National Smart Metering Program National Smart Metering Program File Name: Memo 20090901 v1.0.docx Security Classification: Unrestricted National Smart Metering Program Memorandum To: Interested Parties From: NSSC Secretariat Date: 2 September 2009 Dear All The purpose of this covering note is to advise interested parties of the National Smart Metering Program (NSMP) that the content contained within the following document does not contain the latest information of the NSMP deliverables and schedules. As the NSMP program of work has evolved, reporting on deliverables (and any changes to the deliverables, as endorsed by the NSSC) has been reflected in individual status reports for the work streams. Interested parties are referred to the status reports for the current list of NSMP deliverables and schedules. Kind regards NSSC Secretariat [email protected]

Transcript of National Smart Metering Program Memorandum Task Name % Complete Duration Start Finish 0 NSSC -...

Page 1: National Smart Metering Program Memorandum Task Name % Complete Duration Start Finish 0 NSSC - National Smart Metering Program 0% 547 days Wed 12 Nov '08 Fri 31 Dec '10 1 Detailed

National Smart Metering ProgramNational Smart Metering Program

File Name: Memo 20090901 v1.0.docx Security Classification: Unrestricted

National Smart Metering Program

Memorandum To: Interested Parties From: NSSC Secretariat Date: 2 September 2009 Dear All The purpose of this covering note is to advise interested parties of the National Smart Metering Program (NSMP) that the content contained within the following document does not contain the latest information of the NSMP deliverables and schedules.

As the NSMP program of work has evolved, reporting on deliverables (and any changes to the deliverables, as endorsed by the NSSC) has been reflected in individual status reports for the work streams.

Interested parties are referred to the status reports for the current list of NSMP deliverables and schedules.

Kind regards

NSSC Secretariat

[email protected]

Page 2: National Smart Metering Program Memorandum Task Name % Complete Duration Start Finish 0 NSSC - National Smart Metering Program 0% 547 days Wed 12 Nov '08 Fri 31 Dec '10 1 Detailed

ID Task Name %Complete

Duration Start Finish

0 NSSC - National Smart Metering Program 0% 547 days Wed 12 Nov '08 Fri 31 Dec '101 Detailed schedule 0% 547 days Wed 12 Nov '08 Fri 31 Dec '10

2 Secretariat 0% 48 days Wed 12 Nov '08 Mon 2 Feb '09

3 Procure NSMP Resources 0% 36 days Fri 28 Nov '08 Mon 2 Feb '09

4 NSSC approval resourcing strategy 0% 1 day Fri 28 Nov '08 Fri 28 Nov '08

5 Procurement process 0% 35 days Mon 1 Dec '08 Mon 2 Feb '09

6 Stakeholder Registration 0% 36 days Fri 28 Nov '08 Mon 2 Feb '09

7 NSSC approval advertisement 0% 1 day Fri 28 Nov '08 Fri 28 Nov '08

8 Advertisement 28/29 November 0% 2 days Thu 11 Dec '08 Fri 12 Dec '08

9 Register stakeholders for NSSC Working Groups 0% 25 days Mon 15 Dec '08 Mon 2 Feb '09

10 NSMP Work Plan 0% 14 days Wed 12 Nov '08 Mon 1 Dec '08

11 Draft plan to NSSC 0% 0 days Wed 12 Nov '08 Wed 12 Nov '08

12 NSSC Meeting 0% 1 day Wed 19 Nov '08 Wed 19 Nov '08

13 Detailed NSSC Feedback 0% 10 days Wed 12 Nov '08 Tue 25 Nov '08

14 NSSC Meeting - Teleconference 0% 1 day Fri 28 Nov '08 Fri 28 Nov '08

15 Submit Plan to SCO 0% 1 day Mon 1 Dec '08 Mon 1 Dec '08

16 NSSC Working Groups TORs 0% 20 days Thu 20 Nov '08 Wed 17 Dec '08

17 Prepare drafts 0% 3 days Thu 20 Nov '08 Mon 24 Nov '08

18 NSSC review 0% 3 days Tue 25 Nov '08 Thu 27 Nov '08

19 NSSC Meeting - Teleconference 0% 1 day Fri 28 Nov '08 Fri 28 Nov '08

20 Revisions 0% 8 days Mon 1 Dec '08 Wed 10 Dec '08

21 NSSC Meeting - Approval 0% 1 day Wed 17 Dec '08 Wed 17 Dec '08

28/11 28/11

1/12 2/02

28/11 28/11

11/12 12/12

15/12 2/02

12/11

19/11 19/11

12/11 25/11

28/11 28/11

1/12 1/12

20/11 24/11

25/11 27/11

28/11 28/11

1/12 10/12

17/12 17/12

S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F008 Half 1, 2009 Half 2, 2009 Half 1, 2010 Half 2, 2010 Half 1,

National Smart Metering ProgramNational Smart Metering Program

NSSC - National Smart Metering Program

File Name: NSMP - Highlevel Schedule v1.0.mppNote: Schedule based on duration and not effortVersion: Approved by the NSSC and Baselined on the 28th November 2008

Page 1 of 7 Print Date: Fri 28 Nov '08

Page 3: National Smart Metering Program Memorandum Task Name % Complete Duration Start Finish 0 NSSC - National Smart Metering Program 0% 547 days Wed 12 Nov '08 Fri 31 Dec '10 1 Detailed

