Erection Steps-STG 57.5 MW

download Erection Steps-STG 57.5 MW

of 27

Transcript of Erection Steps-STG 57.5 MW

  • 8/13/2019 Erection Steps-STG 57.5 MW

    1/27

    PRESENTATION ON CONSTRUCTIONAL

    FEATURES OF 57.02MW

    STEAM TURBINEAT AES KELANITISSA

    BY

    G.SRIDHARDEPUTY MANAGER/BHEL

    www.bhelpswr.co.in/Technical/Commissioning%20Status/.../STGCF.ppt

  • 8/13/2019 Erection Steps-STG 57.5 MW

    2/27

    STEAM TURBINE

    Single shaft non-reheat type reaction Turbine

    1ststage is an impulse stage

    Steam enters the turbine from the valves throughthe inter-connecting piping to the HP stages

    17 HP stages

    After the doing work in the HP stages, the steam

    makes its way to the IP stages The IP stages are housed in Guide Blade

    Carriers(GBCs) 1, 2, 3 & 4

  • 8/13/2019 Erection Steps-STG 57.5 MW

    3/27

    GBC-1 consists of 13 stages

    GBC-2 consists of 8 stages

    GBC-3 consists of 4 stages

    GBC-4 consists of 4 stages

    The last 4 stages are housed in the Exhaust Hood

    and are called the LP stages.

    A very important part of the rotor is the Balance

    Piston Disc/Drum which balances a major part of

    the thrust that is caused by impingement of steamon to the blades. The residual thrust is absorbed by

    the Thrust Bearing.

  • 8/13/2019 Erection Steps-STG 57.5 MW

    4/27

  • 8/13/2019 Erection Steps-STG 57.5 MW

    5/27

    In between the 2 bearing pedestals and the casingsare the front and the rear glands. Gland steam for

    sealing the motive steam from coming out of thecasing is supplied to these glands.

    The exhaust hood is provided with 2 nos. ofexplosion/bursting diaphragms which will operate

    when the exhaust hood pressure increases beyond acertain limit. The diaphragm is made of lead.

    On either side of the Turbine are the Main SteamStop and Control Valves with servomotors. Steam

    from the Boiler enters the valves through a nozzleprovided at the bottom of the valves. The valveshouse the strainer which prevents foreign particlesfrom entering the Turbine.

  • 8/13/2019 Erection Steps-STG 57.5 MW

    6/27

    From the valves, the steam is led to the Turbine

    through the Inter-connecting piping/Steam transfer

    piping.

    Looking from the Turbine towards the Generator,

    all that is in front, is front and that at the rear, the

    rear. Similarly the left and the right. The valves are fixed at the rear end in the axial

    direction and at one of the resting palms in the

    transverse direction thus enabling expansion of the

    valve towards the front and away from the Turbinelaterally.

    The rear set of thrust pads are the active pads.

  • 8/13/2019 Erection Steps-STG 57.5 MW

    7/27

  • 8/13/2019 Erection Steps-STG 57.5 MW

    8/27

    The Rear Bearing pedestal houses the rear bearing

    and the Turning/Barring Gear assembly. The

    coupling portion of the Turbine rotor is assembledwith 1 stage of impulse blades on to which oil will

    impinge when the Turning Gear valve is opened.

    This will result in rotation of the rotor. For this the

    rotor has to be lifted on jacking oil by 0.07 to0.10mm.

    Unlike the front bearing housing, the rear bearing

    housing does not slide. The rear bearing pedestal is also the house of the

    Turbine-Generator coupling.

  • 8/13/2019 Erection Steps-STG 57.5 MW

    9/27

    The Steam Turbine is equipped with the

    following auxiliaries:

    a. Main Oil Tank

    b. Auxiliary Oil Pump-tank mounted

    c. Emergency Oil Pump-tank mounted

    d. Duplex Oil Filtere. Oil Coolers

    f. Oil Centrifuge

    g. AC & DC Jacking Oil Pumpsh. CEPs, BFPs, Deaerator etc.

  • 8/13/2019 Erection Steps-STG 57.5 MW

    10/27

    Sequence of Steam Turbine Erection

    1. Mark the longitudinal and transverse center lines

    on the TG deck/verify the center lines markedby the civil agency.

    2. The foundation shall be checked for dimensionalaccuracy by a measuring tape within a tolerance

    of +2mm.3. Before the foundation is cast, check the location

    of inserts, pockets etc. The foundation boltsleeves shall be checked for verticality and shall

    not deviate by more than 3mm along the entireheight of the sleeve. The sleeves shall then belocked firmly to the reinforcement rods to arrestany movement during casting.

