Oakland County Drain Commission, Water and Wastewater Master Plan - Volume 4 - Alternatives Analysis...
-
Upload
peter-cavanaugh -
Category
Documents
-
view
12.667 -
download
3
description
Transcript of Oakland County Drain Commission, Water and Wastewater Master Plan - Volume 4 - Alternatives Analysis...
Oakland County
Water and Wastewater Master Plan
Volume 4 – Alternatives Analysis
Prepared for:
Oakland County Drain Commissioner One Public Works Drive Waterford, MI 48328
Prepared by:
URS Corporation Farmington Hills, MI 248-553-9449 Contact: Jan Hauser, P.E.
In Association With:
TetraTech MPS
Plante & Moran, PLLC Southfield, MI
Raftelis Financial Consultants, Inc.
Environmental Consulting & Technology, Inc.
URS Project No. 13647263
Final Report – September 2007
Table of Contents
Volume 4 – Alternatives Analysis Report i
Table of Contents
Table of Contents ......................................................................................................................................... i
List of Tables ............................................................................................................................................... v
List of Figures........................................................................................................................................... viii
Appendices ................................................................................................................................................. ix
Acronyms and Abbreviations..................................................................................................................... x
1.0 Summary ......................................................................................................................................... 1
1.1 Introduction ........................................................................................................................... 1
1.2 Scope.................................................................................................................................... 3
1.3 Summary of Alternatives ....................................................................................................... 3
1.3.1 Summary of Water Alternatives................................................................................ 4
1.3.2 Summary of Wastewater Alternatives ...................................................................... 5
1.4 Basis of Alternative Costs ..................................................................................................... 7
2.0 Water Alternatives Development................................................................................................... 9
2.1 Alternative 1 – No Change .................................................................................................... 9
2.2 Alternative 2 – Develop/Improve Community Well System ................................................. 11
2.3 Alternative 2a – Develop/Improve Community Well System with Softening ........................ 12
2.4 Alternative 3 – New Service from DWSD ............................................................................ 13
2.4.1 Eligible CVTs.......................................................................................................... 13
2.4.2 Projected Cost of Service....................................................................................... 20
2.5 Alternative 4 – Genesee County to Supply Raw Water....................................................... 22
Table of Contents
Volume 4 – Alternatives Analysis Report ii
2.5.1 Eligible CVTs.......................................................................................................... 23
2.5.2 Projected Cost of Service....................................................................................... 27
2.6 Alternative 5 – Genesee County to Supply Finished Water................................................. 36
2.6.1 Eligible CVTs.......................................................................................................... 39
2.6.2 Projected Cost of Service....................................................................................... 39
2.7 Alternative 6 – Storage Analysis (DWSD Existing Customers) ........................................... 46
2.8 Warren – St. Clair Shores Water Supply Alternative ........................................................... 48
3.0 Discussion of Genesee County Water Supply Alternatives - Alternatives 4 and 5................. 51
3.1 Comparison of Genesee County Water Supply Alternatives ............................................... 51
3.2 Advantages and Disadvantages of the Genesee County Water Supply Alternatives.......... 52
4.0 Wastewater Alternatives Development....................................................................................... 53
4.1 Alternative 1 – No Change .................................................................................................. 53
4.1.1 Clinton-Oakland SDS (COSDS) ............................................................................. 53
4.1.2 Huron-Rouge SDS (HRSDS) ................................................................................. 57
4.1.3 Evergreen-Farmington SDS (EFSDS).................................................................... 57
4.1.4 George W. Kuhn SDS (GWKSDS)......................................................................... 59
4.1.5 Commerce-White Lake SDS (CWLSDS)................................................................ 61
4.1.6 Walled Lake/Novi SDS (WLNSDS) ........................................................................ 63
4.1.7 Pontiac WWTP....................................................................................................... 64
4.1.8 Milford Village WWTP ............................................................................................ 66
4.1.9 South Lyon WWTP................................................................................................. 67
4.1.10 Wixom WWTP........................................................................................................ 68
4.1.11 Lyon Township WWTP........................................................................................... 69
4.1.12 Holly Village WWTP............................................................................................... 71
Table of Contents
Volume 4 – Alternatives Analysis Report iii
4.1.13 Highland Township WWTP .................................................................................... 72
4.2 Alternative 2 – Construction of Relief Sewers ..................................................................... 73
4.2.1 Eligible CVTs.......................................................................................................... 73
4.2.2 Description ............................................................................................................. 73
4.3 Alternative 3 – Diversion of 8 MGD of Flow to the Pontiac WWTP ..................................... 74
4.3.1 Eligible CVTs.......................................................................................................... 74
4.3.2 Description ............................................................................................................. 74
4.4 Alternative 4 – Diversion of 20 MGD of Flow to the Pontiac WWTP.................................... 77
4.4.1 Eligible CVTs.......................................................................................................... 77
4.4.2 Description ............................................................................................................. 77
4.5 Alternative 5 - Diversion of 22 MGD of Flow to the Pontiac WWTP .................................... 79
4.5.1 Eligible CVTs.......................................................................................................... 79
4.5.2 Description ............................................................................................................. 79
4.6 Alternative 6 – Construction of a New WWTP on the Clinton River .................................... 81
4.6.1 Eligible CVTs.......................................................................................................... 81
4.6.2 Description ............................................................................................................. 81
4.7 Alternative 7 – Conveyance to COSDS............................................................................... 83
4.7.1 Eligible CVTs.......................................................................................................... 83
4.7.2 Description ............................................................................................................. 84
4.7.3 Oakland Township ................................................................................................. 84
4.7.4 Springfield .............................................................................................................. 84
4.7.5 White Lake ............................................................................................................. 84
4.8 Alternative 8 – Service from Genesee County Kearsley Creek Interceptor (KCI) Main Arm
Only..................................................................................................................................... 85
4.9 Alternative 9 – Service from Genesee County KCI Main Arm and West Arm...................... 86
Table of Contents
Volume 4 – Alternatives Analysis Report iv
4.10 Alternative 10 – Treatment by Another City/Village/Township (CVT) .................................. 87
4.10.1 Eligible CVTs.......................................................................................................... 87
4.10.2 Brandon Served by the Village of Ortonville........................................................... 88
4.10.3 Lyon Township Served by South Lyon WWTP....................................................... 88
4.10.4 Milford Township Served by Wixom WWTP........................................................... 89
4.10.5 Rose Township Served by Holly Village WWTP .................................................... 89
4.11 Alternative 11 – New/Expansion-of Local Treatment .......................................................... 90
4.11.1 Eligible CVTs.......................................................................................................... 90
4.11.2 Groveland Township .............................................................................................. 90
4.11.3 Holly Township....................................................................................................... 91
4.11.4 Oakland Township ................................................................................................. 91
4.11.5 Ortonville Township................................................................................................ 92
4.11.6 Lyon Township WWTP........................................................................................... 92
4.11.7 White Lake Township............................................................................................. 93
4.12 Alternative 12 – Divert Flow From GWKSDS to an Expanded Warren WWTP ................... 93
5.0 Project Delivery Methods............................................................................................................. 96
5.1 General ............................................................................................................................... 96
5.2 Design-Bid-Build ................................................................................................................. 97
5.3 Design-Build........................................................................................................................ 97
5.4 Design/Build/Operate - Design/Build/Operate/Transfer....................................................... 98
List of Tables
Volume 4 – Alternatives Analysis Report v
List of Tables
Table 1-1 General Basis for Alternative Costs.......................................................................................7
Table 2-1 Communities that may Benefit from Alternative 2 - Develop/Improve Community Well
System .....................................................................................................................................12
Table 2-2 Potential New DWSD Water Customers from Oakland County by Year 2050 ..........................15
Table 2-3 Decade One (2000-2010) DWSD Water System Improvements in Oakland County................16
Table 2-4 Decade Two (2010-2020) DWSD Water System Improvements in Oakland County................17
Table 2-5 Decade Three (2020-2030) DWSD Water System Improvements in Oakland County .............18
Table 2-6 Decade Four (2030-2040) DWSD Water System Improvements in Oakland County ...............19
Table 2-7 Decade Five (2040-2050) DWSD Water System Improvements in Oakland County................19
Table 2-8 Estimated Total Project Cost (2005) for Potential New DWSD Water Customers.....................22
Table 2-9 Potential Oakland County CVTs to Receive Genesee County Raw Water Under
Alternative 4 ..............................................................................................................................24
Table 2-10 Reservoir Costs (2005) to Store the Raw Water Supply from Genesee County .....................28
Table 2-11 Treatment & Transmission Main Cost (2005) for Raw Water Supply.....................................29
Table 2-12 Finished Water Storage Costs (2005) for the Raw Water Alternative ....................................30
Table 2-13 Distribution of Total Project Costs (2005) by Community for Facilities Constructed
within Oakland County ...............................................................................................................31
Table 2-14 Distribution of Total Project Costs (2005) by Community for Raw Water Alternative...............32
Table 2-15 Estimated O & M Costs for Facilities in Oakland County (2005 dollars).................................34
Table 2-16 Estimated O & M Costs (2005) for Facilities Constructed by Genesee County &
Attributed to Oakland County CVTs .............................................................................................35
Table 2-17 Estimated Total O & M Costs for Obtaining Genesee County Raw Water .............................35
List of Tables
Volume 4 – Alternatives Analysis Report vi
Table 2-18 Potential Oakland County CVTs to Receive Genesee Finished Water ..................................39
Table 2-19 Finished Water Transmission Main Costs (2005 dollars) .....................................................41
Table 2-20 Finished Water Storage / Pumping Costs (2005) ................................................................42
Table 2-21 Allocation of Finished Water Costs by Community for Facilities Constructed in
Oakland County.........................................................................................................................42
Table 2-22 Allocation of Total Project Cost (2005) by Community for Genesee County Finished
Water Alternative .......................................................................................................................43
Table 2-23 Potential Oakland County CVTs to Receive Genesee Finished Water ..................................44
Table 2-24 Estimated O & M Costs (2005) Attributed to Oakland County Communities for Facilities
Constructed by Genesee County.................................................................................................45
Table 2-25 Total Estimated O & M Costs (2005) for Finished Water Alternative .....................................45
Table 2-26 DWSD Customer – Ground Storage / Pumping Estimates ...................................................47
Table 2-27 Communities in Warren-St. Clair Shores Water Supply Alternative.......................................50
Table 3-1 Summary of Raw/Finished Water Supply Alternatives from Genesee County..........................51
Table 4-1 CVTs in the COSDS ..........................................................................................................54
Table 4-2 CVTs in the EFSDS ...........................................................................................................58
Table 4-3 CVTs in the GWKSDS .......................................................................................................60
Table 4-4 Capital Cost Summary for Clinton-Oakland Interceptor Relief Sewers ....................................74
Table 4-5 Alternative 3: Capital Cost Summary for 8 MGD Pontiac Diversion ........................................77
Table 4-6 Alternative 4: Treatment Cost Summary for COSDS .............................................................78
Table 4-7 Alternative 4: Capital Cost Summary for 20 MGD Pontiac Diversion.......................................79
Table 4-8 Alternative 5: Capital Cost Summary for 22 MGD Pontiac Diversion.......................................81
Table 4-9 Alternative 6: Capital Cost Summary for New WWTP along the Clinton River ........................83
Table 4-10 O & M Cost Summary for New WWTP along the Clinton River ............................................83
Table 4-11 GCDC Service (KCI Main Arm Only) .................................................................................86
List of Tables
Volume 4 – Alternatives Analysis Report vii
Table 4-12 GCDC Service (Both KCI Main and West Arms) .................................................................87
Table 4-13 Communities that may Benefit from Alternative 10 – Treatment by Another
City/Village/Township .................................................................................................................88
Table 4-14 Communities that may Benefit from Alternative 11 – New/Expansion of Local
Treatment .................................................................................................................................90
Table 4-15 Capital Cost Summary for 14 MGD Warren WWTP Expansion ............................................95
Table 4-16 O & M Cost Summary for 14 MGD Warren WWTP Expansion .............................................95
Table 5-1 Summary of Delivery Method Advantages and Disadvantages ..............................................96
List of Figures
Volume 4 – Alternatives Analysis Report viii
List of Figures
Figure 2-1 Comparison of Water Alternatives Including Private Well System ..........................................10
Figure 2-2 DWSD Expanded Water System........................................................................................14
Figure 2-3 Genesee County Raw Water Supply Alternative Schematic .................................................25
Figure 2-4 Genesee County Raw Water Supply Alternative Geographic Map ........................................26
Figure 2-5 Genesee County Finished Water Supply Alternative Schematic............................................37
Figure 2-6 Genesee County Finished Water Supply Alternative Geographic Map...................................38
Figure 2-7 Warren – St. Clair Shores Water Supply Alternative ............................................................49
Figure 4-1 COSDS Relief Sewers ......................................................................................................56
Figure 4-2 Comparison of Commerce-White Lake WWTP Capacities and Contracts ...............................62
Figure 4-3 Walled Lake/Novi WWTP Capacities and Contracts ............................................................64
Figure 4-4 Pontiac WWTP.................................................................................................................66
Figure 4-5 Milford Village WWTP .......................................................................................................67
Figure 4-6 South Lyon WWTP ...........................................................................................................68
Figure 4-7 Wixom WWTP .................................................................................................................69
Figure 4-8 Lyon Township WWTP .....................................................................................................70
Figure 4-9 Holly Village WWTP .........................................................................................................71
Figure 4-10 8 MGD and 20 MGD Diversion to Pontiac WWTP..............................................................75
Figure 4-11 22 MGD Diversion to Pontiac WWTP ...............................................................................80
Appendices
Volume 4 – Alternatives Analysis Report ix
Appendices
Appendix A DWSD Growth Pays for Growth Policy
Acronyms and Abbreviations
Volume 4 – Alternatives Analysis Report x
Acronyms and Abbreviations
ADD Average Daily Demand (Water)
ADDF Average Daily Design Flow (Wastewater Treatment)
ADF Average Daily Flow (Wastewater Treatment)
ADWF Average Dry Weather Flow
AWWA American Water Works Association
BCC Bioaccumulative Chemicals of Concern
CBOD5 Five-day Carbonaceous Biological Oxygen Demand
CIP Capital Improvement Plan
CFR Code of Federal Regulations
CFS or cfs Cubic Feet per Second
COSDS Clinton-Oakland Sewage Disposal System
CSO Combined Sewer Overflow
CVTs Cities, Villages, and Townships
CWA Clean Water Act
DBP Disinfection Byproducts
DWSD Detroit Water and Sewerage Department
EFSDS Evergreen-Farmington Sewage Disposal System
ENR Engineering News Record
EPA Environmental Protection Agency
ERP Emergency Response Plan
FEMA Federal Emergency Management Agency
Ft. or ft. Foot
GCDC Genesee County Drain Commissioner’s Office
GLI Great Lakes Initiative
GPCD Gallons Per Capita per Day
GPD or gpd Gallons per Day
GPM Gallons per Minute
GWKSDS George W. Kuhn Sewage Disposal System
Acronyms and Abbreviations
Volume 4 – Alternatives Analysis Report xi
HGL Hydraulic Grade Line
HPZ DWSD High Pressure Zone
HRSDS Huron Rouge Sewage Disposal System
I/I Inflow and Infiltration
IPP Industrial Pretreatment Program
IPZ DWSD Intermediate Pressure Zone
LPZ DWSD Low Pressure Zone
Mcf or mcf Thousand Cubic Feet
MCL Maximum Contaminant Level
MDD Maximum Day Demand
MDDF Maximum Daily ADDF (Wastewater Treatment)
MDF Maximum Daily Flow (Wastewater Treatment)
MDEQ Michigan Department of Environmental Quality
µg/1 Micrograms per liter
MG Million Gallons
MGD Million Gallons Per Day
NPDES National Pollutant Discharge Elimination System
NTU Nephelometric Turbidity Unit
OCDC Oakland County Drain Commissioner’s Office
O & M Operations & Maintenance
PDWF Peak Dry Weather Flow
PHD Peak Hour Demand
PHDF Peak Hourly Design Flow (Wastewater Treatment)
PHF Peak Hourly Flow (Wastewater Treatment)
PSI Pounds per Square Inch
PWS Public Water System
PWWF Peak Wet Weather Flow
RDF Regional Development Forecast from SEMCOG
RTB Retention Treatment Basin
RTF Retention Treatment Facility
SEMCOG Southeast Michigan Council of Governments
Acronyms and Abbreviations
Volume 4 – Alternatives Analysis Report xii
SEMCOG RDF SEMCOG Regional Development Forecast
SIU Significant Industrial User
SOCWA Southeast Oakland County Water Authority
SSO Sanitary Sewer Overflow
TAZ Traffic Analysis Zone
TMDL Total Maximum Daily Load
TWP Township
USEPA United States Environmental Protection Agency
WLA Waste Load Allocation
WQS Water Quality Standards
WTP Water Treatment Plant
WWTP Wastewater Treatment Plant
Summary
Volume 4 – Alternatives Analysis Report 1
1.0 Summary
1.1 Introduction
The Oakland County Drain Commissioner’s Office (OCDC) oversees over 500 storm drains, 15
municipal sanitary sewers, 14 municipal water systems, and 92 sewage pumping facilities. A
majority of the 61 cities, villages and townships (CVTs) within Oakland County also own water
and wastewater systems, either individually operated or under contract with OCDC. Historically,
most of these communities have acted independently and evaluated water and wastewater
alternatives based upon their specific community boundaries. To provide a “big picture” look at
the various water and wastewater systems throughout the County on a regional basis, OCDC
contracted with the URS Team of consultants to prepare a Water and Wastewater Master Plan
(Master Plan) to evaluate alternatives that address Oakland County’s (the County) current and
future water and wastewater needs. The objective of the Master Plan is not to recommend
specific courses of action, but rather to provide alternatives for the CVTs to consider based on
costs and feasibility. The completed Master Plan is intended to be used as a tool by the 61 CVTs
within the County, to encourage communication and cooperation. By encouraging a holistic
approach to infrastructure planning, the CVT’s needs can be addressed while simultaneously
obtaining the best value for all the stakeholders and the best solution for environmental
sustainability.
Each phase of the planning project correlates to a volume of the Master Plan and the titles of the
volumes give good insight into the project approach:
Volume 1 – Executive Summary
Volume 2 – Existing Facilities
Volume 3 – Needs Assessment
Volume 4 – Alternatives Analysis
Volume 5 – Financial Analysis
Volume 1 – The Executive Summary provides a summary of the state of the County’s water and
wastewater infrastructure in light of current and projected needs. It highlights important county-
Summary
Volume 4 – Alternatives Analysis Report 2
wide conclusions and opportunities. Appendix A provides a summary of the facilities, the needs
and the alternatives for each CVT.
Volume 2 – The Existing Facilities Report includes an inventory of existing water and
wastewater systems in the County. The asset’s capacities are analyzed, but independent
condition assessments were not performed. Descriptions of existing assets were obtained from
community interviews and published reports. Population projections, build-out analyses, and
environmental considerations are also included in Volume 2.
Volume 3 – The Needs Assessment Report identifies the gaps between what currently exists, and
the projected needs based on population projections in 2035 and local master planning. Needs
were identified based on individual community’s ability to meet the following general
assessment criteria:
Water – Quantity (Supply), Quality (Regulatory and Aesthetic), and Storage
Wastewater – Collection (Capacity and Contracts), Wastewater Treatment Plant (WWTP)
Capacity and Regulatory Compliance
Assessment of private systems is out of the scope of this Master Plan.
Volume 4 – The Alternatives Analysis Report (this document) presents alternatives developed
through a four-step process involving: 1) working sessions with the project team, 2) client input
and review, 3) initial alternative development, and 4) coordination with a municipal advisory
committee for stakeholder input. Alternatives are either formulated as part of the project or
adopted from on-going regional alternatives. Alternatives accommodate the existing and future
needs for the water and wastewater systems in each community. The planning period for this
Master Plan is through 2035.
