NCOP SELECT COMMITTEE ON COMMUNICATIONS AND PUBLIC ENTERPRISES22 April 2015
PRESENTATION ON THE STRATEGIC PLAN AND THE ANNUAL PERFORMANCE PLAN OF THE DEPARTMENT OF COMMUNICATIONS
1
Presentation Outline
2
Purpose
Strategic Overview
Vision, Mission and Value Statement
Mandate
Planned Policy and Legislative Initiatives
Situational Analysis
Organisational Environment
Strategic Outcome Oriented Goals
Programme Overview
Resource Plan
Five-Year Programme Strategic Plans and 2015/16 Annual Performance Plan Priorities
Purpose
3
• The purpose of this Presentation is to present the Strategic Plan (2015/16 to 2019/20) and the Annual Performance Plan (2015/16 – 2017/18) of the Department of Communications to NCOP Select Committee on Communications and Public Enterprises.
• The Strategic overview for both the Strategic Plan and the Annual Performance Plan are the same given the fact that the two plans are still new.
• The programme strategic five year targets of the Strategic Plan are summarised together with the APP 2015/16 targets in the same tables for easy reference.
National Treasury Strategic Plan and Annual Performance Plan Requirements
4
5
Vision and Mission
Vision•Vibrant and sustainable communication services for an informed citizenry and positive image of South Africa
Mission•Create an enabling environment for the provision of inclusive communication services to all South Africans in a manner that promotes socio-economic development and investment through broadcasting, new media, print media and other new technologies, and brand the country locally and internationally.
Value Statement
6
• Certainty of the policy environment• People centred• Quality standards of products and services• Integrity• Responsiveness• Innovation
Constitutional Mandate
7
• The Department's Constitutional mandate is derived from the Bill of Rights in the Constitution of the Republic of South Africa in particular the principles of freedom of expression, freedom to receive or impart information or ideas and freedom of artistic creativity.
• Its main focus is to deepen democracy and sustain nation-building and patriotism by ensuring that the citizenry is informed about government programmes and that they are able to influence and participate in such programmes.
Legislative and Other Mandates
8
The DOC derives its legislative mandate primarily from following Acts:•Broadcasting Act (Act 4 of 1999);•Electronic Communications Act (Act 36 of 2005);•Independent Communications Authority of South Africa Act (Act 13 of 2000);•Film and Publications Act (No. 65 of 1996)•Media Development and Diversity Act (No.14 of 2002)
Legislative and Other Mandates
9
The Department is also guided, amongst others, by:•The Constitution of the Republic of South Africa, 1996 (Act 108 of 1996);•The Public Service Act, 1994 (Act 103 of 1994) as amended;•The Public Finance Management Act, 1999 (Act 1 of 1999) as amended.•International Telecommunications Union (ITU); and•World Intellectual Property Organisation (WIPO).
Legislative and Other Mandates
10
The Department' mandates are derived from the President's pronouncement when establishing the Department, and these are:
Develop an overarching communications and broadcasting policy and strategy;
Provide information, dissemination and publicity to promote an informed citizenry; and
Brand South Africa abroad to assist the country promote investments, economic growth and job creation.
Planned Policy and Legislative Initiatives
11
The Department will in the medium term focus on developing the following policies:
•An overarching communication policy •An overarching broadcasting policy•A community media and broadcasting support strategy •A media bulk-buying strategy
Planned Policy and Legislative Initiatives
12
On the legislative front the Department will amend the following legislation:
•Broadcasting Amendment Bill.•ICASA Amendment Bill.•MDDA Amendment Bill.•Films and Publications Board Amendment Bill.•Brand SA Bill.
Situational Analysis
13
• Communication plays an important supportive role in the realisation of Government strategic objectives as outlined in the National Development Plan and the Medium-Term Strategic Framework
• It energises and mobilises the nation to take active role in realising the government's programme of radical economic transformation which addresses poverty, unemployment and inequality.
• It is a catalyst in promoting nation-building, unity and social cohesion.
• It protects and defends the image of government by proactively communicating government messages and showcasing delivery successes, challenges and corrective action plans.