  • 8/13/2019 Erection Steps-STG 57.5 MW

    11/27

    Care shall be taken to cast the entire deck in onestretch spanning 24 to 36 hours.

    The dimensional and verticality check shall berepeated after casting to check for any deviationsduring casting. After the minimum curing time ofthe deck has elapsed, its ready for erection. All

    dimensional checks shall be carried out withrespect to the longitudinal axis of the Turbine andthe Condenser center line.

    All areas where secondary grout is to be poured or

    where primary packers are to be grouted shall beroughly chipped. This is important for adhesion

    between the primary and the secondary grout.

  • 8/13/2019 Erection Steps-STG 57.5 MW

    12/27

    A bench mark for reference elevation of the TG center line

    shall be transferred from the Boiler/any reference which

    the civil agency has marked. The elevation of allcomponents of the Steam TurbineGenerator shall be set

    w.r.t this bench mark.

    Mark location of packers for placement of the Turbine

    Front and Rear pedestals, Exhaust hood base plate, theGenerator sole plate and the Exciter sole plates.

    Place, align, set elevation and level the packers and grout

    with quick setting non-shrink cement. Cure the grout for as

    long as the manufacturer of the cement recommends.

    Packers shall be so placed to allow for provision of shims

    for adjustment.

  • 8/13/2019 Erection Steps-STG 57.5 MW

    13/27

    48 hours after the packers have been grouted, they are

    ready for loading of the equipment.

    Place the Exhaust hood sole plates, the Turbine front andthe Rear Bearing pedestals. All the above shall be aligned

    w.r.t the longitudinal and transverse axes of the Turbine.

    The elevations of the parting planes of the bearing

    pedestals shall be set w.r.t to the bench mark made earlier

    and shall correspond to the machine center line.

    Place the exhaust hood lower half on the sole plates.

    Bolt the lower half of the Outer Casing with the Exhaust

    hood lower half, while taking care to match the joint. The

    joint shall be checked on either side with a dial gauge. The

    outer casing bottom half rests on jack screws on the FBP.

  • 8/13/2019 Erection Steps-STG 57.5 MW

    14/27

    A piano wire is then stretched from a temporary structure

    in front of the front bearing pedestal to a structure beyond

    the rear bearing pedestal at the same elevation as that ofthe machine centerline and shall hence forth be regarded as

    the longitudinal centerline of the machine.

    The seal bore of the pedestals and the front & rear portion

    of the casing shall be aligned w.r.t to the piano wire to anaccuracy of 0.10mm.

    Place the top half of the outer casing and the exhaust hood

    and bolt the two together. This assembly cannot be made

    later as there is no space to tighten the bolts of the vertical

    joint.

    Remove the top half of the casing and place it on a level

    surface at a convenient location.

  • 8/13/2019 Erection Steps-STG 57.5 MW

    15/27

    Level the rotor on the lifting beam and place therotor on bearings.

    Clamp dial gauges to the rotor and achievecentering values of at the Turbine front and rearseal bore, at the front gland portion and the bellowlocation of the casing as has been recorded at

    works. Insert exhaust hood radial keys.

    Remove the rotor and place it back on the stands.

    Insert eccentric pin assemblies of the BP Gland,Inner casing and GBCs.

    Place the lower halves of BP Gland, Inner casingand all Guide Blade Carriers.

  • 8/13/2019 Erection Steps-STG 57.5 MW

    16/27

  • 8/13/2019 Erection Steps-STG 57.5 MW

    17/27

  • 8/13/2019 Erection Steps-STG 57.5 MW

    18/27

    Place the bottom halves of the BP Gland, Inner

    Casing and all GBCs.

    The rotor shall now be lifted with the axialcompensator(bellow) assembled and placed in

    position.

    Restricted entry to the area may be allowed and itmay be ensured that all personnel working on the

    Turbine have emptied pockets.

    Once the rotor is placed in position, the box-up

    shall be completed with no interruptions at leastuntil the top halves of the BP Gland, Inner Casing

    and all GBCs are placed.

  • 8/13/2019 Erection Steps-STG 57.5 MW

    19/27

    Place the top halves of the BP Gland, Inner Casingand all GBCs. Apply Steam Jointing Paste at the

    parting plane. The usually recommended pastesare BIRKOSIT or STAG-B

    Heat tighten the Inner casing parting plane bolts.

    Tighten all other parting plane bolts as mentioned

    in the bolt tightening protocol. It is important tofollow the sequence of tightening as given in thedrawing.

    Remove all vertical dowel pins from the BP

    Gland, Inner Casing and all GBCs. Tack weld those nuts which have not been heat

    tightened.