Volume 5 – The Financial Model Report contains a financial model to predict water and
wastewater rates and costs for each CVT for the identified alternatives. This financial model
considers current costs and obligations, and the capital and Operations & Maintenance (O & M)
costs associated with the alternatives. It also provides forecasts of water and wastewater
commodity charges through the planning period. This tool allows each community to see the
relative impact of the various alternatives on their future utility rates. Costs generated by the
financial model are summarized in Appendix A of this Executive Summary as a cumulative cost.
Summary
Volume 4 – Alternatives Analysis Report 3
1.2 Scope
The scope of services for this phase of the Master Plan includes the following items.
1. Develop alternatives to fill gaps between current services and projected needs as
identified in Volume 3 – The Needs Assessment Report.
2. Alternatives consider the following topics:
a. Compare the continued use of private on-site water and/or wastewater systems
with publicly owned utility systems.
b. Compare the continued operation of community systems with larger
regionalized systems.
c. Compare greater reliance on DWSD, with reduced reliance on DWSD, and
alternate water/wastewater system providers for existing DWSD customers.
3. Evaluate alternative delivery methods, such as design-build, which may be available
to the project owner for project implementation.
1.3 Summary of Alternatives
The process used to identify the preliminary alternatives considered and presented herein
includes four-steps, namely 1) working sessions with the project team, 2) client input and review,
3) initial alternative development, and 4) coordination with a municipal advisory committee for
stakeholder input. The brainstorming session consisted of key personnel from URS, Tetra Tech
MPS, Plante & Moran, and ECT discussing the following items:
• Existing and projected needs of each community and respective water/wastewater
systems
• Presentation of past or current regional water/wastewater studies, such as the DWSD
master plans, Genesee County Water Supply Study, Warren-St. Clair Shores Water
Feasibility Study, etc.
• Development of potential alternatives list to meet the needs identified
After the initial list was developed, a presentation was made to the OCDC to obtain client
feedback. Consequently, the alternatives were further developed for presentation in this report.
Summary
Volume 4 – Alternatives Analysis Report 4
1.3.1 Summary of Water Alternatives
Alternative 1 – No Change: This alternative assumes the community will continue in its present
direction. For example, it is assumed that communities that had improvement projects under
construction would complete those projects. Growth is assumed to occur on private wells unless
water service in the community is 100% public.
Alternative 2 – Develop/Improve Community Well System: This alternative involves new
community well systems or upgrades and expansion of existing community well systems. The
analysis determines the number of new wells, the improvements to treatment, and the amount of
storage that is necessary to meet projected needs. This alternative addresses the quantity,
regulatory quality and water storage needs, but does not address the water aesthetic quality
criteria.
Alternative 2a – Develop/Improve Community Well System with Softening: This alternative is
identical to Alternative 2 except that the capital and operations & maintenance (O & M) costs
related to softening are estimated and added such that the water quality would be comparable to
that of DWSD. This alternative addresses the water quantity, water regulatory quality
requirements, and the water aesthetic quality criteria.
Alternative 3 – New Service from DWSD: This alternative involves extending DWSD water
service to the community. This alternative addresses both the regulatory and the aesthetic needs,
but not the water storage need.
Alternative 4 – Genesee County to Supply Raw Water: This alternative involves a new water
pumping station in Genesee County sourced from Lake Huron. The raw water transmission lines
would transport raw water to Oakland County. Oakland County would be responsible for
storing, treating, and distributing the water. The project costs assume all 11 potential
communities participate in this alternative. This alternative addresses both the regulatory and the
aesthetic needs, but not the local water storage need.
Alternative 5 – Genesee County to Supply Finished Water: This alternative involves a new
water treatment plant in Genesee County sourced from Lake Huron. The finished water
transmission lines would extend to 13 communities in Oakland County. Project costs assume all
Summary
Volume 4 – Alternatives Analysis Report 5
13 potential communities participate in this alternative. This alternative addresses both the
regulatory and the aesthetic needs, but not the local water storage need.
Alternative 6 – Storage Analysis (DWSD Existing Customers): DWSD customer communities
are evaluated for ground storage and re-pumping to offset peak hour demands and provide fire
and emergency reserve.
1.3.2 Summary of Wastewater Alternatives
Alternative 1 – No Change: This alternative assumes the community will continue in its present
direction. For example, it is assumed that communities that have improvement projects under
construction will complete those projects. Growth is assumed to occur on private septic systems
unless sewer service in the community is 100% public.
Alternative 2 - Construction of Relief Sewers: The size and location of the relief sewers requires
further study and system modeling, however financial considerations were prepared based on the
recommendations of the 1991 Clinton-Oakland Sewage Disposal System (COSDS) Interceptor
Relief Study. This alternative would address the collection capacity needs of the COSDS.
Alternative 3 - Diversion of 8 MGD of Flow to the Pontiac WWTP: The existing Pontiac
WWTP has an average daily excess capacity of approximately 8 MGD. This alternative involves
intercepting flow in the Clinton-Oakland Interceptor and diverting 8 MGD to Pontiac through
approximately 12,000 L.F. of 48-inch diameter gravity sewer line within the existing Grand
Trunk Western Railroad property. This alternative would address the collection capacity needs
of the COSDS.
Alternative 4 - Diversion of 20 MGD of Flow to the Pontiac WWTP: Similar to Alternative 3,
Alternative 4 diverts flow from the Clinton-Oakland Interceptor to the Pontiac WWTP.
However in Alternative 4, a new parallel WWTP is proposed next to Pontiac’s Auburn WWTP.
This alternative would address the collection capacity needs of the COSDS.
Alternative 5 - Diversion of 22 MGD of Flow to the Pontiac WWTP: Similar to Alternatives 3
and 4, Alternative 5 diverts flow from the Clinton-Oakland Interceptor to the Pontiac WWTP.
Alternative 5 utilizes a new parallel WWTP proposed next to Pontiac’s Auburn WWTP.
Alternative 5 expands the proposed new parallel WWTP to accommodate flow from White Lake.
This alternative would address the collection capacity needs of the COSDS.
Summary
Volume 4 – Alternatives Analysis Report 6
Alternative 6 - Construction of a New WWTP on the Clinton River: This alternative proposes a
new WWTP located in Macomb County near the Ford Motor Company Proving Grounds. Land
acquisition costs for this alternative were not included in the financial considerations. This
alternative would address the collection capacity needs of the COSDS.
Alternative 7 – Conveyance to COSDS: The Clinton-Oakland Sewage Disposal System
(COSDS) could be extended to reach Brandon, Ortonville, Springfield, White Lake and
additional portions of Oakland Township.
Alternative 8 – Service from Genesee County Kearsley Creek Interceptor (KCI) Main Arm Only:
The construction of the Northeast Relief Sewer (NERS) (currently under construction) and the
KCI Main Arm would allow Genesee County to serve Brandon and Ortonville, as well as other
Genesee County communities.
Alternative 9 – Service from Genesee County KCI Main Arm and West Arm: The construction
of the Northeast Relief Sewer (NERS) (currently under construction), the KCI Main Arm, and
the KCI West Arm would allow Genesee County to serve Brandon, Ortonville, Holly Township,
and Groveland Township, as well as other Genesee County communities.
Alternative 10 – Treatment by Another City/Village/Township (CVT): A few communities
would benefit from the opportunity to purchase wastewater treatment from neighboring
communities. This alternative examines the technical feasibility of new service only and does
not consider either community’s policy on the topic. The costs associated with accepting the
neighboring community’s additional flow are analyzed.
Alternative 11 – New/Expansion-of Local Treatment: The community may choose to expand an
existing plant or construct a new local wastewater treatment plant. This alternative assumes
Michigan Department of Environmental Quality’s (MDEQ) approval.
Alternative 12 – Divert Flow From GWKSDS to an Expanded Warren WWTP: This alternative
was explored in detail in the DWSD Wastewater Master Plan’s technical memorandum entitled
“Technical Feasibility of Satellite Treatment”. In it a 14 MGD WWTP would be constructed
near the existing Warren WWTP to treat flow from the GWKSDS. A more detailed study is
required to estimate specific costs allocated to each participating community. For this reason,
Summary
Volume 4 – Alternatives Analysis Report 7
Alternative 12 is not included in Volume 5 - Financial Model and no financial considerations are
included in Appendix A.
1.4 Basis of Alternative Costs
Each of the alternatives involving new infrastructure requires an estimate of the additional
capital cost and operation & maintenance cost to implement the alternative. The basis for each
unit cost is presented in Table 1-1 below.
Table 1-1 General Basis for Alternative Costs
Component Basis for Capital Cost1
Well Supply Assume 700 GPM well houses at $600,000 each
Public Well Supply Treatment
Assume $1,200 per GPM of water processed to meet regulatory standards
Assume an additional $1.875 Million per MGD capital costs and $500 per MG O & M costs for softening
Private Well Supply Treatment
Assume every well customer will replace the well in the 30 year planning period. Assume $8,000 per well in capital costs and $330 per year in O & M costs
Transmission Mains Used unit prices in 2003 DWSD Water Master Plan, Task C.
Booster Stations
Used new station construction formula presented in DWSD’s Comprehensive Water Master Plan (DWSD Contract No. CS-1278)
Cost ($1,000/MGD) = 238.34-(0.1496 * Capacity(MGD))
Ground Storage Reservoirs
1-2 MG - $0.70 per gallon
2-3 MG - $0.60 per gallon
3-4 MG - $0.45 per gallon
Wate
r
Elevated Storage Tanks <1.0 MG - $3.00 per gallon
>1.0 MG - $2.00 per gallon
Interceptor Sewers Based on estimates provided in DWSD Wastewater Master Plan or in past engineering estimate completed for a specific alternative and adjusted to May 2005 dollars.
Waste
wate
r
Wastewater Treatment Plants
Based on estimates provided by local consulting firms on past or planned WWTP construction
Notes: 1. All costs are presented in May 2005 dollars.
Summary
Volume 4 – Alternatives Analysis Report 8
Any references to historical construction costs in past engineering studies were adjusted to the
May 2005 baseline using the Engineering News and Record’s Construction Cost Index. Land
acquisition costs are not included in this report. However, as part of the financial model
development, an analysis of the estimated acquisition costs based on acreage needs is included.
These costs are reflected in the financial model output presented as Volume 5 – Financial
Analysis.
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 9
2.0 Water Alternatives Development
The goal of the water alternatives is to give local communities the information necessary to make
decisions about the relative wholesale costs associated with the different water supply
alternatives. The costs presented herein reflect only the capital and O & M costs associated with
supplying the water to the community. The costs do not include local improvements necessary to
convey the water supplied.
2.1 Alternative 1 – No Change
Alternative 1 is independently evaluated for each community because each community is in a
different state of planning, analysis, design, and construction of their water infrastructure. The
URS project team endeavored to present the most up-to-date information available, however
availability of information combined with the inevitable need to document findings, results in a
snapshot-in-time deliverable. With few exceptions, the information included herein was current
as of the Spring of 2007.
In general, this alternative assumes the community will continue to pursue its current direction.
For example, it is assumed that communities that had improvement projects under construction
would complete those projects. The beginning of construction was sufficient evidence of the
community’s commitment to the improvement, regardless of project schedules and delays.
Similarly, some communities communicated strong commitments to plans and designs. For
these communities, Alternative 1 may have assumed completion of those improvements. These
assumptions may have affected the other alternatives. For example, if it was assumed that the
community would finish a 2 MG storage tank, yet the needs analysis determined the need for 4
MG of storage, the improvement alternative would only recommend an additional 2 MG.
Alternative 1 assumes growth occurs on private wells unless water service in the community is
100% public. It is important to note that since this Master Plan includes a financial analysis on
public water alternatives, it leaves the impression that remaining on private well systems, i.e. No
Change, is always the most cost effective alternative. This may not be the case.
To further explore this topic, a financial comparison was made for Brandon Township (selected
as a test case) between maintaining individual residential well systems and constructing a public
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 10
groundwater system. The financial methodology employed throughout the study was applied to
the individual residential well systems and the cumulative costs were compared with the
cumulative costs for a community water supply. Figure 2-1 depicts the results of the
comparison.
Figure 2-1 Comparison of Water Alternatives Including Private Well System
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
Alternative
Co
st
($)
Total Amount To Be Bonded ($M)
Total Cumulative Cost ($M)
Total Amount To Be Bonded ($M) 17.6 10.3 11.6 16.5 18.8
Total Cumulative Cost ($M) 56.0 31.5 39.2 82.0 57.0
Alt. 1: No Change
Alt. 2:
Develop/Improve Community Well
Alt. 2a:
Develop/Improve Community Well
Alt. 3: New Service
from DWSD
Alt. 5: Genesee
County to Supply Finished Water
In an effort to provide an accurate comparison a number of assumptions were made about the
individual well systems. Those assumptions include:
• A residential well system has a useful service life of 20 years and all households would
need to install or replace their well system once during the study period.
• Each system has a point of use treatment system for iron removal and softening.
• Capital costs over the 30 year planning period included $6,500 for the well system and
$1,500 for the treatment system.
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 11
• Capital costs were bonded over 20 years using the same interest rate assumptions as the
community water supply.
• The entire capital costs were bonded in year one (2005). This is the most economically
advantageous method.
• Annual operations and maintenance costs included $150 for salt, $100 for filters, and $80
for electricity.
The service population used was the same for all the scenarios and included a 2005 service
population of 3,975 and a 2035 service population of 5,509. Each household was assumed to
have 2.5 people resulting in 1,590 households in 2005 and 2,203 households in 2035.
The conclusion is that individual private well systems may cost more on an individual basis than
developing a public water system. Furthermore, public well systems may offer water quality and
water reliability advantages. For example, in a power outage public water users often retain their
water supply where individuals relying on a private, electrically pumped well will not. Also,
nearby fire hydrants can reduce a home owner’s insurance premiums. Many factors ultimately
impact the cost of a public system such as local conditions, population densities, etc. and
therefore a detailed analysis should always be conducted prior to decision making.
2.2 Alternative 2 – Develop/Improve Community Well System
Like Alternative 1 – No Change, Alternative 2 is unique for every community to which it
applies. It includes communities that may benefit from a new community well systems or
upgrades and expansion of existing community well systems. It does not include the local
distribution system improvements necessary provide a complete project. Table 2-1 lists the
communities included in Alternative 2. For an understanding of how this alternative compares to
other water alternatives for each of these communities see Appendix A of Volume 1 – Executive
Summary.
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 12
Table 2-1 Communities that may Benefit from Alternative 2 - Develop/Improve
Community Well System
No. Community
1 Highland Twp.
2 Holly Village
5 Lyon Twp.
6 Milford Village
7 Oakland Twp.
8 Oxford Twp.
9 Oxford Village
10 Rochester
11 South Lyon
12 Waterford Twp.
13 White Lake Twp.
The quantity (supply) and treatment (regulatory quality) needs identified in Volume 3- Needs
Assessment Report of this Master Plan are met with this alternative. Well supply and treatment
costs are developed for comparison to other water supply alternatives.
2.3 Alternative 2a – Develop/Improve Community Well System with Softening
Community well systems utilize ground water rather than surface water, for the water source.
Groundwater in many parts of Oakland County is characterized as hard, i.e. having high levels of
calcium and magnesium. Groundwater that has been softened is aesthetically comparable to
DWSD’s water supply. Alternative 2a utilizes the data developed for each of the Alternative 2
communities then adds the capital and O & M costs associated with softening. This allows for a
closer comparison of well supply water to DWSD’s surface supplied water. Independence
Township has a well system that meets projected demands. However, since Independence
Township does not soften its water, Alternative 2a is prepared.
The cost assumptions for water softening resulted in additional capital costs of about $1.88 per
MGD and additional O & M costs of approximately $500 per million gallons. Appendix A of
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 13
Volume 1 – Executive Summary includes the cost of Alternative 2a with the other water
alternatives for each of the applicable communities.
2.4 Alternative 3 – New Service from DWSD
2.4.1 Eligible CVTs
Communities eligible for new service from DWSD by the year 2035 were identified in the
Detroit Water and Sewerage Department (DWSD) “Comprehensive Water Master Plan”
(CWMP) published in June 2004. The study area for the CWMP consisted of nine counties in
Southeast Michigan, including Oakland County. There are a total of 246 communities within the
DWSD study area. Currently, DWSD sells potable water to 126 customers. These include 78
individual communities and 9 water authorities (that serve an additional 48 communities).
Currently, 37 of Oakland County’s 61 CVT’s receive water from DWSD.
Recommended improvements are summarized by decade through the year 2050 in Section 6 of
the CWMP Summary Report. Figure 2-2 illustrates the improvements for the five decades
within Oakland County.
Table 2-2 presents a summary of the projected new DWSD customers from Oakland County
throughout the 2050 planning period. Tables 2-3 through 2-7 summarize the recommended
improvements by decade within Oakland County, which was adapted from the DWSD CWMP
Summary Report.
Lake St. Clair
St.
Cla
irR
iver
Detro
it Rive
r
Auburn Hills
Berkley
Beverly HillsBingham Farms Village
Birmingham
Bloomfield HillsBloomfield Township
Clawson
Commerce Township
Farmington
Farmington Hills
Ferndale
Groveland Township
Hazel Park
Holly Township
Holly Village
Huntington Woods
Keego Harbor
Lake Angelus
Lake Orion Village
Lathrup Village
Leonard Village
Madison Heights
Northville
Novi
Novi Township Oak Park
Orchard Lake
Orion Township
Pontiac
Rochester Hills
Rose Township
Royal Oak
Royal Oak Township
Royal Oak TownshipSouthfield
Southfield Township
Sylvan Lake
Troy
Walled LakeWest Bloomfield Township
Wixom
Lyon Township2010
Lyon Township2010
Oxford Township2010
Oxford Township2010
Milford Township2040
Milford Township2040
Oakland Township2010
Oakland Township2010
Highland Township2040
Highland Township2040
Brandon Township2010
Brandon Township2010
Springfield Township2040
Springfield Township2040
Waterford Township2020
Waterford Township2020
White Lake Township2020
White Lake Township2020
Independence Township2010
Independence Township2010
Rochester2010
Rochester2010
South Lyon2010
South Lyon2010
Milford Village2030
Milford Village2030
Oxford Village2010
Oxford Village2010
Ortonville Village2010
Ortonville Village2010
Clarkston2010
Clarkston2010
Oakland Co.
St. Clair Co.
Wayne Co.
Macomb Co.
Lapeer Co.
Genesee Co.
Washtenaw Co.
Livingston Co.
