NUPCHE LIKHU HYDROPOWER PROJECT
(57.5 MW)
Ramechhap, Nepal
Progress Report
November/December, 2018
------------------------------------------------------
Vision Energy and Power Private Limited
New Baneshwor, Kathmandu, Nepal
Tel : +977-14785528
Email : [email protected]
URL : www.veplinfo.com
Brief highlights of the recent updates in the
Progress Report for November/December 2018 of Nupche
Likhu Hydropower Project
1. HR Audit has been completed and Report has been submitted
2. ISO certification is on process. Contract has been signed with URS Nepal P.
Limited.
3. New Recruitment - Company Secretariat Ms. Rita Niraula Poudyal for
Compliance Department has been recruited from Poush 11, 2075
4. Office shifting – The contract has been signed with the landlord and interior
design of the office is in process. New VEPL office is in Thapagaun, New
Baneshwor.
5. Introduction of New BOD member Mr. Khageswor Bohara (Renowned
Hydropower developer. Director of Kalanga Hydropower Project, BOD
member of Kanchan Development Bank)
6. EIA Report for project has been forwarded to MOE from DOED &
presentation was held on 23rd
December 2018.
7. Scoping notice for EIA of Transmission Line has been published on daily
newspaper and collection of muchulka has been completed
8. Access road from Umathirtha Mandir to Lahaksewar Village (6.344 km)
Location: Power house to Camp Area. Road construction has been completed
up to chainage 3+600m out of chainage 6+344m.
9. Detail Design of the project will be submitted by the consultant (EIM Pvt.
Ltd.) in next two months.
10. Tender drawing for bidding of contractors is going on.
11. Detail Design for camp facilities is going on and contractor selection for
Construction of camp house has been completed.
Table of Contents
CHAPTER ONE – BACKGROUND ............................................................................................................................... 1
1.1 Background ..................................................................................................................................................... 1
1.2 Vision, Mission & Objective of the company ................................................................................................. 1
1.3 Board of Directors ........................................................................................................................................... 1
1.4 About Chairman .............................................................................................................................................. 2
1.5 Sub-Committees .............................................................................................................................................. 2
1.6 Advisory Committee ....................................................................................................................................... 2
1.7 Organogram ..................................................................................................................................................... 3
1.8 Consulting Team ............................................................................................................................................. 4
CHAPTER TWO – PROJECT DESCRIPTION ............................................................................................................... 5
2.1 Introduction ..................................................................................................................................................... 5
2.2 Salient Features of the Project ......................................................................................................................... 6
2.3 Main Features of Project (Based on Draft Due Diligence Report) ................................................................ 10
Dividend Payout Capacity (Considering Project cost as per Draft Due Diligence Study Report) .............................. 10
2.4 Project Milestones (Completed Works) ......................................................................................................... 10
2.5 Project Milestones (Ongoing Works) ............................................................................................................ 11
CHAPTER THREE – OTHERS ..................................................................................................................................... 13
3.1 Public Hearing Notice published on Daily Newspaper ................................................................................. 13
3.2 Photos of Work at Site of the Project : .......................................................................................................... 14
3.3 Financial Closure ........................................................................................................................................... 17
3.4 Construction Work ........................................................................................................................................ 17
3.5 Investment Module ........................................................................................................................................ 17
Vision Energy and Power Private Limited Nupche Likhu Hydropower Project (57.5 MW) Kathmandu, Nepal Ramechhap, Nepal
November/December, 2018 1
CHAPTER ONE – BACKGROUND
1.1 Background
Vision Energy & Power Pvt. Ltd. (VEPL) is registered at Office of Registrar of
Company on Shrawan 2, 2073 with registration no 151997/073/074. It is
registered in Inland Revenue Department on Shrawan 28, 2073 with PAN No.
604286558.
Various professionals and well experienced persons in hydropower sector have
united together and come up with a concept of establishing this company,
which will construct/invest in energy producing companies.
1.2 Vision, Mission & Objective of the company
Vision Become well establish energy producing company in Nepal.
Mission To utilize the available resources for the development of energy in the country
To ensure attractive long term return to our shareholders through professional
management.
Objective Conduct feasibility study of transmission line and environment; perform detail
engineering design, research and survey for the electricity development.