ID Task Name %Complete

Duration Start Finish

22 Business Requirements Work Stream 0% 195 days Mon 2 Feb '09 Fri 30 Oct '09

23 Invitations to 1st Working Group Workshop 0% 1 day Mon 2 Feb '09 Mon 2 Feb '09

24 Prepare draft SMI Functional Specification Paper 0% 15 days Mon 2 Feb '09 Fri 20 Feb '09

25 NSSC Meeting- 18 February (Sydney) 0% 1 day Wed 18 Feb '09 Wed 18 Feb '09

26 Issue draft SMI F.S. Paper to WG 0% 1 day Mon 23 Feb '09 Mon 23 Feb '09

27 1st WG Workshop (Melbourne) 0% 1 day Fri 6 Mar '09 Fri 6 Mar '09

28 Compile feedback 1st WG Workshop 0% 2 days Mon 9 Mar '09 Tue 10 Mar '09

29 Issue 1st WG Workshop Report to NSSC and WG 0% 1 day Wed 11 Mar '09 Wed 11 Mar '09

30 NSSC Meeting- 18 March (Melbourne) -review Workshop Report 0% 1 day Wed 18 Mar '09 Wed 18 Mar '09

31 Revise SMI F.S. Paper 0% 10 days Thu 19 Mar '09 Wed 1 Apr '09

32 Issue SMI F.S. Paper to WG 0% 1 day Thu 2 Apr '09 Thu 2 Apr '09

33 NSSC Meeting- 15 April (Sydney) 0% 1 day Wed 15 Apr '09 Wed 15 Apr '09

34 2nd WG Workshop (Sydney) 0% 1 day Fri 17 Apr '09 Fri 17 Apr '09

35 Compile feedback 2nd WG Workshop 0% 2 days Mon 20 Apr '09 Tue 21 Apr '09

36 Issue 2nd WG Workshop Report to NSSC and WG 0% 1 day Wed 22 Apr '09 Wed 22 Apr '09

37 Revise SMI F.S. Paper for 2nd workshop 0% 8 days Mon 20 Apr '09 Wed 29 Apr '09

38 Issue SMI F.S. Paper to WG 0% 1 day Thu 30 Apr '09 Thu 30 Apr '09

39 3rd WG Workshop (Melb) 0% 1 day Tue 12 May '09 Tue 12 May '09

40 Compile feedback 3rd WG Workshop 0% 2 days Wed 13 May '09 Thu 14 May '09

41 Issue 3rd WG Workshop Report to NSSC and WG 0% 5 days Fri 15 May '09 Thu 21 May '09

42 NSSC Meeting - 21 May (Melbourne) - review 2nd/3rd Workshop Reports 0% 1 day Thu 21 May '09 Thu 21 May '09

43 Revise SMI F.S. Paper for 3rd workshop 0% 5 days Fri 22 May '09 Thu 28 May '09

44 Issue revised SMI F.S. Paper to WG and Metrology Ref Group 0% 1 day Fri 29 May '09 Fri 29 May '09

45 Metrology Reference Group Meeting (Sydney) 0% 1 day Thu 11 Jun '09 Thu 11 Jun '09

46 Compile feedback from Metrology Ref Group Meeting 0% 2 days Fri 12 Jun '09 Mon 15 Jun '09

47 Issue Metrology Ref Grp Meeting Report to NSSC, WG, and Metro. Ref Grp 0% 1 day Tue 16 Jun '09 Tue 16 Jun '09

48 NSSC Meeting 17 June (Sydney) - review SMI F.S. progress 0% 1 day Wed 17 Jun '09 Wed 17 Jun '09

49 Revise SMI F.S. White Paper 0% 5 days Wed 17 Jun '09 Tue 23 Jun '09

50 Issue SMI F.S. White Paper 0% 1 day Wed 24 Jun '09 Wed 24 Jun '09

51 Joint BR WG/Metrology Ref Grp Workshop (Melb) 0% 1 day Tue 7 Jul '09 Tue 7 Jul '09

52 Compile feedback Workshop 0% 2 days Wed 8 Jul '09 Thu 9 Jul '09

53 Issue Workshop Report to NSSC, WG, and Metrology Ref Grp 0% 1 day Fri 10 Jul '09 Fri 10 Jul '09

54 NSSC Meeting 15 July (Melbourne) - review workshop report 0% 1 day Wed 15 Jul '09 Wed 15 Jul '09

55 Revise SMI F.S. Paper 0% 5 days Mon 13 Jul '09 Fri 17 Jul '09

56 Issue for WG and Ref Grp comments 0% 1 day Mon 20 Jul '09 Mon 20 Jul '09

57 Comments Period 0% 10 days Tue 21 Jul '09 Mon 3 Aug '09

58 Revise SMI F.S. Paper 0% 4 days Tue 4 Aug '09 Fri 7 Aug '09

59 Check Stakeholder Register 0% 5 days Mon 10 Aug '09 Fri 14 Aug '09

60 Issue SMI F.S. Paper to NSSC for review 0% 1 day Mon 10 Aug '09 Mon 10 Aug '09

61 Issue Stakeholder Register to NSSC 0% 1 day Fri 14 Aug '09 Fri 14 Aug '09

62 NSSC Meeting 19 August (Sydney) -review paper 0% 1 day Wed 19 Aug '09 Wed 19 Aug '09

63 Revise SMI F.S. Paper for NSSC feedback 0% 2 days Thu 20 Aug '09 Fri 21 Aug '09

64 NSSC confirmation of revisions 0% 5 days Mon 24 Aug '09 Fri 28 Aug '09

65 Public Consultation - SMI F.S. Paper 0% 31 days Mon 31 Aug '09 Mon 12 Oct '09

66 Issue paper 0% 2 days Mon 31 Aug '09 Tue 1 Sep '09

67 Consultation period 0% 20 days Wed 2 Sep '09 Tue 29 Sep '09

68 Public submissions analysis 0% 5 days Wed 30 Sep '09 Tue 6 Oct '09

2/02 2/02

2/02 20/02

18/02 18/02

23/02 23/02

6/03 6/03

9/03 10/03

11/03 11/03

18/03 18/03

19/03 1/04

2/04 2/04

15/04 15/04

17/04 17/04

20/04 21/04

22/04 22/04

20/04 29/04

30/04 30/04

12/05 12/05

13/05 14/05

15/05 21/05

21/05 21/05

22/05 28/05

29/05 29/05

11/06 11/06

12/06 15/06

16/06 16/06

17/06 17/06

17/06 23/06

24/06 24/06

7/07 7/07

8/07 9/07

10/07 10/07

15/07 15/07

13/07 17/07

20/07 20/07

21/07 3/08

4/08 7/08

10/08 14/08

10/08 10/08

14/08 14/08

19/08 19/08

20/08 21/08

24/08 28/08

31/08 1/09

2/09 29/09

30/09 6/10

S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F008 Half 1, 2009 Half 2, 2009 Half 1, 2010 Half 2, 2010 Half 1,

National Smart Metering ProgramNational Smart Metering Program

NSSC - National Smart Metering Program

File Name: NSMP - Highlevel Schedule v1.0.mppNote: Schedule based on duration and not effortVersion: Approved by the NSSC and Baselined on the 28th November 2008

Page 2 of 7 Print Date: Fri 28 Nov '08

Page 4: National Smart Metering Program Memorandum Task Name % Complete Duration Start Finish 0 NSSC - National Smart Metering Program 0% 547 days Wed 12 Nov '08 Fri 31 Dec '10 1 Detailed

ID Task Name %Complete

Duration Start Finish

69 SMI F.S. Paper Revisions 0% 4 days Wed 7 Oct '09 Mon 12 Oct '09

70 Final SMI F.S. Paper to NSSC for consideration 0% 1 day Tue 13 Oct '09 Tue 13 Oct '09

71 NSSC Meeting 21 Oct (Sydney) -review paper 0% 1 day Wed 21 Oct '09 Wed 21 Oct '09

72 Revise SMI F.S.Paper for NSSC feedback 0% 2 days Thu 22 Oct '09 Fri 23 Oct '09

73 NSSC confirmation of revisions 0% 4 days Mon 26 Oct '09 Thu 29 Oct '09

74 Issue SMI F.S. Paper to SCO 0% 1 day Fri 30 Oct '09 Fri 30 Oct '09

7/10 12/10

13/10 13/10

21/10 21/10

22/10 23/10

26/10 29/10

30/10 30/10

S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F008 Half 1, 2009 Half 2, 2009 Half 1, 2010 Half 2, 2010 Half 1,

National Smart Metering ProgramNational Smart Metering Program

NSSC - National Smart Metering Program

File Name: NSMP - Highlevel Schedule v1.0.mppNote: Schedule based on duration and not effortVersion: Approved by the NSSC and Baselined on the 28th November 2008

Page 3 of 7 Print Date: Fri 28 Nov '08

Page 5: National Smart Metering Program Memorandum Task Name % Complete Duration Start Finish 0 NSSC - National Smart Metering Program 0% 547 days Wed 12 Nov '08 Fri 31 Dec '10 1 Detailed