Detroit
Flint
Livonia
Warren
Ray Twp
Romulus
Riley Twp
Taylor
Atlas Twp
Elba Twp
Clay Twp
Lenox Twp
Burton
Imlay Twp
Berlin Twp
Bruce Twp
Attica TwpClyde Twp
Wales Twp
Casco Twp
St Clair Twp
China Twp
Almont TwpMundy Twp
Tyrone Twp
Salem Twp
Kimball TwpHadley Twp
Shelby Twp
Dryden Twp
Canton Twp
Armada Twp
Mussey Twp
Ann Arbor
Emmett Twp
Hartland Twp
Davison Twp
Macomb Twp
Lapeer Twp
Superior Twp Dearborn
Brighton Twp
Northfield Twp
Fenton Twp Richmond Twp Columbus Twp
Kenockee Twp
Van Buren Twp
Clinton Twp
Ypsilanti Twp
Metamora Twp
Green Oak Twp
Sterling Heights
Flint Twp
Ira Twp
Washington Twp
Westland
Grand Blanc Twp
Pittsfield Twp
Lynn Twp
Chesterfield Twp
Lodi Twp
Scio Twp
Richfield Twp Oregon Twp
Cottrellville Twp
Arcadia Twp
Oceola Twp
Genoa Twp
Plymouth Twp
Mayfield Twp
Gaines Twp
Webster Twp
Clayton Twp
Northville Twp
Ann Arbor Twp
Deerfield Twp
Grant TwpGoodland Twp
Harrison Twp
Hamburg Twp
Roseville
Argentine Twp
Brockway TwpMt Morris Twp Genesee Twp
Fort Gratiot Twp
Fenton
Lapeer
Inkster
Greenwood Twp
Redford Twp
Wayne
Port Huron Twp
Port Huron
York Twp Huron Twp
Marysville
St Clair Shores
Allen Park
Saline
Southgate
Dearborn Heights
Wyandotte
Fraser
Augusta Twp Sumpter Twp
EcorseYpsilanti
East China Twp
Garden City
Clay Twp
Eastpointe
Lincoln Park
St Clair
Burtchville TwpFlushing
Brighton
Brownstown Twp Riverview
Linden
Flushing Twp
Utica
Mt Clemens
New Baltimore
Swartz Creek
Grand Blanc
Flint Twp
Marine City
Richmond
River RougeMelvindale
Imlay City
Davison
Plymouth
Saline TwpGrosse Ile Twp
Algonac
Highland ParkHamtramck
Harper Woods
Center Line
Grosse Pointe Woods
Belleville
Grosse Pointe Farms
Northville
Grosse Pointe Park
Trenton
Grosse Pointe
MemphisMemphis
Grosse Pointe Twp
Richmond
Lake Twp
Southeast WTPSoutheast WTP
Northeast WTPNortheast WTP
Lake Huron WTPLake Huron WTP
Springwells WTPSpringwells WTPWater Works Park II WTPWater Works Park II WTP
Addison Township
0 8 164 Miles
LegendExisting
Water Treatment Plant
Ground Reservoir
Booster Station
Transmission Mains
Proposed
2010 Improvement
2020 Improvement
2030 Improvement
2040 Improvement
2050 Improvement
Current (2005) DWSD Service Area in Oakland County
Potential Future Customers
Figure 2-2DWSD Expanded Water System
Oakland County Water and Wastewater Master Plan
NOTE:DWSD FACILITIES DIGITIZED FROMJUNE 2004 WATER MASTER PLAN
J:\1
364
7263
\Wa
ter\
Alte
rn.R
pt\F
ig2
-1.m
xd
14
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 15
Table 2-2 Potential New DWSD Water Customers from Oakland County by Year 2050
*Projected maximum day demand per the Oakland County Master Plan Source: 2003 DWSD Comprehensive Water Master Plan
No. Community Year Added to DWSD System
2035 MDD (MGD)
1 Brandon Twp. (includes
Village of Ortonville) 2010 2.5
2 Franklin Village 2010 1.1
3 & 4 Independence Twp. and
Clarkston 2010 7.8
5 Lyon Twp. 2010 18.2
6 Oakland Twp. 2010 15.3
7 Oxford Village 2010 1.6
8 Oxford Twp. 2010 10.2
9 South Lyon 2010 3.8
10 Wolverine Lake Village 2010 1.2
11 Rochester 2010 2.4
12 Waterford Twp. 2020 26.8
13 White Lake Twp. 2020 15.5
14 Milford Village 2030 1.8
15 Highland Twp. 2040 7.4
16 Milford Twp. 2040 3.0
17 Springfield Twp. 2040 3.0
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 16
Table 2-3 Decade One (2000-2010) DWSD Water System Improvements in
Oakland County
Source: 2003 DWSD Comprehensive Water Master Plan
Facility or Pipe Route Location Description
High ground storage tank west of Newburgh booster
station
8 Mile Rd, west of Sheldon
New 10 MG high ground storage tank (incl. 4 MG new emergency storage) and associated piping (2000 ft of 36” pipe).
Romeo booster pumping station and ground storage
tank Village of Romeo
New booster station with line pumping only (84.4 MGD at 300 ft; ultimate
capacity of 172.8 MGD); 20 MG new emergency storage tank.
31 Mile Rd new pipeline From Romeo to
Independence Twp. Approx 19 miles of 72” to 84” pipe
Orion pipe loop From Independence Twp. to Orion Twp.
Approx 7 miles of 54” to 60” pipe
14 Mile Rd extension Wixom to South Lyon Approx 2 miles of 72” pipe
8 Mile Rd parallel main West Service Center (WSC) to Newburgh
Station Approx 5 miles of 60” pipe
24 Mile Rd parallel main Chesterfield Twp. to
Rochester Approx 13 miles of 36” to 42” to 48” pipe
Parallel main downstream of Newburgh station
Newburgh station to Newburgh Rd, along
8 Mile Rd. Approx 0.4 miles of 60” pipe
14 Mile Rd parallel main Between Franklin and
Haggerty stations Approx 5 miles of 36” pipe
Parallel Adams Rd main Downstream of
Adams Rd station Approx 1 mile of 30” pipe
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 17
Table 2-4 Decade Two (2010-2020) DWSD Water System Improvements in
Oakland County
Facility or Pipe Route Location Description
High ground storage tank north of Orion station
Brown east of Baldwin, Orion Twp.
New 20 MG high ground storage tank and associated piping (approx 8 miles of
36”, 42” and 48” pipe)
Haggerty pipe loop Pontiac to north of Haggerty station
Approx 16 miles of 54”, 60” and 84” pipe
Parallel main downstream of Haggerty station
14 Mile Rd, from Haggerty station to Welch Rd.
Approx 1 mile of 42” pipe
WSC station upgrades West Service Center Replace intermediate line pumps (60
MGD at 185 ft)
Ground storage tank at Newburgh pump station
Newburgh pump station New 20 MG ground reservoir for
emergency storage
High ground storage, southwest of Adams
booster station Adams booster station
New 10 MG high ground tank for emergency storage and associated
piping (2.1 miles of 30” pipe)
24 Mile Rd extension Rochester pump station to
Auburn Hills Approx 6 miles of 72” pipe
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 18
Table 2-5 Decade Three (2020-2030) DWSD Water System Improvements in
Oakland County
Facility or Pipe Route Location Description
Parallel main downstream of Haggerty
station
14 Mile Rd, from Welch Rd to Beck Rd
Approx 4 miles of 42” pipe
North service center capacity upgrades
North service center (NSC)
Additional 110 MGD pumping capacity for line pumps (350 MGD at 370 ft)
Franklin station upgrades
Franklin station Additional 30 MGD line pumping (120
MGD at 250 ft)
Parallel Orion Twp. main Giddings Rd, from
Walton Blvd to Green Rd
Approx 2 miles of 42” pipe
Transmission main to supply Brighton
Pontiac Trail, from west of Wixom to I-96 to
Kensington Rd to Buno Rd
Approx 12 miles of 42”, 48” and 54” pipe
Haggerty station upgrades
Haggerty station Additional 24 MGD line pumping (66 MGD
at 200 ft)
Parallel main downstream of
Newburgh pump station
8 Mile Rd, from Haggerty Rd to
Meadowbrook Rd Approx 1 mile of 30” pipe
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 19
Table 2-6 Decade Four (2030-2040) DWSD Water System Improvements in
Oakland County
Table 2-7 Decade Five (2040-2050) DWSD Water System Improvements in
Oakland County
Facility or Pipe Route Location Description
Springfield pipe loop Independence Twp. to Wixom
Approx 28 miles of 42” to 60” to 72” pipe
Oakland pump station and ground storage
Oakland Twp. New station with line pumps (78MGD at 260 ft
ultimate capacity). New 20 MG ground reservoir for emergency storage.
High ground storage west of Springfield
Springfield Twp. New 10 MG high ground tank for emergency
storage
Facility or Pipe Route
Location Description
Second feed to Flint Springfield Twp. to Genesee
County Approx 12 miles of 36” pipe
North service center upgrades
NSC Additional 50 MGD line pumping
(400 MGD at 370 ft)
Newburgh station upgrades
Newburgh station Additional 12 MGD pumping capacity (64 MGD at 200 ft)
Oakland station upgrades
Oakland station Additional 126 MGD pumping capacity (204 MGD at 260 ft)
Franklin station upgrades
Franklin station Additional 61.2 MGD line pumping
capacity (151.2 MGD at 250 ft)
Parallel main downstream of Franklin station
Inkster Rd, from Franklin station to Maple Rd
Approx 1 mile of 24” pipe
Parallel main downstream of Adams
Rd station
Squirrel Rd from Walton Blvd to South Blvd; Walton Blvd from Squirrel Rd to Avon
Twp.
Approx 5 miles of 24” pipe
Parallel main downstream of
Newburgh booster station
8 Mile Rd, from Meadowbrook Rd to Sheldon
Rd. Approx 3 miles of 24” to 30” pipe
Brighton-Ann Arbor Pipe Loop
From Milford Twp. to Brighton Twp. and from Green Oak
Twp. to Ann Arbor. Approx 22 miles of 48” to 72” pipe
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 20
The DWSD CWMP also identified new customers projected to be added by 2010 and their
expected maximum day demand (MDD). The CWMP notes that if Lyon Twp. and South Lyon
do not join the DWSD system, the 14 Mile Rd extension (Map Key No. 5) will not be needed by
2010. Similarly, if Oxford and Oxford Twp. do not join the DWSD system, the Orion pipe loop
will not be needed, but a ground storage tank and reservoir pumps would be required at the Orion
pumping station to supply existing customers during peak periods.
2.4.2 Projected Cost of Service
The CWMP identified new infrastructure and infrastructure improvements for each decade.
Based on DWSD System Expansion Policy1, the new customers will be expected to pay for new
infrastructure that will be built to serve them. If the new infrastructure serves more than one
potential new customer, the cost for the new infrastructure will be divided proportionally.
The following assumptions were made in calculating projected costs for the above Oakland
County communities listed in Table 1-1:
• Only those infrastructure costs that are associated with the new customer will be paid
for by the new customer.
• If new infrastructure is shared by more than one community, the infrastructure costs
will be divided among the corresponding communities based on their year 2035 MDD
flows.
• The DWSD CWMP transmission system improvements by decade included new
transmission mains, new ground storage, new high ground storage, new booster
stations, new emergency storage, new looped transmission mains, and new parallel
mains. Customer costs for this Master Plan will include the new transmission mains,
new ground or high ground storage, and new booster stations. The costs for
emergency storage are not included in the estimate since it was assumed that the new
customers would not be responsible for this capital investment. Also, costs for new
looped transmission mains and new parallel mains will not be charged to new
1 DWSD system expansion policy provided in Appendix A.
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 21
customers. However, in some cases, partial cost for new parallel mains may be
attributed to new customers.
• The basis for capital costs were developed in the DWSD CWMP’s Task C – “Water
Supply and Service Management Plan” report. The DWSD CWMP costs were
escalated from Year 2003 (January 2003) dollars to current (May 2005) dollars using
the following Construction Cost Indices (CCI):
CCI (01/2003) = 6580.5
CCI (05/2005) = 7398.0
May 2005 Cost = Year 2003 Cost * (7398.0/6580.5) = Year 2003 Cost * 1.1242
Table 2-8 below outlines the total project cost for each of the communities listed as potential
DWSD customers in the DWSD CWMP.
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 22
Table 2-8 Estimated Total Project Cost (2005) for Potential New DWSD Water Customers
Notes: 1. Data obtained from CWMP
2.5 Alternative 4 – Genesee County to Supply Raw Water
Genesee County currently has a water supply agreement with the City of Flint to purchase
DWSD water through September 2010. As a result of water reliability concerns, recent and
projected future rate increases from DWSD, the County was evaluating a number of water
supply alternatives.
The Genesee County Drain Commissioner, Jeffrey Wright, commissioned a Preliminary
Engineering Feasibility Study, which looked at numerous alternatives to provide water service to
the existing County Agency customers, as well as expanding water service to other areas outside
their existing service area. The two-volume report is titled “Preliminary Report Long-Term
Water Supply for Genesee County - Second Draft”, dated January 2006. The Genesee County
report evaluated three base alternatives as follows:
Community Year Added to DWSD
System1 Total Project
Cost ($ Million)
Brandon Twp. (incl. Village of Ortonville) 2010 22.3
Independence Twp. and Clarkston 2010 41.2
Oakland Twp. 2010 74.8
Oxford Village 2010 11.2
Oxford Twp. 2010 53.3
Rochester 2010 6.5
Franklin Village 2010 3.0
Wolverine Lake Village 2010 5.2
Lyon Twp. 2010 20.6
South Lyon 2010 5.2
Waterford Township 2020 111.0
White Lake Township 2020 71.6
Milford Village 2030 10.3
Highland Twp. 2040 66.4
Milford Twp. 2040 30.0
Springfield Twp. 2040 28.4
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 23
Alternative I – No Change, maintain existing mode of operation,
Alternative II – Purchase water directly from DWSD,
Alternative III – Develop a new Lake Huron Water Supply.
Numerous scenarios (a total of over twenty) were evaluated for the three base alternatives. The
planning period for the study runs through the year 2050.
Scenarios 1 through 15 looked only at supplying water to Genesee County customers and
potential customers within their existing service area (Group 1). Scenarios 16 through 20
evaluated extending water service into other areas delineated as Groups 2, 3, 4 and 5. The
breakdown for the Groupings is as follows:
Group 1 – Genesee County Agency existing and potential customers
Group 2 – City of Flint
Group 3 – Lapeer County
Group 4 – Northern Oakland County
Group 5 – Southern Oakland County/Macomb County
Scenarios involving Group 4 are of the most interest for the Oakland County Master Plan Study
as they relate to providing water service from Genesee County to several northern Oakland
County communities. The raw water supply option to get water to northern Oakland County
communities is defined as Scenario 16 in the Genesee County Report. Refer to Figure 2-3 for a
schematic of the layout (Genesee County portion) for Scenario 16. Figure 2-4 illustrates the
approximate location of the transmission mains, reservoirs, treatment plant, and storage tanks
planned for this alternative.
2.5.1 Eligible CVTs
Table 2-9 lists the potential communities that could receive raw water from Genesee County in
Scenario 16.
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 24
Table 2-9 Potential Oakland County CVTs to Receive Genesee County Raw Water Under
Alternative 4
Note: 1. Brandon Township and the Village of Ortonville are excluded from the Raw Water
Alternative due to their proximity to the proposed improvements.
Community 2035 ADD
(MGD) 2035 MDD
(MGD) Cost Share
Highland Township 2.6 7.4 7.5%
Independence Township &
Clarkston 4.1 7.8 7.9%
Oakland Township 5.5 15.3 15.5%
Oxford Township 3.7 10.2 10.3%
Oxford Village 0.7 1.6 1.6%
Waterford Township 11.6 26.8 27.1%
White Lake Township 4.8 15.5 15.7%
Springfield Township (Partial) 1.2 3.0 3.0%
Lake Orion Village 0.5 0.6 0.6%
Orion Township 8.3 10.6 10.7%
Totals 43.0 98.8 100.0%
Figure 2-3Genesee County Raw Water
Supply AlternativeOakland County Water and Wastewater Master Plan
J:\13647263\Water\Altern.rpt\Fig2-3.mxd
SOURCE - PRELIMINARY REPORT: LONG-TERM WATER SUPPLY FOR GENESEE COUNTY - SECOND DRAFT (JAN 2006)
25
26
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 27
Table 2-9 also shows the projected Average Daily Demand (ADD) and Maximum Daily Demand
(MDD) for the respective communities along with their respective percentage of the total
demand. This percentage will be used to distribute costs to each community for Alternative 4 –
Genesee County to Supply Raw Water.
2.5.2 Projected Cost of Service
The report does not make any specific recommendations, but it does present cost data for each of
the scenarios considered. Costs for each of the Genesee County alternatives are comprised of
those costs associated with the Genesee County Facilities required to get the water to Oakland
County and those costs attributed to facilities required to be constructed within Oakland County
for storage/treatment (as applicable) and transmission to the various communities. Also, an
estimated cost for operation and maintenance of the facilities is presented.
Oakland County’s share of the capital cost expended by Genesee County for Alternative 4 would
be approximately $458,197,000 in 2007 dollars (Source: Preliminary Report, Long-Term Water
Supply for Genesee County, Volume 2- Existing Facilities Report – Appendices, Second Draft,
January 2006, Appendix N, Table 4, pg. 8). This equates to about $432 million in 2005 dollars.
For this alternative, Genesee County would supply Oakland County with untreated water from
Lake Huron. The raw water would be delivered to two raw water storage reservoirs, with a total
capacity of 700 million gallons. A potential location for the reservoirs would be on the east side
of the County.
The reservoirs have an estimated capital cost of $188.1 million in 2005 dollars (see Table 2-10).
Treatment of the Raw Water would be provided by a 99 MGD treatment plant located adjacent to
the reservoirs. Treated water would then be distributed and stored throughout Oakland County,
serving a total of 10 communities.
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 28
Table 2-10 Reservoir Costs (2005) to Store the Raw Water Supply from Genesee County
Estimated project costs for treatment and transmission mains are approximately $426.4 million.
Finished water storage and booster station costs are estimated at $102.6 million (see Tables 2-11
and 2-12).
Table 2-13 presents the total project cost ($717.0 million) divided among the communities on a
water demand basis for facilities required to store the raw water, treat it, and distribute it to the
above noted Oakland County Communities.
Item Description Unit Quantity Total Unit
Cost Total Cost
1 Earthwork CY 3,500,000 3.00$ 10,500,000$
2 Slope Protection: Type "C" Rock CY 190,300 40$ 7,612,000$
3 Slope Protection: Stone Bedding CY 190,300 40$ 7,612,000$
4 Slope Protection: Geotextile Filter SY 375,000 3.00$ 1,125,000$
5 Seeding and Mulching at Reservoir SY 657,145 2.50$ 1,643,000$
6 Valves and Related Processes LS 1 300,000$ 300,000$
7 Concrete Headwalls Each 16 5,000$ 80,000$
8 Reservoir Inlet Structure Each 2 250,000$ 500,000$
9 Reservoir Outlet Structure Each 2 40,000$ 80,000$
10 Toe and Blanket Drains LS 1 1,900,000$ 1,900,000$
11 Reservoir Levee Roadway LS 1 200,000$ 200,000$
12 84" Water Line to Reservoirs LF 47,600 854$ 40,670,000$
13 Miscellaneous Site Construction LS 1 5,000,000$ 5,000,000$
14 Property Acquisition Acre 175 20,000$ 3,500,000$
15 100 MGD Pump Station LS 2 22,328,000$ 44,656,000$
125,378,000$
Construction Contingencies 30% 37,613,000$
Engineering, Legal, etc. 20% 25,076,000$
Raw Water Storage Construction Sub-total
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 29
Table 2-11 Treatment & Transmission Main Cost (2005) for Raw Water Supply
Item Description Unit Quantity Total
Unit Cost Total Cost
1 18" Transmission Main LF 10,718 141$ 1,506,188$
2 18" Road / waterway crossings LF 1,300 393$ 511,524$
3 24" Transmission Main LF 18,294 197$ 3,599,168$
4 24" Road / waterway crossings LF 500 491$ 245,645$
5 30" Transmission Main LF 13,855 242$ 3,348,892$
6 30" Road / waterway crossings LF 600 604$ 362,226$
7 42" Transmission Main LF 29,149 333$ 9,699,979$
8 42" Road / waterway crossings LF 400 831$ 332,324$
9 54" Transmission Main LF 71,056 517$ 36,746,334$
10 54" Road / waterway crossings LF 1,500 1,293$ 1,939,305$
11 60" Transmission Main LF 20,095 604$ 12,131,590$
12 60" Road / waterway crossings LF 1,400 1,510$ 2,113,776$
13 72" Transmission Main LF 17,778 755$ 13,430,977$
14 72" Road / waterway crossings LF 200 1,188$ 237,516$ 15 Water Treatment Facility Gallon/Day 99,000,000 2.00$ 198,000,000$
284,205,000$
30% 85,262,000$
20% 56,841,000$
426,308,000$ Treatment/Transmission Total Project Cost
Treatment/Transmission Construction Sub-Total
Construction Contingencies
Engineering, Legal, etc.