Generate electricity through small or medium scale projects by using alternative
source of energy such as water, wind, solar power, biogas etc.
Sale of electricity to Nepal government and other institutions or supply of
electricity directly to consumers whenever necessary in wholesale or other basis.
1.3 Board of Directors
S.N. Name Position Qualification Experience
1 T. N. Acharya Chairman FCA, B.Com More than 15 years experience in various audit,
public sector & hydropower sector. Ex Board
Member of CIT, NEA, NAC and Current Board
Member of NTA.
2 Rajesh Kumar
Shrestha
Memb er MA (Economics) Renowned Hydropower Developer, Chairman of
Century Commercial Bank. Director (Finance&
Management) of Little Angles School and other
many companies.
3 Desh Bandhu
Karki
Member BBS and
Bachelor’s in
Community
Welfare
Development
More than 5 years of experience in various
sectors. Currently a Businessman.
4 Ramesh
Adhikari
Member B. Com 20 years experience in various government,
private and hydropower sector
5 Khageswor
Bohara
Member MBA Renowned Hydropower developer. Director of
Kalanga Hydropower Project
6 Bhimsen Kumar
Gautam
Member MBS, RA More than 20 years of experience in audit and
involved in various sectors.
7 Snigdha Bhatta Member B.A. / B.Sc. L.LB.
(Hons.) Course
Has experience in Legal Consultancies for more
than 5 years.
Vision Energy and Power Private Limited Nupche Likhu Hydropower Project (57.5 MW) Kathmandu, Nepal Ramechhap, Nepal
November/December, 2018 2
1.4 About Chairman
Mr. T. N. Acharya is a fellow Chartered Accountant with more than 15 years of experience in audit,
consultancy service and hydro power projects.
He is actively involved in development of various hydro powers in the form of investor and
consultant for the past decade. He is actively involved as financial consultant of various
Hydropower companies on behalf of Banks also.
• Current Board Member of Nepal Telecommunications Authority (NTA)
• Senior/Managing Partner at T. N. Acharya & Co., Chartered Accountants
• Member of The Institute of Chartered Accountants of Nepal (ICAN); The Institute of Chartered
Accountants of India (ICAI); and Management Association of Nepal.
• Has experience as Board Member of Nepal Airlines Corporation, Nepal Electricity Authority,
Citizen Investment Trust; Executive Member of The Institute of Chartered Accountants of
Nepal; and Member of Local Body Fiscal Commission under Ministry of Local Development
1.5 Sub-Committees
There are various sub-committees as follows:
1) High Level Coordination Sub-Committee
2) Advisory Committee
3) Technical Sub-Committee
4) Forest and Environment Co-ordination Sub-Committee
5) Financial Management Sub-Committee
6) Local Area Coordination Sub-Committee
7) International Coordination Sub-Committee
1.6 Advisory Committee
5 members Advisory Committee in the Chairmanship of Mr. Umesh Shrestha (Member of
Parliament, Renowned businessman, Founder Chairman of Little Angels School). Other
Members of the Advisory Committee are Mr. Jiwan Bahadur Shahi, Mr. Hitraj Pandey.
Vision Energy and Power Private Limited Nupche Likhu Hydropower Project (57.5 MW) Kathmandu, Nepal Ramechhap, Nepal
November/ December, 2018
1.7 Organogram
Vision Energy & Power Pvt. Ltd. Board of Directors
High Level Coordination Sub-Committee
Technical Sub-Committee
Advisory Committee
International Co-ordination Sub-Committee
Technical Department
Public Relation Department
Finance Department
Administration Department
Local Coordinator
Project
Manager
Public Relation Officer
Finance
Manager
Administration
Manager
Civil Engineer
Electrical Engineer
Mechanical Engineer
Local Coordinator Assistant
Assist. Public Relation Officer
Account
Assistant
Admin Assistant
Civil Sub Engineer
Electrical Sub Engineer Mechanical Sub Engineer
Geologist Project Engineer
Executive
Chairman
Province Coordinator
Compliance Department
Consultant/Contractors
Legal Advisors
Local Area Coordination Sub-Committee
Vision Energy and Power Private Limited Nupche Likhu Hydropower Project (57.5 MW) Kathmandu, Nepal Ramechhap, Nepal
November/ December, 2018 4
1.8 Consulting Team
SN Particulars Name of Consultant
1. Desk Study of Project E.I. Maven Pvt. Ltd
2. Feasibility Study of Project (57.5
MW)
E.I. Maven Pvt. Ltd
3. Desk Study of Transmission line E.I. Maven Pvt. Ltd
4. Feasibility Study of Transmission
line
E.I. Maven Pvt. Ltd
5. Topographic Survey of the
project
R.K. Survey Company Pvt. Ltd.
