Erection Steps-STG 57.5 MW
-
Upload
ciriuscool -
Category
Documents
-
view
239 -
download
2
Transcript of Erection Steps-STG 57.5 MW
-
8/13/2019 Erection Steps-STG 57.5 MW
1/27
PRESENTATION ON CONSTRUCTIONAL
FEATURES OF 57.02MW
STEAM TURBINEAT AES KELANITISSA
BY
G.SRIDHARDEPUTY MANAGER/BHEL
www.bhelpswr.co.in/Technical/Commissioning%20Status/.../STGCF.ppt
-
8/13/2019 Erection Steps-STG 57.5 MW
2/27
STEAM TURBINE
Single shaft non-reheat type reaction Turbine
1ststage is an impulse stage
Steam enters the turbine from the valves throughthe inter-connecting piping to the HP stages
17 HP stages
After the doing work in the HP stages, the steam
makes its way to the IP stages The IP stages are housed in Guide Blade
Carriers(GBCs) 1, 2, 3 & 4
-
8/13/2019 Erection Steps-STG 57.5 MW
3/27
GBC-1 consists of 13 stages
GBC-2 consists of 8 stages
GBC-3 consists of 4 stages
GBC-4 consists of 4 stages
The last 4 stages are housed in the Exhaust Hood
and are called the LP stages.
A very important part of the rotor is the Balance
Piston Disc/Drum which balances a major part of
the thrust that is caused by impingement of steamon to the blades. The residual thrust is absorbed by
the Thrust Bearing.
-
8/13/2019 Erection Steps-STG 57.5 MW
4/27
-
8/13/2019 Erection Steps-STG 57.5 MW
5/27
In between the 2 bearing pedestals and the casingsare the front and the rear glands. Gland steam for
sealing the motive steam from coming out of thecasing is supplied to these glands.
The exhaust hood is provided with 2 nos. ofexplosion/bursting diaphragms which will operate
when the exhaust hood pressure increases beyond acertain limit. The diaphragm is made of lead.
On either side of the Turbine are the Main SteamStop and Control Valves with servomotors. Steam
from the Boiler enters the valves through a nozzleprovided at the bottom of the valves. The valveshouse the strainer which prevents foreign particlesfrom entering the Turbine.
-
8/13/2019 Erection Steps-STG 57.5 MW
6/27
From the valves, the steam is led to the Turbine
through the Inter-connecting piping/Steam transfer
piping.
Looking from the Turbine towards the Generator,
all that is in front, is front and that at the rear, the
rear. Similarly the left and the right. The valves are fixed at the rear end in the axial
direction and at one of the resting palms in the
transverse direction thus enabling expansion of the
valve towards the front and away from the Turbinelaterally.
The rear set of thrust pads are the active pads.
-
8/13/2019 Erection Steps-STG 57.5 MW
7/27
-
8/13/2019 Erection Steps-STG 57.5 MW
8/27
The Rear Bearing pedestal houses the rear bearing
and the Turning/Barring Gear assembly. The
coupling portion of the Turbine rotor is assembledwith 1 stage of impulse blades on to which oil will
impinge when the Turning Gear valve is opened.
This will result in rotation of the rotor. For this the
rotor has to be lifted on jacking oil by 0.07 to0.10mm.
Unlike the front bearing housing, the rear bearing
housing does not slide. The rear bearing pedestal is also the house of the
Turbine-Generator coupling.
-
8/13/2019 Erection Steps-STG 57.5 MW
9/27
The Steam Turbine is equipped with the
following auxiliaries:
a. Main Oil Tank
b. Auxiliary Oil Pump-tank mounted
c. Emergency Oil Pump-tank mounted
d. Duplex Oil Filtere. Oil Coolers
f. Oil Centrifuge
g. AC & DC Jacking Oil Pumpsh. CEPs, BFPs, Deaerator etc.
-
8/13/2019 Erection Steps-STG 57.5 MW
10/27
Sequence of Steam Turbine Erection
1. Mark the longitudinal and transverse center lines
on the TG deck/verify the center lines markedby the civil agency.
2. The foundation shall be checked for dimensionalaccuracy by a measuring tape within a tolerance
of +2mm.3. Before the foundation is cast, check the location
of inserts, pockets etc. The foundation boltsleeves shall be checked for verticality and shall
not deviate by more than 3mm along the entireheight of the sleeve. The sleeves shall then belocked firmly to the reinforcement rods to arrestany movement during casting.