  • 8/13/2019 Erection Steps-STG 57.5 MW

    20/27

    Place the outer casing top half and tighten the parting plane

    bolts.

    This completes box-up. Until this point, the entire weight of the front portion of the

    casing had been transferred to the front bearing pedestal

    vide jacking screws. Now, transfer the load of the casing

    from the jack screws to the load bearing screw and pad

    assembly in the FBP. Release the jack screw.

    Recheck centering of the Turbine casing w.r.t after

    transferring of load and in case of change, re-center the

    casing to the original values.

    Fill a sand-cement mixture into the foundation bolt sleeves,

    carryout shuttering and grout the Front Bearing pedestal,

    the Exhaust hood sole plate and the Rear Bearing Pedestal

    with quick setting cement.

  • 8/13/2019 Erection Steps-STG 57.5 MW

    21/27

    48 hrs after grouting, tighten all foundation bolts of theTurbine FBP, EH and RBP to required values mentioned inthe drawing.

    Align Generator rotor with the Turbine rotor.

    A misalignment of +0.02mm radially and axially ispermissible.

    Record free runouts of the Turbine and Generator rotors at

    the journals and the coupling. Couple the Turbine and Generator rotors using the 4

    auxiliary coupling bolts supplied and achieve runouts, thesame or with minor variation of free runout.

    Ream and Hone the coupling bolt holes and machine thebolts so as to have a clearance of 0.02mm between the boltand the hole. Stretch the coupling bolts to the requiredvalue and record coupled runout again.

  • 8/13/2019 Erection Steps-STG 57.5 MW

    22/27

    While Reaming and Honning of the Turbine-Generator

    coupling is in progress, Inter-connecting pipes between

    valves and Turbine can be installed.

    The Main Steam Inlet Insert is inserted through the outer

    casing into an opening in the inner casing. The insert is

    kept in position by ring nuts which are threaded on to the

    outer casing.

    Leakage of steam from the inner casing to the outer casing

    is sealed by the U-sealing ring.

    The inter-connecting pipes are supported by dampers and

    supports extending from the valve block.

    After welding and stress relieving of the inter-connecting

    pipes is completed, the centering of the casing w.r.t the

    rotor shall be checked.

  • 8/13/2019 Erection Steps-STG 57.5 MW

    23/27

    TURBOGENERATOR

    The Turbogenerator supplied for this project is of

    Air cooled type. 5 coolers have been supplied, ofwhich 1 shall be spare.

    The Generator Stator rests on sole plates which are

    welded at site to form an assembly.

    The Generator rotor rests on 2 bearings, much like

    the Turbine rotor.

    The air gap of the Generator is adjusted by shims

    provided underneath the bearing pedestals.

    The air gap is set and the bearing pedestals are

    dowelled.

  • 8/13/2019 Erection Steps-STG 57.5 MW

    24/27

    For alignment of the Generator rotor with the

    Turbine rotor, the Turbine rotor is assumed to be

    the reference rotor. The entire Turbogeneratorassembly is moved left/right and top/bottom to

    achieve the desired alignment.

    While carrying out the radial and axial alignment,

    care shall be taken to fix the axial position of the

    stator by measuring the axial clearances at various

    locations.

    The Generator rotor has 2 sets of fan blades, oneeach on the front and rear sides. These fan suck air

    and discharge them into the stator for cooling of

    the windings.

  • 8/13/2019 Erection Steps-STG 57.5 MW

    25/27

    The radial and axial clearances of the fan blades rings andthe end shields shall be maintained as per drawing.

    After alignment of Turbine-Generator rotors, alignment ofExciter rotor with Generator rotor shall be done.

    The Exciter rotor shall be axially aligned and swing checkcarried out. The swing check values for this Exciter shall

    be

  • 8/13/2019 Erection Steps-STG 57.5 MW

    26/27

    The Zero position of the rotor is that position of rotorabout which, the float on either side of the thrust bearing isequal i.e; the rotor has been set at mid float. It is this

    position of the rotor w.r.t which the Differential expansionprobe and the axial shift probe are set.

    While Turbovisory works are on, thermal clearances onholding down bolts at various locations are to be made as

    per drawings. On completion of Turbovisory works in the pedestals, the

    bearing pedestals can be boxed-up.

    The machine is now ready for Turning Gear operation.

    Set rotor lift of 0.07 to 0.10mm by adjusting jacking oilpressure in each bearing and put the machine on TurningGear.

    The machine is now set to receive steam.

  • 8/13/2019 Erection Steps-STG 57.5 MW

    27/27