ID Task Name %Complete

Duration Start Finish

75 Business Processes and procedures Work Stream 0% 480 days Mon 2 Mar '09 Fri 31 Dec '10

76 Invitations to 1st Working Group Meeting 0% 1 day Mon 2 Mar '09 Mon 2 Mar '09

77 Draft NEM SMI Operating Model (Level 1 only) 0% 19 days Mon 30 Mar '09 Thu 23 Apr '09

78 Issue draft NEM SMI OM to WG 0% 1 day Fri 24 Apr '09 Fri 24 Apr '09

79 1st WG Workshop (Melbourne) 0% 1 day Thu 7 May '09 Thu 7 May '09

80 Compile feedback 1st WG Workshop 0% 2 days Fri 8 May '09 Mon 11 May '09

81 Issue 1st WG Workshop Report to NSSC and WG 0% 1 day Tue 12 May '09 Tue 12 May '09

82 NSSC Meeting - 21 May (Melbourne) - review Workshop Report 0% 1 day Thu 21 May '09 Thu 21 May '09

83 Revise NEM SMI OM 0% 10 days Tue 12 May '09 Mon 25 May '09

84 Issue NEM SMI OM (Level 1) to WG 0% 1 day Tue 26 May '09 Tue 26 May '09

85 2nd WG Workshop (Sydney) 0% 1 day Tue 9 Jun '09 Tue 9 Jun '09

86 Compile feedback 2nd WG Workshop 0% 2 days Wed 10 Jun '09 Thu 11 Jun '09

87 Issue 2nd WG Workshop Report to NSSC and WG 0% 1 day Fri 12 Jun '09 Fri 12 Jun '09

88 NSSC Meeting 17 June (Sydney) - review 2nd Workshop Report 0% 1 day Wed 17 Jun '09 Wed 17 Jun '09

89 Revise NEM SMI OM (Level 1) 0% 10 days Wed 10 Jun '09 Tue 23 Jun '09

90 Issue revised OM to WG and Process & Data Ref Grp 0% 1 day Wed 24 Jun '09 Wed 24 Jun '09

91 Process and Data Ref Group Meeting (Melbourne) 0% 1 day Thu 9 Jul '09 Thu 9 Jul '09

92 Compile feedback from Ref Grp Meeting 0% 2 days Fri 10 Jul '09 Mon 13 Jul '09

93 Issue P&D Ref Grp Meeting Report to NSSC, WG, and P&D Ref Grp 0% 1 day Tue 14 Jul '09 Tue 14 Jul '09

94 NSSC Meeting- 15 July (Melbourne) - review Ref Grp Meeting Report 0% 1 day Wed 15 Jul '09 Wed 15 Jul '09

95 Revise NEM SMI OM (Level 1) 0% 8 days Tue 14 Jul '09 Thu 23 Jul '09

96 Issue revised OM to WG and Process & Data Ref Grp 0% 1 day Fri 24 Jul '09 Fri 24 Jul '09

97 Joint WG & PD Ref Group Meeting (Sydney) 0% 1 day Thu 6 Aug '09 Thu 6 Aug '09

98 Compile feedback from Joint Meeting 0% 2 days Fri 7 Aug '09 Mon 10 Aug '09

99 Issue Joint Meeting Report to NSSC, WG, and P&D Ref Grp 0% 1 day Tue 11 Aug '09 Tue 11 Aug '09

100 NSSC Meeting- 19 August (Sydney) - review Joint Meeting Report 0% 1 day Wed 19 Aug '09 Wed 19 Aug '09

101 Revise NEM SMI OM (Level 1) 0% 5 days Wed 12 Aug '09 Tue 18 Aug '09

102 Issue NEM SMI OM (Level 1) to WG for Comments 0% 1 day Wed 19 Aug '09 Wed 19 Aug '09

103 Comments Period 0% 7 days Thu 20 Aug '09 Fri 28 Aug '09

104 Revise NEM SMI OM (Level 1) 0% 5 days Mon 31 Aug '09 Fri 4 Sep '09

105 Final SMI OM (L1) to NSSC for endorsement 0% 1 day Mon 7 Sep '09 Mon 7 Sep '09

106 Check Stakeholder Register 0% 5 days Mon 7 Sep '09 Fri 11 Sep '09

107 Issue Stakeholder Register to NSSC 0% 1 day Fri 11 Sep '09 Fri 11 Sep '09

108 NSSC Meeting- 16 Sept (Melb) - review SMI OM (L1) 0% 1 day Wed 16 Sep '09 Wed 16 Sep '09

109 Issue endorsed Model to WG and PD Ref Group 0% 2 days Thu 17 Sep '09 Fri 18 Sep '09

110 Develop NEM SMI OM (Level 2) 0% 138 days Mon 21 Sep '09 Wed 31 Mar '10

111 NEM SMI OM Model Complete 0% 0 days Wed 31 Mar '10 Wed 31 Mar '10

112 Modifications to Enforceable Instruments 0% 197 days Thu 1 Apr '10 Fri 31 Dec '10

113 B2B Procedures 0% 197 days Thu 1 Apr '10 Fri 31 Dec '10

114 MSATS Procedures 0% 197 days Thu 1 Apr '10 Fri 31 Dec '10

115 Metrology Procedures 0% 197 days Thu 1 Apr '10 Fri 31 Dec '10

116 Service Level Agreements 0% 131 days Fri 2 Jul '10 Fri 31 Dec '10

117 Meter Service Provider Accreditation 0% 131 days Fri 2 Jul '10 Fri 31 Dec '10

118 NEM Procedures Complete 0% 0 days Fri 31 Dec '10 Fri 31 Dec '10

2/03 2/03

30/03 23/0430/03 23/04

24/04 24/0424/04 24/04

7/05 7/057/05 7/05

8/05 11/058/05 11/05

12/05 12/05

21/05 21/05

12/05 25/0512/05 25/05

26/05 26/0526/05 26/05

9/06 9/069/06 9/06

10/06 11/06

12/06 12/06

17/06 17/06

10/06 23/0610/06 23/06

24/06 24/0624/06 24/06

9/07 9/079/07 9/07

10/07 13/0710/07 13/07

14/07 14/07

15/07 15/07

14/07 23/0714/07 23/07

24/07 24/07

6/08 6/086/08 6/08

7/08 10/087/08 10/08

11/08 11/0811/08 11/08

19/08 19/08

12/08 18/0812/08 18/08

19/08 19/0819/08 19/08

20/08 28/0820/08 28/08

31/08 4/0931/08 4/09

7/09 7/097/09 7/09

7/09 11/09

11/09 11/09

16/09 16/0916/09 16/09

17/09 18/0917/09 18/09

21/09 31/0321/09 31/03

31/03

1/04 31/121/04 31/12

1/04 31/121/04 31/12

1/04 31/121/04 31/12

2/07 31/122/07 31/12

2/07 31/122/07 31/12

31/1

S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F008 Half 1, 2009 Half 2, 2009 Half 1, 2010 Half 2, 2010 Half 1,

National Smart Metering ProgramNational Smart Metering Program

NSSC - National Smart Metering Program

File Name: NSMP - Highlevel Schedule v1.0.mppNote: Schedule based on duration and not effortVersion: Approved by the NSSC and Baselined on the 28th November 2008

Page 4 of 7 Print Date: Fri 28 Nov '08

Page 6: National Smart Metering Program Memorandum Task Name % Complete Duration Start Finish 0 NSSC - National Smart Metering Program 0% 547 days Wed 12 Nov '08 Fri 31 Dec '10 1 Detailed

