![Page 1: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/1.jpg)
NCDENRDivision of Waste Management
Underground Storage Tank Section
![Page 2: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/2.jpg)
Discover a release BEFORE a major contamination occurs
Required for regulated systems:
EXCEPTIONS:
Temporarily closed tanks
Emergency generator tanks installed before 11/1/07
![Page 3: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/3.jpg)
Conducted monthly
Detects a release from any portion of the tank
Manufacturer’s instructions dictate installation, calibration, operation and maintainance
![Page 4: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/4.jpg)
Third Party Certification:
documentation that your leak detection method works for your UST system
All Methods Have Limitations
- e.g. - tank size, minimum fuel levels, throughput, “down time”
![Page 5: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/5.jpg)
A
Statistical Inventory
Reconciliation (SIR)
B
AutomaticTank Gauging (ATG) Systems
C
Secondary Containment
with Interstitial Monitoring
![Page 6: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/6.jpg)
Leak DetectionGeneral
10 – Tank – Primary leak detection method
9/1/2016
• SIR (Statistical Inventory Reconciliation)
• ATG
(Automatic Tank Gauge)
• IM
(Interstitial Monitoring)
• N/A
(Generator tank)
• Unknown?
![Page 7: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/7.jpg)
7
10
![Page 8: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/8.jpg)
AStatistical Inventory
Reconciliation (SIR)
AutomaticTank Gauging (ATG) Systems
Secondary Containment
with Interstitial Monitoring
![Page 9: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/9.jpg)
![Page 10: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/10.jpg)
The analysis of the inventory, delivery, and
dispensing data to detect leaks
![Page 11: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/11.jpg)
Use stick or ATG console
Measure product level
daily – to nearest 1/8th
inch
Measure water levels
monthly
![Page 12: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/12.jpg)
Replace broken
or unreadable tank sticks
Have same person stick tanks daily
Stick tanks and read meters at same time daily
![Page 13: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/13.jpg)
Product measurement:
per tank, DAILY, for 12 months
Water measurement:
per tank, MONTHLY, for 12 months
![Page 14: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/14.jpg)
Use appropriate calibration charts
Supply daily inventory to SIR vendor each month
Review SIR reports when received from vendor
Make sure dispensers calibrated within past 18
months
![Page 15: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/15.jpg)
Keep SIR Reports:
per tank, PER MONTH, for 12 months
![Page 16: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/16.jpg)
SIRp.16
Fuel daily,Water
Monthly,Submit to
vendor monthly
Calibration charts,daily Fuel,
monthly Water,Monthly SIR reports
All for a year
--/--/--
10
![Page 17: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/17.jpg)
Statistical Inventory
Reconciliation (SIR)
BAutomatic
Tank Gauging Systems (ATG)
Secondary Containment
with Interstitial Monitoring
![Page 18: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/18.jpg)
Console located inside facility
Probe installed at tank
![Page 19: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/19.jpg)
Probe permanently installed
Wired to monitor
Product level and temperature recorded
Calculates changes in product volume
![Page 20: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/20.jpg)
Check if:
• Wires intact
• Capped
![Page 21: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/21.jpg)
![Page 22: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/22.jpg)
• Present
• Powered on
• No warnings
• No alarms
![Page 23: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/23.jpg)
UST Site Diagram for: _____________________________________________
*
Fuel Mart 27
Raleigh Blvd
Hart Road
Fuel Mart 27
UST
Spill Bucket
Overfill PreventionFlapper Valve
*
*
*
Vapor RecoveryCoaxial
STP
ATG
Dispenser
ATG Console
IM Console
Rectifier
Probe
![Page 24: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/24.jpg)
How much is a 0.2 gphleak?
