Offshore Wind Update Massachusetts Wind Working Group Nils Bolgen May 28, 2014.
-
Upload
blake-buddy-butler -
Category
Documents
-
view
215 -
download
0
Transcript of Offshore Wind Update Massachusetts Wind Working Group Nils Bolgen May 28, 2014.
Offshore Wind Update
Massachusetts Wind Working Group
Nils Bolgen
May 28, 2014
Offshore Wind Overview
• New Technology/Higher Cost
• Huge Resource, Close to Load
• Better coincidence with peak system loads
• Massachusetts-made Energy
• New Industry and Jobs
• Climate Change
• Coal and nuclear plant retirements
2
3
Massachusetts Activities
• Policy & Legislation
• Stakeholders engagement
• Research & Data
• Supply Chain Analysis
• Offshore Wind Transmission Project
• Investment in OSW Infrastructure
Atlantic Offshore Wind Planning
4
Massachusetts Offshore Wind Hub
5
Massachusetts Wind Energy Area• Largest Wind Energy Area on East Coast
~743,000 acres (3,000 square kilometers)
Water depths range from 35 – 65 meters
Average wind speeds 9.2 – 9.4 m/s
• NREL projects 5 GW of generating capacity potential
• To be separated into four lease areas
• BOEM auction expected November/December 2014
6
Rhode Island /Massachusetts WEA
• BOEM held the first U.S. auction for offshore wind lease on July 31, 2013 for the RI/MA Wind Energy Area
• Deepwater Wind won the 164,750-acre lease area RI/MA for $3.8 million
• Development potential of 1.2 GW
7
8
Offshore Wind Research
• Methods– Aerial Surveys – Underwater Passive Acoustic Data
• MassCEC & BOEM– NE Aquarium– College of Staten Island– UMass Dartmouth SMAST
• Survey Periods– Year 1 -- 10/11 - 10/12– Year 2 -- 12/12 - 12/13– Year 3 -- 3/14 - 3/15
• Results– Year 1 reports: Dec. 2013– Year 2 reports coming
• Benthic Surveys (2012, 2013)
Contractor – Global Wind Network (GLWN)
Near Term Survey capabilities of regional manufacturers and service providers
Focused on machining, forge, casting, electronics, composites, coatings
Connect local manufacturers and service providers with documented developer needs
Long Term Foundations – fabrication, machining, coatings
Towers – fabrication, forging, machining, coatings
Blades – composites, processing, machining
Support Bases & Hubs –fabrication, machining, coatings
Cable & Substation – all major manufacturing sectors
OSW Supply Chain Analysis
9
10
Offshore Wind Transmission Project
Purpose:• Identify and characterize interconnection points
• Describe transmission infrastructure components and system requirements for WEA development scenarios
• Identify routes that minimize transmission cable distance with least environmental impact and fewest conflicts (through EEA update of MA Ocean Management Plan)
• Support coordinated state permitting for the transmission routes in state waters
• Support coordinated access and permitting process for areas in federal waters
Potential Interconnction Points
Existing High Voltage Transmission Lines Existing 345 kV Substations
11
System Components for HVDC Transmission Line
|-- 1-20 miles -- | ----- 30-90 miles ---- | -- 2-20 miles -- |
Not to uniform scale
12
New Bedford Marine Commerce Terminal
OSW Investment in Infrastructure
13
Terminal Before Major Site Work Began: Photo Taken 7/9/2013 Apex
New Bedford Marine Commerce Terminal
14
View of Terminal Looking South: Photo Taken 4/25/2013 Apex
New Bedford Marine Commerce Terminal
15
Future New Bedford Marine Commerce Terminal
Grenaa-Anholt, Denmark
16