ID Task Name %Complete

Duration Start Finish

119 Regulation Work Stream 0% 147 days Mon 2 Feb '09 Tue 25 Aug '09

120 Issue invitations 1st WG Workshop 0% 1 day Mon 2 Feb '09 Mon 2 Feb '09

121 Prepare draft SMI Regulatory Architecture Paper 0% 15 days Mon 2 Feb '09 Fri 20 Feb '09

122 Prepare draft SMI Cost Recovery Paper 0% 15 days Mon 2 Feb '09 Fri 20 Feb '09

123 NSSC Meeting- 18 February (Sydney) 0% 1 day Wed 18 Feb '09 Wed 18 Feb '09

124 Issue draft papers to WG 0% 1 day Mon 23 Feb '09 Mon 23 Feb '09

125 1st WG Workshop (Melbourne) 0% 1 day Mon 9 Mar '09 Mon 9 Mar '09

126 Compile feedback 1st WG Workshop 0% 3 days Tue 10 Mar '09 Thu 12 Mar '09

127 Issue 1st WG Workshop Report to NSSC and WG 0% 1 day Fri 13 Mar '09 Fri 13 Mar '09

128 NSSC Meeting- 18 March (Melbourne) 0% 1 day Wed 18 Mar '09 Wed 18 Mar '09

129 Finalise SMI Regulatory Architecture 0% 32 days Fri 13 Mar '09 Mon 27 Apr '09

130 Revise Draft SMI Regulatory Architecture 0% 3 days Fri 13 Mar '09 Tue 17 Mar '09

131 Issue revised paper to WG 0% 1 day Wed 18 Mar '09 Wed 18 Mar '09

132 Final WG Comments Period 0% 7 days Thu 19 Mar '09 Fri 27 Mar '09

133 Revise paper for WG Comments (confirm with WG) 0% 5 days Mon 30 Mar '09 Fri 3 Apr '09

134 Issue to NSSC for review 0% 1 day Mon 6 Apr '09 Mon 6 Apr '09

135 NSSC Meeting- 15 April (Sydney) - review Reg Arch. paper 0% 1 day Wed 15 Apr '09 Wed 15 Apr '09

136 Revise paper NSSC feedback 0% 2 days Thu 16 Apr '09 Fri 17 Apr '09

137 NSSC confirmation 0% 5 days Mon 20 Apr '09 Fri 24 Apr '09

138 Issue paper to SCO 0% 1 day Mon 27 Apr '09 Mon 27 Apr '09

139 Prepare draft SMI NER Ch 7 Review Paper 0% 15 days Mon 23 Feb '09 Fri 13 Mar '09

140 Issue draft SMI NER Ch 7 Review Paper to WG 0% 1 day Mon 16 Mar '09 Mon 16 Mar '09

141 Revise draft SMI Cost Recovery Paper 0% 5 days Thu 19 Mar '09 Wed 25 Mar '09

142 Issue revised SMI Cost Recovery Paper to WG 0% 1 day Thu 26 Mar '09 Thu 26 Mar '09

143 2nd WG Meeting (Sydney) 0% 1 day Thu 2 Apr '09 Thu 2 Apr '09

144 Compile feedback 2nd WG Workshop 0% 2 days Fri 3 Apr '09 Mon 6 Apr '09

145 Issue 2nd Workshop Report to NSSC and WG 0% 1 day Tue 7 Apr '09 Tue 7 Apr '09

146 NSSC Meeting- 15 April (Sydney) - review Workshop report 0% 1 day Wed 15 Apr '09 Wed 15 Apr '09

147 Revise SMI NER Ch 7 Review Paper 0% 10 days Tue 7 Apr '09 Mon 20 Apr '09

148 Issue revised SMI NER Ch 7 Review Paper to WG 0% 1 day Tue 21 Apr '09 Tue 21 Apr '09

149 Revise SMI Cost Recovery Paper 0% 10 days Tue 7 Apr '09 Mon 20 Apr '09

150 Issue Revised SMI Cost Recovery Paper to WG 0% 1 day Tue 21 Apr '09 Tue 21 Apr '09

151 3rd WG Meeting (Melbourne) 0% 1 day Tue 5 May '09 Tue 5 May '09

152 Compile feedback 3rd WG Workshop 0% 3 days Wed 6 May '09 Fri 8 May '09

153 Issue 3rd Workshop Report to NSSC and WG 0% 1 day Mon 11 May '09 Mon 11 May '09

154 NSSC Meeting - 21 May (Melbourne) - review Workshop Report 0% 1 day Thu 21 May '09 Thu 21 May '09

155 Finalise SMI Cost Recovery paper 0% 36 days Mon 11 May '09 Mon 29 Jun '09

156 Revise paper from 3rd Workshop 0% 4 days Mon 11 May '09 Thu 14 May '09

157 Issue revised SMI Cost Recovery paper to WG 0% 1 day Fri 15 May '09 Fri 15 May '09

158 Comments from WG 0% 7 days Mon 18 May '09 Tue 26 May '09

159 Revise paper 0% 3 days Wed 27 May '09 Fri 29 May '09

160 Check stakeholder comments with WG 0% 5 days Mon 1 Jun '09 Fri 5 Jun '09

161 Issue paper to NSSC 0% 1 day Mon 8 Jun '09 Mon 8 Jun '09

162 NSSC Meeting 17 June (Sydney) - review paper 0% 1 day Wed 17 Jun '09 Wed 17 Jun '09

163 Revise paper NSSC feedback 0% 2 days Thu 18 Jun '09 Fri 19 Jun '09

164 NSSC confirmation 0% 5 days Mon 22 Jun '09 Fri 26 Jun '09

165 Issue paper to SCO 0% 1 day Mon 29 Jun '09 Mon 29 Jun '09

2/02 2/02

2/02 20/02

2/02 20/02

18/02 18/02

23/02 23/02

9/03 9/03

10/03 12/03

13/03 13/03

18/03 18/03

13/03 17/03

18/03 18/03

19/03 27/03

30/03 3/04

6/04 6/04

15/04 15/04

16/04 17/04

20/04 24/04

27/04 27/04

23/02 13/03

16/03 16/03

19/03 25/03

26/03 26/03

2/04 2/04

3/04 6/04

7/04 7/04

15/04 15/04

7/04 20/04

21/04 21/04

7/04 20/04

21/04 21/04

5/05 5/05

6/05 8/05

11/05 11/05

21/05 21/05

11/05 14/05

15/05 15/05

18/05 26/05

27/05 29/05

1/06 5/06

8/06 8/06

17/06 17/06

18/06 19/06

22/06 26/06

29/06 29/06

S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F008 Half 1, 2009 Half 2, 2009 Half 1, 2010 Half 2, 2010 Half 1,

National Smart Metering ProgramNational Smart Metering Program

NSSC - National Smart Metering Program

File Name: NSMP - Highlevel Schedule v1.0.mppNote: Schedule based on duration and not effortVersion: Approved by the NSSC and Baselined on the 28th November 2008

Page 5 of 7 Print Date: Fri 28 Nov '08

Page 7: National Smart Metering Program Memorandum Task Name % Complete Duration Start Finish 0 NSSC - National Smart Metering Program 0% 547 days Wed 12 Nov '08 Fri 31 Dec '10 1 Detailed

