Tips Tricks with Version Six (Client) Don Louser PMP, PMA Consultants LLC

description

 

Transcript of P6 tips tricks-client

Page 1: P6 tips tricks-client

Tips Tricks with Version Six (Client)Don Louser PMP, PMA Consultants LLC

Page 2: P6 tips tricks-client

2

Give Us Your Card

• There are more items in this presentation than we will have time to demonstrate

• Give us your business card and we will send you the entire presentation complete with notes

• Or, contact me @ [email protected]

Page 3: P6 tips tricks-client

3

• What’s New in Client v. 6.0 (Slides 1-20)• Use of Indicators (Slide 21)• Global Changes – De-status the Schedule (Slides 22-26)• Global Changes – Change WBS from Filters (Slide 27)• Export and Importing Projects (Slides 28-39)• Project details that are often forgotten (Slides 40-42)• Renumbering Activities (Slides 43-45)• Building your Schedule – Making a List (Slides 46-47)• Building your Schedule - Linking Shortcuts (Slide 48)• The Schedule Report (Slides 49-52)• Lag Calendars (Slides 53-54)

What we have for you today...

Page 4: P6 tips tricks-client

4

• Fragnets (Slides 55-58)• Coding and WBS Shortcuts (Slides 59-63)• Finding and Filtering Activities (Slides 64-65)• Roles and Resource Loading (Slides 66)• Schedule Crashing Basics (Slides 67-68)• Advanced Layouts For Communication (Slides 69-71)• Advanced Gantt Chart Formatting (Slides 72-76)• Exporting and Importing Layouts/Reports (Slide 77)• Add Bar-charts & Graphics to Reports (Slides 78-83)• Working with Baselines (Slides 84-91)

What we have for you today (cont.)...

Page 5: P6 tips tricks-client

5

What’s New – Reflection Projects

• Power with Simplicity !!!

• A Reflection is a Copy of a Project that enhances Your Ability to “What If” or Update Your Project

• Same Name – What If – Internal Link to Source – Baseline –Timesheet Data – Activity Owner

• “Activity Owner” make changes via .xer or Web

• Review & Change or Merge As Is (Check Boxes)

• Merge Will Not remove Activities, Resource Assignments, WBS Elements, Work Products & Docs, Expenses, Issues or Risks if deleted from Reflection

DEMO

Page 6: P6 tips tricks-client

6

What’s New - Create Reflection Project

Page 7: P6 tips tricks-client

7

Making Changes to Reflection Projects

• Use to test Scenarios or Update Project

• Send w/Project Specific Layout to Others to Update

• Import/Export just like any other Project file

• Activity Owner – designate Owner w/Required Web License & Privileges to Update/Change

• Admin or Project Superuser gets last shot to Review/Correct before merging back into Source Project

• Merge Will Not remove Activities, Resource Assignments, WBS Elements, Work Products & Docs, Expenses, Issues or Risks if deleted from Reflection

Page 8: P6 tips tricks-client

8

Merging Reflection into Source Project

• Close all Projects

• Go to Projects Table – Select Reflection Project

• Right Click – Merge Reflection into Source Project

Page 9: P6 tips tricks-client

9

Merging Reflection into Source Project

Page 10: P6 tips tricks-client

10

Merging Reflection into Source Project

Page 11: P6 tips tricks-client

11

Merging Reflection into Source Project

Page 12: P6 tips tricks-client

12

What’s New – Future Bucket Planning

• Redistribute Even Distribution of Budgeted Units

• Editable Security Privilege

• Duration Type Must be Fixed Duration & Units, or Fixed Duration & Units/Time

• Use Resource Spreadsheet or Resource Assignment

• In Future Bucket Period type or change Values as Needed

Page 13: P6 tips tricks-client

13

What’s New – Future Bucket Planning

4010R10R4A8A8AFuture Bucket

4088888Even Spread

TOTALDay 5Day 4Day 3Day 2Day 1

•Assuming Daily TS – P5 spread evenly

•Actual levels of work may vary

•Example shows 20 A units in 3 days

•Remaining needs to be adjusted

•Two remaining buckets reflect adjustment

•Activity Adjusted must have Fixed Duration & Units, orFixedDuration & Units/Time