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 30
Table 2-12 Finished Water Storage Costs (2005) for the Raw Water Alternative
Item Description Unit Quantity Total Unit
Cost Total Cost
1 1-MG Ground Storage Tank gal 1,000,000 0.70$ 700,000$
2 3-MG Ground Storage Tank gal 3,000,000 0.60$ 1,800,000$
3 Five 5-MG Ground Storage Tanks gal 25,000,000 0.45$ 11,250,000$
4 11-MG Storage Tank gal 11,000,000 0.40$ 4,400,000$
5 2 MGD Booster Station LS 1 533,000$ 533,000$
6 6 MGD Booster Station LS 1 1,590,000$ 1,590,000$
7 10 MGD Booster Station LS 3 2,650,000$ 7,950,000$
8 20 MGD Booster Station LS 2 5,260,000$ 10,520,000$
9 50 MGD Booster Station LS 1 11,538,000$ 11,538,000$
10 80 MGD Booster Station LS 1 18,101,760$ 18,102,000$
68,383,000$
Construction Contingencies 30% 20,515,000$
Engineering, Legal, etc. 20% 13,677,000$
102,575,000$ Raw Water Storage Total Project Costs
Raw Water Storage Construction Sub-total
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 31
Table 2-13 Distribution of Total Project Costs (2005) by Community for Facilities
Constructed within Oakland County
Community 2035 MDD
(MGD) Cost Share Total Project Cost
Highland Township 7.4 7.5% $53,500,000
Independence Township 7.8 7.9% $56,877,000
Oakland Township 15.3 15.5% $111,060,000
Oxford Township 10.2 10.3% $74,152,000
Oxford Village 1.6 1.6% $11,665,000
Waterford Township 26.8 27.1% $194,311,000
White Lake Township 15.5 15.7% $112,757,000
Springfield Township (Partial) 3.0 3.0% $21,516,000
Lake Orion Village 0.6 0.6% $4,411,000
Orion Township 10.6 10.7% $76,752,000
Totals 98.8 100% $717,001,000
The Total Project Costs required for each Oakland County CVT that can be attributed to getting
raw water from Genesee County, treat it and convey to each of their respective communities in
Oakland County are presented in Table 2-14. This cost does not include the cost of local
distribution system improvements that may be necessary to distribute water from the County
transmission main to customers.
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 32
Table 2-14 Distribution of Total Project Costs (2005) by Community for Raw Water
Alternative
Community 2035 MDD
(MGD)
Cost Share
Facilities Constructed in
Oakland County
Proportional Share of Genesee
Co. Facilities
Total Project Costs for GCDC
Raw Water
Highland Township
7.4 7.5% $53,500,000 $32,215,000 $85,715,000
Independence Township
7.8 7.9% $56,877,000 $34,249,000 $91,126,000
Oakland Township
15.3 15.5% $111,060,000 $66,875,000 $177,935,000
Oxford Township
10.2 10.3% $74,152,000 $44,650,000 $118,802,000
Oxford Village 1.6 1.6% $11,665,000 $7,024,000 $18,689,000
Waterford Township
26.8 27.1% $194,311,000 $117,004,000 $311,315,000
White Lake Township
15.5 15.7% $112,757,000 $67,896,000 $180,653,000
Springfield Township (Partial)
3.0 3.0% $21,516,000 $13,110,000 $34,626,000
Lake Orion Village
0.6 0.6% $4,411,000 $2,656,000 $7,067,000
Orion Township 10.6 10.7% $76,752,000 $46,216,000 $122,968,000
Totals 99 100% $717,001,000 $431,895,000 $1,148,896,000
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 33
Preliminary transmission main sizes and alignments are selected throughout Oakland County for
the purposes of estimating the capital cost to treat and convey a Lake Huron water supply to the
communities in the alternative service area. The unit prices tabulated in the DWSD
Comprehensive Water Master Plan are used for the proposed transmission main construction
costs. The unit prices are also adjusted using the Engineering News Record (ENR) CCI to arrive
at May 2005 construction costs.
Treatment plant capital costs are estimated at $2.00 per gallon and based on the Maximum Daily
Demand (MDD).
Capital costs presented in the Genesee County report are shown in 2007 dollars. These costs
were deflated to 2005 dollars assuming an inflation rate of 3% per year for 2006 and 2007.
Operation and Maintenance costs are estimated for both the Genesee County Facilities and the
Oakland County Facilities. O & M costs for the Oakland County treatment facilities are based
on $2.90 per 1000 cubic feet of water treated on an Average Daily Demand (ADD) basis.
Transmission/Storage O & M costs are based on $1.00 per 1000 cubic feet of ADD. Costs for
the Genesee County facilities are estimated based on data presented in the Genesee County
Long-Term Water Supply Report for Scenario 16. Tables 2-15 through 2-17 present the
estimated O & M costs for the proposed improvements.
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 34
Table 2-15 Estimated O & M Costs for Facilities in Oakland County (2005 dollars)
O & M Cost Source Avg. O & M Cost/mcf
Annual O & M Cost/mcf
Treatment Plant O & M @ ADD=23 MGD $2.90 $3,250,000
Transmission Mains O & M (ADD=23 MGD) $1.00 $1,122,000
Total Amount of O & M Costs $4,372,000
Community Proportional Share Share of O & M
Costs
Highland Township 7.5% $326,000
Independence Township 7.9% $347,000
Oakland Township 15.5% $677,000
Oxford Township 10.3% $452,000
Oxford Village 1.6% $71,000
Waterford Township 27.1% $1,184,000
White Lake Township 15.7% $687,000
Springfield Township (Partial) 3.0% $133,000
Lake Orion Village 0.6% $27,000
Orion Township 10.7% $468,000
Totals 100% $4,372,000
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 35
Table 2-16 Estimated O & M Costs (2005) for Facilities Constructed by Genesee County &
Attributed to Oakland County CVTs
Community Proportional
Share Share of O & M
Costs
Highland Township 7.5% $179,000
Independence Township 7.9% $190,000
Oakland Township 15.5% $372,000
Oxford Township 10.3% $248,000
Oxford Village 1.6% $39,000
Waterford Township 27.1% $650,000
White Lake Township 15.7% $377,000
Springfield Township (Partial) 3.0% $73,000
Lake Orion Village 0.6% $15,000
Orion Township 10.7% $257,000
Totals 100% $2,400,000
Table 2-17 Estimated Total O & M Costs for Obtaining Genesee County Raw Water
Community Share of O & M
Costs Share of O & M
Costs Total O & M Costs
Highland Township $326,000 $179,000 $505,000
Independence Township $347,000 $190,000 $537,000
Oakland Township $677,000 $372,000 $1,049,000
Oxford Township $452,000 $248,000 $700,000
Oxford Village $71,000 $39,000 $110,000
Waterford Township $1,184,000 $650,000 $1,834,000
White Lake Township $687,000 $377,000 $1,064,000
Springfield Township (Partial) $133,000 $73,000 $206,000
Lake Orion Village $27,000 $15,000 $42,000
Orion Township $468,000 $257,000 $725,000
Totals $4,372,000 $2,400,000 $6,772,000
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 36
2.6 Alternative 5 – Genesee County to Supply Finished Water
Scenario 19 in Genesee County’s “Preliminary Report Long-Term Water Supply for Genesee
County - Second Draft”, dated January 2006, represents the alternative that would provide
finished water to northern Oakland County. Refer to Figure 2-5 for a schematic layout of the
facilities to be constructed by Genesee County in order to provide finished water to Oakland
County communities. Figure 2-6 illustrates the approximate geographic location of transmission
mains and storage tanks.
Figure 2-5Genesee County Finished Water
Supply AlternativeOakland County Water and Wastewater Master Plan
J:\13647263\Water\Altern.rpt\Fig2-5.mxd
SOURCE - PRELIMINARY REPORT: LONG-TERM WATER SUPPLY FOR GENESEE COUNTY - SECOND DRAFT (JAN 2006)
37
38
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 39
2.6.1 Eligible CVTs
In Alternative 4 – Genesee County to Supply Finished Water, a total of 13 communities in
Oakland County would potentially be supplied finished water from Genesee County. Brandon
Township and Village of Ortonville are included in this alternative where they were excluded in
the raw water option due to their geographic location and proximity to the point of connection
with Genesee County. The Oakland County communities identified as potential customers and
their corresponding water demands are provided in Table 2-18 below.
Table 2-18 Potential Oakland County CVTs to Receive Genesee Finished Water
Community 2035 ADD
(MGD) 2035 MDD
(MGD) Cost Share
Highland Township 2.6 7.4 7.3%
Independence Township 4.1 7.8 7.7%
Oakland Township 5.5 15.3 15.1%
Oxford Township 3.7 10.2 10.1%
Oxford Village 0.7 1.6 1.6%
Brandon Township 0.7 1.8 1.8%
Ortonville Village 0.3 0.7 0.7%
Waterford Township 11.6 26.8 26.4%
White Lake Township 4.8 15.5 15.3%
Springfield Township (Partial) 1.2 3.0 2.9%
Lake Orion Village 0.5 0.6 0.6%
Orion Township 8.3 10.6 10.4%
Totals 44 101.3 100%
2.6.2 Projected Cost of Service
Costs for the Genesee County facilities are estimated based on data presented in the Genesee
County Long-Term Water Supply Report for Scenario 19. The same assumptions and estimates
used to calculate costs in Alternative 3 – Genesee County to Supply Raw Water are utilized in
Alterative 4 – Genesee County to Supply Finished Water.
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 40
Oakland County’s proportional share of capital costs for this alternative is about $810 million in
2005 dollars (source: Preliminary Report, Long-Term Water Supply for Genesee County). The
treated water would be metered and fed directly into a 72” transmission main on the north side of
the county along highway M-15. The finished water transmission main costs are estimated at
$142.2 million (Table 2-19) and the storage costs are estimated at $103.6 million (Table 2-20).
Table 2-21 presents the total project cost ($245.8 million) for facilities to be constructed in
Oakland County, allocated to the communities on a water demand basis. It should be noted that
these costs do not include the costs of local distribution improvements that may be necessary to
distribute water from the county transmission main to customers.
Table 2-22 shows a breakdown of Total Project Cost, ($1,055 million), which includes facilities
to be constructed in Oakland County and Oakland County’s share of the cost for facilities
constructed by Genesee County. Costs are allocated by Community for the Finished Water
Alternative.
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 41
Table 2-19 Finished Water Transmission Main Costs (2005 dollars)
Item Description Unit Quantity Total Unit
Cost Total Cost
1 18" Transmission Main LF 5,486 $141 $770,941
2 18" Road/ waterway crossings LF 1,600 $393 $629,568
3 24" Transmission Main LF 21,823 $197 $4,293,465
4 24" Road/ waterway crossings LF 400 $491 $196,516
5 36" Transmission Main LF 8,134 $287 $2,331,846
6 36" Road/ waterway crossings LF 200 $717 $143,452
7 42" Transmission Main LF 54,805 $333 $18,237,585
8 42" Road/ waterway crossings LF 800 $831 $664,648
9 48" Transmission Main LF 45,307 $509 $23,076,846
10 48" Road/ waterway crossings LF 800 $1,133 $906,576
11 54" Transmission Main LF 47,555 $517 $24,592,883
12 54" Road/ waterway crossings LF 2,000 $1,150 $1,150,000
13 72" Transmission Main LF 21,932 $755 $16,569,254
14 72" Road/ waterway crossings LF 600 $1,888 $1,132,548
Transmission Main
Construction Sub-Total $94,696,128
Construction Contingencies 30% $28,408,838
Engineering, Legal, etc. 20% $18,939,226
Transmission Main Total
Project Cost $142,044,192
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 42
Table 2-20 Finished Water Storage / Pumping Costs (2005)
Item Description Unit Quantity Total Unit
Cost Total Cost
1 Two 1-MG Ground Storage Tanks gal 2,000,000 $ 0.70 $ 1,400,000 2 3-MG Ground Storage Tank gal 3,000,000 $ 0.60 $ 1,800,000 3 Five 5-MG Ground Storage Tanks gal 25,000,000 $ 0.45 $ 11,250,000 4 11-MG Storage Tank gal 11,000,000 $ 0.40 $ 4,400,000 5 2 MGD Booster Station LS 1 $ 533,000.00 $ 533,000 6 6 MGD Booster Station LS 1 $ 1,590,000 $ 1,590,000 7 10 MGD Booster Station LS 3 $ 2,650,000 $ 7,950,000 8 20 MGD Booster Station LS 2 $ 5,260,000 $ 10,520,000 9 50 MGD Booster Station LS 1 $ 11,538,000 $ 11,538,000
10 80 MGD Booster Station LS 1 $ 18,101,760 $ 18,102,000
$ 69,083,000
Construction Contingencies 30% $ 20,725,000
Engineering, Legal, etc. 20% $ 13,817,000
$ 103,625,000 Storage/Pumping Total Project Costs
Storage/Pumping Construction Sub-total
Table 2-21 Allocation of Finished Water Costs by Community
for Facilities Constructed in Oakland County
Community 2035 MDD
(MGD) Percent of
Total Project Share
Costs
Highland Township 7.4 7.3% $17,881,000
Independence Township 7.8 7.7% $19,009,000
Oakland Township 15.3 15.1% $37,119,000
Oxford Township 10.2 10.1% $24,783,000
Oxford Village 1.6 1.6% $3,899,000
Brandon Township 1.8 1.8% $4,366,000
Ortonville Village 0.7 0.7% $1,698,000
Waterford Township 26.8 26.4% $64,943,000
White Lake Township 15.5 15.3% $37,685,000
Springfield Township (Partial)
3.0 3.0% $7,277,000
Lake Orion Village 0.6 0.6% $1,474,000
Orion Township 10.6 10.4% $25,652,000
Totals 101 100% $245,786,000
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 43
Table 2-22 Allocation of Total Project Cost (2005) by Community for Genesee County
Finished Water Alternative
Tables 2-23 through 2-25 present the estimated O & M costs for the proposed improvements
broken down by community by Oakland County/Genesee County projects.
Community
2035 MDD
(MGD)
Cost Share
Facilities Constructed in
Oakland County (Trans/Stor/Pump)
Proportional Share of Genesee
Co. Facilities
Total Project Costs for GCDC Finished Water
Highland Township
7.4 7.3% $17,881,000 $58,864,000 $76,745,000
Independence Township
7.8 7.7% $19,009,000 $62,579,000 $81,588,000
Oakland Township
15.3 15.1% $37,119,000 $122,194,000 $159,313,000
Oxford Township 10.2 10.1% $24,783,000 $81,586,000 $106,369,000
Oxford Village 1.6 1.6% $3,899,000 $12,834,000 $16,733,000
Brandon Township
1.8 1.8% $4,366,000 $14,373,000 $18,739,000
Ortonville Village 0.7 0.7% $1,698,000 $5,589,000 $7,287,000
Waterford Township
26.8 26.4% $64,943,000 $213,791,000 $278,734,000
White Lake Township
15.5 15.3% $37,685,000 $124,061,000 $161,746,000
Springfield Township (Partial)
3.0 3.0% $7,277,000 $23,954,000 $31,231,000
Lake Orion Village
0.6 0.6% $1,474,000 $4,853,000 $6,327,000
Orion Township 10.6 10.4% $25,652,000 $84,447,000 $110,099,000
Totals 101 100% $245,786,000 $809,125,000 $1,054,911,000
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 44
Table 2-23 Potential Oakland County CVTs to Receive Genesee Finished Water
Community Avg. O & M Cost/Mcf Annual O & M
Cost/Mcf
Treatment Plant O & M
Transmission Mains O & M (ADD=23 MGD) $1.00 $1,122,000
Total Amount of O & M Costs $1,122,000
Community Proportional Share Share of O & M
Costs
Highland Township 7.3% $82,000
Independence Township 7.7% $87,000
Oakland Township 15.1% $169,000
Oxford Township 10.1% $113,000
Oxford Village 1.6% $18,000
Brandon Township 1.8% $20,000
Ortonville Village 0.7% $8,000
Waterford Township 26.4% $296,000
White Lake Township 15.3% $172,000
Springfield Township (Partial) 3.0% $33,000
Lake Orion Village 0.6% $7,000
Orion Township 10.4% $117,000
Totals 100% $1,122,000
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 45
Table 2-24 Estimated O & M Costs (2005) Attributed to Oakland County Communities for
Facilities Constructed by Genesee County
Community Proportional Share Share of O & M Costs
Highland Township 7.3% $172,000
Independence Township 7.7% $183,000
Oakland Township 15.1% $357,000
Oxford Township 10.1% $239,000
Oxford Village 1.6% $38,000
Brandon Township 1.8% $42,000
Ortonville Village 0.7% $16,000
Waterford Township 26.4% $625,000
White Lake Township 15.3% $363,000
Springfield Township (Partial) 3.0% $70,000
Lake Orion Village 0.6% $14,000
Orion Township 10.4% $247,000
Totals 100% $2,366,000
Table 2-25 Total Estimated O & M Costs (2005) for Finished Water Alternative
Community O & M for Oakland
Co Facilities O & M for Genesee
Co Facilities Share of O &
M Costs
Highland Township $82,000 $172,000 $254,000
Independence Township $87,000 $183,000 $270,000
Oakland Township $169,000 $357,000 $526,000
Oxford Township $113,000 $239,000 $62,000
Oxford Village $18,000 $38,000 $56,000
Brandon Township $20,000 $42,000 $62,000
Ortonville Village $8,000 $16,000 $24,000
Waterford Township $296,000 $625,000 $921,000
White Lake Township $172,000 $363,000 $535,000
Springfield Township (Partial)
$33,000 $70,000 $103,000
Lake Orion Village $7,000 $14,000 $21,000
Orion Township $117,000 $247,000 $364,000
Totals $1,122,000 $2,366,000 $3,198,000
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 46
2.7 Alternative 6 – Storage Analysis (DWSD Existing Customers)
Most of the Oakland County communities served by DWSD water do not store water within their
local system. These communities rely on DWSD storage and pumping to provide the level of
service necessary to serve their customers. A number of communities initiated studies over the
last few years to evaluate in the feasibility of adding storage to accomplish several objectives.
Objectives included the following:
• Reduce or eliminate the peak hour surcharge, which is built into the DWSD rate
policy
• Provide additional pressure stability in the water distribution system to compensate
for variations at the DWSD master meters
• Provide storage for areas in the local distribution system where maximum day and
peak hour demands reduce pressure below desirable levels regardless of the DWSD
supply pressures
• Provide emergency storage within the community in the event of a loss of service
from DWSD
As part of this Master Plan, the URS project team evaluated 1) the storage need to offset the peak
hour demands and provide fire reserve, 2) the costs for ground storage and re-pumping, and 3)
the additional operation and maintenance expense of adding these facilities. Also, an assessment
was performed of the projected rates for each community with and without peak hour surcharge
to determine whether the added expense of storage can be recovered in the adjusted rate. The rate
calculations and cost-effective analyses are provided in Volume 5 – Financial Analysis.
The storage need is calculated assuming that each community would store the difference
between the max day and peak hour demands for a three hour period and provide a fire reserve of
0.72 MG, which is 3,000 GPM for four hours. The booster station cost estimate is based on
meeting the peak hour demand of the community. A summary of the storage and sizes are
presented in Table 2-26 below.
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 47
Table 2-26 DWSD Customer – Ground Storage / Pumping Estimates
Community
Sto
rag
e
Vo
lum
e (
MG
)
Tan
k C
ost
($M
)1
Bo
oste
r S
tati
on
Co
st
($
M)
To
tal C
ap
ital
Co
st
($M
)
Base C
on
st.