ID Task Name %Complete

Duration Start Finish

166 Finalise SMI NER Ch 7 Review paper 0% 47 days Fri 22 May '09 Mon 27 Jul '09

167 Revise paper from 3rd WG Workshop 0% 6 days Fri 22 May '09 Fri 29 May '09

168 Issue revised paper to WG 0% 1 day Mon 1 Jun '09 Mon 1 Jun '09

169 4th Working Group Workshop (Sydney) 0% 1 day Mon 15 Jun '09 Mon 15 Jun '09

170 Revise paper from 4th WG Workshop 0% 2 days Tue 16 Jun '09 Wed 17 Jun '09

171 Issue revised paper to WG 0% 1 day Thu 18 Jun '09 Thu 18 Jun '09

172 Comments period 0% 5 days Fri 19 Jun '09 Thu 25 Jun '09

173 Revise paper 0% 2 days Fri 26 Jun '09 Mon 29 Jun '09

174 Check stakeholder comments with WG 0% 5 days Tue 30 Jun '09 Mon 6 Jul '09

175 Issue to NSSC 0% 1 day Tue 7 Jul '09 Tue 7 Jul '09

176 NSSC Meeting 15 July (Melbourne) - review paper 0% 1 day Wed 15 Jul '09 Wed 15 Jul '09

177 Revise paper NSSC feedback 0% 2 days Thu 16 Jul '09 Fri 17 Jul '09

178 NSSC confirmation 0% 5 days Mon 20 Jul '09 Fri 24 Jul '09

179 Issue paper to SCO 0% 1 day Mon 27 Jul '09 Mon 27 Jul '09

180 CH 7 Rule Change Submission 0% 20 days Wed 29 Jul '09 Tue 25 Aug '09

22/05 29/05

1/06 1/06

15/06 15/06

16/06 17/06

18/06 18/06

19/06 25/06

26/06 29/06

30/06 6/07

7/07 7/07

15/07 15/07

16/07 17/07

20/07 24/07

27/07 27/07

29/07 25/08

S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F008 Half 1, 2009 Half 2, 2009 Half 1, 2010 Half 2, 2010 Half 1,

National Smart Metering ProgramNational Smart Metering Program

NSSC - National Smart Metering Program

File Name: NSMP - Highlevel Schedule v1.0.mppNote: Schedule based on duration and not effortVersion: Approved by the NSSC and Baselined on the 28th November 2008

Page 6 of 7 Print Date: Fri 28 Nov '08

Page 8: National Smart Metering Program Memorandum Task Name % Complete Duration Start Finish 0 NSSC - National Smart Metering Program 0% 547 days Wed 12 Nov '08 Fri 31 Dec '10 1 Detailed

