P6 Tips-Tricks Client 1

30
Tips Tricks with Version Six (Client) Don Louser PMP, PMA Consultants LLC

Transcript of P6 Tips-Tricks Client 1

Page 1: P6 Tips-Tricks Client 1

Tips Tricks with Version Six (Client)Don Louser PMP, PMA Consultants LLC

Page 2: P6 Tips-Tricks Client 1

2

Give Us Your Card

• There are more items in this presentation than we will have time to demonstrate

• Give us your business card and we will send you the entire presentation complete with notes

• Or, contact me @ [email protected]

Page 3: P6 Tips-Tricks Client 1

3

• What’s New in Client v. 6.0 (Slides 1-20)• Use of Indicators (Slide 21)• Global Changes – De-status the Schedule (Slides 22-26)• Global Changes – Change WBS from Filters (Slide 27)• Export and Importing Projects (Slides 28-39)• Project details that are often forgotten (Slides 40-42)• Renumbering Activities (Slides 43-45)• Building your Schedule – Making a List (Slides 46-47)• Building your Schedule - Linking Shortcuts (Slide 48)• The Schedule Report (Slides 49-52)• Lag Calendars (Slides 53-54)

What we have for you today...

Page 4: P6 Tips-Tricks Client 1

4

• Fragnets (Slides 55-58)• Coding and WBS Shortcuts (Slides 59-63)• Finding and Filtering Activities (Slides 64-65)• Roles and Resource Loading (Slides 66)• Schedule Crashing Basics (Slides 67-68)• Advanced Layouts For Communication (Slides 69-71)• Advanced Gantt Chart Formatting (Slides 72-76)• Exporting and Importing Layouts/Reports (Slide 77)• Add Bar-charts & Graphics to Reports (Slides 78-83)• Working with Baselines (Slides 84-91)

What we have for you today (cont.)...

Page 5: P6 Tips-Tricks Client 1

5

What’s New – Reflection Projects

• Power with Simplicity !!!

• A Reflection is a Copy of a Project that enhances Your Ability to “What If” or Update Your Project

• Same Name – What If – Internal Link to Source – Baseline –Timesheet Data – Activity Owner

• “Activity Owner” make changes via .xer or Web

• Review & Change or Merge As Is (Check Boxes)

• Merge Will Not remove Activities, Resource Assignments, WBS Elements, Work Products & Docs, Expenses, Issues or Risks if deleted from Reflection

DEMO

Page 6: P6 Tips-Tricks Client 1

6

What’s New - Create Reflection Project

Page 7: P6 Tips-Tricks Client 1

7

Making Changes to Reflection Projects

• Use to test Scenarios or Update Project

• Send w/Project Specific Layout to Others to Update

• Import/Export just like any other Project file

• Activity Owner – designate Owner w/Required Web License & Privileges to Update/Change

• Admin or Project Superuser gets last shot to Review/Correct before merging back into Source Project

• Merge Will Not remove Activities, Resource Assignments, WBS Elements, Work Products & Docs, Expenses, Issues or Risks if deleted from Reflection

Page 8: P6 Tips-Tricks Client 1

8

Merging Reflection into Source Project

• Close all Projects

• Go to Projects Table – Select Reflection Project

• Right Click – Merge Reflection into Source Project

Page 9: P6 Tips-Tricks Client 1

9

Merging Reflection into Source Project

Page 10: P6 Tips-Tricks Client 1

10

Merging Reflection into Source Project

Page 11: P6 Tips-Tricks Client 1

11

Merging Reflection into Source Project

Page 12: P6 Tips-Tricks Client 1

12

What’s New – Future Bucket Planning

• Redistribute Even Distribution of Budgeted Units

• Editable Security Privilege

• Duration Type Must be Fixed Duration & Units, or Fixed Duration & Units/Time

• Use Resource Spreadsheet or Resource Assignment

• In Future Bucket Period type or change Values as Needed

Page 13: P6 Tips-Tricks Client 1

13

What’s New – Future Bucket Planning

4010R10R4A8A8AFuture Bucket

4088888Even Spread

TOTALDay 5Day 4Day 3Day 2Day 1

•Assuming Daily TS – P5 spread evenly

•Actual levels of work may vary

•Example shows 20 A units in 3 days

•Remaining needs to be adjusted

•Two remaining buckets reflect adjustment

•Activity Adjusted must have Fixed Duration & Units, orFixedDuration & Units/Time

•Use Resource Spreadsheet to adjust future bucket period

Page 14: P6 Tips-Tricks Client 1

14

Edit Future Bucket Security

Page 15: P6 Tips-Tricks Client 1

15

What’s New – Group & Sort Dialog

• New Checkbox for Show Group Totals, Shrink Vertical Bands

SHOW PIX & EXPLAIN

Page 16: P6 Tips-Tricks Client 1

16

What’s New - Search in Pop-Up Dialog and Type Ahead in Drop Down

SHOW PIX & EXPLAIN

Page 17: P6 Tips-Tricks Client 1

17

What’s New - Copy Baselines• Checkbox in Copy Project Options

• Copy Baselines Dialog

# Copies Controlled by New Setting in Admin Preferences

Page 18: P6 Tips-Tricks Client 1

18

Admin preferences Setting for Copying Baselines

Page 19: P6 Tips-Tricks Client 1

19

What’s New - Role Limits

• Similar to Limits for Resources

• Effective Date and Max Units/Time

Page 20: P6 Tips-Tricks Client 1

20

What’s new – Project Specific Layouts (Yeah!)

• Layout with Filter when Project Exported

• Reduces Need for Global Layouts

• Only Global and Layout Filters will Restrict Use

• Expanded & Collapsed Bars & Row Height Setting when switching between layouts and Windows (Yeah!)

Page 21: P6 Tips-Tricks Client 1

21

Use of Indicators

Page 22: P6 Tips-Tricks Client 1

22

Re-create a Baseline, Copy an Existing Schedule that has Been Progressed

Project Detail Calculations Tab =

Any Actual Units that Exist Must be set to 0• See Actual Units Slide

Run 2 Global Changes to Reset Activities to Not Started

• See De-Progress GCs

Make any Needed Changes and Reschedule

Useful Global Changes –De-Status the Schedule

Skip

Page 23: P6 Tips-Tricks Client 1

23

Actual Work Units

Useful Global Changes –De-Status the Schedule (cont.)

Go Back

Page 24: P6 Tips-Tricks Client 1

24

De-Statusthe GC’s

Useful Global Changes –De-Status the Schedule (cont.)

Go Back

Page 25: P6 Tips-Tricks Client 1

25

Sometimes...

An Activity may have a Unit without a Resource Assigned...

Errors?

Page 26: P6 Tips-Tricks Client 1

26

Useful Global Changes –De-Status the Schedule (cont.)

Delete Manually, or Use the Fill-Down Feature

Set Cols for All Units

Page 27: P6 Tips-Tricks Client 1

27

Useful Global Changes –Change WBS Based on Filters

Page 28: P6 Tips-Tricks Client 1

28

Primavera PM/MM (.xer)

MS Project

Project Planner (P3)

Spreadsheet (.xls)

Primavera Contractor 4.1 (.xer)

Exporting and Importing Projects

Page 29: P6 Tips-Tricks Client 1

29

1. Select Items for Export

2. Separate Sheet for Each Item

Exporting and Importing Projects – Spreadsheet (.XLS)

Page 30: P6 Tips-Tricks Client 1

30

3. Select a Project (it must be open)

Exporting and Importing Projects – Spreadsheet (.XLS) (cont.)