![Page 25: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/25.jpg)
Periodic (static) test mode:
Data collected over ‘long’ period of time so tank needs “quiet” time
Continuous test mode:
Data gathered during many short periods, (when no product is being added to or taken from tank)
e.g., CSLD, SCALD
![Page 26: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/26.jpg)
• Keep: 1 valid, 0.2 gph test result
per tank, monthly, for 12 months
![Page 27: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/27.jpg)
27
![Page 28: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/28.jpg)
10
Yes
![Page 29: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/29.jpg)
If there are drinking water wells nearby:
• Keep: 1 valid 0.2 gph test result
per tank, PER WEEK, for 12 months
![Page 30: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/30.jpg)
Know how to access and print leak test results
Check testing printouts routinely
Follow manufacturer’s recommendations for tests
and service
Check console after electrical storms
Do not ignore warnings or alarms
![Page 31: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/31.jpg)
31
ATGp 17
Monthly(Weekly if near well)
12 monthsof results
--/--/--
10
![Page 32: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/32.jpg)
Statistical Inventory
Reconciliation (SIR)
AutomaticTank Gauging
Systems(ATG)
CSecondary
Containment w/Interstitial Monitoring
(IM)
![Page 33: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/33.jpg)
Product
![Page 34: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/34.jpg)
Double Walled Tank
Monitor space between walls (interstice)
![Page 35: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/35.jpg)
Electronic Sensors:
◦Detect leaked substance:
Liquid (using a Liquid-Detecting Sensor)
OR
◦Detect change in condition:
Vacuum loss
Change in brine level
![Page 36: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/36.jpg)
• Present and powered on
• No warnings No alarms
Symbol:
![Page 37: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/37.jpg)
UST Site Diagram for: _____________________________________________
*
Fuel Mart 27
Raleigh Blvd
Hart Road
Fuel Mart 27
UST
Spill Bucket
Overfill PreventionFlapper Valve
*
*
*
Vapor RecoveryCoaxial
STP
ATG
Dispenser
ATG Console
IM Console
Rectifier
![Page 38: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/38.jpg)
Keep:
- 1 valid
sensor status
test result,
- per tank,
- PER MONTH,
- for 12 months
![Page 39: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/39.jpg)
depends on CP Installation Date
Find #1
CP Installation Date is 2 rows down
CP Method 11
![Page 40: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/40.jpg)
Recommended for
tanks installed
BEFORE 11/1/2007:
- one alarm history
report printed,
- per tank sensor,
- PER YEAR
REQUIRED for tanks installed AFTER 11/1/2007:
- one alarm historytest result printed,
- per tank sensor,- PER MONTH, - for 12 months
![Page 41: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/41.jpg)
Double-walled tank installed BEFORE
11/1/2007 may have “port” or
opening for checking interstice
Maintain monthly log for each tank;
keep previous 12 months
![Page 42: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/42.jpg)
REQUIREMENT:
◦ Annual Tank Sensor check
◦ Complete UST-22B form
![Page 43: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/43.jpg)
REQUIREMENT: ( if using ‘Liquid Detecting Sensor’ )
Interstice Tightness Test
Frequency: - At time of installation,
- 6 to 12 months after install
- Every 3 years
Complete UST-6E/23D form
![Page 44: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/44.jpg)
Liquid-detecting (dry) sensor
This comes after the # 11 in your inspection checklist IF you have it
![Page 45: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/45.jpg)
45
IMp. 18
MonthlyYearly
(2007)
Sensorstatus
Alarmhistory[log]
--/--/--
10
![Page 46: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/46.jpg)
• Enhanced Leak Detection
• Inventory Control and Tightness Testing
• Manual Tank Gauging and Tightness Test
• Groundwater Monitoring
• Vapor Monitoring
• Mechanical Vacuum Gauging
![Page 47: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/47.jpg)
Please answer questions 18 - 25
Take a Break
![Page 48: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/48.jpg)
North Carolina Department of Environment and Natural Resources
Division of Waste Management
Underground Storage Tank Section
![Page 49: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/49.jpg)
To discover a release before a major contamination incident occurs
Required for all regulated systems:
EXCEPTIONS:
Temporarily closed UST systems
Emergency generator UST systems installed before 11/1/07
![Page 50: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/50.jpg)
Third Party Certification:
◦ Installed, calibrated, operated and maintained per manufacturer’s instructions.