ID Task Name %Complete

Duration Start Finish

181 Pilots and Trials Work Stream 0% 152 days Wed 17 Dec '08 Fri 31 Jul '09

182 Pilots/Trials Status Report (Completed/Current) 0% 42 days Wed 17 Dec '08 Fri 27 Feb '09

183 NSSC approval - Pilot and Trials Summary Report Template 0% 1 day Wed 17 Dec '08 Wed 17 Dec '08

184 Issue Summary Report Templates to companies 0% 1 day Mon 5 Jan '09 Mon 5 Jan '09

185 Report preparation by companies 0% 33 days Tue 6 Jan '09 Fri 20 Feb '09

186 Major Findings - Working paper 0% 5 days Mon 23 Feb '09 Fri 27 Feb '09

187 Invitation to 1st Working Group Workshop 0% 1 day Mon 2 Feb '09 Mon 2 Feb '09

188 Issue 2008 Pilots/Trials Status Report to WG 0% 1 day Mon 2 Mar '09 Mon 2 Mar '09

189 1st WG Workshop(Melb) 0% 1 day Thu 12 Mar '09 Thu 12 Mar '09

190 Revisions - Draft 2008 Pilots/Trials Status Report 0% 6 days Fri 13 Mar '09 Fri 20 Mar '09

191 NSSC Meeting- 18 March (Melbourne) 0% 1 day Wed 18 Mar '09 Wed 18 Mar '09

192 WG Feedback on draft report 0% 7 days Mon 23 Mar '09 Tue 31 Mar '09

193 Final Report Revisions 0% 2 days Wed 1 Apr '09 Thu 2 Apr '09

194 Issue 2008 Pilots/Trials Status Report to NSSC 0% 1 day Fri 3 Apr '09 Fri 3 Apr '09

195 NSSC Meeting- 15 April (Sydney) - review 2008 Report 0% 1 day Wed 15 Apr '09 Wed 15 Apr '09

196 Issue 2008 Pilots/Trials Status Report to SCO 0% 1 day Fri 17 Apr '09 Fri 17 Apr '09

197 2nd WG Workshop (Sydney) 0% 1 day Thu 23 Apr '09 Thu 23 Apr '09

198 Prepare Pilots/Trials Scenarios Working Paper for NSSC 0% 10 days Fri 24 Apr '09 Thu 7 May '09

199 Issue Working paper to WG 0% 1 day Fri 8 May '09 Fri 8 May '09

200 3rd WG Workshop (Melbourne) 0% 1 day Wed 20 May '09 Wed 20 May '09

201 NSSC Meeting - 21 May (Melbourne) 0% 1 day Thu 21 May '09 Thu 21 May '09

202 Revise Pilots/Trials Scenarios Working Paper 0% 6 days Thu 21 May '09 Thu 28 May '09

203 Issue Working paper to WG 0% 1 day Fri 29 May '09 Fri 29 May '09

204 NSSC Meeting- 17 June (Sydney) 0% 1 day Wed 17 Jun '09 Wed 17 Jun '09

205 4th WG Workshop (Sydney) 0% 1 day Thu 18 Jun '09 Thu 18 Jun '09

206 Revise Pilots/Trials Scenarios Working Paper 0% 4 days Fri 19 Jun '09 Wed 24 Jun '09

207 Issue Working paper to WG 0% 1 day Thu 25 Jun '09 Thu 25 Jun '09

208 Final feedback from WG 0% 5 days Fri 26 Jun '09 Thu 2 Jul '09

209 Final revision Working paper 0% 2 days Fri 3 Jul '09 Mon 6 Jul '09

210 Issue Pilots/Trials Scenarios Working Paper to NSSC 0% 1 day Tue 7 Jul '09 Tue 7 Jul '09

211 NSSC Meeting- 15 July (Melbourne) - review Pilots/Scen WP 0% 1 day Wed 15 Jul '09 Wed 15 Jul '09

212 Issue Pilots/Trials Scenarios Working Paper to SCO 0% 1 day Mon 20 Jul '09 Mon 20 Jul '09

213 Jan-June 09 Pilots/Trials Status Report 0% 20 days Mon 8 Jun '09 Fri 3 Jul '09

214 Status reports from companies 0% 15 days Mon 8 Jun '09 Fri 26 Jun '09

215 Major findings working paper 0% 5 days Mon 29 Jun '09 Fri 3 Jul '09

216 Issue Jan-June 09 Pilots/Trials Status Report to WG 0% 1 day Mon 6 Jul '09 Mon 6 Jul '09

217 5th WG Workshop (Melbourne) 0% 1 day Mon 13 Jul '09 Mon 13 Jul '09

218 WG Feedback on draft Jan-June 09 Status Report 0% 5 days Tue 14 Jul '09 Mon 20 Jul '09

219 Final Status Report Revisions 0% 2 days Tue 21 Jul '09 Wed 22 Jul '09

220 Issue Jan-June 09 Pilots/Trials Status Report to NSSC 0% 1 day Thu 23 Jul '09 Thu 23 Jul '09

221 NSSC Out of Session review 0% 1 day Thu 30 Jul '09 Thu 30 Jul '09

222 Issue Jan-June 09 Pilots/Trials Status Report to SCO 0% 1 day Fri 31 Jul '09 Fri 31 Jul '09

17/12 17/12

5/01 5/01

6/01 20/02

23/02 27/02

2/02 2/02

2/03 2/03

12/03 12/03

13/03 20/03

18/03 18/03

23/03 31/03

1/04 2/04

3/04 3/04

15/04 15/04

17/04 17/04

23/04 23/04

24/04 7/05

8/05 8/05

20/05 20/05

21/05 21/05

21/05 28/05

29/05 29/05

17/06 17/06

18/06 18/06

19/06 24/06

25/06 25/06

26/06 2/07

3/07 6/07

7/07 7/07

15/07 15/07

20/07 20/07

8/06 26/06

29/06 3/07

6/07 6/07

13/07 13/07

14/07 20/07

21/07 22/07

23/07 23/07

30/07 30/07

31/07 31/07

S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F008 Half 1, 2009 Half 2, 2009 Half 1, 2010 Half 2, 2010 Half 1,

National Smart Metering ProgramNational Smart Metering Program

NSSC - National Smart Metering Program

File Name: NSMP - Highlevel Schedule v1.0.mppNote: Schedule based on duration and not effortVersion: Approved by the NSSC and Baselined on the 28th November 2008

Page 7 of 7 Print Date: Fri 28 Nov '08

Page 9: National Smart Metering Program Memorandum Task Name % Complete Duration Start Finish 0 NSSC - National Smart Metering Program 0% 547 days Wed 12 Nov '08 Fri 31 Dec '10 1 Detailed

National Smart Metering ProgramNational Smart Metering Program

National Stakeholder Steering Committee

NSMP Work Plan – Schedule Overview

Version number: Version 1.0

Status: Final

Author Harry Koller, Program Director

Date published 28 November 2008

File name NSMP Schedule overview v1.0.doc

Page 10: National Smart Metering Program Memorandum Task Name % Complete Duration Start Finish 0 NSSC - National Smart Metering Program 0% 547 days Wed 12 Nov '08 Fri 31 Dec '10 1 Detailed

National Smart Metering ProgramNational Smart Metering Program

NSMP Work Plan – Schedule Overview

File Name: NSMP Schedule overview v1.0.docSecurity Classification:Page 2 of 6

1 Document Control

Version Control

Version Date Description Amended by:

0.6 12/11/2008 Issued to NSSC for review and comment H. Koller

0.7 26/11/2008 Updated to reflect change in schedule date & feedback fromNSSC members

H. Koller

1.0 28/11/2008 Baselined post approval from NSSC H. Martinson

Approval

Authorised by Signature Date

NSSC

Program Director

28/11/08

MCE

Page 11: National Smart Metering Program Memorandum Task Name % Complete Duration Start Finish 0 NSSC - National Smart Metering Program 0% 547 days Wed 12 Nov '08 Fri 31 Dec '10 1 Detailed

National Smart Metering ProgramNational Smart Metering Program

NSMP Work Plan – Schedule Overview

File Name: NSMP Schedule overview v1.0.docSecurity Classification:Page 3 of 6

Business Requirements Work Stream

February 2009 March 2009 April 2009 May 2009 June 2009 July 2009 August to October 2009

Issue invitations to 1st

BusinessRequirements Working Group(BRWG) meeting (2/2)

Prepare draft Smart MeteringInfrastructure (SMI) FunctionalSpecification Paper (2/2 to 20/2)

SMI Strategic Objectives:Mapping the MCE and otherstakeholders’ SMI objectivesto the SMI enabling functionsso as to confirm the requiredSMI minimum functions (e.g.identify the mechanisms thatwill be required to deliver theSMI objectives)

SMI Components: Identifyand confirm the SMIcomponents to be included inthe SMI FunctionalSpecification (SMI FS) Paper

SMI Requirements: Specifythe business requirements,performance requirements,and service standards for theSMI components

Cost benefits analysis:Indicative cost and benefitsusing the Phase 2 CBA studymanaged by NERAConsulting as an initialbaseline

Policy advice: on mattersraised in the NSSC terms ofreference (eg. Items (p), (q)and (r))

Issue draft SMI FS Paper toBRWG (23/2)

Note: The initial draft of this papermay not contain all of thesesections. The timing of each sectionof the SMI FS Paper will bedeveloped by the SME appointed tolead this work stream. This will bediscussed with the NSSC.

1st

BRWG Workshop6/3 (Melbourne)

Compile feedback 1st

BRWG Workshop(9/3 to 10/3)

Issue 1st

BRWGWorkshop Report toNSSC and BRWG(11/3)

NSSC Meeting 18March (Melbourne) -review WorkshopReport

Revise SMI FS Paper(19/3 to 1/4) (Note:Incorporate findingsof draft 2008Pilots/Trials StatusReport)

Note: The timing andapproach to developHAN Use Cases will bedeveloped by the SMEappointed to lead thiswork stream. This will bediscussed with theNSSC. This schedulemay be amended infuture to reflect thosechanges.

Issue SMI FS Paperto BRWG (2/4)

NSSC Meeting 15April (Sydney)

2nd

BRWGWorkshop 17/4(Sydney)

Compile feedback 2nd

BRWG Workshop(20/4 to 21/4)

Issue 2nd

BRWGWorkshop Report toNSSC and BRWG(22/4)

Revise SMI FS Paperfor 3

rdworkshop (20/4

to 29/4)

Issue SMI FS Paperto BRWG (30/4)

3rd

BRWG Workshop12/5 (Melbourne)

Compile feedback 3rd

BRWG Workshop(13/5 to 14/5)

Issue 3rd

BRWGWorkshop Report toNSSC and BRWG(15/5)

NSSC Meeting 21May (Melbourne) -review 2nd/3rdWorkshop Reports

Revise SMI FS Paperfor next workshop(22/5 to 28/5)

Issue revised SMI FSPaper to BRWG andMetrology ReferenceGroup (MRG) (29/5)

MetrologyReference GroupMeeting 11/6(Sydney)

Compile feedbackfrom MRG Meeting(12/6 to 15/6)

Issue MRG MeetingReport to NSSC,BRW, and MRG(16/6)

NSSC Meeting 17June (Sydney) -review SMI FSprogress

Revise SMI FS Paper(17/6 to 23/6)

Issue SMI FS Paper(24/6)

Joint BRWG/MRGWorkshop 7/7(Melbourne)

Compile feedbackWorkshop (8/7 to 9/7)

Issue WorkshopReport to NSSC,BRWG and MRG(10/7)

NSSC Meeting 15July (Melbourne) -review workshopreport

Revise SMI FS Paper(13/7 to 17/7)

Issue for BRWG andMRG comments(20/7)

Comments Period(21/7 to 3/8)

Comments Period (21/7 to 3/8)

