Project Name
RevDrawing No
Scale :
Original Drawing Size :
Drawing Title
Dimensions :A1
As constructed
For construction
Date:
Design:
Drawn: For tender
For target cost
Preliminary
c
Copyright Amey
www.amey.co.ukwww.staffordshire.gov.uk
Trim
to this line for A1
..
010
20
30
40
50
100
A1
J:\H
ighw
ays\M
ajor Projects\Pow
erhouse Central\Branston Locks\1. Phase O
ne - Link Road and Canal Bridge\CAD
\D
isciplines\W
IP\1 Live D
rgs\CD
X8620-R05-13 - Service ducting.dw
g
CD
X8620-R05-13
Grid reference :
Approved by:- (Drawing NOT approved if this box is empty)
Checked by:-
Original Version
CDX8620/R05/13 T0
Service Ducting
1:500
RS
RS
Other
Branston Locks - Phase One
CONSULTING
Revisions
Rev Detail
By
Date
Notes
1. For details of existing services refer to Drawing
Number CDX8620/R27/01-07
2. For details of new service provision works refer
to Drawing Number CDX8620/R27/09-13 and
Appendix 1/16
3. For details of street lighting proposals refer to
Drawing Number SCC-HL-1001
4. For drainage proposals refer to Drawing Number
CDX8620/R05/01-12
5. For details of illuminated traffic signs refer to
Drawing Number CDX8620/R12/01 & 03.
6. Main contractor to excavate for and lay one way
125mm dia. black coloured ducts to verge and
footway areas providing a cover of 450mm,
indicated thus:-
7. Main contractor to excavate for and lay two way
125mm dia. black coloured ducts to verge and
footway areas providing a cover of 750mm,
indicated thus:-
8. Main contractor to excavate and lay one way
100mm dia. orange coloured duct to carriageway
providing cover of 750mm indicated thus:-
9. Joint pit for LV/SL connection to be provided
approximately every 250m.
Straight joint ( 2 x 1 x 0.75m)
Breech joint (2.5 x 1 x 0.75 metres)
9. The exact cable/ducting requirements between
the DLH mains cable network and private cable
network is to be agreed during the target Cost
10. Street Lighting orders shall be placed by SCC.
11. All works and materials to be supplied and
installed fully compliant with the latest issue of
the following E-on Street Lighting documents;
i) 'Street Lighting Design Policy', ref SLP500.
ii) 'Specification for Road Lighting and Lit Traffic
Signs on New Developments' document ref
SLP501.
iii) 'Highway Works Detail Drawings', document
ref SLP502.
iv) Trench depths in pavement or private land
shall be 530mm (min. cover over cable 450mm)
and in carriageway shall be 600mm (min. cover
520mm).
v) Where cables are not protected in a duct they
must be blinded with 75mm of crushed stone
dust and approved yellow 'electric cable' marker
tape laid above.
vi) For details of WPD ducting requirements refer
to quotation
vii) It is the responsibility of the contractor to liaise
with the DLH for a mains service to street lighting
and lit traffic signs unless otherwise instructed.
The Main Contractor shall;
excavate all trenches and intermediate cable joint bays
(2000mm-2500mm) to the specification and satisfaction of
WPD.
supply and lay 'danger electric cable' warning tape to
specification ENA TS 12-23 and shall cover the ducts.
ensure that trench depths in pavement or private land shall
be 530mm (min. cover over cable 450mm) and in
carriageway shall be 600mm (min. cover 520mm).
ensure that trench width for single cable is 300m and for
two cables 400mm (min. 150mm spacing).
shall liaise with WPD/E-on representative prior to
undertaken any works.
shall be responsible for all traffic management and
co-ordination including that required by WPD/Eon for their
installation and jointing works.