◦ Documentation that your leak detection method works for your UST system
◦ Keep documents for inspection
ALL METHODS HAVE LIMITATIONS:
◦ e.g.,: Tank size, Minimum fuel levels, Throughput, “Down time”
![Page 51: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/51.jpg)
Suction:
◦ European Suction [safe]
◦ American Suction [standard]
Pressurized
![Page 52: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/52.jpg)
Leak Detection
General
8 – Piping Type
9 – Type LLD Present
11 – Piping Primary leak detection method
9/1/2016
![Page 53: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/53.jpg)
SUCTION SYSTEMS
Pump is under dispenser
![Page 54: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/54.jpg)
Under Dispenser
Containment
Sump
Vertical
check
valveNo Pump here
so No Sump
Shear
valve
![Page 55: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/55.jpg)
Piping slopes back to tank, AND
Piping operates at less than atmospheric pressure, AND
Only one check valve, located at dispenser
![Page 56: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/56.jpg)
Installed BEFORE 11/1/2007:
- Leak detection is NOT required
Installed or replaced AFTER 11/1/2007:
- Interstitial Monitoring (IM) is required (info at end of unit)
![Page 57: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/57.jpg)
UST 19 form – completed by installeror contractor to verify an exempt suction system
Keep completed UST-19 form
Keep all records of maintenance and repairs
![Page 58: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/58.jpg)
p. 19
N/A
UST 19
N/A
8
![Page 59: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/59.jpg)
Check
valve
Check
valve
Under
Dispenser
Containment
sumpShear
valve
![Page 60: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/60.jpg)
Installed BEFORE 11/1/2007:
- Line Tightness Test every 3 years
- SIR
Installed or replaced AFTER 11/1/2007:
- Interstitial Monitoring (IM) is required
(info at end of unit)
![Page 61: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/61.jpg)
P 20
LTT 3 years
or SIR
LTT results
or 12 mos. SIR
--/--/--
8
9
![Page 62: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/62.jpg)
Leak Detection
9 – Type LLD Present
9/1/2016
![Page 63: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/63.jpg)
Containment
Sumps
Submersible
Turbine
Pump
Automatic
Line Leak
Detector
Shear
valve
![Page 64: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/64.jpg)
![Page 65: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/65.jpg)
Automatic
Line Leak
Detector AND
Piping
Primary Leak Detection Method
One Required
MLLD
or
ELLD
LTTLine
Tightness
Test
SIRStatistical
Inventory
Reconciliation
ELLDElectronic
Line Leak
Detector
IMInterstitial
Monitoring
Pressurized Piping - Leak Detection -
![Page 66: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/66.jpg)
MLLD ELLD
• Detects catastrophic leaks (3.0 gph)
• May slow flow of fuel if triggered
![Page 67: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/67.jpg)
![Page 68: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/68.jpg)
◦ Test Required
Every 12 months
◦Contractorshould check for proper operation
◦ Keep report for inspector
![Page 69: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/69.jpg)
![Page 70: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/70.jpg)
◦ Test Required
Every 12 months
◦ Contractor/Console
check operation
◦ Keep report or
print-out for inspector
◦ Should be programmed to shut down STP if triggered
![Page 71: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/71.jpg)
Testedyearly
Test results
--/--/--
Circle one
p 21
p 20
![Page 72: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/72.jpg)
Automatic
Line Leak
Detector
AND
Piping
Primary Leak Detection Method
One Required
MLLD
or
ELLD
LTT(Line
Tightness
Test)
SIR(Statistical
Inventory
Reconciliation)
ELLD(Electronic
Line Leak
Detector)
IM(Interstitial
Monitoring)
Pressurized Piping - Leak Detection -
![Page 73: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/73.jpg)
11- Piping Primary Leak Detection Method
1. LTT (Line Tightness Test)
2. SIR
3. ELLD
4. IM (Interstitial Monitoring)- before or after 2007?
9/1/2016
![Page 74: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/74.jpg)
Checks for 0.1 gph leak, Every year
Keep maintenance record forever.
Conducted by contractor,
OR
by ELLD programmed to perform 0.1 gph tests
![Page 75: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/75.jpg)
LTTYearlyp. 21
Test Results from
contractor or ELLD
--/--/--
11
![Page 76: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/76.jpg)
Submit
dispenser meter readings to SIR vendor to have SIR cover piping
SIR cannot be used for leak detection for piping to a satellite dispenser
![Page 77: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/77.jpg)
p 21-22
p 21-22
p 21-22
--/--/--
11
![Page 78: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/78.jpg)
9/1/2016
Calibration charts,12 months daily fuel,
12 months monthly water,12 months SIR reports from vendor
Product daily, Water monthly,
Submit to vendor monthly
SIR page 21-22method
testing frequency
documentation
next test date
--/--/--
![Page 79: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/79.jpg)
79
- Keep one 0.2 gph printout, for each piping run, Every month
- Keep one year’s worth of results
![Page 80: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/80.jpg)
p 22
monthly
12 month of 0.2 gph
printouts
--/--/--
11
![Page 81: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/81.jpg)
• Requirements depend on whenpiping was installed:
BEFORE 11/1/07
or
AFTER 11/1/07
![Page 82: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/82.jpg)
depends on Pipe Installation Date
Find #1
Date Pipe Installed is in section above
1
Date Pipe Installed
![Page 83: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/83.jpg)