Revise SMI FS Paper (4/8 to 7/8)

Check Stakeholder Register (10/8to 14/8)

Issue SMI FS Paper to NSSC forreview (10/8)

Issue Stakeholder Register toNSSC (14/8)

NSSC Meeting 19 August(Sydney) –review SMI FS Paper

Revise SMI FS Paper for NSSCfeedback (20/8 to 21/8)

NSSC confirmation of revisions(24/8 to 28/8)

Public Consultation - SMI FS Paper

Issue paper (30/8)

Consultation period (2/9 to 29/9)

Public submissions analysis (30/9to 6/10)

SMI FS Paper Revisions (7/10 to12/10)

Final SMI FS Paper to NSSC forconsideration (13/10)

NSSC Meeting 21 October(Sydney) –review paper

Revise SMI FS Paper for NSSCfeedback (22/10 to 23/10)

NSSC confirmation of revisions(26/10 to 29/10)

Issue SMI FS Paper to SCO(30/10)

The SMI Functional SpecificationPaper will be baselined and put underchange control by the NSSCSecretariat. Changes may be requiredbased on inputs from the BusinessProcesses and Procedures WorkingGroup or the outcomes of pilots andtrials.

Page 12: National Smart Metering Program Memorandum Task Name % Complete Duration Start Finish 0 NSSC - National Smart Metering Program 0% 547 days Wed 12 Nov '08 Fri 31 Dec '10 1 Detailed

National Smart Metering ProgramNational Smart Metering Program

NSMP Work Plan – Schedule Overview

File Name: NSMP Schedule overview v1.0.docSecurity Classification:Page 4 of 6

Business Processes and Procedures Work Stream

March/April 2009 May 2009 June 2009 July 2009 August 2009 September 2009 October 2009

Invitations to 1st

BusinessProcesses andProcedures WorkingGroup (BPPWG)Workshop (2/3)

Prepare draft NEM SMIOperating Model (Level 1only) (30/3 to 23/4)

List of Level 1processes to confirmoperating modelscope

Process descriptionand process diagramusing VictorianOperating Model(VIC OM) as astarting point

Where requiredLevel 2 processeswill be addressed asnecessary tocorrectly specify theLevel 1 process.However the intent isto document Level 1processes firstbefore workcommences onLevel 2

Issue draft NEM SMIOperating Model (Level 1only) to BPPWG (24/4)

1st

BPPWG Workshop7/5 (Melbourne)

Compile feedback 1st

BPPWG Workshop (8/5to 11/5)

Issue 1st

BPPWGWorkshop Report toNSSC and BPPWG(12/5)

NSSC Meeting 21 May(Melbourne) - reviewWorkshop Report

Revise NEM SMI OM(12/5 to 25/5)

Issue NEM SMI OM(Level 1) to BPPWG(26/5)

2nd

BPPWG Workshop9/6 (Sydney)

Compile feedback 2nd

BPPWG Workshop (10/6to 11/6)

Issue 2nd

BPPWGWorkshop Report toNSSC and BPPWG(12/6)

NSSC Meeting 17 June(Sydney) - review 2

nd

Workshop Report

Revise NEM SMI OM(Level 1) (10/6 to 23/6)

Issue revised OM toBPPWG and BusinessProcess and DataReference Group (PDRG)(24/6)

PDRG Meeting 9/7(Melbourne)

Compile feedback fromPDRG Meeting (10/7 to13/7

Issue PDRG MeetingReport to NSSC, BPPWGand PDRG (14/7)

NSSC Meeting 15 July(Melbourne) - reviewPDRG Report

Revise NEM SMI OM(Level 1) (14/7 to 23/7)

Issue revised OM toBPPWG and PDRG(24/7)

Joint BPPWG & PDRGMeeting 6/8 (Sydney)

Compile feedback fromJoint Meeting (7/8 to10/8)

Issue Joint MeetingReport to NSSC, BPPWGand PDRG (11/8)

NSSC Meeting 19August (Sydney) -review Joint MeetingReport

Revise NEM SMI OM(Level 1) (12/8 to 18/8)

Issue NEM SMI OM(Level 1) to BPPWG forcomments (19/8)

Comments Period (20/8to 28/8)

Revise NEM SMI OM(Level 1) (31/8 to 4/9)

Revise NEM SMI OM(Level 1) (31/8 to 4/9)

Final SMI OM (Level 1) toNSSC for endorsement(7/9)

Check StakeholderRegister (7/9 to 11/9)

Issue StakeholderRegister to NSSC (11/9)

NSSC Meeting 16September (Melbourne)- review SMI OM (Level1)

Issue endorsed Model toBPPWG and PDRG (17/9to 18/9)

Develop NEM SMI OM(Level 2) (21/9 to31/3/2010)

Develop NEM SMI OM(Level 2) (21/9 to31/3/2010)

Note: NEM SMI OM (Level 2)is expected to be completedby end March 2010.

Page 13: National Smart Metering Program Memorandum Task Name % Complete Duration Start Finish 0 NSSC - National Smart Metering Program 0% 547 days Wed 12 Nov '08 Fri 31 Dec '10 1 Detailed

National Smart Metering ProgramNational Smart Metering Program

NSMP Work Plan – Schedule Overview

File Name: NSMP Schedule overview v1.0.docSecurity Classification:Page 5 of 6

Regulation Work Stream

February 2009 March 2009 April 2009 May 2009 June 2009 July 2009

Issue invitations to 1st

Regulation Working Group(RWG) Workshop (2/2)

Prepare draft SMI RegulatoryArchitecture Paper (2/2 to 20/2)

Scope: Provide advice toSCO on the regulatorymatters to be addressed inthe NER (e.g. roles/resp.)versus the NEMProcedures (e.g. meterperformance standards)

Prepare draft SMI CostRecovery Paper (2/2 to 20/2)

Objective: Respond toSCO paper issued in 2008with cost recoveryprinciples for pilots/trialsand rollout of smart meters

NSSC Meeting 18 February(Sydney)

Issue both draft papers to RWG(23/2)

Prepare draft SMI NER Ch 7Review Paper (23/2 to 13/3)

1st

RWG Workshop 9/3(Melbourne)

Draft SMI RegulatoryArchitecture

Draft SMI Cost RecoveryPaper

Compile feedback – 1st

RWGWorkshop (10/3 to 12/3)

Issue RWG Progress report toNSSC and RWG (13/3)

NSSC Meeting 18 March(Melbourne)

Draft SMI NEM RegulatoryArchitecture

Revise paper (13/3 to17/3)

Issue revised paper toRWG (18/3)

Final RWG CommentsPeriod (19/3 to 27/3)

Revise paper for RWGComments (confirm withRWG) (30/3 to 4/4)

Prepare draft SMI NER Ch 7Review Paper (23/2 to 13/3)

Issue draft SMI NER Ch 7Review Paper to RWG (16/3)

Revise draft SMI CostRecovery Paper (19/3 to 25/3)

Issue revised SMI CostRecovery Paper to RWG (26/3)

Draft SMI Regulatory Architecture

Revise paper for RWG Comments(confirm with RWG) (30/3 to 4/4)

Issue to NSSC for review (6/4)

NSSC Meeting 15 April (Sydney)– review paper

Revise paper – NSSC Feedback(16/4 to 17/4)

NSSC confirmation (20/4 to 24/4)

Issue SMI Regulatory Architectureto SCO (27/4)

Note: Public consultation is not required forthis deliverable as the NSSC is only definingthe regulatory matters to be covered in theNER or NEM Procedures.