Situational Analysis
14
• Government communication happens largely at three levels, namely, print media, broadcasting and face-to-face engagement with the citizens through programmes such as Izimbizo
• Key challenges that need to be addressed and which informs the Department’s strategic plans are:– The media has remained largely dominated by monopoly players with
its ownership and management remaining far below prevailing population demographics, hence the need for transformation
– Communication content which is driven by a minority of companies– The challenges posed by the emergence of social media– Poor funding of the public broadcaster– Inadequate performance of public and community broadcasting
Situational Analysis
15
Key challenges that needs to be addressed and which informs the Department’s strategic plans are:
– Governance challenges of state owned entities– Delayed digital migration project– Inadequate communication of government programmes
and plans
Organisational Environment
16
The Department of Communications is made up of three Branches and two Chief Directorates:
Communications Policy, Research
and Development
Branch
Industry and Capacity
Development Branch
Entity Oversight Branch
DEPARTMENT OF COMMUNICATIONS
Corporate Services Chief Directorate
Financial Management Chief Directorate
Organisational Environment
17
The following entities report to the Department of Communications:
Department of Communications
GCIS
MDDA
FPB
ICASA
SABC
Brand SA
Strategic Oriented Goals
18
• The following strategic goals and strategic Objectives have been set to achieve the Department’s mandate as set out by the President:
Strategic Goals Strategic Objectives
A responsive communications policy and regulatory environment
Conduct research in order to improve universal access to broadcasting services by 31 March 2019 Conduct research and develop the broadcasting spectrum policy and plan in order to ensure equitable allocation of spectrum to public, private and community players by 31 March 2017 Develop broadcasting policy papers for international engagements
Strategic Oriented Goals
19
Strategic Goals Strategic Objectives
Improved Government communication and country branding
Conduct research and develop media policies in order to broaden access to information by all citizens by 31 March 2019
Conduct research and develop branding policies that positively market the country locally and internationally in a manner that promotes socioeconomic development and investment by 31 March 2019
Transformed communications sector Build a competitive communications industry through the
implementation of targeted interventions to support the
growth and development of the creative industries by 31
March 2019Manage digital broadcasting migration to ensure the successful migration from analogue to digital television in South Africa within 2 years
Strategic Oriented Goals
20
Strategic Goals Strategic Objectives
Transformed communications sector Manage industry research and analysis on an on-going basis to ensure evidence based policy making through the provision of qualitative and quantitative analysisDevelop and implement structured programmes of intergovernmental and stakeholders engagement in order to leverage support to strategic priorities of the Department by 31 March 2018
Implementation of the National Development Plan and the Outcomes Approach
21
• Outcome 14 - Nation Building and Social Cohesion• The Department plays a role in implementing Outcome 14:
Nation Building and Social Cohesion. • It is expected to provide support to the Department of Sport
and Recreation in improving the pride South Africans have in the national sporting teams. The target is achieving 66% by 2019.
• The Department has a role in "Forging a new overarching identity". It needs to influence South Africans to be proud South Africans and it has to improve the target from 66% to 75% of South Africans reflecting pride to be South Africans.
Implementation of the National Development Plan and the Outcomes Approach
22
Outcome 14 - Nation Building and Social Cohesion•The Department has also a role in improving identity based on self-description, from 52% to 60% target. •It will also drive a broadcasting system that preserves, informs and reflects the cultural heritage of all South Africans with a view to achieving 70% content that reflects South Africans.
The above targets forms part of the Performance Agreement of the Minister of Communications and the President signed towards the end of 2014.