6. Topographic Survey of the
Project access road and
transmission line
R.K. Survey Company Pvt. Ltd.
7. EIA of the Project Nepal Environmental and Scientific Services (P) Ltd.
8. EIA of Transmission line Nepal Environmental and Scientific Services (P) Ltd.
9. ERT Explorer Geophysical Consultants Pvt. Ltd.
10. Geological/Geotechnical
Interpretation Report by MASW,
MAM and SRT with ERT
Geophysical Research and Consultancy Service (P).
.Ltd.
11. Review of Feasibility Report Keshav Raj Bhatta (Expert: Director of NEA).
Bijay Lal Shrestha (Designer)
Prakash Man Singh (Geologist)
Dr. Prem Chandra Jha (Hydrologist)
Surendra Awasti (Civil Engineer)
12. Automatic Gauge Station Real Time Solutions Pvt. Ltd.
13. DPR E.I. Maven Pvt. Ltd.
14. Due Diligence Study Sanima Hydro and Engineering Pvt. Ltd.
Vision Energy and Power Private Limited Nupche Likhu Hydropower Project (57.5 MW) Kathmandu, Nepal Ramechhap, Nepal
November/ December, 2018 5
CHAPTER TWO – PROJECT DESCRIPTION
2.1 Introduction
VEPL aims to develop Nupche Likhu Hydropower Project in Ramechhap District using
local technical, managerial and financial capability and is dedicated to supply the power to
the National Grid to fulfill domestic energy demand. This Project is a run-of-river (RoR)
hydropower project.
Fig.: Project Layout Source: Google Earth
The Nupche Likhu Hydropower Project (57.5 MW) is located in Gumdel VDC (Currently
Umakunda Rural Municipality) of Ramechhap District, Nepal. The proposed intake of the
Nupche Likhu Hydropower Project is located North of Lahaksewar village in left bank of
Nupche Khola at an elevation of 3330m above msl.
The source of water for Nucphe Likhu hydropower project is originated from snow fed
rivers starting from the High Mountain/Hilly areas.
The project is proposed to develop with an installed capacity of 57.5 MW by utilizing a
design discharge of 7.11 m3/s with a gross head of 994m.
Vision Energy and Power Private Limited Nupche Likhu Hydropower Project (57.5 MW) Kathmandu, Nepal Ramechhap, Nepal
November/ December, 2018 6
2.2 Salient Features of the Project
S.N. Particulars Remarks
1. General
Name of the Project Nupche Likhu Hydropower Project
Type of the Project Snow fed Run-off River Hydropower Project
2. Location
Zone/ Development Region Janakpur Zone/Central Development Region
District Ramechhap
Project Location Umakunda Rural Municipality, (Gumdel VDC)
River Nucphe Khola and Likhu Khola
License Boundary
Longitude 86°26’30” E - 86°30’30” E
Latitude 27°40’37” N - 27°43’37” N
3. Hydrology
Catchment Area at Headworks 150 Km2 (Nupche 82km2&Likhu 68 km2)
Design Discharge (Q 45 %) 3.89 m3/s+ 3.22 m3/s (Nupche & Likhu) = 7.11m3/s
Catchment Area at powerhouse:
100 yrs. Flood at Nupche
Headworks
76 m3/s
100 yrs. Flood at Likhu
Headworks
63m3/s
100 yrs. Flood at Powerhouse 178m3/s
4. Likhu- Headworks
Weir
Type Boulder line weir
Spillway length 18.80 m
Weir crest level 3338.00 m amsl
Undersluice
Sill level 3334.3 m amsl
Size 3 m x 2.5 m
Intake
Type Orifice, Side Intake
No. 2
Size 2 m x 1.2 m (W x H)
Sill level 3336.00 m amsl
