NAVY • LEED • COMMISSIONING2010 NAVFAC Symposium • 1 December 2010David Bylund AIA LEED-AP • Architects Hawaii
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
• LEED v3• Navy & Sustainability• Commissioning• Lessons Learned
INTRODUCTION
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
LEED v3
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
LEED v3
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
LEED v3
What's different from v2.2• Harmonization• Credit Weightings• Regionalization
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
LEED v3
What's different from v2.2• Credit requirements
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
LEED v3
What's different from v2.2• Minimum Project Requirements
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
LEED v3
What's different from v2.2• Regional Credits
• Hawaii• Guam• Outside US
SSc6WEc2 (25%)WEc3 (62.5%)EAc1 (80 rating / 30 percentile)EAc4 (12%/100%)MRc5
WEc1WEc2WEc3EAc1EAc3EAc5
???
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
LEED v3
What's different from v2.2• Addenda
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
LEED v3
What's different from v2.2• Addenda
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
LEED v3
What's different from v2.2• GBCI• CIRs
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
LEED v3
What's different from v2.2• LEED-Online
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
NAVY & SUSTAINABILITY
MOUGuiding Principles EO 13423 EPACT 2005
Federal Mandates & Policy
ECB 2008-01 NDAA 2007NAVFAC Policy
EO 13514 EISA 2007
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
NAVY & SUSTAINABILITY
MOUGuiding Principles
EPACT 2005EISA 2007
Federal Mandates & Policy
ECB 2008-01
For FY11 & beyond:
• LEED v3 Silver rating
• USGBC certified (process)*
• EPAct 2005 as codified under US Code 10 CFR 433 & 435
• E.O. 13424, Strengthening Federal Environmental, Energy and Transportation Management
ECB 2009-02: Addresses LEED 2009
EO 13423
NAVFAC Policy
EO 13514
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
EPACT 2005
EISA 2007
NDAA 2007
NAVY & SUSTAINABILITY
MOUGuiding Principles
Federal Mandates & Policy
ECB 2008-01
EO 13423
NAVFAC Policy
EO 13514
Federal Leadership in High Performance and Sustainable Buildings MOU (Jan 2006)
• Outlines the Guiding Principles for Federal Leadership in high Performance and Sustainable Buildings (Guiding Principles)
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
NAVY & SUSTAINABILITY
Federal Mandates & Policy
MOUGuiding Principles
ECB 2008-01
EO 13423 (Jan 2007)
• 15% of Building Inventory must be “Sustainable” by 2015 (LEED certified or similar)
• At least 50% of statutory renewable goals come from new sources (1999+)
• Reduce Water consumption 2% / year from a 2007 baseline (20% by 2020)
• Codified by Congress via 2009 Omnibus Appropriations Act
EO 13423 EPACT 2005
EO 13514 EISA 2007
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
NAVY & SUSTAINABILITY
Federal Mandates & Policy
MOUGuiding Principles
ECB 2008-01
EO 13514 (Oct 2009)
• Reduce GHG Emissions 34% from a 2008 Baseline
• 100% of New buildings, designed after 2020, must be fully “Zero Net Energy” by 2030
EO 13423 EPACT 2005
EO 13514 EISA 2007
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
NAVY & SUSTAINABILITY
MOUGuiding Principles
Federal Mandates & Policy
ECB 2008-01
EO 13423 EPACT 2005
NDAA 2007NAVFAC Policy
EO 13514 EISA 2007
EPACT 2005
• New federal buildings shall achieve energy savings 30% below ASHRAE Standard 90.1-2004.
• Renewable Electricity “Consumption” -3% by 2009, 5% by 2012, 7.5% by 2013
• Electrical Metering on all Federal Buildings by 2012 (EiSA added Gas/ Steam by ’16)
• Purchase 100% Alt Fuel Vehicles (extent practical)
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
EO 13423 EPACT 2005
NDAA 2007NAVFAC Policy
EO 13514 EISA 2007
NAVY & SUSTAINABILITY
MOUGuiding Principles
Federal Mandates & Policy
ECB 2008-01
EISA 2007
• Reduce Energy Consumption per SF 3%/YR, 30% total by 2015
• New construction/renovations >$2.5M, reduce facility fossil fuel use by 55% by 2010 and 100% by 2030
• 20% reduction in vehicle petroleum and 10% increase in Alternative Fuel use by 2020
• Comprehensive Energy Audits of 100% of buildings on a 4-year cycle (starting in 2012)
• Increases LCC Analysis from 25 to 40 yrs
• Min. 30% of Building Domestic Hot Water by Solar (unless not LCC effective compared to other available technologies)
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
EO 13423 EPACT 2005
NAVFAC Policy
EO 13514 EISA 2007
NAVY & SUSTAINABILITY
MOUGuiding Principles
Federal Mandates & Policy
ECB 2008-01
NDAA’07
• “Produce or Procure” 25% of Electricity used from Renewable sources by 2025
• Alternative Fuel Stations at each Fleet Fuel Center >100KGAL/YR by 2010
NDAA 2007
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
EO 13423 EPACT 2005
NDAA 2007
EO 13514 EISA 2007
NAVY & SUSTAINABILITY
MOUGuiding Principles
Federal Mandates & Policy
ECB 2008-01
NAVFAC Policy mandates two LEED Sustainable Site (SS) credits to meet LEED Silver certification