•Use Resource Spreadsheet to adjust future bucket period

Page 14: P6 tips tricks-client

14

Edit Future Bucket Security

Page 15: P6 tips tricks-client

15

What’s New – Group & Sort Dialog

• New Checkbox for Show Group Totals, Shrink Vertical Bands

SHOW PIX & EXPLAIN

Page 16: P6 tips tricks-client

16

What’s New - Search in Pop-Up Dialog and Type Ahead in Drop Down

SHOW PIX & EXPLAIN

Page 17: P6 tips tricks-client

17

What’s New - Copy Baselines• Checkbox in Copy Project Options

• Copy Baselines Dialog

# Copies Controlled by New Setting in Admin Preferences

Page 18: P6 tips tricks-client

18

Admin preferences Setting for Copying Baselines

Page 19: P6 tips tricks-client

19

What’s New - Role Limits

• Similar to Limits for Resources

• Effective Date and Max Units/Time

Page 20: P6 tips tricks-client

20

What’s new – Project Specific Layouts (Yeah!)

• Layout with Filter when Project Exported

• Reduces Need for Global Layouts

• Only Global and Layout Filters will Restrict Use

• Expanded & Collapsed Bars & Row Height Setting when switching between layouts and Windows (Yeah!)

Page 21: P6 tips tricks-client

21

Use of Indicators

Page 22: P6 tips tricks-client

22

Re-create a Baseline, Copy an Existing Schedule that has Been Progressed

Project Detail Calculations Tab =

Any Actual Units that Exist Must be set to 0• See Actual Units Slide

Run 2 Global Changes to Reset Activities to Not Started

• See De-Progress GCs

Make any Needed Changes and Reschedule

Useful Global Changes –De-Status the Schedule

Skip

Page 23: P6 tips tricks-client

23

Actual Work Units

Useful Global Changes –De-Status the Schedule (cont.)

Go Back

Page 24: P6 tips tricks-client

24

De-Statusthe GC’s

Useful Global Changes –De-Status the Schedule (cont.)

Go Back

Page 25: P6 tips tricks-client

25

Sometimes...

An Activity may have a Unit without a Resource Assigned...

Errors?

Page 26: P6 tips tricks-client

26

Useful Global Changes –De-Status the Schedule (cont.)

Delete Manually, or Use the Fill-Down Feature

Set Cols for All Units

Page 27: P6 tips tricks-client

27

Useful Global Changes –Change WBS Based on Filters

Page 28: P6 tips tricks-client

28

Primavera PM/MM (.xer)

MS Project

Project Planner (P3)

Spreadsheet (.xls)

Primavera Contractor 4.1 (.xer)

Exporting and Importing Projects

Page 29: P6 tips tricks-client

29

1. Select Items for Export

2. Separate Sheet for Each Item

Exporting and Importing Projects – Spreadsheet (.XLS)

Page 30: P6 tips tricks-client

30

3. Select a Project (it must be open)

Exporting and Importing Projects – Spreadsheet (.XLS) (cont.)

Page 31: P6 tips tricks-client

31

4. Establish Templates for each Item

Exporting and Importing Projects – Spreadsheet (.XLS) (cont.)

Page 32: P6 tips tricks-client

32

5. Certain items are mandatory, and you can filter & sort

Exporting and Importing Projects – Spreadsheet (.XLS) (cont.)

Page 33: P6 tips tricks-client

33

6. Select any or all templates

Exporting and Importing Projects – Spreadsheet (.XLS) (cont.)

Page 34: P6 tips tricks-client

34

7. Select the file path and name

Exporting and Importing Projects – Spreadsheet (.XLS) (cont.)

Page 35: P6 tips tricks-client

35

8. Confirm before you finish

Exporting and Importing Projects – Spreadsheet (.XLS) (cont.)

Page 36: P6 tips tricks-client

36

One Worksheet Per Subject

Exporting and Importing Projects (cont.)