Vision Energy and Power Private Limited Nupche Likhu Hydropower Project (57.5 MW) Kathmandu, Nepal Ramechhap, Nepal
November/ December, 2018 7
Gravel Trap
Type Single, Duffer
Size 4 m x 4.5 m
Settling Basin
Basin No. 2
Type Double Bay Duffer
Size 75 m x 7.9 m x 6.2 m each
5. Nupche - Headworks
Weir
Type Boulder line weir
Spillway length 27.0 m
Weir crest level 3338.00 m amsl
Undersluice
Sill level 3334.12 m amsl
Size 3 m x 2.5 m
Intake
Type Orifice, Side Intake
No. 2
Size 2.2 m x 1.2 m (W x H)
Sill level 3335.80 m amsl
Gravel Trap
Type Single, Duffer
Size 4 m x 5 m
Settling Basin
Basin No. 2
Type Double Bay Duffer
Size 82 m x 8.7 m x 6.9 m each
6. Headrace Pipe
Headrace Pipe 839 m & 160 m (Likhu & Nupche River)
Headrace Pipe Dia 1.6 m & 1.6 m (Likhu & Nupche River)
Thickness 8 mm
7. Tunnel Length
Nupche Intel Portal to Junction 1673 m
Likhu Intel Portal to Junction 1424 m
Vision Energy and Power Private Limited Nupche Likhu Hydropower Project (57.5 MW) Kathmandu, Nepal Ramechhap, Nepal
November/ December, 2018 8
Outlet/Surge Tank to Junction 3242 m
Adit Tunnel Length 360 m
Tunnel Size 2.8m x 3.5m
8. Surge Tank
Type Underground, Circular
Diameter 6 m
Height 33 m
Up surge level 3342.00 m amsl
Normal operating level 3334.92 m amsl
Down surge level 3326.70 m amsl
9. Penstock Pipe Length
Total Steel Penstock Pipe 2780 m
Internal Diameter 1.3-1.6 m
Thickness 8 mm to 44 mm
Steel Lined Vertical shaft 170 m
Steel Lined Tunnel 230 m
10. Power House
Type Surface
Size (L x B x H) 48.5 m x 24.2 m x 16.78 m
Turbine center line 2336 m above msl
Number of Generating Units 3
Turbine Type Pelton
11. Tail-Race Canal
Type Box Culvert
Size 1.5 m x 2 m (each)
Length 38 m
12. Power and Energy as per
PPA
Gross Head 994 m
Net Head at Full Flow 967.15 m
Installed Capacity 57.5 MW
Generated Energy per Annum 139.76 GWh, 36.61% (Dry) and 241.98 GWh, 63.39%
(Wet) Total: 381.74 GWh
13. Transmission Line & Grid This project has to develop the approx. 30 km 132 kV line
up to National grid at 132 kV switchyard of Proposed NEA
Hub at Garjan Substation, Ramechhap district.
Vision Energy and Power Private Limited Nupche Likhu Hydropower Project (57.5 MW) Kathmandu, Nepal Ramechhap, Nepal
November/ December, 2018 9
14. Approach Road Connection There is an existing all weather road up to Manthali
which is 131km from Kathmandu. From Manthali to
Kyama, Gumdel VDC, there is partly stone paved
earthen road which is about 125 km long and to the
proposed PH site of the project, there exist a foot trail of
about 12 km.
15. Project Road to HW & PH 34 km (estimated)
16. Approximate Cost of
Project
10,578 million NPR (Subjected to increase/decrease after
DPR & DDS)
17. Approximate Construction
Period :
4 Years
18. Required Commercial
Operation Date (RCOD)
2080/05/02(2023/08/19)
19. Financial Indicators
IRR 17.64%
EIRR 27.18%
NPV Nrs. 7,293,135 thousands
BC Ratio 1.82
Pay -back Period –Simple 4.75 Years
Pay-back Period - Discounted
7.64 Years
7.64 Years
DSCR Ratio 1.77
Vision Energy and Power Private Limited Nupche Likhu Hydropower Project (57.5 MW) Kathmandu, Nepal Ramechhap, Nepal