Programme Overview
23
Programme Purpose
Programme 1 - Administration
To provide coordinated strategic and administrative support services to enable the Ministry and the Department to deliver on their mandates
Programme 2 - Communications Policy, Research and Development
To conduct research and develop communications and broadcasting policies
Programme 3 - Industry and Capacity Development
To manage enterprise development, broadcasting digital migration and industry research and analysis
Programme 4 - Entity Oversight
To monitor the implementation of policies by state owned enterprises and regulatory institutions and to provide guidance and oversight on their governance matters
Resource Plan
24
Programme
2014-2015
(GCIS Budget)
2015-2016 2016-2017 2017-2018
Administration R24 800 000 R42 400 000 R45 100 000 47 500 000
Communications Policy, Research and Development
R6 500 000 R7 900 000 R8 400 000 8 900 000
Industry and Capacity Development
R9 300 000 R10 200 000 R10 900 000 11 600 000
Entity Oversight R1 226 600 000 R1 220 400 000 R1 280 300 000 1 350 900 000
Total R1 267 200 000 R1 280 900 000 R1 344 700 000 1 418 900 000
Five-Year Strategic Plan Targets and 2015/16 Annual Performance Plan Priorities
25
Programme 1: AdministrationFive-Year Strategic Plan Targets and 2015/16 Priorities
26
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Develop and implement policies, plans, procedures and set up HRM&D systems
Approved Human Resource Management and Development policies and plans including setting up of HRMD systems
Develop and approve policies, plans, procedures, and set up HRM&D systems
Prepare and submit reports on the implementation of HRM&D plans
20 reports on the implementation of HRM&D plans
4 reports on the implementation of HRM&D plans
Prepare and submit workplace skills plans to the Public Service Sector Education and Training Authority (PSeta)
5 Workplace skills plans prepared and submitted to the Public Service Sector Education and Training Authority (PSeta)
1 workplace skill plan prepared and submitted
Compile and implement employment equity plan
20 reports compiled against the employment equity plan
4 employment equity reports compiled
Implement employee wellness programmes
20 Employee wellness programmes reports compiled
4 employee wellness programmes reports compiled
Implement learnership programmes
Learnership programmes implemented and 20 reports compiled
Implement learnership programmes and compile 4 reports
Programme 1: AdministrationFive-Year Strategic Plan Targets and 2015/16 Priorities
27
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Implement Internship programme
Internship programme implemented and 20 reports compiled
Implement Internship programme and compile 4 reports
Advertise and recruit staff Staff recruitment
Advertise and recruit staff
Develop and implement induction and capacity development programmes to staff
Induction and capacity development programmes to staff developed and implemented
20 reports compiled
Develop and implement induction and capacity development programmes to staff and compile 4 reports
Develop or apply Information and Communication Technology policies relevant to the public service
Information and Communication Technology policies relevant to the public service developed or applied
Develop or apply Information and Communication Technology policies relevant to the public service
Develop and implement Information and Technology Management strategy and plan
Information and Technology Management strategy and plan developed, implemented and 20 reports compiled
Develop and implement Information and Technology Management strategy and plan
4 reports compiled
Programme 1: AdministrationFive-Year Strategic Plan Targets and 2015/16 Priorities
28
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Procure and manage information technology and systems
Information technology and systems procured and managed
20 reports -
Procure and manage information technology and systems
4 reports compiled
Develop and implement Facilities Management policies
Facilities management policies developed, implemented and 16 reports compiled
Develop and implement facilities management policies and compile 4 quarterly reports
Develop and implement security management policies
Security management policies developed, implemented and 16 reports compiled
Develop and implement security management policies
Compile 4 quarterly reports
Procure and implement security systems
Security systems procured and implemented
Procure and implement security systems
Programme 1: AdministrationFive-Year Strategic Plan Targets and 2015/16 Priorities
29
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Develop and implement information security measures including Minimum Information Security System
Information security measures including Minimum Information Security System developed and implemented
Develop and implement information security measures including Minimum Information Security System
Develop and implement communication policies, plans and procedures
Communication policies, plans and procedures developed
20 quarterly communication reports compiled
Develop and implement communication policies, plans and procedures
4 quarterly communications reports compiled
Set up and manage communication systems
Communication systems set up and managed
20 reports compiled
Set up and manage communication systems
4 quarterly reports compiled
Programme 1: AdministrationFive-Year Strategic Plan Targets and 2015/16 Priorities
30
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Develop communication content, graphics, publications branding and marketing materials
Communication content, graphics, publications, branding and marketing materials developed
20 reports compiled
Develop communication content, graphics, publications, branding and marketing materials
4 quarterly reports compiled
Render legal services to the Department
Legal services rendered to the Department and 20 reports compiled
Render legal services to the Department
4 quarterly reports compiledManage contracts, memoranda of understanding, legal instruments and litigation
Contracts, memoranda of understanding, legal instruments and litigation managed and 20 reports compiled
Manage contracts, memoranda of understanding, legal instruments and litigation
4 quarterly reports compiled
Programme 1: AdministrationFive-Year Strategic Plan Targets and 2015/16 Priorities
31
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Review legislation and prepare bills
Reviewed legislation and prepared bills
20 reports compiled
Review legislation and prepare bills
4 quarterly reports compiled
Prepare, submit, implement and review 5-year Strategic Plan
5-year Strategic Plan prepared, approved and reviewed
Prepare and get approval for the 5-year Strategic Plan
Prepare, submit and implement Annual Performance Plan
5 Annual Performance Plans prepared and approved