Sump sensor 2” from bottomtypical, but not required
Use sensorORvisually inspectsumps for product / water
Piping interstice
is open to sump
![Page 84: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/84.jpg)
For ALL containment sumps
One valid SENSOR STATUS test result for each sensor
Per month
for 12 months
OR WRITTEN LOG (sump check) for each sump,
Per month
for 12 months
![Page 85: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/85.jpg)
p22
p22
--/--/--
11
![Page 86: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/86.jpg)
Piping interstice
is open to sump
Sump sensor REQUIRED
(less than 2” from bottom)
Sump sensorcontinuously
monitors for leaks
The requirements in this section also apply to suction piping installed after 11-1-2007
![Page 87: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/87.jpg)
Needed for ALL containment sumps
• One valid SENSOR STATUS test result, - Per month,- for 12 months
AND
• One ALARM HISTORY test result, - Per month, - for 12 months
![Page 88: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/88.jpg)
REQUIRED Checks:
Sump SENSORS - Every year - UST 22B
Sump INTERIOR - Every year - UST 22C------------------------------------------------------------------
Sump Integrity - Every 3 years - UST 23B
Piping Integrity - Every 3 years - UST 23C
(*Integrity = Tightness Test)
![Page 89: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/89.jpg)
p22
p22
--/--/--
11
![Page 90: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/90.jpg)
Section
5Section
7Section
6Section
8
#1 #10 #2 #3 #4 #8
#8 #9 #11
![Page 91: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/91.jpg)
UST Site Diagram for: _____________________________________________
*
Fuel Mart 27
Raleigh Blvd
Hart Road
Fuel Mart 27
*
*
*
UST
Spill Bucket
Overfill PreventionFlapper Valve
Vapor RecoveryCoaxial
STP
ATG
Dispenser
ATG Console
Rectifier Box
probe
![Page 92: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/92.jpg)
![Page 93: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/93.jpg)
Fuel Releases
![Page 94: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/94.jpg)
NCDENRDivision of Waste Management
Underground Storage Tank Section
![Page 95: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/95.jpg)
Suspected
Confirmed
![Page 96: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/96.jpg)
Leak Detection Failures
Unusual Operating Conditions
Environmental Conditions
![Page 97: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/97.jpg)
Interstitial Monitoring:
Sensor report indicates: ALARM
![Page 98: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/98.jpg)
Automatic Tank Gauge (ATG)
Report indicates:
FAIL or INCREASE
![Page 99: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/99.jpg)
Statistical Inventory Reconciliation (SIR)
Report indicates FAIL, INCONCLUSIVE, or
anything other than pass, for ANY MONTH
![Page 100: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/100.jpg)
Fuel
Spray
from
ALLD
![Page 101: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/101.jpg)
Product
In
pump sump
![Page 102: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/102.jpg)
Product
in dispenser
sump
![Page 103: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/103.jpg)
Flexible
Piping
split
![Page 104: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/104.jpg)
Flexible
Piping
- expanded
![Page 105: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/105.jpg)
Cracked
spill
bucket
![Page 106: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/106.jpg)
Stained soil
![Page 107: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/107.jpg)
Stained
soil
![Page 108: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/108.jpg)
9/1/2016
Spill / Overfill
![Page 109: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/109.jpg)
Product overflowing from the vapor recovery tube
![Page 110: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/110.jpg)
Sludge
accumulation
under
dispenser
![Page 111: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/111.jpg)
Dead Grass
at fill port
![Page 112: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/112.jpg)
1. Submit UST-17A form
‘UST Suspected Release 24 Hour Notice’
2. Investigate
3. Submit UST-17B form
‘UST Suspected Release 7 Day Notice’
![Page 113: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/113.jpg)
• Use UST-17A form
• What indicated the suspected release?
![Page 114: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/114.jpg)
Methods may include:
Tank tightness test
Line tightness test
Site check/soil sampling
Meter calibration
Hydrostatic test
other
![Page 115: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/115.jpg)
• Use UST-17B
• What was the cause?
![Page 116: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/116.jpg)
UST-17B:
◦ Attach results from investigation
Tank and line tightness testing
Sales receipts, invoices
Corrected leak detection results, etc.
![Page 117: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/117.jpg)
![Page 118: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/118.jpg)
Suspected
release
investigation
finds
contamination
![Page 119: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/119.jpg)
Submit UST-61 form
within 24 hours of discovery
![Page 120: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/120.jpg)
Contact your regional office
Conduct further action as recommended
![Page 121: NCDENR Division of Waste Management Underground … Management/DWM/UST/Tank School/unit 7-9.leak...Temporarily closed tanks Emergency generator tanks installed before11/1/07 Conducted](https://reader034.fdocuments.in/reader034/viewer/2022042102/5e7eabef53ab7515da1e48f7/html5/thumbnails/121.jpg)
Finish Exam (Questions 26-30)
Bring answer sheet to be graded
Bring Graded answer sheet to check out
Please turn in:
Exam questions
Envelope
Course Evaluation
Pencil