M
ark
- up
50%
($
M)
Lan
d
Acq
uis
itio
n
Co
st
($M
)
To
tal
Am
ou
nt
To
B
e B
on
ded
($
M)
Ad
dit
ion
al
O&
M ($
M/y
r)
To
tal
Cu
mu
lati
ve
Co
st
($M
)1
Auburn Hills 2.0 1.4 4.4 5.8 2.9 0.75 9.45 0.06 144.9
Bloomfield Hills 1.0 0.7 2.4 3.1 1.6 0.75 5.45 0.03 91.0
Bloomfield Twp. 2.0 1.4 10.4 11.8 5.9 0.75 18.45 0.12 382.3
Commerce Twp. 2.5 1.5 7.49 9.0 4.5 0.75 14.25 0.09 313.0
Farmington Hills 4.5 2.0 19.27 21.3 10.6 1.5 33.4 0.21 526.3
Hazel Park 1.0 0.7 1.07 1.7 0.9 0.75 3.35 0.02 35.2
Keego Harbor 1.0 0.7 1.0 1.7 0.9 0.75 3.4 0.02 19.0
Lake Orion Village 1.0 0.7 1.0 1.7 0.85 0.75 3.3 0.02 29.6
Madison Heights 1.5 1.1 3.4 4.5 2.25 0.75 7.5 0.04 102.5
Novi 3.0 1.8 10.65 12.5 6.25 1.5 20.2 0.12 566.4
Orchard Lake 1.0 0.7 1.0 1.7 0.85 0.75 3.3 0.02 23.6
Orion Twp. 2.0 1.4 4.48 5.9 2.95 0.75 9.6 0.06 336.3
Rochester 1.0 0.7 1.0 1.7 0.85 0.75 3.3 0.02 78.4
Rochester Hills 3.5 2.1 12.38 14.5 7.25 1.5 23.2 0.14 477.4
Sylvan Lake 1.0 0.7 1.0 1.7 0.85 0.75 3.3 0.02 14.9
Troy 4.0 2.4 16.3 18.7 9.4 1.5 29.6 0.2 595.6
Walled Lake 1.0 0.7 1.0 1.7 0.85 0.75 3.3 0.02 41.0
West Bloomfield Twp. 3.0 1.8 11.31 13.1 6.6 1.5 21.2 0.13 562.8
Totals 36 22.5 219.1 132.1 66.25 17.25 215.55 1.34 4340.2
Notes:
1. Pontiac, Ferndale, SOCWA, Oak Park, Farmington, and Wixom are not included in the analysis since they presently have storage facilities. Based on the DWSD rate data, only Wixom and SOCWA have peak hour factors of 1.0.
2. Costs are presented in 2005 dollars; ($M) is millions. 3. Base Construction Mark-up includes 20% for engineering, legal, etc. and 30% in construction contingencies. 4. Land Acquisition Costs assumed to be $250,000 per acre 5. O&M costs assumed to be 1% of capital costs
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 48
2.8 Warren – St. Clair Shores Water Supply Alternative
In December 2004, phase 1 of a water system study to determine the feasibility of constructing a
new water system to serve a number of communities in Oakland, Macomb, and Wayne Counties.
The communities within the study area are depicted in Figure 2-6 and listed in Table 2-27.
Three primary water alternatives were developed as part of the Phase 1 study. The baseline
alternative included the construction of a new WTP on Lake St. Clair and infrastructure to
provide a maximum day capacity of 292 MGD to the entire planning area. The estimated project
cost for that alternative was $1.425 billion.
The second alternative evaluated a smaller service area (exclusion of Oakland County). The
design maximum day demand for this alternative was 73 MGD with a total project cost of $363
million. A comparison of this alternative to the baseline alternative clearly demonstrates the
significant cost increase when attempting to provide a new supply to the service area
communities within Oakland County.
The third alternative used existing available capacities (19 MGD total) from the Highland Park,
Mount Clemens, and Grosse Pointe Farms WTPs. This reduced the size of a new WTP from 73
MGD to 54 MGD, resulting in a project cost of $310 million.
The projected costs of a new water supply with any of the above scenarios exceeded the
anticipated future DWSD wholesale water costs using the projected rate increases in the DWSD
CWMP. It was concluded by the project’s steering committee that further study of the above
alternatives was not warranted. As such, this alternative was not included in Volume 5 – The
Financial Analysis and is only briefly explained in Volume 1 – The Executive Summary.
Figure 2-7
49
Water Alternatives Development
Volume 4 – Alternatives Analysis Report 50
Table 2-27 Communities in Warren-St. Clair Shores Water Supply Alternative
Oakland County Macomb County Wayne County
Bloomfield Township Center Line Grosse Pointe Shores
Bloomfield Hills Eastpointe Grosse Point Township
Franklin Village Fraser Grosse Point Woods
Madison Heights Grosse Pointe Shores Harper Woods
Oak Park Lake Township
Pontiac Roseville
SOCWA (All 10 CVTs) St. Clair Shores
Southfield Township Warren
Troy
Hazel Park
Ferndale
Royal Oak Township
Discussion of Genesee County Water Supply Alternatives - Alternatives 4 and 5
Volume 4 – Alternatives Analysis Report 51
3.0 Discussion of Genesee County Water Supply Alternatives -
Alternatives 4 and 5
Each CVT’s water infrastructure needs and alternatives are unique. For that reason, Appendix A
of Volume 1 – Executive Summary, presents water alternatives by CVT. This section presents a
discussion of the Genesee County water supply alternatives.
3.1 Comparison of Genesee County Water Supply Alternatives
Table 3-1 provides a side-by-side comparison of the Raw Water versus Finished Water
alternatives. It can be seen that the capital investment is approximately the same $1.1 billion,
however, the annual O & M cost for the Finished Water alternative is about half that of the Raw
Water alternative.
It should be noted that the costs developed in this report are based on all communities
participating in the project. Should one or more of the communities choose not to participate,
then the share of the project costs for the remaining communities will increase proportionally.
Table 3-1 Summary of Raw/Finished Water Supply Alternatives from Genesee County
Capital Costs (2005) Raw Water Alternative
Finished Water Alternative
OAKLAND COUNTY FACILITIES:
Raw Water Reservoir $188,067,000
Treatment (99 MGD) $297,000,000
Transmission Mains $129,366,000 $142,160,000
Finished Water Storage $102,575,000 $103,625,000
Sub-Total $717,008,000 $245,785,000
GENESEE COUNTY FACILITIES: $431,895,000 $809,125,000
Total Capital Costs $1,148,903,000 $1,054,910,000
O & M COSTS (2005)
OAKLAND COUNTY FACILITIES: $4,372,000 $1,120,000
GENESEE COUNTY FACILITIES: $2,400,000 $2,370,000
Total O & M Costs $6,772,000 $3,490,000
Discussion of Genesee County Water Supply Alternatives - Alternatives 4 and 5
Volume 4 – Alternatives Analysis Report 52
3.2 Advantages and Disadvantages of the Genesee County Water Supply
Alternatives
Some of the advantages and disadvantages to a Lake Huron (via Genesee County) water supply
are listed below:
Advantages
• Surface water supply typically requires less treatment (no softening) than a
groundwater supply.
• Regional facilities generally allow smaller communities to take advantage of
economies of scale where smaller facilities usually have a higher per unit cost, which
depends greatly on population density and amount of transmission mains necessary to
get the finished water to the customer.
• There may be a potential for lower end-user costs compared to projected DWSD
rates.
Disadvantages
• Regional facilities usually require a significant customer base to be a cost effective
alternative. Many of the northern Oakland County communities’ local land use plans
require low-density (5-10 acre lots) development, which makes distribution costs
significantly higher.
• DWSD already has significant water infrastructure in the Oakland County.
• Genesee County’s present implementation schedule requires community
commitments in 2006, design in 2007, and construction beginning in 2010. This fast-
track schedule may not give some communities time to make informed economic
decisions.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 53
4.0 Wastewater Alternatives Development
Reviews are provided for each of the sanitary systems. Alternatives for flow exchange and
treatment optimization are developed where feasible to meet projected needs. Note that any
surcharging of the system is unacceptable by current design standards.
4.1 Alternative 1 – No Change
Unlike the water “No Change” alternative, which is unique to the circumstances of each
individual CVT, the wastewater “No Change” alternative can be organized by the Sewage
Disposal System (SDS) or Wastewater Treatment Plant (WWTP). However, within a SDS the
impacts of the “No Change” alternative may vary by community. These impacts are explored in
Appendix A of Volume 1 – The Executive Summary.
The URS project team endeavored to present the most up-to-date information available.
Availability of information combined with the inevitable need to document findings, results in a
snapshot-in-time deliverable. With few exceptions, the information included herein was current
as of the Spring of 2007.
4.1.1 Clinton-Oakland SDS (COSDS)
4.1.1.1 Member CVTs
Table 4-1 lists the CVTs in the COSDS with their Purchased Capacity and their Maximum
Assignment Capacity (MAC) when applicable.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 54
Table 4-1 CVTs in the COSDS
4.1.1.2 Background
The needs of the COSDS are related to the contractual discharge capacities of the individual
member communities and overall system conveyance of future flows. Previous studies (Clinton
Oakland Sewage Disposal System Interceptor Relief Study, 1991; Clinton Oakland SDS System
Analysis Report, 1994; and DWSD Wastewater Master Plan, 2003) stated that the design
capacities of certain sections of the Clinton-Oakland Interceptor are not capable of conveying the
allowable purchased capacity flows under open channel flow conditions. As a result,
surcharging is expected in these sections when flows approach purchased capacity. The 1996
Clinton-Oakland SDS Management Agreement established higher thresholds for community
discharges into the Clinton-Oakland Interceptor. These increased discharge thresholds, called
maximum assignment capacities, allow the respective communities to collectively discharge an
additional 29 MGD into the system. This is 55% more flow in the COSDS than was allowed
prior to the 1996 agreement.
The COSDS was modeled as part of the 1991 COSDS Interceptor Relief Study. This study
identified approximately 8 miles of the Clinton-Oakland Interceptor (Figure 4-1) that needed
Community Purchase
Capacity (MGD) Maximum Assignment
Capacity (MGD)
Auburn Hills 5.95 9.69
Independence Twp & Clarkston
5.69 6.79
Lake Angelus - -
Lake Orion Village 1.19 -
Oakland Township 3.63 -
Orion Township 5.71 -
Oxford Township 4.35 -
Oxford Village 2.07 -
Rochester Hills 10.69 24.24
Waterford Township 24.21 29.08
West Bloomfield Township 3.31 5.82
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 55
relief sewers based on possible surcharging in the pipes during various design storm events. This
study also identified sections of the interceptor where ADDF is less than the sum of the
purchased capacities. These sections could act as bottlenecks in the system and cause
surcharging when peak flows approach purchased capacity. The 2035 flow projections discussed
in Volume 3 - The Needs Assessment Report of this Master Plan indicate that seven of the
COSDS communities would exceed purchased capacity during peak flows, resulting in possible
surcharging of the system. The additional 29 MGD of flow that can be contractually discharged
into the system as per the 1996 COSDS Management Agreement potentially exacerbates the
problem. Also, the addition of any new flows from outside the current COSDS service boundary
would increase the need for system improvements.
4.1.1.3 Impact of the No Change Alternative
This alternative means taking no action beyond what is currently being done. This includes:
• Continued monitoring of the system,
• Flow management, and
• I/I reduction efforts by OCDC and the system’s member communities.
The potential results of “No Change” are as follows:
• Most communities will approach or exceed purchased capacity during projected 2035
peak flows.
• Auburn Hills and West Bloomfield Township will approach or exceed their
maximum assignment capacity during 2035 peak hour flows.
• Certain sections of the Clinton-Oakland interceptor will continue to surcharge when
peak flows approach purchased capacity.
• The COSDS appears to have more than enough in-system storage to attenuate peak
flows such that the COSDS discharge at the County line will be within the contractual
limits of the agreement with DWSD.
See Appendix A of Volume 1 – Executive Summary for a community-by-community of analysis
of wastewater alternatives.
Metered Connectionwith DWSD (Oakland Arm)
Metered Connectionwith DWSD (Avon Arm)
CLINTON
-OAKLANDINTERCEPTOR
CLIN
TON
-OAK
LANDINTE
RCEPTOR
MSU-OINTERCEPTOR
PAINTCREEKINTERCEPTOR
SARGENTCREEKA
R
M
STON
YCREEK
ARM
Elizabeth Lake Pump Station
Troy
Pontiac
Orion Township
Rochester Hills
Oxford Township Addison Township
Oakland Township
Brandon Township
Waterford Township
Independence Township
Auburn Hills
Bloomfield Township
West Bloomfield Township
Groveland Township
Springfield Township
White Lake Township
Commerce Township
Rochester
Bloomfield Hills
Orchard Lake
Birmingham
Lake Angelus
Oxford Village
Walled Lake
Wolverine Lake Village
Lake Orion Village
Sylvan Lake
Leonard Village
Ortonville Village
Clarkston
Keego Harbor
Clawson
0 4 82 Miles
Legend
Sections of Interceptor Requiring Parallel Relief*
OCDC Interceptor Sewer
Force Main
Pump Station
Figure 4-1Clinton - Oakland SDS
Limits of Proposed Relief Sewer Construction
Oakland County Water and Wastewater Master Plan
Oakland Co.
Wayne Co.
Macomb Co.
Lapeer Co.Genesee Co.
Livingston Co.
Washtenaw Co.
St. Clair Co.
J:\1
364
7263
\Wa
ter\
Alte
rn.R
pt\F
ig3
-1.m
xd
* Per the 1991 Relief Study
56
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 57
4.1.2 Huron-Rouge SDS (HRSDS)
4.1.2.1 Member CVTs
The HRSDS is made up of only one member community (City of Novi) actually discharging
flow to the system. Two other CVTs (Northville and Novi Twp.) lie within the HRSDS service
boundary, but do not discharge into the system. The City of Northville discharges to the
interceptor in Wayne County and Novi Township is not sewered.
4.1.2.2 Background
The needs of the HRSDS are related to the contracted discharge capacity allotted to the City of
Novi. The original 1962 agreement between Oakland County and Wayne County set the
discharge limit at 2.58 MGD (4 CFS), but the current agreement is for 13.24 MGD. The City of
Novi currently discharges 4.36 MGD average daily flow with a future average daily flow of 7.77
MGD.
4.1.2.3 Impact of the No Change Alternative
The result of doing nothing is that Novi will continue to exceed contract discharge capacity
during peak flows. However there seems to be no mechanism in the contract documents to
enforce this discharge capacity and there has not been a problem to date. As such, the only
identified need for the HRSDS (City of Novi) is to reconcile the original contract with the actual
current discharge.
4.1.3 Evergreen-Farmington SDS (EFSDS)
4.1.3.1 Member CVTs
Table 4-2 lists the CVTs in the EFSDS with their Town Outlet Capacity (TOC).
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 58
Table 4-2 CVTs in the EFSDS
4.1.3.2 Background
As discussed in the Volume 3 – The Needs Assessment Report, the Oakland County Drain
Commissioner (OCDC) and the Michigan Department of Environmental Quality (MDEQ),
entered into a second Amended Consent Order (ACO) in December 7, 2004. The ACO outlined
several projects that the County is committed to complete. OCDC also has a plan to demonstrate
that Clean Water Act goals can be met through a program with substantially lower costs than
required by the conventional MDEQ approach. The program evaluates all aspects of SSO
treatment, infiltration/inflow (I/I) reduction, and system capacity expansion. As part of the
demonstration approach that OCDC is pursuing and the second ACO between OCDC and
MDEQ, OCDC recently completed hydrologic and hydraulic modeling analysis to enable OCDC
and the Communities to better understand the operation of the system, identify the critical
Community Town Outlet Capacity
(MGD)
Auburn Hills 1.11
Beverly Hills Village 5.62
Bingham Farms Village 0.70
Birmingham 4.51
Bloomfield Hills 2.57
Bloomfield Township 13.63
Farmington 0.87
Farmington Hills 30.29
Franklin Village 0.95
Keego Harbor 1.13
Lathrup Village 2.17
Orchard Lake 0.89
Southfield 38.97
Troy 5.51
West Bloomfield Township 17.71
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 59
constraints of the system, and determine how to optimize the operation of the system. Thus, the
development of alternatives is deferred to that Contract and is not repeated herein.
Other improvements that are outlined in the ACO include:
1. A connection from the Farmington interceptor (at the Walnut #1 Pumping Station) to
the Evergreen interceptor allows the transfer of up to 14 CFS of wet weather sanitary
flow. As part of this project, the County modified the regulators that control flow
from the Acacia Park, Bloomfield Village, and Birmingham Retention Treatment
Basins (RTB) during wet weather to the Evergreen interceptor and replace this
available capacity amounting to 14 CFS in the Evergreen interceptor with excess
separate sanitary flow.
2. Removal of four siphons crossing the Edwards Drain in West Bloomfield Township,
and replacement of the sanitary sewer conveyance system.
The County is considering a wet weather connection from the Evergreen Farmington interceptor
system to the Bloomfield Village RTB (subject to Part 41 permit review). As part of this project,
storm sewer relief will be provided to offset the increase in wet weather sanitary flow to the
RTB.
4.1.3.3 Impact of the No Change Alternative
The impact of the No Change Alternative varies by community. See Appendix A of Volume 1 –
Executive Summary for a community-by-community of analysis of wastewater alternatives.
4.1.4 George W. Kuhn SDS (GWKSDS)
4.1.4.1 Member CVTs
Table 4-3 lists the CVTs in the GWKSDS.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 60
Table 4-3 CVTs in the GWKSDS
4.1.4.2 Background
The George W. Kuhn (GWK) Sanitary Disposal System (SDS) is a combined sanitary and storm
water system. The average daily flow during dry weather is approximately 46 MGD. However,
peak flows can be 100 times larger than the average daily dry weather flow. The GWKSDS can
send up to 170 MGD (260 CFS) to DWSD under the current contract. The GWK retention
treatment facility (RTF) is designed to control the combined sewer overflows for the 10 year, 1
hour storm, in accordance with MDEQ requirements, assuming an outlet capacity of 260 CFS to
DWSD. Due to the large difference between the average peak flows and the contract flow
limitations, approximately 10 to 12 overflows occur each year.
A requirement of the NPDES permit re-issued in 1998 was to make improvements to the GWK
RTF. These improvements included the construction of new storage, screening, and disinfection
downstream from the existing inlet structure. The new structure adds 30.7 million gallons of
storage, increasing the storage volume upstream of the RTF from 32 million gallons to 64.9
million gallons. The total system storage increased from 94 million gallons to 122 million
gallons. The construction of a new dewatering pumping station with a force main discharging to
the Twelve Mile Road Interceptor allows the contractual limit of 260 CFS to be achieved early in
a storm event and maximize the amount of flow that can be stored and treated.
The population in the GWKSDS is projected to decrease in the future. The area is built out,
allowing for few growth opportunities.
Community Community
Berkley Madison Heights
Beverly Hills Village Oak Park
Birmingham Pleasant Ridge
Clawson Royal Oak
Ferndale Royal Oak Township
Hazel Park Southfield
Huntington Woods Troy
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 61
Alternate treatment strategies for the wastewater generated in the Twelve Towns area were
investigated. A report prepared by Hubbell, Roth & Clark, Inc. (HRC) in 1999 investigated the
possibility of constructing a new 45 MGD WWTP that would discharge to the Red Run Drain.
Piping modifications would be needed to direct the flow to the new WWTP. The cost for the
WWTP, pump stations, and force main would be approximately $711 million in 1999 dollars.
The WWTP would discharge in the vicinity of the GWK RTF. The Red Run Drain in this area
has the potential of having relatively low flows during the summer, which can lead to more
restrictive permit limits. This option is not proposed to be pursued due to the high cost, probable
restrictive permit limits, and limited need for additional capacity.