1 Annual Performance Plans prepared and approved
Prepare and submit Annual Report
5 Annual Reports prepared and submitted to the Executive, the Presidency and Parliament
Prepare and submit 1 Annual Report
Programme 1: AdministrationFive-Year Strategic Plan Targets and 2015/16 Priorities
32
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Prepare and submit quarterly reports
20 quarterly reports prepared and submitted to the executive and regulatory authorities
4 quarterly reports on the implementation of APP prepared and submitted to the executive authority and regulatory bodies
Prepare and submit annual monitoring and evaluation report
5 Annual monitoring and evaluation reports prepared and submitted to the executive authority
1 Annual monitoring and evaluation report prepared
Implement Management Performance Assessment Tool (MPAT) to improve performance and compliance
Management Performance Assessment Tool implemented to improve performance and compliance achieving a score of 4 (satisfactory performance)
Implement Management Performance Assessment Tool to improve performance and compliance and achieve a score of 3
Programme 1: AdministrationFive-Year Strategic Plan Targets and 2015/16 Priorities
33
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Develop and implement financial policies, plans and procedures
Financial policies, plans and procedures developed and 20 financial reports compiled
Develop and implement financial policies, plans and procedures
4 quarterly financial reports compiled
Prepare and manage budget in line with National Treasury legislation and guidelines
Budget is prepared and managed in line with National Treasury legislation and guidelines
Prepare and manage budget in line with National Treasury legislation and guidelines
Comply with National Treasury reporting requirements
20 quarterly financial reports submitted to National Treasury
4 quarterly financial reports submitted to National Treasury
Prepare and submit financial statements for audit within set timeframes
Unqualified audited financial statements by the Auditor General
Obtain unqualified audit opinion from the Auditor General on financial statements
Programme 1: AdministrationFive-Year Strategic Plan Targets and 2015/16 Priorities
34
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Develop and implement Supply Chain Management Policy
Supply Chain Management Policy developed and 20 implementation reports compiled
Develop and implement Supply Chain Management Policy
4 SCM implementation reports compiled
Compile and implement Procurement Plan
Procurement Plan compiled and 20 implementation reports compiled
Compile and implement Procurement Plan
4 implementation reports compiled
Develop and implement Asset Management Plan
Asset Management Plan developed and 20 implementation reports compiled
Develop Asset Management Plan
4 implementation reports compiled
Programme 1: AdministrationFive-Year Strategic Plan Targets and 2015/16 Priorities
35
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Develop and implement risk management policy, strategy and plan
Risk management policy, strategy and plan developed and 20 implementation reports compiled
Develop and implement risk management policy, strategy and plan
4implementation reports compiled
Implement systems of risk management and control
Systems of risk management and control implemented and 20 implementation reports compiled
Implement systems of risk management and control
4 implementation reports compiled
Conduct regular risk identification, assessment and monitoring
10 risk identification and assessment reports compiled
2 risk identification and assessment reports compiled
Develop and implement fraud prevention policy
Fraud prevention policy developed and 20 implementation reports compiled
4 implementation reports compiled
Programme 1: AdministrationFive-Year Strategic Plan Targets and 2015/16 Priorities
36
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Develop and implement internal audit policy and plan
Internal audit policy and plan developed, approved and 20 quarterly reports compiled
Internal audit policy and plan developed and approved
4 quarterly internal audit reports compiled
Manage and conduct compliance audits
20 compliance audit reports compiled
4 compliance audit reports compiled
Manage and conduct performance audits
20 Performance audit reports compiled
4 Performance audit reports compiled
Coordinate and facilitate forensic investigations
20 forensic investigation reports compiled
4 forensic investigation reports compiled
Programme 2: Communication Policy, Research and Development
Five-Year Strategic Plan Targets and 2015/16 Priorities
37
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Conduct broadcasting Policy review, develop, adopt and implement White Paper on Broadcasting policy
Broadcasting policy reviewed and White Paper on Broadcasting policy developed, adopted and implemented
8 implementation monitoring reports compiled
Conduct broadcasting policy review and develop
Green Paper and white Paper on Broadcasting Policy for South Africa for Cabinet approval
Draft the Broadcasting Amendment Bill, obtain Cabinet approval, facilitate enactment by Parliament and monitor implementation
Broadcasting Amendment Bill drafted, approved by Cabinet, enacted into law by Parliament and its implementation monitored
8 implementation monitoring reports compiled
Broadcasting Amendment Bill drafted, approved by Cabinet and enacted into law by Parliament
Programme 2: Communication Policy, Research and Development
Five-Year Strategic Plan Targets and 2015/16 Priorities
38
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Draft the ICASA Amendment Bill, obtain Cabinet approval, facilitate enactment by Parliament and monitor implementation
ICASA Amendment Bill drafted, approved by Cabinet, enacted into law by Parliament and its implementation monitored
8 implementation monitoring reports compiled
ICASA Amendment Bill drafted, approved by Cabinet and enacted into law by Parliament
Develop, implement and monitor Community Broadcasting Support Strategy
Community Broadcasting Support Strategy developed, implemented and monitored
8 implementation monitoring reports compiled
Community Broadcasting Support Strategy developed and approved
39
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Broadcast and communication policies and legislation approved for implementation
15 broadcasting and communication policies and legislation approved for implementation
3 broadcasting and communication policies and legislation approved and implemented
Develop broadcasting policy papers for international engagements
10 broadcasting policy papers produced for international engagements
2 broadcasting policy papers produced for international engagements
Conduct research and develop a broadcasting radio frequency spectrum dividend policy which will be used to issue policy directions to ICASA.