November/ December, 2018 10
2.3 Main Features of Project (Based on Draft Due Diligence Report)
1. Internal Rate of Return (IRR): 17.64% , Equity Internal Rate of Return (EIRR): 27.18%
2. Simple Payback Period: 4.75 Years; Discounted Payback Period: 7.64 years.
3. The Project has high head. It ensures cost efficiency and high energy.
4. High Energy per MW (6.63 GWh p.a.), Dry Energy 36.61% and Wet Energy 63.29%
5. Total project cost of the project : 10,578,458 thousands and total cost per MW = Nrs.183,973
thousands
6. Income Per MW: More than NPR 4 Crore
7. Professional, Transparent and Responsible Management.
8. Aims to benefit Small Investors too.
9. Focused on high Return on Investment and high value in secondary market
Dividend Payout Capacity (Considering Project cost as per Draft Due Diligence Study
Report)
a. No Change in Project Cost, Revenue & Interest Rate: Year 2081-26%, Year 2082-30%, Year
2083-35%, Year 2084-40%, Year 2085-45% and from Year 2086 to 2110 - 45% - 80%
b. Project Cost increase by 5%, Revenue Decrease by 5% & Interest Rate at 12%: Year 2081-17%,
Year 2082-21%, Year 2083-25%, Year 2084-30%, Year 2085-35% and from Year 2086 to
2110- 35% - 70%
c. Project Cost increase by 10%, Revenue Decrease by 10% & Interest Rate at 12%: Year 2081-
10%, Year 2082-14%, Year 2083-15%, Year 2084-24%, Year 2085-25% and from Year 2086
to 2110 – 25% - 60%
2.4 Project Milestones (Completed Works)
S.N Activities Status Remarks
1 Survey License of project License obtained of 57.5 MW on
2074/06/29(15/10/2017)
Completed.
2 Topography Survey of Project Topography Survey Report Obtained Completed.
3 Quality Measurement of Water Report of Water Measurement has
been obtained.
Completed.
4 Electronic Resistivity
Tomography (ERT)
ERT Consultant has Completed ERT
Works and has submitted Final
Report.
Completed.
5 Geological and Geotechnical
Interpretation Report By
MASW, MAM and SRT with
ERT
Consultant team has submitted the
Final Report
Completed
6 Feasibility Study report of
project
Final Feasibility Study Report has
been obtained from Consultant and
submitted to DOED for approval.
Completed.
7 Review of Feasibility Study
Report of Project by
Independent Consultant Team
The Expert team has submitted Final
review report after field visit.
Completed
Vision Energy and Power Private Limited Nupche Likhu Hydropower Project (57.5 MW) Kathmandu, Nepal Ramechhap, Nepal
November/ December, 2018 11
8 Approval from Ministry of
Forest.
Approval for Survey Work Obtained. Completed.
9 Desk Study Report of
Transmission line
The consultant team has submitted
Final Desk Study Report.
Completed.
10 Survey license of Transmission
line
License obtained for transmission line
on 2074/12/15 (29/3/2018)
Completed.
11 Transmission Line Survey Transmission Line Survey license
obtained from DOED. Consultant has
submitted the final report of survey
Completed
12 Grid Agreement Connection Agreement has been
entered with NEA to evacuate the
power at Garjyang Sub-station.
(Estimated distance 30 KM).
Completed.
13 PPA PPA has been done with Nepal
Electricity Authority (NEA) on
2074/11/28 (12/03/2018).
Completed.
14 Road Survey The consultant has completed the
survey work
Completed
2.5 Project Milestones (Ongoing Works)
S.N Activities Status Remarks
1 Environment Impact
Assessment (EIA) study of
Project
EIA Consultant has completed initial
field visit and has submitted
preliminarily report. Further the
consultant has presented TOR in
Department of Electricity
Development (DOED) for approval.
EIA Report has been forwarded to
MOE from DOED & presentation is
going to held on 23/12/2018
Ongoing
2 Feasibility Study report of
Transmission line
Consultant team has submitted the
draft Feasibility Study Report
Ongoing
3 Environment Impact
Assessment (EIA) study of
Transmission line.