• SS 6.1 Stormwater Design -Quantity Control
• SS 6.2 Stormwater Design -Quality Control
Applicable Unified Facility Criteria
• UFC 3-210-10 Low Impact Development (LID)
• UFC 4-030-01 Sustainable Development
NAVFAC Policy
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
NAVY & SUSTAINABILITY
Federal Mandates & Policy – and LEEDSSc6 Stormwater Design ECB 2008-01 NAVFAC, EISA
WEc1 Water-Efficient Landscaping ECB 2008-01 MOU, EPAct
WEc3 Water Use Reduction ECB 2008-01 MOU, EPAct
EAp1 Fundamental Commissioning ECB 2008-01 MOU, EPAct
EAp2 Minimum Energy Compliance EPAct, EISA
EAc1 Optimize Energy Performance – 30% ECB 2008-01 EPAct, EISA
EAc2 On-Site Renewable energy EPAct, NDAA, EISA
EAc3 Enhanced Commissioning MOU, EPAct
EAc4 Enhanced Refrigerant Management ECB 2008-01
EAc5 Measurement & Verification ECB 2008-01 EPAct
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
NAVY & SUSTAINABILITY
Federal Mandates & Policy – and LEEDEAc6 Green Power EPAct, NDAA, EISA
MRc2 Construction Waste Management ECB 2008-01 Federal Waste Diversion Reqts.
MRc4 Recycled Content ECB 2008-01 EPA Procurement Guidelines
MRc6 Rapidly Renewable Materials ECB 2008-01 USDA Biobased Pref. Procurement Prog.
MRc7 Certified Wood ECB 2008-01
EQc4 Low Emitting Materials ECB 2008-01
EQc7.1 Thermal Comfort: Design ECB 2008-01
EQc8.1 Daylighting ECB 2008-01
IDc1.1 Moisture Control Plan ECB 2008-01
IDc1.2 Bio-based Products ECB 2008-01 USDA Biobased Pref. Procurement Prog.
IDc2 LEED Accredited Professional ECB 2008-01
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
NAVY & SUSTAINABILITY
Directives for LEED• Design Transition RFP
SUSTAINABLE DESIGN / LEEDA. STANDARDS AND REFERENCES
• LEED, EPAct, ASHRAE, ECB…B. FUNCTIONAL AND TECHNICAL
REQUIREMENTS• LEED, EPAct
C. DESIGN OBJECTIVE• Minimum 50 LEED points
D. LEED IMPLEMENTATION STRATEGIES• Details of design team’s
approaches to specific credits• Options for more than minimum
50 pointsE. LEED ASSUMPTIONS
• Actions / conditions assumed by NAVFAC
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
NAVY & SUSTAINABILITY
• Reference: www.WBDG.org
www.wbdg.org/references/pa_dod_sust.php
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
NAVY & SUSTAINABILITY
• Project delivery
design constructionpre-design occupancy
fundamental commissioning
enhanced commissioning
1391
D/B
RFP
star
t PC
AS
end
PCA
S
$> $> $> $>
$>
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
NAVY & SUSTAINABILITY
• Accountability • Failure to achieve Silver
certification • Achievement of more
than Silver certification• Failure of government to
fulfill 5-year commitments -> failure of contract?
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
• Commissioning - Cx•General•Fundamental•Enhanced
• Commissioning authority - CxA• OPR: Owner’s Project Requirements
• BOD: Basis of Design• Pre-functional and functional testing
• Commissioning plan, commissioning report
COMMISSIONING
• Terminology
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
• Commissioning•General•Fundamental•Enhanced
• Commissioning authority, • OPR: Owner’s Project Requirements
• BOD: Basis of Design• Pre-functional and functional testing
• Commissioning plan, commissioning report
COMMISSIONING
• Terminology• Energy & water systems
descriptions, efficiency goals and metrics
• Communications goals and strategies
• IEQ standards; pollutant sources; CO2 monitoring
• Space requirements: comfort, controls, noise
• Applicable codes, standards• Operations, maintenance, training
requirements• Typical daily use• Response to issues, complaints,
emergencies
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
•HVAC
•Refrigeration
•Lighting & daylighting controls
•Domestic hot water
•Renewable energy
COMMISSIONING
Commissioning scope• Systems
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
• Designate CxA• Report directly to Owner• Independent of AE team
• OPR, BOD• Cx requirements in CDs
• Design review in CDs• Cx plan: develop, implement• Review Contractor submittals• Verify installation and performance of
commissioned systems• Systems operations manual• Training program• Summary Cx report• Operations review within 10 months
COMMISSIONING
• LEED requirements for commissioning• Fundamental• Enhanced
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
• CxA
• Owner
• AE team, mechanical engineer in particular
• Contractor
• LEED administrator
COMMISSIONING
• Roles & responsibilities
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
a. Executive Order 13423 Technical Guidance Commissioning
b. Portland Energy Conservation, Inc. (PECI) • www.peci.org
c. Model Commissioning Plan and Guide Specifications
d. Building Commissioning Association (BCA) • www.bcxa.org
e. Building Commissioning (WBDG) • www.wbdg.org/project/
buildingcomm.phpf. AABC Commissioning Group (ACG)
• www.commissioning.org
COMMISSIONING
• More information
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
COMMISSIONING
• Lessons learned: Funding, Phases
design constructionpre-design occupancy
fundamental commissioning
enhanced commissioning
1391
D/B
RFP
star
t PC
AS
end
PCA
S
$> $> $> $>
