Workgroup.  Members also had questions about ATLAS points of interest (POI) categories, which were 

mostly clarified through discussion.  Sarah noted how the documentation for the eligible points of 

interest will need to be very clearly defined this time, so there will be follow‐up with the Workgroup to 

assist with the definitions and ensure all realistic types within each POI category are included.  This 

includes what types of facilities are included in government buildings and tourist destinations, where 

central business districts fit, and how a single employment center point is defined.  It was noted that this 

approach is not perfect, but it is a vast improvement over the prior completely manual entry approach, 

and it will continue to be improved in future cycles.  A discussion also took place on the reasoning 

behind not capping points of interest or averaging connection points, and it was established that the 

intent of the new Accessibility/Connectivity criteria is to allow more flexibility in the purpose of each 

project, whether it be to connect bicycle/pedestrian networks or to connect destinations.  The 

Workgroup reached consensus on all proposed changes to Bicycle/Pedestrian scoring for P6.0.  

Sarah provided an update on development of the Bike/Ped cost estimation tool for P6.0 projects.  The 

tool is expected to be completed and available for use for P6.0 project submittals by June 2019. 

Merging of Bicycle/Pedestrian and Public Transportation Divisions 

Julie White provided an informational update on the merger of the NCDOT Bicycle/Pedestrian Division 

and the Public Transportation Division.  A key component of this merger is to create an organizational 

structure that is able to stay up‐to‐date with the rapid change of pace in this area.  

On‐Going Prioritization Committee  

Jason proposed an approach to set up an on‐going Prioritization Committee to address research and 

develop ideas to improve scoring before P7.0 begins.  [See Workgroup presentation slides for more 

information and a list of potential discussion topics.]  Ideally, the committee would meet every 4 to 6 

weeks, for 3 hours at a time, beginning in August 2019 and ending in July 2020 before P7.0 Workgroup.  

The goal is not to have a completely new group, but to treat the group as a continuing subcommittee of 

the P6.0 Workgroup, and to have the Workgroup members attend the proposed meetings and include 

subject matter experts related to the discussion topics.  The group will meet in a less formal way than 

Workgroup meetings, including call‐in options.  It was also suggested that the meetings operate on an 

“informational agenda”, as opposed to a “consensus agenda”, in order to reflect that the intent is about 

research, issues, and options to use in informing the future P7.0 Workgroup.  Meetings would also be 

open to additional/new attendees (as recommended by current Workgroup members), in order to 

introduce new interested persons to the Workgroup process. 

Page 33: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

4  

The Workgroup expressed strong support for this approach, with the clarification that it should still be 

referred to as the Prioritization Workgroup.  

P6.0 Workgroup Plus/Delta 

The Workgroup participated in a Plus/Delta exercise to identify positives and improvements from the 

P6.0 Workgroup process.  [See Workgroup presentation slides for the list of Plus and Delta items.] 

Wrap Up 

Jason closed the meeting by expressing the gratitude of the SPOT Office to the Workgroup for their time 

and efforts.  

Page 34: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

1  

P6.0 Workgroup Meeting #9:  Summary Notes 

RTP Headquarters, 12 Davis Drive, Research Triangle Park 

Monday, August 5th, 2019, 9:30 am – 3:00 pm 

 

Attendees 

Participant  Advisory  Other 

Anthony Prinz  Jason Schronce  Aldea Coleman  James Bridges 

Austin Chamberlain  Justin Green  Brooke Boyle  LaToya Caldwell 

Brian Wert  Karyl Fuller  George Hoops  Mark Johnston 

Bryant Buck  Matt Day    Neil Perry 

Chris Lukasina  Neil Burke    Rich Denbow (Admin.) 

Chris Werner  Pat Ivey    Tim Brock 

Dana Magliola  Randi Gates    Todd Meyer 

David Wasserman  Ronnie Keeter     

Hanna Cockburn  

(for Julie White) Sarah Lee     

Jason Gray  Tyler Meyer     

 

Welcome/Agenda Review 

Jason Schronce opened the meeting by welcoming the attendees.  He summarized P6.0 activities since 

the last Workgroup meeting on April 29, 2019 and reviewed the agenda and desired meeting outcomes. 