-
8/13/2019 Erection Steps-STG 57.5 MW
11/27
Care shall be taken to cast the entire deck in onestretch spanning 24 to 36 hours.
The dimensional and verticality check shall berepeated after casting to check for any deviationsduring casting. After the minimum curing time ofthe deck has elapsed, its ready for erection. All
dimensional checks shall be carried out withrespect to the longitudinal axis of the Turbine andthe Condenser center line.
All areas where secondary grout is to be poured or
where primary packers are to be grouted shall beroughly chipped. This is important for adhesion
between the primary and the secondary grout.
-
8/13/2019 Erection Steps-STG 57.5 MW
12/27
A bench mark for reference elevation of the TG center line
shall be transferred from the Boiler/any reference which
the civil agency has marked. The elevation of allcomponents of the Steam TurbineGenerator shall be set
w.r.t this bench mark.
Mark location of packers for placement of the Turbine
Front and Rear pedestals, Exhaust hood base plate, theGenerator sole plate and the Exciter sole plates.
Place, align, set elevation and level the packers and grout
with quick setting non-shrink cement. Cure the grout for as
long as the manufacturer of the cement recommends.
Packers shall be so placed to allow for provision of shims
for adjustment.
-
8/13/2019 Erection Steps-STG 57.5 MW
13/27
48 hours after the packers have been grouted, they are
ready for loading of the equipment.
Place the Exhaust hood sole plates, the Turbine front andthe Rear Bearing pedestals. All the above shall be aligned
w.r.t the longitudinal and transverse axes of the Turbine.
The elevations of the parting planes of the bearing
pedestals shall be set w.r.t to the bench mark made earlier
and shall correspond to the machine center line.
Place the exhaust hood lower half on the sole plates.
Bolt the lower half of the Outer Casing with the Exhaust
hood lower half, while taking care to match the joint. The
joint shall be checked on either side with a dial gauge. The
outer casing bottom half rests on jack screws on the FBP.
-
8/13/2019 Erection Steps-STG 57.5 MW
14/27
A piano wire is then stretched from a temporary structure
in front of the front bearing pedestal to a structure beyond
the rear bearing pedestal at the same elevation as that ofthe machine centerline and shall hence forth be regarded as
the longitudinal centerline of the machine.
The seal bore of the pedestals and the front & rear portion
of the casing shall be aligned w.r.t to the piano wire to anaccuracy of 0.10mm.
Place the top half of the outer casing and the exhaust hood
and bolt the two together. This assembly cannot be made
later as there is no space to tighten the bolts of the vertical
joint.
Remove the top half of the casing and place it on a level
surface at a convenient location.
-
8/13/2019 Erection Steps-STG 57.5 MW
15/27
Level the rotor on the lifting beam and place therotor on bearings.
Clamp dial gauges to the rotor and achievecentering values of at the Turbine front and rearseal bore, at the front gland portion and the bellowlocation of the casing as has been recorded at
works. Insert exhaust hood radial keys.
Remove the rotor and place it back on the stands.
Insert eccentric pin assemblies of the BP Gland,Inner casing and GBCs.
Place the lower halves of BP Gland, Inner casingand all Guide Blade Carriers.
-
8/13/2019 Erection Steps-STG 57.5 MW
16/27
-
8/13/2019 Erection Steps-STG 57.5 MW
17/27
-
8/13/2019 Erection Steps-STG 57.5 MW
18/27
Place the bottom halves of the BP Gland, Inner
Casing and all GBCs.
The rotor shall now be lifted with the axialcompensator(bellow) assembled and placed in
position.
Restricted entry to the area may be allowed and itmay be ensured that all personnel working on the
Turbine have emptied pockets.
Once the rotor is placed in position, the box-up
shall be completed with no interruptions at leastuntil the top halves of the BP Gland, Inner Casing
and all GBCs are placed.
-
8/13/2019 Erection Steps-STG 57.5 MW
19/27
Place the top halves of the BP Gland, Inner Casingand all GBCs. Apply Steam Jointing Paste at the
parting plane. The usually recommended pastesare BIRKOSIT or STAG-B
Heat tighten the Inner casing parting plane bolts.
Tighten all other parting plane bolts as mentioned
in the bolt tightening protocol. It is important tofollow the sequence of tightening as given in thedrawing.