Page 37: P6 tips tricks-client

37

Caution! – Don’t Edit this Sheet

Exporting and Importing Projects (cont.)

Page 38: P6 tips tricks-client

38

Importing is a Snap!

Importing Projects

Page 39: P6 tips tricks-client

39

Importing Projects (cont.)

Page 40: P6 tips tricks-client

40

Project details that are often forgotten

Page 41: P6 tips tricks-client

41

Project details that are often forgotten

Page 42: P6 tips tricks-client

42

Project details that are often forgotten

Page 43: P6 tips tricks-client

43

Many GCs like Intelligent IDs

CSI Code – Bldg – Floor

Establish UDF (Activity) or Activity Code

Put in Column in Layout

Type Codes in Column

Use Global Change

Codes Become Activity IDs

Renumbering Activities

Page 44: P6 tips tricks-client

44

Leave Blank

Renumbering Activities (cont.)

Page 45: P6 tips tricks-client

45

For those a bit more familiar with (GC’s)

Create Activity Code

Add Activity Code column in Layout

Fill Column

Create GC’s that add suffix for Bldg & Floor

Renumbering Activities (cont.)

Page 46: P6 tips tricks-client

46

Building your schedule – Making a list

Page 47: P6 tips tricks-client

47

Building your schedule – Making a list

Page 48: P6 tips tricks-client

48

<Ctrl-Click> the order to link the activities, then <right-click> your mouse and choose “Link Activities.”

They are now linked in the order you clicked on them.

Building your schedule – Linking shortcuts

Page 49: P6 tips tricks-client

49

When you schedule your project, don’t forget to choose “Log to file” and click on the ellipsis to specify the location of the “schedule.txt” file.

Always view the log to spot errors.

Building your schedule – The Schedule Report

Page 50: P6 tips tricks-client

50

Building your schedule – The Schedule Report

Page 51: P6 tips tricks-client

51

Building your schedule – The Schedule Report

Page 52: P6 tips tricks-client

52

Building your schedule – The Schedule Report

Page 53: P6 tips tricks-client

53

Lag Calendars and Schedule Result - Version 5.0

+ =

Page 54: P6 tips tricks-client

54

Lag Calendars Reschedule

+ =

?

This has been changed in v 6.0 to default to the predecessor

Page 55: P6 tips tricks-client

55

• Time Saving – why recreate the wheel?– Building a Single Schedule– Modifying Many Schedules

• Create New or Modify Existing– New = As You Would New Project– Modify = Delete from Existing

• WBS is the Key to Integration

Fragnets

Page 56: P6 tips tricks-client

56

Modify a template with a Fragnet

Fragnets (cont.) 2 Projects

Move to 2 WBS elements

To Here

From Here

Page 57: P6 tips tricks-client

57

Objective – Add 22 new Activities in Template to 2 WBS Nodes

• Copy the Template as Fragnet, Delete All Activities Except those to Remain in Planning & Design WBS Nodes

• Add the 22 New Activities & All Links to Fragnet

• Open Template & Fragnet

• Delete All Activities in Planning & Design TemplateWBS Nodes

• Select & Copy All Fragnet Activities

Fragnets (cont.)

Page 58: P6 tips tricks-client

58

• Paste into one of the empty Template Nodes (Preserves all Links)

• Control-Click all Activities to be moved to other Node

• <Ctrl-X> (Cut)

• <Ctrl-V> (Paste) into other Node

• Re-establish any Links from 2 Nodes to others

• Use Template to create new Schedules

Fragnets (cont.)

Page 59: P6 tips tricks-client

59

Here is one person’s Layout

Coding and WBS Shortcuts

Page 60: P6 tips tricks-client

60

Coding and WBS Shortcuts (cont.)

Page 61: P6 tips tricks-client

61

Coding and WBS Shortcuts (cont.)

Page 62: P6 tips tricks-client

62

Here. the work is organized by WBS1 and Level

Coding and WBS Shortcuts (cont.)

Page 63: P6 tips tricks-client

63

Here, the work is organized only by Level

Coding and WBS Shortcuts (cont.)