4.1.4.3 Impact of the No Change Alternative
The total system storage capacity is 121.8 million gallons. Up to 170 MGD continues to be
treated at the DWSD WWTP. Due to the decreasing population, capacity in this area is not a
problem except during wet weather. See Appendix A of Volume 1 – Executive Summary for a
community-by-community of analysis of wastewater alternatives.
4.1.5 Commerce-White Lake SDS (CWLSDS)
4.1.5.1 Member CVTs
Commerce-White Lake WWTP currently service portions of Commerce Township, White Lake,
the City of Novi, and the Village of Wolverine Lake.
4.1.5.2 Background
The Commerce-White Lake WWTP is owned by Commerce Township. It is made up of two
wastewater treatment plants, the “East” and the “North” plants. Currently, the North plant is
designed to treat an average daily flow of 2.0 MGD, and the East plant 1.0 MGD. The East plant
is currently not in service, and would need repairs before being brought back into service. There
are currently no plans to return the East plant to service. Commerce Township has contracted
with an engineering firm to design an expansion to the North plant, but the size of this expansion
has not been formalized.
The Village of Wolverine Lake has an agreement with Commerce Township for a capacity of
0.535 MGD. White Lake has an agreement with Commerce Township to be served by the lesser
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 62
of 3.64 MGD or 11,546 REUs, for treating the wastewater from the densest areas of the
Township in the southern half of the Township. White Lake’s contribution to the 1.5 MGD
treated in the WWTP during 2005, was approximately 0.38 MGD. In 1991, Novi exchanged
2,000 REUs (about 0.67 MGD) in the Walled Lake-Novi WWTP for 2,000 units from
Commerce. Total WWTP flow in 2004 was 1.5 MGD, of which approximately 0.9 MGD was
contributed by Commerce Township. Figure 4-2 summarizes the flows and contracts for the
Commerce-White Lake WWTP.
As can be seen in Figure 4-2, the current capacity of the Commerce-White Lake WWTP is less
than the sum of its service contracts (2.0 MGD < 4.85 MGD). In 2035 the projected Average
Dry Weather Flow (ADWF) for Commerce and its contract communities (6.97 MGD) is less
than ultimate plant capacity of 8.5 MGD as determined by the Michigan Department of
Environmental Quality (MDEQ) National Pollutant Discharge Elimination System (NPDES)
permit. The current plans to expand the North WWTP range from 5 MGD to 8.5 MGD
depending on the expected input flow from neighboring communities, specifically White Lake
Township.
Figure 4-2 Comparison of Commerce-White Lake WWTP Capacities and Contracts
0.9
2.12
3.64
3.64
0.67
0.67
0.54
0.54
1.52.0
8.5
1.7
0
1
2
3
4
5
6
7
8
9
2005
Flows/Contracts
2005 ADWF 2005 ADDF Design
Capacity
Projected 2035
Flow (Based on
Actual)
Projected 2035
Flows/Contracts
Ultimate Capacity
Year and Year Capacity
Flo
w a
nd
Co
ntr
acts
(M
GD
)
2035 Projected Flow
Ultimate Capacity
2005 Design Capacity
2005 Actual Flow
Wolverine Lake Contract Capacity
Novi Contract Capacity
White Lake Contract Capacity
Commerce Flow
Note: 1. Temporary transfer of 270 REUs from the Commerce WWTP to Walled Lake-Novi WWTP (February 2006) for Wolverine Lake not shown.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 63
4.1.5.3 Impact of the No Change Alternative
This alternative assumes Commerce will carry out its plans to expand the North WWTP. The
expanded capacity is yet to be determined. It is premature to discuss cost of services since it
depends on the size of the expansion. An expanded WWTP could serve the needs of Commerce
Twp., and satisfy the service contracts with White Lake Twp., the City of Novi, and Wolverine
Lake Village.
4.1.6 Walled Lake/Novi SDS (WLNSDS)
4.1.6.1 Member CVTs
The Walled Lake-Novi WWTP serves Walled Lake and portions of the City of Novi, Commerce,
and (temporarily) Wolverine Lake. It has an interchange agreement with Commerce to receive
flow from the Commerce-White Lake WWTP.
4.1.6.2 Background
The Walled Lake-Novi WWTP is owned and operated by OCDC. Both Walled Lake and Novi
originally had an agreement with OCDC for approximately 0.95 MGD each of the Walled
Lake/Novi WWTP. In 1991 this agreement was amended to provide 1.32 MGD for Walled Lake
and 1.21 MGD to Novi. Also in 1991, Novi exchanged 2,000 units in the Commerce-White
Lake WWTP for 2,000 units in the Walled Lake-Novi WWTP. Figure 4-3 summarizes the
contracts and capacities of the Walled Lake-Novi WWTP.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 64
Figure 4-3 Walled Lake/Novi WWTP Capacities and Contracts
4.05
1.65
4.301.21
3.37
1.38
3.58
1.28
1.423.50
9.10
1.01
0.58
1.45
0.390.23
0.65
0.26
0.69
0.003
0.01
0.003
0.01
0.09
0
2
4
6
8
10
12
Contracts Estimated 2005
ADWF
Estimated 2005
PHF
ADDF Design
Capacity
PHF Design
Capacity
Projected 2035
ADWF
Projected 2035
PHF
Year and Year Capacity
Flo
w a
nd
Co
ntr
acts
(M
GD
)
Novi Walled LakeNovi Contract Walled Lake ContractDesign Capacity Additional Flow from New Sewers in Walled LakeCommerce-White-Lake SDS Commerce-White-Lake SDS ContractWolverine Lake Wolverine Lake Contract
Note: 1. For the majority of this Master Plan 2005 is considered “current’, however for Walled Lake-Novi WWTP flows 2007 data was available and used.
4.1.6.3 Impact of the No Change Alternative
The No Change Alternative is a viable alternative for the WLNSDS and its member
communities. Based on REUs the plant is nearly at capacity (approximately 86% of the plant’s
REUs are connected). However, flows at the plant are not near capacity. This suggests that per
capita flow may be less than the 337 gallon-per-day-per-REU currently used. Furthermore, a
stress test may reveal that the plant can process flow rates greater than its design.
The City of Novi may negotiate for the option to divert flow to the HRSDS and thereby make
capacity available in the Walled Lake-Novi WWTP.
4.1.7 Pontiac WWTP
4.1.7.1 Member CVTs
Currently, the Pontiac WWTP serves the City of Pontiac and Sylvan Lake.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 65
4.1.7.2 Background
Pontiac has two wastewater treatment plants, the Auburn Plant and the East Boulevard Plant.
Recent evaluations by others of these plants resulted in the recommendation to route current dry
weather flow from the East Plant to the Auburn Plant and use the East Plant only for wet weather
flow equalization.
It was recommended that the excess flow receive primary treatment and be stored in equalization
tanks until it can be returned to the Auburn Plant for full treatment. Flows exceeding the
capacity of the equalization tank would be discharged to the Clinton River. As of this writing,
however, the recommended conversion has not been implemented.
The reported design capacities for the existing Auburn WWTP are as follows:
Average Daily Design Flow (ADDF): 16.9 MGD
Peak Hour Flow (PHF): 20.5 MGD
The reported design capacities for the existing East Boulevard WWTP are as follows:
Average Daily Design Flow (ADDF): 4.7 MGD
Peak Hour Flow (PHF): 9.5 MGD
The population projections estimate that there will be an increase of approximately 10% in
Pontiac’s population through 2035. Applying this percentage to the current combined average
daily flow of 9.4 MGD, it is expected that the average daily flow will increase by approximately
0.9 MGD to 10.3 MGD.
Using a peaking factor of 2.1 (from Ten States Standards Figure 1, ratio of peak hourly/average
daily flow) will project the total future combined peak hour flow to be approximately 21.6 MGD.
The projected 2035 combined average daily flow and the peak hour flow can be accommodated
by the existing Auburn plant. Figure 4-4 graphically depicts the flows and capacities of the
Pontiac WWTP.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 66
Figure 4-4 Pontiac WWTP
16.9
4.7
9.5
9.4
18.7
10.30
21.6
12.2
11.3
11.3
8.4
20.5
0
5
10
15
20
25
30
35
2005 ADWF 2005 ADDF
Design Capacity
2005 PHF 2005 PHF Design
Capacity
2035 ADWF 2035 PHF
Year and Year Capacity
Flo
ws
(M
GD
)
Auburn WWTP East Blvd. WWTP 2005 Combined Actual ADWF
2005 Estimated Combined PHF 2035 Estmated Combined ADWF 2035 Estimated Combined PHF
Excess Capacity
4.1.7.3 Impact of the No Change Alternative
The “No Change” alternative is a viable option for the City of Pontiac, as there is adequate spare
capacity.
4.1.8 Milford Village WWTP
4.1.8.1 Member CVTs
The Milford Village WWTP serves the Village of Milford and Camp Dearborn.
4.1.8.2 Background
The Milford Village WWTP is designed for an average daily wastewater flow of 1.04 MGD. The
current average daily flow is approximately 0.7 MGD, expected to increase to 0.8 MGD over the
study period. Figure 4-5 graphically depicts the flows and capacities of the Milford WWTP.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 67
Figure 4-5 Milford Village WWTP
0.6250.68
0.075
0.075
0.7
1.04
0
0.2
0.4
0.6
0.8
1
1.2
2005 Flows/Contracts 2005 ADWF 2005 ADDF Design
Capacity
Projected 2035
Flows/Contracts
Year and Year Capacity
Flo
w a
nd
Co
ntr
ac
ts (
MG
D)
2005 Design Capacity
2005 Actual Flow
Camp Dearborn Contract
Milford Village
4.1.8.3 Impact of the No Change Alternative
The anticipated future average daily flow is expected to be below the design average daily flow.
The “No Change” alternative therefore, is a feasible option for Milford Village.
4.1.9 South Lyon WWTP
4.1.9.1 Member CVTs
The South Lyon WWTP serves the City of South Lyon.
4.1.9.2 Background
The newly upgraded plant’s capacity exceeds current and projected demands. Figure 4-6
graphically depicts the excess capacity.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 68
Figure 4-6 South Lyon WWTP
2.5
1.0
2.7
1.1
3.01.5
4.2
1.4
3.9
6.9
0
1
2
3
4
5
6
7
8
2005 ADWF ADDF Design
Capacity
2005 PHF PHF Design
Capacity
2035 ADWF 2035 PHF
Year and Year Capacity
Flo
ws
(M
GD
)
South Lyon WWTP Capacity 2005 Estimated ADF 2005 Estimated PHF
2035 Estimated ADF 2035 Estimated PHF Excess Capacity
4.1.9.3 Impact of the No Change Alternative
The “No Change” alternative is a viable option for the City of South Lyon, as there is adequate
spare capacity.
4.1.10 Wixom WWTP
4.1.10.1 Member CVTs
The Wixom WWTP serves the City of Wixom and recently contracted with Milford for 1.0
MGD of treatment capacity.
4.1.10.2 Background
The current Wixom WWTP capacity is 4 MGD. Plans for expansion have been put on hold until
the effects of the loss of the Ford plant’s flow can be understood. Ford contributed
approximately 0.35 MGD to the ADWF. The 2005 Average Dry Weather Flow (ADWF) is 2.2
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 69
MGD (including Ford); this leaves an excess capacity of approximately 1.8 MGD. Figure 4-7
summarizes the current and projected dry weather flows for the Wixom WWTP.
Figure 4-7 Wixom WWTP
4.0
2.2
1.0
3.7
1.8
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
ADDF Design Capacity 2005 ADWF Estimated 2035 ADWFYear and Year Capacity
Flo
ws (
MG
D)
Wixom WWTP Capacity 2005 Estimated ADF 2035 Estimated ADF
Milford Contract Excess Capacity
4.1.10.3 Impact of the No Change Alternative
The City of Wixom is committed to expand their plant if it is necessary. The “No Change”
alternative for the Wixom WWTP, means holding to that commitment. The recent
decommissioning of the local Ford plant, has brought the need for expansion into question.
4.1.11 Lyon Township WWTP
4.1.11.1 Member CVTs
The Lyon Twp. WWTP serves Lyon Twp.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 70
4.1.11.2 Background
The preliminary Sanitary Sewer System and Future Expansion Plans issued August 26, 2004
shows an aggressive plan to sewer the Township. It anticipates an expansion of the existing
groundwater discharge plant to an intermediate average daily flow capacity of 2.0 MGD, and an
ultimate average daily flow capacity capable of treating the projected build out ADWF of 4.24
MGD. The original design capacity was 1.0 MGD, while the plant is currently permitted for 3.0
MGD. MDEQ re-rated the two 0.5 MGD biological treatment units to a total design capacity of
0.75 MGD. Figure 4-8 summarizes the flows and capacities for the Lyon Township WWTP.
Figure 4-8 Lyon Township WWTP
0.75
0.26
4.24
0.49
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
2005 ADWF ADDF Design Capacity 2035 ADWF
Year and Year Capacity
Flo
ws (
MG
D)
Lyon Twp. WWTP Capacity 2005 Estimated ADF 2035 Estimated ADF Excess Capacity
4.1.11.3 Impact of the No Change Alternative
The “No Change” alternative assumes continued use existing WWTP without any upgrades and
all growth will utilize on-site private septic. Lyon Township determined that this is neither the
likely nor the intended option. The Township is aggressively adding sewers and the community
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 71
is actively pursuing upgrades to the WWTP. This alternative does not address any of the
Township’s needs.
4.1.12 Holly Village WWTP
4.1.12.1 Member CVTs
The Holly Village WWTP serves Holly Village and the Pulte development in Holly Township.
The development is known as the Silverman property.
4.1.12.2 Background
The WWTP was recently upgraded and expanded to 1.8 MGD. Figure 4-9 summarizes the flows
and capacities Holly Village WWTP.
Figure 4-9 Holly Village WWTP
1.80
0.32
0.320.14
1.351.49
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
2
2005 ADF ADDF Design Capacity 2035 ADF
Year and Year Capacity
Flo
ws (
MG
D)
Holly Village WWTP Capacity 2005 Estimated ADF 2035 Estimated ADF
Holly Twp. Contract Excess Capacity
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 72
4.1.12.3 Impact of the No Change Alternative
The “No Change” alternative is a feasible option for Holly Village, since the projected average
daily flow is equal to the plant capacity. Holly Village may want to consider another upgrade
when the plant reaches 80% capacity.
4.1.13 Highland Township WWTP
4.1.13.1 Member CVTs
The Highland Township WWTP will serve portions of Highland Township.
4.1.13.2 Background
The recently completed Sewer master plan indicates an aggressive plan to sewer the most
densely populated areas of the Township, and treat the sewage in a new groundwater discharge
plant located in the north-west corner of the Township. The WWTP is associated with and 850-
acre proposed residential development known as the Levy property. The Township negotiated
with developers to connect to their water and wastewater systems. Two resolutions will build
approximately four miles of sanitary sewer along Milford Road as Special Assessment Districts
(SADs). Highland Township has a Sewer master plan that aggressively sewer the densely
populated areas of the Township. Highland is pursuing the construction of a local 2.18 MGD
groundwater discharge WWTP with an estimated cost of $17.4 million. Annual operating costs
are estimated at $1.26 million.
4.1.13.3 Impact of the No Change Alternative
This alternative assumes Highland will carry out its plans to construct a WWTP and continue to
progress with the installation of sewage infrastructure. The proposed 2.18 MGD (average daily
flow) groundwater water discharge wastewater treatment plant is estimated to cost $17.4 million
(engineer’s estimate escalated to May 2005 dollars). The annual operating cost, assuming 100%
tie-in at startup of the plant, is estimated at $1.26 million or $11.90/Mcf. It is estimated that
approximately 28.5 acres of land will be required. Portions of the Township will still remain on
individual systems.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 73
4.2 Alternative 2 – Construction of Relief Sewers
4.2.1 Eligible CVTs
This alternative affects the COSDS and its member communities.
4.2.2 Description
This alternative proposes construction of relief sewers for the COSDS with continued discharge
to DWSD, see Figure 4-1. For the purposes of developing this alternative, this Master Plan
acknowledges that there were improvements in flow management and reductions in extraneous
flow since 1991, but there are segments of the system that will continue to surcharge when peak
flows approach purchased capacity. The question as to how much surcharging will occur should
be further studied. It is beyond the scope of this Master Plan to examine such a complex system
as the COSDS in sufficient detail to contradict the findings of previous studies and/or establish
the requirement for new relief sewers. Therefore, this Master Plan will defer to the findings of
the modeling effort undertaken in the 1991 study as a “worst case” scenario. The 1991 report’s
findings included the following:
1. The recommended construction of relief sewers to convey peak wet weather flows out
of the system without surcharging the interceptor, or;
2. The construction of local storage structures to detain peak flows and release them at a
lower rate.
Table 4-4 shows the total project costs for the construction of relief sewers as detailed in the
1991 study. The construction of local storage basins in place of relief sewers was not a feasible
alternative due to the high cost. Construction costs for local storage at or near the major COSDS
connections were estimated to be $23 million in 1991 dollars. Including project contingencies,
this is over $50 million in total project costs in 2005 dollars.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 74
Table 4-4 Capital Cost Summary for Clinton-Oakland Interceptor Relief Sewers
"Refined" Parallel Pipe Size (inches)
Length (ft) Unit Cost*
(1991 Dollars/ ft) Total cost*
(1991 Dollars)
12 20522 $87 $1,785,400
18 20028 $115 $2,303,200
42 929 $140 $130,100
Construction Subtotal(1991Dollars)= $4,218,700
Construction Subtotal(2005Dollars)= $6,500,000
20%Eng.,Legal,Admin.= $1,300,000
30%ConstructionContingencies= $1,950,000
Total Capital Cost(2005Dollars)= $9,750,000
4.3 Alternative 3 – Diversion of 8 MGD of Flow to the Pontiac WWTP
4.3.1 Eligible CVTs
This alternative affects the COSDS and its member communities.
4.3.2 Description
This alternative involves intercepting flow in the Clinton-Oakland Interceptor at a location near
Perry Street and diverting 8 MGD to the Pontiac WWTP through approximately 12,000 L.F. of
48-inch diameter gravity sewer line within the existing Grand Trunk Western Railroad
(GTWRR) property. This conveyance system was examined in detail in the technical
memorandum entitled “Technical Feasibility of Satellite Treatment” that is part of the DWSD
Wastewater Master Plan (2003). The area tributary to the point of diversion is illustrated in
Figure 4-10. The 2005 and 2035 average daily flows (ADF) at the point of interception are 15
MGD and 20 MGD, respectively.
Troy
Pontiac
Orion Township
Rochester Hills
Oxford Township Addison Township
Oakland Township
Brandon Township
Springfield Township
Waterford Township
Groveland Township
White Lake Township
Independence Township
Auburn Hills
Commerce TownshipBloomfield Township
West Bloomfield Township
Rose Township
Holly Township
Milford Township
Highland Township
Wixom
Rochester
Bloomfield Hills
Orchard Lake
Birmingham
Milford Village
Lake Angelus
Walled Lake
Oxford Village
Holly Village
Wolverine Lake Village
Lake Orion Village
Sylvan Lake
Leonard Village
Ortonville Village
Clawson
Clarkston
Keego Harbor
0 4 82 Miles
LegendExpanded Pontiac WWTP Service Area
Area Remaining in COSDS with DWSD Discharge
Pontiac WWTP
Interceptor to Pontiac WWTP - Proposed
Elizabeth Lake Pump Station
Existing Interceptor Sewer
Existing Force Main
Oakland Co.
St. Clair Co.
Wayne Co.
Lapeer Co.
Genesee Co.
Washtenaw Co.
Macomb Co.Livingston Co.