Remove all vertical dowel pins from the BP
Gland, Inner Casing and all GBCs. Tack weld those nuts which have not been heat
tightened.
-
8/13/2019 Erection Steps-STG 57.5 MW
20/27
Place the outer casing top half and tighten the parting plane
bolts.
This completes box-up. Until this point, the entire weight of the front portion of the
casing had been transferred to the front bearing pedestal
vide jacking screws. Now, transfer the load of the casing
from the jack screws to the load bearing screw and pad
assembly in the FBP. Release the jack screw.
Recheck centering of the Turbine casing w.r.t after
transferring of load and in case of change, re-center the
casing to the original values.
Fill a sand-cement mixture into the foundation bolt sleeves,
carryout shuttering and grout the Front Bearing pedestal,
the Exhaust hood sole plate and the Rear Bearing Pedestal
with quick setting cement.
-
8/13/2019 Erection Steps-STG 57.5 MW
21/27
48 hrs after grouting, tighten all foundation bolts of theTurbine FBP, EH and RBP to required values mentioned inthe drawing.
Align Generator rotor with the Turbine rotor.
A misalignment of +0.02mm radially and axially ispermissible.
Record free runouts of the Turbine and Generator rotors at
the journals and the coupling. Couple the Turbine and Generator rotors using the 4
auxiliary coupling bolts supplied and achieve runouts, thesame or with minor variation of free runout.
Ream and Hone the coupling bolt holes and machine thebolts so as to have a clearance of 0.02mm between the boltand the hole. Stretch the coupling bolts to the requiredvalue and record coupled runout again.
-
8/13/2019 Erection Steps-STG 57.5 MW
22/27
While Reaming and Honning of the Turbine-Generator
coupling is in progress, Inter-connecting pipes between
valves and Turbine can be installed.
The Main Steam Inlet Insert is inserted through the outer
casing into an opening in the inner casing. The insert is
kept in position by ring nuts which are threaded on to the
outer casing.
Leakage of steam from the inner casing to the outer casing
is sealed by the U-sealing ring.
The inter-connecting pipes are supported by dampers and
supports extending from the valve block.
After welding and stress relieving of the inter-connecting
pipes is completed, the centering of the casing w.r.t the
rotor shall be checked.
-
8/13/2019 Erection Steps-STG 57.5 MW
23/27
TURBOGENERATOR
The Turbogenerator supplied for this project is of
Air cooled type. 5 coolers have been supplied, ofwhich 1 shall be spare.
The Generator Stator rests on sole plates which are
welded at site to form an assembly.
The Generator rotor rests on 2 bearings, much like
the Turbine rotor.
The air gap of the Generator is adjusted by shims
provided underneath the bearing pedestals.
The air gap is set and the bearing pedestals are
dowelled.
-
8/13/2019 Erection Steps-STG 57.5 MW
24/27
For alignment of the Generator rotor with the
Turbine rotor, the Turbine rotor is assumed to be
the reference rotor. The entire Turbogeneratorassembly is moved left/right and top/bottom to
achieve the desired alignment.
While carrying out the radial and axial alignment,
care shall be taken to fix the axial position of the
stator by measuring the axial clearances at various
locations.
The Generator rotor has 2 sets of fan blades, oneeach on the front and rear sides. These fan suck air
and discharge them into the stator for cooling of
the windings.
-
8/13/2019 Erection Steps-STG 57.5 MW
25/27
The radial and axial clearances of the fan blades rings andthe end shields shall be maintained as per drawing.
After alignment of Turbine-Generator rotors, alignment ofExciter rotor with Generator rotor shall be done.
The Exciter rotor shall be axially aligned and swing checkcarried out. The swing check values for this Exciter shall
be
-
8/13/2019 Erection Steps-STG 57.5 MW
26/27
The Zero position of the rotor is that position of rotorabout which, the float on either side of the thrust bearing isequal i.e; the rotor has been set at mid float. It is this
position of the rotor w.r.t which the Differential expansionprobe and the axial shift probe are set.
While Turbovisory works are on, thermal clearances onholding down bolts at various locations are to be made as
per drawings. On completion of Turbovisory works in the pedestals, the
bearing pedestals can be boxed-up.
The machine is now ready for Turning Gear operation.
Set rotor lift of 0.07 to 0.10mm by adjusting jacking oilpressure in each bearing and put the machine on TurningGear.
The machine is now set to receive steam.
-
8/13/2019 Erection Steps-STG 57.5 MW
27/27