$>
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
1. Commissioning scope reviewa. Commissioning specification sectionb. Commissioning planc. Roles and responsibilitiesd. Reportinge. CxA scope schedule
2. Schedule:a. Coordinated Cx / TAB / Flushout scheduleb. Detailed Cx schedule
i. Pre-functional testingii. Functional testingiii. Trainingiv. Reporting
c. Coordination with contractor, subcontractors3. HVAC controls; impact on Cx schedule4. Document review: status of review of document
revisions.5. Submittal comments:
a. Review pathb. Status of Owner review of CxA comments
on relevant project submittalsc. Outstanding comments review
6. Other issues
COMMISSIONING
• Lessons learned• Enhanced
commissioning as predictable credit
• OPR & BOD• Cx kickoff and team
coordination
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
• Removed Cx references from the QC Section
• Inserted a GENERAL COMMISSIONING Section (01 91 13)
• For the Cx of HVAC section, we changed the format of the Pre-Functional Performance Test Checklist and Functional Performance Test.
• Forms were tailored for the project and simplified.
• Revisions made in concert with CxA.
COMMISSIONING
• Lessons learned• Specifications
Report from recent project team:• No UFGS for Cx in general. • UFGS for Cx of HVAC (23 08 00.00
10)• Current UFGS folds in Fundamental
Cx into the QC Section (01 45 00.00 20)
• Project team added: • Cx of Plumbing (22 08 00)• Cx of Electrical Systems (26 07
00)• Cx of Photovoltaic Systems (48
01 00)
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
COMMISSIONING
• Lessons learned• Submittal review
projectsubmittalslist
Cx submittals
list
Contractor
AEteam
Cx submittal
sCx
Owner
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
COMMISSIONING
• Lessons learned• Schedule coordination
functional testingTAB building flush-out
pre-functional testing reporting, training
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
LESSONS LEARNED
• Guam issues• Recycling• Stormwater• PVs
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
LESSONS LEARNED
• Recycled content, and other materials credits
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
LESSONS LEARNED
• PVs• Costs, funding
mechanisms• PPAs• Federal goals• Installation-specific
goals• Location-specific
issues
ECB 2010-05• New construction and major
renovation projects beginning with the POM 2012 MILCON program
• Facility Sustainment, Restoration and Modernization (FSRM) projects beginning in FY10
• Where design requirements do not substantially impact project execution.
• Marine Corps Community Service (MCCS) is enjoined to comply with this guidance where feasible.
All new construction and major renovation projects requiring complete roof replacements will incorporate roof top solar thermal and/or photovoltaic systems.
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
LESSONS LEARNED
• RECs accessibility• Relative cost / value• Federal goals• Navy and federal
government abilities
$
REC
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
Specific language with regards to updated monthly information. • In UFGS providing updated
data is somewhat buried within updating the LEED Notebook.
Clarified references to include USGBC addenda up to a post date.
LESSONS LEARNED
• Specifications• UF Guide Specs
"L" designation for submittals• To identify items required to
be reviewed by the LEED Administrator
• To reinforce LEED Admin receipt
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
Designated a title to a specific Contractor's LEED personnel. "Contractor's LEED Coordinator" (CLC) • Shall be named in the LEED
Implementation Plan.List each credit that the Contractor has some role in, even if referenced to another location.
LESSONS LEARNED
• Specifications• UF Guide Specs
Language for contractor to use LEED online. • UFGS may have been
written for hardcopy templates.
Statement that despite it being a metric project, LEED documentation is in imperial units.
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
For example:• Minimum Performance
Requirements• EAp1: Fundamental
Commissioning• EQp2: Environmental Tobacco
Smoke Control• EQc7.2: Thermal Comfort –
Verification
LESSONS LEARNED
• Owner signatories• Minimum performance
requirements• LEED credit
requirements
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
UFC 4-030-01The key to providing a sustainable facility is the integrated design process. The integrated design, or “whole building,” approach involves interaction between all issues, objectives and life-cycle requirements, as well as between the customer, user, designer, consultants, and contractor early on (in the project planning stage) and throughout the project development process. This fosters a multidisciplinary project team and allows them to develop creative solutions that yield multiple benefits.
LESSONS LEARNED
• Integrated design• Owner• AE team• Contractor
NAVY • LEED • COMMISSIONING • 2010 NAVFAC SYMPOSIUM • 1 DECEMBER 2010
NAVY • LEED • COMMISSIONING2010 NAVFAC Symposium • 1 December 2010David Bylund AIA LEED-AP • Architects Hawaii