Broadcasting radio frequency spectrum dividend policy research conducted, the policy developed and policy directions issued to ICASA
Policy direction at least one once per annum
Research conducted on broadcasting radio frequency spectrum dividend policy and policy developed
Programme 2: Communication Policy, Research and Development
Five-Year Strategic Plan Targets and 2015/16 Priorities
Programme 1: AdministrationFive-Year Strategic Targets and 2015/16 Priorities
40
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Produce set top boxes 481 000 set top boxes produced
235 000 set top boxes produced
Provide community radio stations with broadcasting infrastructure
5 community radio stations provided with broadcasting infrastructure
5 community radio stations provided with broadcasting infrastructure
Develop and obtain Cabinet approval of a National Communication Policy and Plan which include branding of the country.
Cabinet approved National Communication Policy and Plan and 18 quarterly implementation reports compiled
National Communication Policy developed and approved by Cabinet
2 quarterly implementation reports compiled
Programme 2: Communication Policy, Research and Development
Five-Year Strategic Plan Targets and 2015/16 Priorities
Programme 1: AdministrationFive-Year Strategic Targets and 2015/16 Priorities
41
Key Priority 5-Year Output / Target 2015/16 APP PrioritiesDevelop a media transformation, diversity and development policy
Media Transformation Policy developed and approved by Cabinet and 8 monitoring reports compiled
Media Transformation policy developed and approved by Cabinet
Media Development and Diversity Position Paper developed, approved and recommendations implemented
8 implementation reports compiled
Media Development and Diversity Position Paper developed and approved
MDDA Amendment Bill developed and approved by Cabinet, enacted into law by Parliament and its implementation monitored
8 monitoring reports compiled
MDDA Amendment Bill approved by Cabinet and enacted into by Parliament
Programme 2: Communication Policy, Research and Development
Five-Year Strategic Plan Targets and 2015/16 Priorities
Programme 1: AdministrationFive-Year Strategic Targets and 2015/16 Priorities
42
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Implement community media projects
120 community media projects implemented
20 community media projects implemented
Develop, adopt and implement Community Media Support Strategy
Community Media Support Strategy developed, adopted and implemented
8 implementation reports compiled
Community Media Support Strategy developed and adopted
Draft Films and Publications Board Amendment Bill
Films and Publications Board Bill drafted, enacted into law by Parliament and its implementation monitored
8 implementation reports compiled
Films and Publications Board Bill drafted and enacted into law by Parliament
Programme 2: Communication Policy, Research and Development
Five-Year Strategic Plan Targets and 2015/16 Priorities
Programme 1: AdministrationFive-Year Strategic Targets and 2015/16 Priorities
43
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Review the films and media classification system
Films and media classification system reviewed, review paper approved by Cabinet and its implementation monitored
8 implementation monitoring reports compiled
Films and media classification system reviewed and review paper approved by Cabinet
Develop and implement Brand South Africa legislation.
Brand SA Act passed by Parliament and 8 bi-annual monitoring reports compiled
Brand SA Bill developed, approved by Cabinet and enacted into law by Parliament.
Programme 2: Communication Policy, Research and Development
Five-Year Strategic Plan Targets and 2015/16 Priorities
Programme 1: AdministrationFive-Year Strategic Targets and 2015/16 Priorities
44
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Develop, adopt and implement the Audio visual digital content development strategy.