Page 64: P6 tips tricks-client

64

Unleash the power of Find with <Ctrl-F>

Finding and Filtering Activities

Page 65: P6 tips tricks-client

65

Finding and Filtering Activities (cont.)

Page 66: P6 tips tricks-client

66

• Roles are placeholders for Resources that are not yet assigned. • Roles allow teams to be assigned quickly to project activities, once the resource team is identified.• Only resources for roles that are unfilled are shown in the assign resources for roles dialogue box.• <Shift-Click> and <Ctrl-Click> can be used to select the activities being assigned resources by roles.• A project team could be assigned to all of the project’s activities at once.

Roles and Resource Loading

Page 67: P6 tips tricks-client

67

28 DaysTotal Duration

Schedule Crashing Basics

Page 68: P6 tips tricks-client

68

28 Days Total Duration

Assume We Need to Reduce Duration by 5 Days

Schedule Crashing Basics (cont.)

Page 69: P6 tips tricks-client

69

• User Defined Fields

• Bring in Related Data from Other Sources

• Tabular + Graphic Presentation

Advanced Layouts to Enhance Communication

Page 70: P6 tips tricks-client

70

Schedule DataUser Defined Random Data

Advanced Layouts to Enhance Communication (cont.)

Page 71: P6 tips tricks-client

71

Advanced Layouts to Enhance Communication (cont.)

Page 72: P6 tips tricks-client

72

Advanced Gantt Chart Formatting

Page 73: P6 tips tricks-client

73

Advanced Gantt Chart Formatting

Page 74: P6 tips tricks-client

74

Advanced Gantt Chart Formatting

Page 75: P6 tips tricks-client

75

Advanced Gantt Chart Formatting

Page 76: P6 tips tricks-client

76

Advanced Gantt Chart Formatting

Page 77: P6 tips tricks-client

77

.plf filename extension

Exporting and Importing Layouts and Reports

Page 78: P6 tips tricks-client

78

Adding Barchart Graphics to Reports

1. Create a layout that you want to print in your report

2. From the tool menu or print preview, choose Publish

3. Choose the directory for the report

4. Open a notebook topic and insert the graphic

5. Include that notebook topic in your tabular report

6. Run the report

BC1

Page 79: P6 tips tricks-client

Slide 78

BC1 Please doublecheck first bullet. Thanks, BCBill Camarda, 10/17/2006

Page 80: P6 tips tricks-client

79

Publish to HTML

From the Tool menu or Print Preview, choose Publish

Adding Barchart Graphics to Reports (cont.)

Page 81: P6 tips tricks-client

80

Adding Graphics to Reports

Page 82: P6 tips tricks-client

81

Click on the Picture Icon, and browse for a graphic file to insert into the Notebook topic

Adding Graphics to Reports (cont.)

Page 83: P6 tips tricks-client

82

Adding Graphics to Reports (cont.)

Page 84: P6 tips tricks-client

83

Page 85: P6 tips tricks-client

84

Baselines are an established method of tracking progress and measuring results

When you first begin using Baselines, you may see some strange results that are difficult to diagnose

Baselines can refer to either the Current Project or another Project

How can you know which, without opening?

Working with Baselines

Page 86: P6 tips tricks-client

85

Baseline CodeProject

DateResp

Sort

Why Alpha Prefix??

Add aBaselineColumn

Working with Baselines (cont.)

Sort by BLName

Page 87: P6 tips tricks-client

86

Are we a year ahead?

Is the Current Schedule Ahead or Behind the Original Plan?

Working with Baselines (cont.)

Page 88: P6 tips tricks-client

87

Summarized Dates

Something is Wrong?

Working with Baselines (cont.)

MAGIC!

Page 89: P6 tips tricks-client

88

Perform a Global Change on a Baseline

Working with Baselines (cont.)

Page 90: P6 tips tricks-client

89

1

2 PL Strt = Start (Milestone): If = SM, Then, PS = Start

3

Here are the details...

Working with Baselines (cont.)

Page 91: P6 tips tricks-client

90

Here are the changes

Working with Baselines (cont.)

Page 92: P6 tips tricks-client

91

Questions?