The actual changes to the NER and NEMProcedures will involve public consultation.

2nd

RWG Workshop 2/4 (Sydney)

Draft SMI Cost Recovery Paper

Draft SMI NER Ch 7 ReviewPaper

Compile feedback from 2nd

Workshop

Issue 2nd

Workshop Report to NSSCand RWG

NSSC Meeting 15 April (Sydney) –review Workshop Report

Revise Draft SMI Cost Recovery Paper(7/4 to 20/4)

Issue revised SMI Cost RecoveryPaper to RWG (21/4)

Draft SMI NER Ch 7 Review Paper(7/4 to 20/4)

Issue revised SMI NER Ch 7 ReviewPaper to RWG (21/4)

3rd

RWG Workshop 5/5(Melbourne)

Draft SMI CostRecovery Paper

Draft SMI NER Ch 7Review Paper

Compile feedback from 3rd

Workshop

Issue 3rd

Workshop Report toNSSC and RWG

NSSC Meeting 21 May(Melbourne) – reviewWorkshop Report

Finalise SMI Cost Recoverypaper

Revise paper from 3rd

RWG Workshop (11/5 to14/5)

Issue revised paper toRWG (15/5)

Feedback from RWG(18/5 to 26/5)

Revise paper (27/5 to29/5)

Finalise SMI NER Ch 7Review Paper

Revise paper from 3rd

RWG Workshop (22/5 to29/5)

Finalise SMI Cost Recoverypaper

Check stakeholdercomments with RWG(1/6 to 5/6)

Issue paper to NSSC(8/6)

NSSC Meeting 17 June(Sydney) – reviewpaper

Revise paper NSSCfeedback (18/6 to 19/6)

NSSC confirmation(22/6 to 26/6)

Issue paper to SCO(29/6)

Note: Public consultation on theSMI Cost Recovery paper is notrequired because any rulechanges to the NER will go theAEMC consultation processes.

Finalise SMI NER Ch 7Review Paper

Issue revised paper toRWG (1/6)

4th

RWG Workshop15/6 (Sydney)

Revise paper from 4th

RWG Workshop (16/6 to17/6)

Issue revised paper toRWG (18/6)

Comments period (19/6to 25/6)

Revise paper (26/6 to29/6)

Finalise SMI NER Ch 7Review Paper

Check stakeholdercomments with RWG(30/6 to 6/7)

Issue to NSSC (7/7)

NSSC Meeting 15 July(Melbourne) - reviewpaper

Revise paper NSSCfeedback (16/7 to 17/7)

NSSC confirmation(20/7 to 24/7)

Issue paper to SCO(27/7)

Note: Public consultation on theSMI NER CH 7 paper is notrequired because any rulechanges to the NER will go theAEMC consultation processes.

Page 14: National Smart Metering Program Memorandum Task Name % Complete Duration Start Finish 0 NSSC - National Smart Metering Program 0% 547 days Wed 12 Nov '08 Fri 31 Dec '10 1 Detailed

National Smart Metering ProgramNational Smart Metering Program

NSMP Work Plan – Schedule Overview

File Name: NSMP Schedule overview v1.0.docSecurity Classification:Page 6 of 6

Pilots/Trials Work Stream

January 2009 February 2009 March 2009 April 2009 May 2009 June 2009 July 2009

Issue Summary ReportTemplates to companiesfor completed andcurrent trials (5/1)

2008 Status Reportpreparation bycompanies for existingpilots/trials (6/1 to 20/2)

NSSC Meeting 21January (Melbourne)

Invitation to 1st

Pilots &Trials Working Group(PTWG) Workshop (2/2)

2008 Status Reportpreparation bycompanies for existingpilots/trials (6/1 to 20/2)

NSSC Meeting 18February (Sydney)

Major Findings extractedfrom existing pilot/trials2008 Status Reports –Pilots/TrialsCompleted/Current (23/2to 27/2)

Issue ExistingPilots/Trials draft 2008Status Report to PTWG(2/3)

1st

PTWG Workshop12/3 (Melbourne)

Discuss 2008 P/TStatus Report

Discuss future SMIcomponents fortesting

Revisions – Draft 2008Pilot/Trials Status Report(13/3 to 20/3)

NSSC Meeting 18March (Melbourne)

Feedback from PTWGon 2008 P/T StatusReport (23/3 to 31/3)

Revise P/T StatusReport for WGFeedback (1/4 to 2/4)

Issue 2008 P/T StatusReport to NSSC (3/4)

NSSC Meeting 15 April(Sydney) – review 2008Pilots/Trials StatusReport

Issue 2008 Pilots/TrialsStatus Report to SCO(17/4)

2nd

PTWG Workshop23/4 (Sydney)

Identify a list ofpreferred technicalmatters that mustbe tested

Discuss futurescenarios that maywarrant testing

PTWG Leader toprepare Pilot/TrialsScenarios WorkingPaper for NSSC (24/4 to7/5)

PTWG Leader toprepare Pilot/TrialsScenarios WorkingPaper for NSSC (24/4 to7/5)

Issue Pilots/TrialsScenarios WorkingPaper to NSSC (8/5)

3rd

PTWG Workshop20/5 (Melbourne)

Discuss Pilot/TrialsScenarios WorkingPaper

NSSC Meeting 21 May(Melbourne)

Revise Pilot/TrialsScenarios WorkingPaper (21/5 to 28/5)

Issue Pilot/TrialsScenarios WorkingPaper to WG (29/5)

NSSC Meeting 17 June(Sydney)

4th

PTWG Workshop18/6 (Sydney)

Discuss Pilot/TrialsScenarios WorkingPaper

Revise Pilots/TrialsScenarios WorkingPaper (19/6 to 24/6)

Issue Pilot/TrialsScenarios WorkingPaper to PTWG (25/6)

Final feedback fromPTWG (26/6 to 2/7)

January to June 2009Pilots/Trials StatusReport for MCE

Status reports fromcompanies (8/6 to26/6)

Major FindingsWorking Paper(29/6 to 3/7)

Final feedback from PTWGPilots/Trials Scenarios WorkingPaper (26/6 to 2/7)

Final revisions Pilots/TrialsScenarios Working Paper (3/7 to6/7)

Issue Pilots/Trials ScenariosWorking Paper to NSSC (7/7)

NSSC Meeting 15 July(Melbourne) – reviewPilots/Trials Scenario WorkingPaper

Issue Pilots/Trials ScenariosWorking Paper to SCO (20/7)

January to June 2009 Pilots/TrialsStatus Report for MCE

Major Findings WorkingPaper (29/6 to 3/7)

Issue Jan-June 09 Pilots/TrialsStatus Report to PTWG (6/7)

5th

PTWG Workshop 13/7(Melbourne)

PTWG feedback on Jan-June 09Pilots/Trials Status Report (14/7to 20/7)

Final Jan-June 09 Status Reportrevisions (21/7 to 22/7)

Issue Jan-June 09 Status Reportto NSSC (23/7)

NSSC Out of Session review(30/7)

Issue Jan-June Pilots/TrialsStatus Report to SCO (31/7)