Figure 4-10
Diversion of 8 MGD and 20 MGD of Flow
to Pontiac WWTP
Oakland County Water and Wastewater Master Plan
J:\1
364
7263
\Wa
ter\
Alte
rn.R
pt\F
ig3
-2.m
xd
75
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 76
As discussed in Volume 2- Existing Facilities Report of this Master Plan, the existing treatment
facilities owned by the City of Pontiac include the East Boulevard and Auburn WWTPs. These
two plants are collectively referred to as the Pontiac WWTP since they operate under a single
NPDES permit. Expansion of the Pontiac WWTP was only considered at the Auburn Plant
because of the land available at this site.
The combined plants have a reported ADDF of 21.6 MGD average daily flow and a maximum
flow of 30.0 MGD. The City of Pontiac has pursued continuing I/I reduction efforts, and the
reported average daily flow was 9.4 MGD and peak hour flow was 18.7 MGD. Based on these
values, there appears to be some available capacity in the Pontiac WWTP. However it is beyond
the scope of this Master Plan to conduct the detailed analysis required to determine exactly how
much capacity is available based on influent loadings and effluent permit limits. Therefore this
Master Plan will conservatively assume that the available Pontiac WWTP capacity is 8 MGD.
Additional detailed study and a plant stress test are recommended to determine the exact capacity
that is available and under what conditions.
Any flows in excess of 8 MGD would be discharged to DSWD via the Clinton-Oakland
Interceptor so there would be no need for additional flow equalization at the Pontiac WWTP site.
This arrangement would require the construction of a flow splitting interconnect structure at the
point of diversion. The COSDS would remain intact as a single SDS with two discharge points.
A portion of the COSDS flow would be treated at the Pontiac WWTP site at a certain treatment
cost per unit, and the remainder of the flow would be treated by DSWD at another treatment cost
per unit.
The COSDS communities would pay a single “blended” rate for wastewater treatment. The
estimated cost of treatment at the Pontiac WWTP was determined from analysis of the “City of
Pontiac Sewer Rate Study (1996)”. Review of this study indicates that it would cost the City of
Pontiac about $16.40 (2.20/1,000 gallon) per thousand cubic feet (2005 dollars) for wastewater
treatment from a wholesale customer. The final wholesale user rate charged by the City of
Pontiac for treatment of COSDS flows would need to be negotiated. The current DWSD
wholesale user rate is $11.01 per thousand cubic feet (2005 dollars).
The installation of relief sewers, as discussed in Alternative 2 above, may still be required for
this alternative to address the interceptor capacity upstream from the point of diversion to
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 77
Pontiac (see Figure 4-1). The cost of installing interceptor relief sewers upstream from the point
of diversion is detailed in Table 4-5. An updated system model and analysis should be completed
to determine the future conveyance requirements for this portion of the Clinton-Oakland
Interceptor.
Table 4-5 Alternative 3: Capital Cost Summary for 8 MGD Pontiac Diversion
Item Cost
Relief Sewers $4,900,000
Conveyance System Construction $27,400,000
Construction Subtotal $32,300,000
20% Eng., Legal, Admin. $6,500,000
30% Construction Contingencies $9,700,000
Total Capital Cost (2005 Dollars) $48,500,000
4.4 Alternative 4 – Diversion of 20 MGD of Flow to the Pontiac WWTP
4.4.1 Eligible CVTs
This alternative affects the COSDS and its member communities.
4.4.2 Description
This alternative is similar to Alternative 3 above in all respects except that the proposed flow-
splitting interconnect structure at the point of diversion would divert a maximum 20 MGD to the
Pontiac WWTP site. 20 MGD of flow is significant because it represents the year 2035 average
daily flow for the entire service area. In this alternative 8 MGD would be treated at the existing
Pontiac WWTP facilities at an estimated treatment cost of $16.40 per thousand cubic feet (2005
dollars), and the remaining 12 MGD would be treated at a new parallel WWTP that would be
constructed at the site of the existing Pontiac WWTP.
The cost of treatment at this new WWTP is estimated to be $12.42 per thousand cubic feet (2005
dollars). All peak wet weather flows in excess of this 12 MGD would be discharged via the
Clinton-Oakland Interceptor to DWSD at a treatment cost of $11.01 per thousand cubic feet
(2005 dollars). Table 4-6 summarizes the costs per thousand cubic feet for each of the 3 sources
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 78
of treatment. The COSDS communities would pay a single “blended” rate for wastewater
treatment.
Table 4-6 Alternative 4: Treatment Cost Summary for COSDS
Source of Treatment
2035 ADF from COSDS (MGD)
Treatment Cost per Mcf
Ex. City of Pontiac WWTP
8 $16.40
New Parallel WWTP
12 $12.42
DWSD 15 $11.01
The DWSD Wastewater Master Plan (2003) examined expansion of the Pontiac WWTP in the
technical memorandum entitled “Technical Feasibility of Satellite Treatment”. The approach in
the technical memorandum was to divert as much flow as possible (100%) out of the COSDS for
treatment at a new WWTP constructed near the site of the existing Pontiac WWTP. In
comparison, this Master Plan will examine an alternative whereby the existing facilities at the
Pontiac WWTP are maximized to treat the average daily flow diverted out of the COSDS and the
peak wet weather flows are discharged to DWSD.
Interceptor relief in the Clinton-Oakland Interceptor would still be constructed upstream from the
point of diversion (contingent upon further study). Table 4-7 summarizes the capital costs for
Alternative 4.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 79
Table 4-7 Alternative 4: Capital Cost Summary for 20 MGD Pontiac Diversion
4.5 Alternative 5 - Diversion of 22 MGD of Flow to the Pontiac WWTP
4.5.1 Eligible CVTs
This alternative affects the COSDS , its member communities, and White Lake Township.
4.5.2 Description
This alternative is similar to Alternative 3 and Alternative 4 above in all respects except that the
proposed flow splitting interconnect structure at the point of diversion would divert a maximum
22 MGD average daily flow to the Pontiac WWTP site. This alternative assumes the addition of
2 MGD of flow from White Lake Township into the COSDS. The area tributary to the point of
diversion is illustrated in Figure 4-11. Of the total 22 MGD of average daily flow, 8 MGD would
be treated at the existing Pontiac WWTP facilities. A new WWTP constructed near the site of
the existing Pontiac WWTP would treat the remaining 14 MGD of average daily flow. All peak
wet weather flows would be discharged to DWSD via the Clinton-Oakland Interceptor.
Item Alternative 4
Cost
Relief Sewers Upstream of Pontiac $4,900,000
Conveyance System Construction $27,400,000
WWTP Construction $50,500,000
Construction Subtotal $82,800,000
20% Eng., Legal, Admin. $16,600,000
30% Construction Contingencies $24,800,000
Total Capital Cost (2005 Dollars) $124,200,000
Troy
Pontiac
Orion Township
Rochester Hills
Oxford Township Addison Township
Oakland Township
Brandon Township
Springfield Township
Waterford Township
Groveland Township
White Lake Township
Independence Township
Auburn Hills
Commerce TownshipBloomfield Township
West Bloomfield Township
Rose Township
Holly Township
Milford Township
Highland Township
Wixom
Rochester
Bloomfield Hills
Orchard Lake
Birmingham
Milford Village
Lake Angelus
Walled Lake
Oxford Village
Holly Village
Wolverine Lake Village
Lake Orion Village
Sylvan Lake
Leonard Village
Ortonville Village
Clawson
Clarkston
Keego Harbor
0 4 82 Miles
LegendExpanded Pontiac WWTP Service Area
Area Remaining in COSDS with DWSD Discharge
Pontiac WWTP
Interceptor to Pontiac WWTP - Proposed
Elizabeth Lake Pump Station
Existing Interceptor Sewer
Existing Force Main
Oakland Co.
St. Clair Co.
Wayne Co.
Lapeer Co.
Genesee Co.
Washtenaw Co.
Macomb Co.Livingston Co.
Figure 4-11
Diversion of 22 MGD of Flow to
Pontiac WWTP
Oakland County Water and Wastewater Master Plan
J:\1
364
7263
\Wa
ter\
Alte
rn.R
pt\F
ig3
-3.m
xd
80
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 81
Interceptor relief would still be constructed upstream from the point of diversion. However, the
relief sewers would need to be sized larger (compared to those in Alternatives 3 and 4) to
accommodate the additional flow from White Lake Township. This Master Plan will assume
that the increase in construction cost for the larger relief sewers as compared to those in
Alternative(s) 3 (and 4) will be proportional to the increase in flow (20% more flow). Table 4-8
summarizes the capital costs for Alternative 5.
Table 4-8 Alternative 5: Capital Cost Summary for 22 MGD Pontiac Diversion
Item Alternative 5
Cost
Relief Sewers $ 5,900,000
Conveyance System Construction $ 27,400,000
WWTP Construction $ 55,300,000
Construction Subtotal $ 88,600,000
20% Eng., Legal, Admin. $ 17,700,000
30% Construction Contingencies $ 26,600,000
Total Capital Cost (2005 Dollars) $132,900,000
4.6 Alternative 6 – Construction of a New WWTP on the Clinton River
4.6.1 Eligible CVTs
This alternative affects the COSDS and its member communities.
4.6.2 Description
Alternative 6 involves the construction of a new WWTP on the Clinton River that would accept
all flow diverted from the Clinton Oakland Interceptor.
Three possible locations for WWTPs that would discharge to the Clinton River were examined in
the technical memorandum entitled “Technical Feasibility of Satellite Treatment” which is part
of the DWSD Wastewater Master Plan (2003). These alternatives were developed for flows
anticipated through 2050. The most cost effective alternative (on a dollars per gallon) basis was
shown to be construction of a new WWTP on the Clinton River in Macomb County. The
proposed location for the WWTP would be east of Mound Road and north of 22 Mile Road at the
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 82
Ford Motor Company (FOMOCO) Proving Grounds. One advantage of this site is that it is
located along the existing interceptor, so conveyance costs would be minimized. It should be
noted that FOMOCO has not been contacted concerning this option. If this option is pursued in
the future, Oakland County will need to discuss this alternative with FOMOCO. Note that land
acquisition costs associated with this alternative were not developed and could be significant.
The cost would be completely dependent upon negotiations between the parties involved.
The treatment plant size for this option was reduced from that in the DWSD WWMP using a
linear regression to predict the ADDF that would be required in 2035. The resulting annual
average ADDF was 52.8 MGD. The costs were reduced based on the decreased ADDF and
updated to a May 2005 basis using published ENR values. In addition, conveyance costs were
developed, as they were assumed to be negligible in the DWSD WWMP. The resulting costs
anticipated for Oakland County are summarized in Table 4-9.
The proposed service area includes all of the COSDS and a portion of Macomb County. Based
on the projected 2035 service area population, the new WWTP would treat an average daily flow
of 52.8 MGD and a maximum day flow of 102 MGD from this service area. The system would
be designed such that flow in the interceptor that exceeds the maximum ADDF would travel past
the new plant and be treated at the existing DWSD WWTP. A new 96-inch gravity sewer would
be constructed to carry the flow from the Interceptor to the WWTP. A 96-inch gravity effluent
pipe would discharge the treated flow to the Clinton River. The cost of the WWTP is
approximately $274.9 million, as shown in Table 4-9. Operation and Maintenance costs are
shown in Table 4-10.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 83
Table 4-9 Alternative 6: Capital Cost Summary for New WWTP along the Clinton River
Cost Categories Cost ($ Million)
WWTP $148.4
Conveyance $10.7
Total Capital and Conveyance Cost $159.1
Engineering, Legal, and Administrative Fees (20%) $31.8
Contingencies 30%) $47.7
Total Capital Cost (April 2002 Dollars) $238.6
Total Capital Cost (May 2005 Dollars) $274.9
Table 4-10 O & M Cost Summary for New WWTP along the Clinton River
Annual O & M Costs Cost ($ Million)
In April 2002 Dollars $22.5
In May 2005 Dollars $25.9
Treatment at the new plant would consist of screening, grit removal, primary settling, aeration,
final settling, filtration, and ultraviolet disinfection. Solids would be treated, dewatered, and
disposed of in a landfill.
4.7 Alternative 7 – Conveyance to COSDS
4.7.1 Eligible CVTs
This alternative affects the COSDS, its existing member communities, and the following
additional communities:
• Oakland Township (additional portions)
• Springfield Township
• White Lake Township
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 84
4.7.2 Description
Alternative 7 expands the COSDS to new, previously unsewered areas, but requires there be
available capacity in the COSDS interceptors. Alternative 2 through Alternative 6 provide
methods of generating capacity in the COSDS.
4.7.3 Oakland Township
The southwest portion of Oakland Twp. is in the COSDS. The remainder of the Township is
outside of the COSDS service area boundary. The future land use for much of this area (from
the Oakland County Composite Master Plan) is single-family homes on lots smaller than one
acre. This alternative assumes that additional capacity becomes available in the COSDS and that
the contract can be modified to include this portion of Oakland Township. If these two criteria
are met, then conveyance into the COSDS could be achieved through construction of a pump
station on Snell Rd. near the bridge over the West Branch Stony Creek. Wastewater would be
pumped via 4,900 LF of force main and 6,900 LF of gravity sewer. The total estimated project
cost for this alternative is $7.4 Million.
4.7.4 Springfield
The Township would like to see sewers only in selected areas. The most densely developed areas
in the Township are along Dixie Highway and I-75. This area represents an estimated 0.75
MGD of wastewater.
4.7.5 White Lake
White Lake could convey wastewater flow through a new gravity interceptor sewer to the
COSDS. It is assumed that the future average daily wastewater flow from White Lake Township
will be 3.5 MGD and the peak flow would be 9.7 MGD. Assuming a new gravity line installed
at minimum recommended slope, the interceptor would need to be 42-inches in diameter. This
new line would intercept the wastewater flow from White Lake Township in the vicinity of
meter 6600 near the intersection of Glade St. and Cooley Lake Road. The interceptor would
follow Cooley Lake Road up to Cass Elizabeth Rd. and tie into the 54-inch diameter Clinton-
Oakland Interceptor. The estimated capital cost for construction of the 22,500-foot long, 42-inch
diameter White Lake Interceptor is $28.9 Million.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 85
4.8 Alternative 8 – Service from Genesee County Kearsley Creek Interceptor
(KCI) Main Arm Only
Since the 1970s, the Genesee County Drain Commissioner’s wastewater master plan has
included the northwest portion of Oakland County in the regional service area. Service to this
portion of Oakland County is contingent upon the construction of two new interceptor sewers.
The first is called the Northeast Relief Sewer (NERS), which is currently under construction and
the second interceptor is the Kearsley Creek Interceptor (KCI), which has yet to been designed.
The KCI could potentially have two arms, a Main Arm to serve Village of Ortonville and
Brandon Township (described in this alternative) and a West Arm to serve the I-75/Dixie
Highway corridor in Holly and Groveland Townships (described in Alternative 9).
The construction costs for the KCI Main Arm are detailed in a 2001 Sewer System Analysis
Update of Genesee County Sewage Disposal System #1 ARTP Service Area. The total
estimated capital cost for the recommended route of the Main Arm is $25.8 Million.
The proposed Main Arm varies in size from 24-inch diameter at the county line to 36-inch
diameter at the discharge to the NERS. It is mostly gravity with one section of 20-inch diameter
force main. The 2004 Village of Ortonville Wastewater Facilities Feasibility Study examined
participation in constructing the KCI Main Arm. The cost of constructing the Main Arm was
proposed to be shared by four Genesee County CVTs and two Oakland County CVTs. The total
combined units from all of these communities were 14,800 REUs. The Village of Ortonville was
estimated to have 1,000 REUs and Brandon Township to have 1,600 REUs. If no other
communities participated, then the full burden of the capital cost would be supported by only
these 2,600 REUs in Village of Ortonville and Brandon Twp.
If all other communities participated (14,800 REUs), and each community contributed in
proportion to their number of REUs, then the Village of Ortonville/Brandon Twp. portion would
be approximately $4.53 million. Table 4-11 summarizes the costs associated with the KCI Main
Arm alternative.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 86
Table 4-11 GCDC Service (KCI Main Arm Only)
Community REUs Portion of
GCDC Cap. Cost ($M)
Local Cap. Cost ($M)
Total Cost ($M)
Brandon Twp. 1,600 2.79 5.85 8.63
Village of Ortonville 1,000 1.74 3.65 5.39
Genesee Co. CVTs 12,200 21.25 - -
Total 25.78 - -
The projected cost of service for wastewater treatment by GCDC is currently $12 per REU per
month. Assuming an REU is equivalent to 315 gallons per day (which is the GCDC design
standard), then the volumetric cost of service for the GCDC treatment option is $9.50/Mcf.
4.9 Alternative 9 – Service from Genesee County KCI Main Arm and West Arm
This alternative includes the construction of the KCI West Arm in addition to the Main Arm.
Holly Twp. and Groveland Twp. could contribute an additional 3,100 REUs (2,800 and 300
REUs respectively) from the I-75 corridor. It is assumed that the West Arm would be gravity
sewer, and that it would not be any smaller than 24-inch diameter to accommodate any additional
future flows.
The total estimated capital cost associated with construction of the West Arm is $4.7 million. In
addition to the cost of the West Arm, it is assumed that Holly and Groveland Townships would
also have to fund some proportional share of the KCI Main Arm. The estimated Holly/Groveland
proportional share of the construction cost of the Main Arm (based on number of REUs) could
be an additional $3.5 million. So the total capital cost to Holly and Groveland Townships would
be a combined $17.71 million for this scenario. Table 4-12 summarizes the costs associated with
the KCI Main and West Arm alternative.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 87
Table 4-12 GCDC Service (Both KCI Main and West Arms)
Community REUs Portion of
GCDC Cap. Cost ($M)
Local Cap. Cost ($M)
Total Cost ($M)
Brandon Twp. 1,600 1.80 5.85 7.65
Village of Ortonville 1,000 1.13 3.65 4.78
Holly Twp. 2,800 7.41 - 7.41
Groveland Twp. 300 0.80 9.50 10.30
Genesee Co. CVTs 17,200 27.82 - -
Total 38.96 - -
The projected cost of service for Alternative 9 is the same as that for Alternative 8, i.e.
$12 per REU per month.
4.10 Alternative 10 – Treatment by Another City/Village/Township (CVT)
4.10.1 Eligible CVTs
In order to meet the wastewater treatment needs identified in Volume 3 – The Needs
Assessment, several communities may want to consider agreements with neighboring
communities’ WWTPs. Table 4-13 identifies the Oakland County CVTs for which Alternative
10 is viable.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 88
Table 4-13 Communities that may Benefit from Alternative 10 – Treatment by Another
City/Village/Township
No. Community
1 Brandon Township
2 Lyon Township
3 Milford Township
4 Rose Township
4.10.2 Brandon Served by the Village of Ortonville
Brandon Township indicated it would like the Bald Eagle Lake and Lake Louise areas as well as
the M-15 corridor to be sewered. This is consistent with the composite master land use plan
located in Appendix A of the Volume 3- Needs Assessment Report. These areas will have the
highest population density in the Township. It is estimated that this area would produce
approximately 0.5 MGD of average daily wastewater flow. This Ortonville could account for
this flow in its expansion plans (see Section 4.11.5). Adding the flow from Brandon Township
would increase the proposed capacity to 0.82 MGD.
Based on 0.5 MGD being contributed by Brandon Township, it is estimated that the expanded or
larger plant would cost approximately $11.1 million. Assuming that Brandon Township and
Village of Ortonville build the plant together, Brandon’s share would be $ 7.4 million. Brandon
Township’s share of the estimated annual operating costs of $0.74 million or $18.5/Mcf would
be approximately $0.44 million or $18.2/Mcf. It is estimated that approximately 6.7 acres of
land will be required.
4.10.3 Lyon Township Served by South Lyon WWTP
Since the Lyon Township has worked towards expanding its own groundwater discharge plant,
South Lyon has not planned on serving the Township. However, pending the outcome of that
Lyon Township’s expansion efforts, the possibility of expanding the South Lyon plant to treat
wastewater from the Township could be considered.