 Highway Capacities Update 

The SPOT Office opened a discussion about how to best incorporate the most current methods for 

calculating highway capacity.  Capacities are generated using the North Carolina Level of Service (NCLOS) 

tool, which is based on methodologies in TRB’s Highway Capacity Manual (HCM) and parameters from 

North Carolina specific data.  NCLOS was developed by ITRE and NCDOT.  Prioritization Rounds 2.0 

through 5.0 used NCLOS that was based on the 2010 version of HCM.  In October 2016, TRB released a 

revised HCM.  NCLOS was subsequently updated by NCDOT‐DIT to reflect HCM 2016.  The Department 

has been working on incorporating the update into P6.0 but still needs to validate the changes before 

the tool can be used during project submittals.  The validation process may not be finished in time for 

P6.0 scoring. 

The Workgroup discussed three options to address this for P6.0: 

1. Complete the validation of HCM 2016 capacities so it is available for use in P6.0 before opening 

the submittal window. This option may potentially delay the P6.0 submittal window for 

validation time.  

2. Open the P6.0 submittal window as planned and use HCM 2010 capacities for P6.0 scoring, 

deferring the use of HCM 2016 capacities to P7.0.  

Page 35: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

2  

3. Open the P6.0 submittal window as planned and submit projects using the HCM 2010 capacities, 

then update them during data review with HCM 2016 capacities after validation is completed.  

The Workgroup generally agreed that it is preferable to use HCM 2016 capacities for P6.0.  HCM 2016 

equations reflect multimodal issues and new technologies that were not included in HCM 2010 and are 

currently being used for project design work.  The key issue with the first option is how long the 

validation process will take.  It will take time to get a contractor approved and underway to begin the 

validation.  The worst case is that HCM 2016 won’t be available until P7.0. 

The Workgroup agreed that NCDOT should move forward with validation as quickly as possible, with the 

goal of having it available in P6.0.  Then use option 3 if validation is not completed in time to get into 

SPOT On!ine, with a disclaimer during submittal saying the 2010 capacities are being used initially but 

will be updated during data review to reflect HCM 2016 capacities once validation is complete.  It may 

also be possible to derive 2016 capacities in the meantime.  NCDOT will discuss this internally to 

determine what resources are available to complete validation as quickly as possible and will keep the 

Workgroup updated.   

 P6.0 Schedule 

The Workgroup discussed potential changes in the P6.0 schedule due to the STIP schedule extending to 

three years.  This one‐time STIP schedule change will result in the Draft 2023‐2032 STIP being released in 

January 2022.  The STIP extension is primarily due to future funding uncertainty with the FAST Act 

expiring in September 2020, and to allow NCDOT to get a handle on cost increases for projects and 

maintain an adequate cash balance.  The P6.0 submittal window will still open in early October 2019 as 

planned.  The SPOT Office requested input from the Workgroup on how to use the extra time in the P6.0 

schedule resulting from extending the STIP schedule – specifically the extra time between project 

submittal and the release of quantitative scores.  

Prior to discussing how to utilize the extra time, some participants noted that moving the STIP to three 

years will impact MPO planning schedules, especially for MPOs that are required to conduct air quality 

conformity on their MTPs and TIPs at least every four years.  Some participants expressed a preference 

for moving to four years to better align the STIP with the prioritization process and MPO schedules.  

Others prefer the three year schedule because they have already begun the P6.0 submittal process, and 

because funds could possibly become available that would make the additional fourth year unnecessary.  

At this time, at the guidance of the STIP Unit, the Department is planning to move ahead with extending 

the schedule to three years as already discussed.  

The participants expressed an interest in more time to work on submittals and to coordinate with 

partner organizations.  The Workgroup discussed and proposed changes to the schedule, including 

additional time for the STIP unit to program Regional Impact and Division Needs projects, and extending 

the Regional Impact local input point assignment window to 3 months to match the Division Needs 

window.  It was also proposed to push back the release of the Draft STIP to February 2022 in order to 

incorporate some of these extensions, so the SPOT Office noted that they will discuss the proposed 

changes with the STIP unit during the break and report back to the Workgroup.  

After clearing the Draft STIP release date with the STIP unit, the SPOT Office confirmed the changes to 

the P6.0 schedule with the Workgroup.  [See Workgroup presentation slides for more information.]  

Page 36: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

3  

SPOT will send an updated schedule to the Workgroup for quick review by the next day, in order to 

finalize it and share with all partners this week. 

 Other Fund Contributions 

Jason presented on the topic of leveraging new non‐state or non‐federal dollars during 3 different 

windows:  project submittal, Regional Impact local input points, and Division Needs local input points.  