1 Audio Digital Content Development Strategy developed, adopted and implemented
8 implementation reports compiled
1 Audio Digital Content Development Strategy developed and adopted
Develop content which reflects South African perspectives and cultural diversity
70% content that reflects South African perspectives and cultural diversity
55% content reflecting South African perspectives and cultural diversity
Improve South African national identity based on self-description
60% improvement in South African national identity based on self-description
53% improvement in South African national identity based on self-description
Programme 3: Industry and Capacity DevelopmentFive-Year Strategic Plan Targets and 2015/16 Priorities
Programme 1: AdministrationFive-Year Strategic Targets and 2015/16 Priorities
45
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Improve the number of South Africans reflecting pride to be South Africans
75% South Africans reflecting pride to be South Africans
35% South Africans reflecting pride to be South Africans
Establish a South African Broadcast Production Advisory Body
Establishment of the South African Broadcast Production Advisory Body
Establish a South African Broadcast Production Advisory Body
Facilitate the development, approval and implementation of skills in the broadcasting industry
Development and approval of Broadcasting Skills Development Programme and 10 implementation reports compiled
Development and approval of Broadcasting Skills Development Programme
2 implementation reports compiled
Programme 3: Industry and Capacity DevelopmentFive-Year Strategic Plan Targets and 2015/16 Priorities
46
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Migration from analogue to digital broadcasting.
Digital broadcasting migrated from analogue and analogue signal switched-off within timelines
Migration from analogue to digital broadcasting.
4 quarterly reports on digital migration from analogue compiled
13 000 000 TV owning households reached through digital broadcasting awareness campaign
6 500 000 TV owning households reached through digital broadcasting awareness campaign
20 quarterly reports showing consumer access to digital broadcasting in particular those supported by government programmes
4 quarterly reports showing consumer access to digital broadcasting in particular those supported by government programmes
Industry research and trend analysis
10 industry research and trend analysis reports compiled
2 industry research and trend analysis reports compiled
Programme 3: Industry and Capacity DevelopmentFive-Year Strategic Plan Targets and 2015/16 Priorities
47
Key Priority 5-Year Output / Target 2015/16 APP PrioritiesDevelop, adopt and implement an inter-governmental relations framework
1 adopted inter-governmental relations framework and 18 quarterly implementation reports compiled
1 adopted inter-governmental relations framework
2 Inter-governmental relations Framework implementation reports compiled
Develop, adopt and implement stakeholder engagement framework
1 adopted Stakeholder engagement framework and 18 quarterly implementation reports compiled
1 adopted Stakeholder engagement framework
2 Stakeholder Engagement Framework implementation reports compiled
Develop, adopt and implement an international stakeholder engagement strategy
1 adopted international stakeholder engagement strategy and 18 quarterly implementation reports compiled
1 adopted international stakeholder engagement strategy
2 International stakeholder engagement strategy implementation reports compiled
Programme 3: Industry and Capacity DevelopmentFive-Year Strategic Plan Targets and 2015/16 Priorities
48
Key Priority 5-Year Output / Target 2015/16 APP Priorities
Monitor compliance of all entities with all relevant legislations and regulations
20 Quarterly entity oversight reports submitted to the Executive Authority
4 quarterly entity oversight reports submitted to the Executive Authority
Performance Management System of ICASA Chairperson and Councillors implemented 100%
100% implementation of Performance Management System of ICASA Chairperson and Councillors
Presidential Review Committee report on SOE’s analysed.
1 Presidential Review Committee report on SOE’s analysed
Review Shareholder Compact Review of shareholder compact/Accountability arrangements of 6 entities reporting to the Minister and 30 implementation monitoring reports compiled
Review of 6 entities shareholder compact/ Accountability arrangements and 6 implementation monitoring reports compiled
Programme 4: Entity Oversight Five-Year Strategic Plan Targets and 2015/16 Priorities
49
Key Priority 5-Year Output / Target 2015/16 APP Priorities
SOE strategy and policy alignment
10 reports on alignment of entities strategies to Departmental priorities
2 reports on alignment of entities strategies to Departmental priorities compiled
Compile monitoring reports on the performance of regulatory institutions and issue policy directions as and when required
10 Monitoring reports on the performance of regulatory institutions compiled and policy directions issued as and when required
Compile 2 monitoring reports on the performance of regulatory institutions and issue policy directions as and when required
Compile reports on entity funding requests
60 entity funding requests reports compiled
12 entity funding requests reports compiled
Review funding of entities and implement review recommendations
Funding of entities reviewed and recommendations implemented
2 reports compiled
Review funding of entities and 1 report compiled
Programme 4: Entity Oversight Five-Year Strategic Plan Targets and 2015/16 Priorities
Thank You