Expanding the South Lyon plant by 3.24 MGD from 2.5 MGD to 5.74 MGD is estimated to cost
approximately $17.5 million. Based on completing construction in 2015, the estimated annual
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 89
operating cost at startup (with 25% hook-up of Lyon Twp. residents) is approximately $1.48
million or $9.18/MCF. In 2035 the annual operating costs are estimated to be approximately
$1.78 million or $6.34/MCF. It is estimated that approximately 8.7 acres will be required for
expanding the surface water discharge plant.
4.10.4 Milford Township Served by Wixom WWTP
The Township started a study in 1999 to provide sanitary service to the southerly four sections of
the Township. A draft report was issued in March 2000. Three alternatives were investigated: 1)
New Groundwater Discharge Plant, 2) Discharge to Wixom WWTP , and 3) New Surface Water
Discharge WWTP. Due to the large area required for the GWDP, and the need for low
phosphorous levels in alternative 3, the Township chose alternative 2.
The Township now has an agreement with the City of Wixom to treat up to 1.0 MGD of
wastewater from the proposed development corridor in the southeast corner of the Township.
The additional flow may or may not require an expansion of the Wixom WWTP (see Section
4.1.10).
A 1.22 MGD plant expansion is estimated to cost approximately $7.5 million (engineer’s
estimate in May 2005 dollars). Although in Milford’s original study the estimated capital cost
for this option ranged from approximately $2 to $3.3 million, it appears the cost will be closer to
$7.5 million dollars, and possibly higher. Based on completing construction in 2010, the
estimated annual operating costs at startup (with an additional 25% hook-up of Township
residents) are approximately $1.45 million or $9.44/Mcf. In 2035 the annual operating costs are
estimated to be approximately $1.57 million or $8.26/Mcf. It is estimated that approximately 4.1
acres will be required for expanding Wixom’s surface water discharge plant.
4.10.5 Rose Township Served by Holly Village WWTP
Rose Township expressed a strong desire to remain rural and expects a modest increase in
population over the years. Presently, there is about 50 new homes built per year, and the
Township expects these to be served by on-site disposal systems. The development immediately
south of Holly Village near Stiff Mill Pond, and the area immediately west of this area may be
candidates for being served by Holly Village. It is estimated that this area may represent
approximately 500 REUs, or approximately 0.16 MGD of wastewater.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 90
The Holly Village WWTP will have 1.35 MGD Average Daily Design Flow (ADDF), however
if any excess capacity exists, it will not be known until it has been running for several months. If
the WWTP accepted wastewater from Rose Township there would be minimal cost of
conveyance due to the proximity of the developments. The annual operating cost will increase
the current cost of approximately $1.0 million to approximately $1.08 million in 2035. Financial
considerations for this alternative were not developed due to the insignificant portion of the
Township that might be served and Rose Township’s desire to remain rural.
4.11 Alternative 11 – New/Expansion-of Local Treatment
4.11.1 Eligible CVTs
In order to meet the wastewater treatment needs identified in Volume 3 – The Needs
Assessment, several communities may want to consider building a new WWTP or expanding an
existing WWTP. Table 4-14 identifies the Oakland County CVTs for which Alternative 11 is
viable.
Table 4-14 Communities that may Benefit from Alternative 11 – New/Expansion of Local
Treatment
No. Community
1 Groveland Township
2 Holly Township
3 Oakland Township
4 Ortonville Village
5 Lyon Township
6 Springfield Township
7 White Lake Township
4.11.2 Groveland Township
Groveland Township does not have a public wastewater system and expects that future growth
will likely be served by on-site disposal systems. The Township recommends the installation of
sewers in the area of the old gravel pits near Grange Hall Road, which represents an estimated
0.1 MGD average daily flow. Should the Township be interested in constructing their own
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 91
ground water discharge plant, it is recommended that they hire an engineering firm to prepare
detailed construction and operating costs.
Assuming a plant capacity of 0.1 MGD, and using the cost estimates obtained from many of the
wastewater treatment plant expansions in Oakland County, it is estimated that the cost of a new
groundwater discharge plant will cost approximately $3.6 million. This excludes the cost of
conveyance from theses areas to the plant. Construction is assumed to be completed in 2015.
The estimated annual operating costs at startup (with 25% hook-up) are approximately $0.06
million or $49.2/Mcf. In 2015 the annual operating costs are estimated to be approximately
$0.13 million or $26.7/Mcf. Approximately 2.0 acres of land will be required.
4.11.3 Holly Township
Several years ago, the Township pursued an interest in providing sewers for the business area in
the northeast part of the Township between Dixie Highway and Interstate 75. This area was
estimated to produce approximately 0.75 MGD of wastewater flow and planned to be connected
to Genesee County for treatment. However, should the Township be interested in constructing
their own ground water discharge plant, it is recommended that they hire an engineering firm to
prepare detailed construction and operating costs. A groundwater discharge treatment plant with
a capacity of 0.75 MGD, is estimated to cost $13.4 million. This excludes the cost of
conveyance to the plant. Construction is assumed to be completed in 2010. The estimated
annual operating costs at startup (with 25% hook-up) are approximately $0.21 million or
$23.0/Mcf. In 2030 the annual operating costs are estimated to be approximately $0.69 million
or $18.9/Mcf. It is estimated that approximately 10.9 acres will be required for a groundwater
discharge plant.
The Township has recently secured an agreement with Holly Village for a capacity of 0.315
MGD to serve the new (Pulte) developments immediately west of the Village.
4.11.4 Oakland Township
The Township has indicated that “any growth will be on sewers if there is sewer capacity”. The
Township is expected to grow by 12,131 people between 2005 and 2035. Assuming 75% of this
growth is sewered, and applying the criteria of 2.7 persons per REU, and a wastewater quantity
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 92
of 315 gallons per REU, it is estimated that this number of people will produce an average daily
wastewater flow of approximately 1.0 MGD.
Following these assumptions, a plant capacity of 1.0 MGD is required in the year 2035. Since
the average life span of a wastewater treatment plant is 20 years, and construction is assumed to
be completed in 2010, an expansion is required in the year 2030. The capacity of the initial plant
is 0.85 MGD, and the capacity of the expansion is 0.15 MGD.
A groundwater discharge treatment plant with a capacity of 0.85 MGD, is estimated to cost $14.1
million. A groundwater discharge treatment plant with a capacity of 0.15 MGD, is estimated to
cost $4.8 million. Both these estimates exclude the cost of conveyance. The estimated annual
operating costs at startup in year 2010 (with 25% hook-up) are approximately $0.27 million or
$22.1/Mcf. In 2030 the annual operating costs are estimated to be approximately $0.76 million
or $18.3/Mcf. The annual operating cost at year 2035 is estimated at approximately $0.84
million or $17.2/Mcf. It is estimated that the initial groundwater discharge plant will require
approximately 12.2 acres, and that the expansion in 2030 will require an additional 2.7 acres.
4.11.5 Ortonville Township
The Village of Ortonville hired an engineering firm to perform a Wastewater Facilities
Feasibility Study. This was completed in April 2004, and recommended the construction of a
low-pressure collection system, and a surface water discharge wastewater treatment plant. The
wastewater treatment plant is sized to accommodate 1,000 REUs (currently there are 855 REUs
within the Village), which corresponds to a capacity of 0.32 MGD at the 315 gallons per capita
per day criteria used in the study.
Their engineer recommended the use of package WWTP with discharge to Kearsley Creek. The
estimated cost for the 0.32 MGD average daily flow WWTP is $3.7 million (engineer’s estimate
escalated to May 2005 dollars). The annual operating cost is estimated to be approximately
$0.33 million or $21.5/Mcf. It is estimated that approximately 5.1 acres of land would be
required.
4.11.6 Lyon Township WWTP
Lyon Township is currently pursuing plans to expand its WWTP. The current capacity of the
WWTP is limited by the biological reactors to 0.75 MGD, however planned upgrades will
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 93
improve the plant capacity to an Average Daily Design Flow (ADDF) of 2.0 MGD. This
expansion, if approved by the MDEQ, is scheduled to be completed in 2008. In view of the
projected population increases and planned increases in sewered areas, Lyon Township’s flow
will require another WWTP upgrade in approximately 2018. It is assumed that this upgrade will
be sized to treat the projected 4.24 MGD of flow generated by the build-out population. The
current NPDES permit allows for a discharge of up to 3.0 MGD. It is also assumed that an
updated NPDES permit will be approved for the discharge of at least 4.24 MGD.
The proposed 1.0 MGD expansion of the wastewater treatment plant in 2008 is estimated to cost
$15.0 million. The annual operating cost is expected to increase from $0.70 million or
$20.51/MCF at a flow of 0.7 MGD in 2008 to $1.21 million or $12.41/MCF at a flow of 2.0
MGD in 2018. It is estimated that approximately 14.1 acres will be required for the 2008
expansion of the groundwater discharge plant.
The proposed 2.24 MGD expansion of the wastewater treatment plant in 2018 is estimated to
cost $20.1 million. The annual operating cost is expected to increase from $1.21 million or
$12.1/MCF at a flow of 2.0 MGD in 2018 to $1.61 million or $7.79/MCF at a flow of 4.24 MGD
in 2035. It is estimated that approximately 29.3 acres will be required for the 2018 expansion of
the groundwater discharge plant.
4.11.7 White Lake Township
White Lake is served by the Commerce-White Lake WWTP. Expansion of the Commerce-
White Lake WWTP is discussed in Section 4.1.5 under “Alternative 1 – No Change” because
Commerce Township is committed to expanding the plant. The size of the expansion depends
greatly on White Lake Township’s decision regarding its wastewater treatment alternatives. This
alternative (Alternative 11 – New/Expansion–of Local Treatment) assumes White Lake will
leverage its contract for 3.64 MGD of treatment at the Commerce-White Lake WWTP after the
WWTP expansion. White Lake’s projected 2035 ADWF of 3.5 MGD is less than its contracted
amount (3.64 MGD).
4.12 Alternative 12 – Divert Flow From GWKSDS to an Expanded Warren WWTP
This alternative involves transporting wastewater from the Twelve Towns area and expanding
the Warren WWTP to accommodate the additional flow.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 94
The existing Warren WWTP was constructed in 1959 and later expanded to its current capacity
of 36 MGD. The WWTP effluent is discharged to the Red Run Drain. The WWTP has an
average daily flow of approximately 23.2 MGD. The collection system is separated, but due to
the age of the system, wet weather flows are relatively high due to inflow and infiltration. There
is a 50 million gallon retention basin at the WWTP to retain wet weather flows in excess of the
treatment capacity. On occasion, the basin capacity is exceeded and wastewater discharged is a
blend of treated effluent. For the purposes of this Master Plan, it is assumed that there is no
available capacity available to serve districts outside of the existing service area. There are
approximately 25 acres of land available for expansion of the Warren WWTP southwest of the
existing facility that is south of Big Beaver Creek and north of Red Run Drain.
The DWSD Wastewater Master Plan (2003 technical memorandum entitled “Technical
Feasibility of Satellite Treatment”) contains detailed information on the alternative to expand the
Warren WWTP. In the memorandum, two WWTPs options were considered depending on the
population to be served. The first option was to construct a 14 MGD WWTP and the second was
to investigate a 40 MGD facility. The 40 MGD option includes portions of Macomb County in
the service area. It was decided to focus on serving areas within Oakland County only at this
time. For this reason, the Master Plan only investigates a 14 MGD expansion of the Warren
WWTP.
The DWSD Master Plan evaluated an ADDF of 14 MGD. This area is anticipated to experience
minimal growth between 2000 and 2050, as the current flow in this area is 13.8 MGD. For this
reason, the 14 MGD ADDF from the DWSD Master Plan was retained in this evaluation for
Oakland County. The new WWTP would treat an average daily flow of 14 MGD and a
maximum day flow of 35 MGD. In order to handle peak flows, it assumed that the existing 50
million gallon retention basin at the Warren WWTP would be available to equalize the flow to
the expanded portion of the plant. Wastewater would be taken from the Dequindre Interceptor
that is located west of the Warren WWTP. Bringing the wastewater to the expanded Warren
WWTP would involve installing a 48-inch gravity sewer pipe of approximately 20,000 linear
feet. The sewer pipe would have to be placed in a tunnel.
Wastewater Alternatives Development
Volume 4 – Alternatives Analysis Report 95
Treatment at the expanded plant would consist of screening, grit removal, primary settling,
aeration, secondary settling, filtration, and ultraviolet disinfection. Solids would be treated,
dewatered, and disposed of in a landfill.
The capital costs for the Warren WWTP are shown in Table 4-15. The anticipated operation and
maintenance cost is shown in Table 4-16.
Table 4-15 Capital Cost Summary for 14 MGD Warren WWTP Expansion
Cost Categories Cost ($ Million)
WWTP $48.1
Conveyance $43.8
Total Capital and Conveyance Cost $98.2
Engineering, Legal, and Administrative Fees (20%) $19.6
Contingencies 30%) $29.5
Total Capital Cost (April 2002 Dollars) $147.3
Total Capital Cost (May 2005 Dollars) $169.7
Table 4-16 O & M Cost Summary for 14 MGD Warren WWTP Expansion
Annual O & M Costs Cost ($ Million)
In April 2002 Dollars $6.7
In May 2005 Dollars $7.7
A more detailed study is required to estimate specific costs allocated to each participating
community. For this reason, Alternative 12 is not included in Volume 5 - Financial Model and
no financial considerations are included in Appendix A.
Project Delivery Methods
Volume 4 – Alternatives Analysis Report 96
5.0 Project Delivery Methods
5.1 General
A municipality has several different project delivery options when considering the design and
construction of new public infrastructure. They include the following:
• Conventional Design-Bid-Build
• Design/Build
• Design/Build/Operate & Design/Build/Operate/Transfer
A description of each project delivery method along with the advantages and disadvantages of
each is provided below. Refer to Table 5-1 for a summary of the options.
Table 5-1 Summary of Delivery Method Advantages and Disadvantages
Method Advantages Disadvantages
Desig
n-B
uild
� Single entity responsible for design and construction
� Optimized communication between designer and builder
� Single point of accountability
� Time savings
� Early knowledge of project costs
� Not legal in some jurisdictions
� Relatively new concept.
Desig
n-B
id-B
uil
d
� Traditional, Proven Approach
� Competitive bidding results in lowest cost.
� Building is fully defined.
� Relative ease of assuring quality control
� Agency gets involved with conflicts
� Builder not involved in design process
� May be slower
� Price is not certain until construction bids are received.
Desig
n-B
uild
-O
pera
te
� Single entity responsible for design, construction, & operation
� Optimized communication between designer, builders, & Operators
� Reduced risk of unnoticed issues
� Extremely difficult to price
� Potential to limit competition
� Less direct control over the project
� Owner is required to make quicker decisions
Project Delivery Methods
Volume 4 – Alternatives Analysis Report 97
5.2 Design-Bid-Build
The traditional project delivery method is the Design-Bid-Build approach. This approach
separates the design and construction responsibilities by assigning separate contracts to a design
firm and contractor. This method consists of a Design Phase, a Bidding Phase and a Construction
Phase.
During the initial design phase, a design contract would be awarded to an engineer, who is
responsible for preparing a complete design package. In the bidding phase, the owner solicits
bids from contractors based on the bid documents prepared by the design firm. Contractors
submit competitive bids, and the owner awards the construction contract to lowest and best bid.
Typically, the owner secures the services of the design firm to administer the construction
contract with the Contractor.
The Design-Bid-Build approach has many advantages. Because the drawings and specifications
are completed before bids are solicited, there is little uncertainty about the owner expectations
and the contract terms are relatively clear. The bidding process creates a competitive
environment with contractors and presumably provides low cost product. The contract between
the owner and the construction contractor are the detailed working drawings and specifications,
which provides a clear standard to verify the contractors’ materials and workmanship on the
project.
Disadvantages with the traditional approach include the following. In the design-bid-build
process the owner is the guarantor of the engineer’s drawings and specifications, involving the
owner in conflicts and disputes. Another disadvantage is that builder is not involved in the design
phase and therefore cannot input on construction materials or methods. The design-bid-build
approach is normally slower than other approaches such as design-build because the design-bid-
build approach involves a sequential process. The engineer will give the owner a cost estimate
for the project but there is no cost certainty until the construction bids were received.
5.3 Design-Build
In the Design-build method, two usually separate services are combined into one contract. With
the design-build method, owners execute a single contract for both engineering services and
Project Delivery Methods
Volume 4 – Alternatives Analysis Report 98
construction. The design-build entity may be a single firm, a group, a joint venture or other
organization assembled for a particular project.
With the design-build method, the designer-builder assumes responsibility for the majority of the
design work and all construction activities. When using the design-build method, owners usually
retain responsibility for financing, operating and maintaining the project. While design-build
methods were more prevalent in private sector work, it is also gaining acceptance among many
public sector owners.
Some of the advantages of the Design-Build method are that a single entity is responsible for the
design and the construction of the project creating better understanding and communication
between the design phase and the construction phase. Because the design and construction
personnel work and communicate as a team, value engineering and construction are used
continuously and more effectively. Since the design and construction are overlapped and because
bidding and redesign periods are eliminated, total design and construction time can be drastically
reduced. The firm that is responsible for the design is simultaneously estimating the construction
cost and can accurately conceptualize the completed project and a firm construction cost can be
guaranteed earlier. Other advantages include a single source of accountability and responsibility
for the project, which serves as motivation for quality and proper project performance.
Some disadvantages of the Design-Build method include that since this method is not the most
popular, there will be some new things to learn such as the process and new front-end
documentation and different insurance/bonding products. There may also be some resistance
from those who are not familiar with the approach. There may also be some barriers in some
states with procurement and licensing.
5.4 Design/Build/Operate - Design/Build/Operate/Transfer
In the Design-Build-Operate method, there is a single entity that is responsible for the design, the
construction, and the operation of the project. This method is increasingly being utilized as the
Design-Build-Operate-Transfers method.
The Design-Build-Operate-Transfer model is the same relationship that combines the design and
construction responsibilities of design-build methods with operations and maintenance
responsibilities. This method also combines the aspect that the contractor will be responsible for
Project Delivery Methods
Volume 4 – Alternatives Analysis Report 99
the operation and maintenance of the project for a fixed period. The operators become involved
with the project’s design to ensure that all aspects of operating the system are considered as early
as possible. The contractor guarantees the project’s annual operating cost and provides bonds to
assure the owner that the system will be operated on a fixed price in accordance with all
contractual obligations.
Owners award Design-Build-Operate contracts by a competitive bid. Qualified candidates
respond to the specifications provided in the bid documents and are usually required to provide a
single price for the design, construction and maintenance of the facility for whatever period of
time is specified. Candidates are also required to submit documentation on their qualifications,
thereby allowing owners to compare the costs of the different offers and the ability of the
candidate to meet their specific needs.
The advantage of the Design-Build-Operate-Transfer / Design-Build-Operate approach is that it
combines responsibility for usually different functions—design, construction, and operation—
under a single entity. This allows the private partners to take advantage of a number of
efficiencies. The project design can be customized to the construction equipment and materials
that will be used. In addition, the Design-Build-Operate-Transfer entity is also required to
establish a long-term maintenance program up front, together with estimates of the associated
costs. The team’s detailed knowledge of the project design and the materials used allows it to
develop a custom maintenance plan that foresees and addresses the needs as they occur, thus
reducing the risk that issues will go unnoticed or unattended and then develop into more costly
problems.
As with any approach the Design-Build-Operate-Transfer / Design-Build-Operate approach has
some disadvantages. The disadvantages include the following: potential to limit competition, less
direct control over the project, difficult to price and owner is required to make quicker decisions.
DWSD Growth Pays for Growth Policy
Volume 4 – Alternatives - Appendix A