Scoping notice has been published on
daily newspaper and process of
collection of muchulka is ongoing
process.
Ongoing
4 Detail Design/DPR Agreement with technical Consultant
has been completed.
Work is being done as per
agreement. Expected date
May 2019
5 Generation License Will be applied after approval of
Feasibility Study report.
Ongoing
6 Gauge Station Installation Automatic Gauge Station has been
Installed at Project Site.
Collection of data from
the Gauge Station is going
on.
7 Land Acquisition
Required lands for the project are
identified. 45% of Land acquisition
completed.
Acquisition of required
lands will be completed
within Chaitra 2075.
(Timeline & Required
land changed due to small
changes in penstock
alignment).
Vision Energy and Power Private Limited Nupche Likhu Hydropower Project (57.5 MW) Kathmandu, Nepal Ramechhap, Nepal
November/ December, 2018 12
7 Access road from Umathirtha
Mandir to Lakschewar Village
(6.344 km)
Location: Power house to Camp
Area
1) Contactor & equipments for
Access road has been mobilized to
site & has started the work.
2) Excavation, boulder breaking etc,
has been done.
3) Excavation for road construction
has been completed up to chainage
3+ 500 (3500 m) out of 6+300
(6300m)
Ongoing.
8 Up-gradation of local road from
Gumdel to Kyama (Approx. 5
km)
Out of 7 km, approx 3.5 km road has
been upgraded
Ongoing
9 Due Diligence Study The Consultant has visited the site. Draft Report has been
submitted & under review.
10 Electromechanical Works Discussion with potential supplier is
going on.
Ongoing
11 Camp Facilities Final Design of Camp area for outlet
has been completed and selection of
potential contractor has been going
on.
Ongoing
12 HR, Finance and Good
Governance Related Activities
HR, Finance & corporate
Governance Guidelines is finalized.
Approval from BOD is
remaining.
Vision Energy and Power Private Limited Nupche Likhu Hydropower Project (57.5 MW) Kathmandu, Nepal Ramechhap, Nepal
November/ December, 2018 13
CHAPTER THREE – OTHERS
3.1 Public Hearing Notice published on Daily Newspaper
Vision Energy and Power Private Limited Nupche Likhu Hydropower Project (57.5 MW) Kathmandu, Nepal Ramechhap, Nepal
November/ December, 2018 14
3.2 Photos of Work at Site of the Project :
Fig. 1 Ongoing Access Road Construction from Power House to Camp Area
Fig 2: Ongoing Boulder Breaking Works near Power House Area
Vision Energy and Power Private Limited Nupche Likhu Hydropower Project (57.5 MW) Kathmandu, Nepal Ramechhap, Nepal
November/ December, 2018 15
Fig 3: Ongoing Road Upgradation Works from Gumdel to Kyama
Fig 4: Ongoing Road Upgradation Works from Umathirtha Mandir to Lakschewar Village
Vision Energy and Power Private Limited Nupche Likhu Hydropower Project (57.5 MW) Kathmandu, Nepal Ramechhap, Nepal
November/ December, 2018 16
Fig 5: Recent snowfall at Lakschewar i.e Camp Area
Vision Energy and Power Private Limited Nupche Likhu Hydropower Project (57.5 MW) Kathmandu, Nepal Ramechhap, Nepal
November/ December, 2018 17
3.3 Financial Closure
After PPA, the process for financial closure with Banks is going
on. The company aims to finalize financial closure within Poush
End 2075.In special case it is targeted maximun Falgn End 2075.
Various meeting and presentation are going on with various banks
for loan process for the project.
3.4 Construction Work
The company will start its construction work after
obtaining Generation Liscence. The company plans
to generate electricity within the period of 4 years
from the commencement of construction work
subject to complex disturbances. The construction
work will be commenced after the completion of
the first stage and second stage. Currently
agreement has been done for road construction and
work has been started as per TOR. Identification of
contractors is going on for other construction
works.
3.5 Investment Module
The Investment in Promoters Share has been closed from Aswin End 2075. However any interested
person can apply for the Promoters Share with special approval from the Management. In this case
maximum & minimum limit of the investment will be same as before. Investment schedule will be as
per the Management decision.