This discussion topic was presented as an informational item on the Benefit‐Cost criteria, as well as to 

emphasize the multiple opportunities for contributing other funds.  [See Workgroup presentation slides 

for more information.]  This has previously been applied only to Highway project scoring, but now will 

also apply to Aviation and Rail.  Workgroup members asked NCDOT for a summary of how many projects 

have received local fund contributions in previous prioritization rounds.  The SPOT Office will also 

discuss if there will be a requirement for Aviation and Rail (like Highway already requires) for a letter of 

contribution to be provided at the time that the other funds are submitted for the project. 

 Bicycle/Pedestrian POI Definitions 

The SPOT Office requested Workgroup assistance with defining the types of eligible facilities of the 

previously‐decided Point of Interest (POI) categories.  Some categories also did not have adequate data 

for use in automation – Sarah noted that Historic Landmarks would now need to be a manual category 

(within Tourist Destinations), and the Workgroup agreed to remove Adult Education Centers and 

Fire/EMS facilities from the POI categories.  During discussion on eligible facilities for manual categories, 

the Workgroup agreed on the points listed below.  

Museums, Theaters, and Auditoriums (within Tourist Destinations):  centered around 

performing arts destinations, but the Workgroup felt this should include any general tourist 

attractor/destination that is typically included in a tourism/visitor’s guide.  Must be open to the 

public.  Department of Commerce, visitors bureaus, or local tourism divisions/groups may be 

good data sources.  Would be helpful to provide examples (botanical gardens was suggested as 

one). 

Historic Landmarks (within Tourist Destinations):  not to include historic markers only.  Must be 

an actual standing destination, not already included in Historic Districts POIs, and must be listed 

on an official historic registry (national, state, or local).  Would be helpful to provide examples. 

Shelters:  intended to be a place for the homeless or victims of domestic abuse, not emergency 

shelters.  North Carolina DHHS, 211, or the Red Cross may be good data sources.  Does not have 

to be licensed by the State. 

Employment Centers:  businesses with at least 25 employees.  May include a single building of 

multiple businesses that total at least 25 employees.  Information should be verifiable.  InfoUSA 

may be a good data source. 

Documentation:  Submitters will be required to provide a spreadsheet of the manual POIs 

within their project buffer, noting the following:  POI category, facility name, and data source.  

Hanna Cockburn noted that the Bicycle/Pedestrian Division will now have adequate staff to assist in 

reviewing project data, including the POI submissions.  Sarah also noted that an additional destination 

outside the pre‐defined POI categories can always be provided to the SPOT Office for consideration 

Page 37: P6.0 Workgroup Meeting #1: Summary Notes · 3 David presented options for the Committed Project window: 1. increase to 8 years, 2. increase to 7 years, or 3. keep as 5 years (P5.0

 

4  

during project submittal, if there exists a unique facility that is sensible as a destination but does not fit 

the official categories. 

It was also questioned if a destination that fits more than one category can count multiple times.  The 

Workgroup agreed that this would be acceptable, since the destination is serving multiple purposes. 

The SPOT Office will use this input to develop submittal guidance regarding what qualifies as a POI.  

Sarah also reviewed submitter responsibilities in ensuring the accuracy of the results for each project.  

[See Workgroup presentation slides for more information.] 

 On‐Going Prioritization Committee  

The Workgroup discussed holding continuing prioritization discussions to address research and develop 

scoring improvement ideas before P7.0 WG begins in the fall of 2021 (based on the new schedule).  [See 

Workgroup presentation slides for more information and a list of potential discussion topics.]  The 

participants decided to meet every other month, beginning on the third Monday in September, from 

9am to 12pm.  Attendance will be allowed by phone or in person at NCDOT.  The SPOT Office will 

provide a list of meeting topics to be discussed at each meeting ahead of time.  

 Identified Needs Form 

The Spot Office discussed the Identified Needs form for P6.0 that has now been incorporated into SPOT 

On!ine and provided several need category examples.  Austin Chamberlain pointed out that if 

submitters use safety as a primary need, a further set of needs and constraints will be required.  The 

SPOT Office will provide more guidance on this.  

Wrap Up / Next Steps 

Jason closed the meeting by thanking the participants for their input.  The SPOT Office will update the 

Workgroup with the P6.0 schedule changes as discussed today and send a draft version for review.  They 

will also set up a group invitation for the Ongoing Prioritization Committee meetings, which will begin on 

Monday, September 16th.