NBCNBC – – (Revised) IRR(Revised) IRRNational Building Code (PD 1096)
Administration and Enforcement
Engr. Agustin S. Torres, mpmMember: NBC – (Revised) IRR
Oversight Committee NBCRC / DPWH
Head: Structural SectionProcessing DivisionOBO – Quezon City
eMail: obodpwh&yahoo.com Web: buildingcode.200u.com
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 2/148
IntroductionIntroduction
• Administration and Enforcement
Sect 201 – Responsibility for Adm & Enf. Sect 202 – Technical Staff
Sect 203 – General Power & Function Sect 204 – Profession & Tech. Assistance
Sect 205 – Building Official Sect 206 – Qualification of Bldg Official
Sect 207 – Duties of the Bldg Official
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 3/148
IntroductionIntroduction
• Administration and Enforcement
Sect 208 – Fees Sect 209 – Exemption
Sect 210 – Use of Income from Fees Sect 211 – Implementing Rules and Regulation
Sect 212 – Administrative Fines Sect 213 – Penal Provisions
Sect 214 – Dangerous and Ruinous Bldgs.
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 4/148
IntroductionIntroduction
• Administration and Enforcement
Sect 215 – Abatement of Dangerous Bldgs. Sect 216 – Other Remedies
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 5/148
IntroductionIntroduction
• Expectation in this lecture
Application Building Permit
Processing of Application for Bldg Permit Fees
Administrative Sanction
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 6/148
IntroductionIntroduction
• Lessons learned from the implementation
BP 344
Tragedies Decision of the Secretary
Opinions from DOJ
Relevant cases on implementation
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 7/148
Agenda / Overview Agenda / Overview• Application for Building Permit Building Permit and the Form
Ancillary Permits and the Forms
Accessory Permits and the Forms Processing of Application for Bldg Permit
Concept of Evaluation
Tools of processing
Steps in processing
Fees Imposition
Building Fees
Fines, Surcharges and Penalty
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 8/148
Application for Building Permit Application for Building Permit
• Building Permit – Section 301 / PD 1096 (NewIRR)
Section 301 – No person, firm or corporation, including anyagency or instrumentality of the government shall construct,
alter, repair, convert, use, occupy, move, demolish and add
any building/structure or any portion thereof or cause the
same to be done, without first obtaining a building permit
therefore from the Building Official assigned in the place
where the subject building/structure is located or to be done.
The prescribed application form (NBC Form B-01) shall beused by all application.
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 9/148
Application for Building Permit Application for Building Permit• Building Permit – Section 301 / PD 1096 (New IRR)
Feature of the Revised BP Form No. B – 01
Distinction of two side (Frontal & Dorsal Side)
Front Side – indicated entries from the applicant to be filled up by appropriate concerns.
Box 1 for detail, scope of application
Box 2 for full-time inspector of the construct’nBox 3 for applicant
Box 4 for lot owner
Box 5 for the Notary
Dorsal side – indicated entries from the OBO
Box 6 for processing & evaluation division
Box 7 for the Building Official which is the
Building Permit itself.
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 10/148
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 11/148
A li ti f B ildi P itA li ti f B ildi P it
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 12/148
Application for Building Permit Application for Building Permit• Building Permit – Section 301 / PD 1096 (New
IRR)Revised BP vs Old BPBox 1 for detail, Box 1- detail, scope of
scope, of application application
Cost/sty/date Box 3A – Cost/sty/dateBox 2 for full-time Box 7 – In-Charge of
project inspector Construction
Box 3 & 4 for applicant/owner Box 8 & 9
Box 6 for eval. Assest w/ ncso Box 4
New Revised / Removed
Box 5 for the notary (not in old BP form)
(not in revised BP form Box 2 – Bldg doc recd
Box 7 Building Permit itself . Box 3 – action of BO(not in revised BP form) Box 5 – time/flow
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 13/148
Application for Building Permit Application for Building Permit
• Box 6 (Old Bldg Permit) –Designing Architect / Engineer
1. Not included in the Building Permit Form for the fact
that he/she already responsible for the functional
design of the building/structure along with other
designers (civil, electrical, mechanical, etc).
2. The same way Civil/Structural, Mechanical, Electrical,
Plumbing, Sanitary and Electronic are not also
signatories of the Building Permit .
NBCNBC (N ) IRR(N ) IRR
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 14/148
NBCNBC – – (New) IRR(New) IRR
Box 1 – To be filled-up by the applicant;
OTHERS (specify) ________________
OCCUPANCY CLASSIFIED__________________________ TOTAL ESTIMATED COST P___________________________
NUMBER OF UNITS _______________________________ PROPOSED DATE OF CONSTRUCTION __________________
TOTAL FLOOR AREA __________________SQUARE METERS EXPECTED DATE OF COMPLETION _____________________
GROUP A: RESIDENTIAL DWELLINGS
APPLICATION NO.
OWNER/APPLICANT LAST NAME FIRST NAME M.I. TIN
FOR CONSTRUCTION OWNED BY AN ENTERPRSE FORM OF OWNERSHIP
ADDRESS NO STREET BARANGAY CITY/MUNICIPALITY ZIP CODE TELEPHONE NO.
LOCATION OF CONSTRUCTION LOT NO._________ BLK NO ________ TCT NO ________ TAX DEC NO ________
STREET _______________ BARANGAY _______________ CITY /MUNICIPALITY OF _______________________
SCOPE OF WORK
GROUP C: EDUCATIONAL, RECREATIONAL
GROUP B: RESIDENTIAL HOTEL APARTMENT
NEW CONSTRUCTION
ERECTION ______________
ADDITION ______________
ALTERATION ___________
GROUP D: INSTITUTIONAL
GROUP G: INDUSTRIAL STORAGE AND HAZA RDOUS
GROUP H: RECREATIONAL ASSEMBLY OCCUPANT LOAD LESS THAN 10
GROUP I: RECREATIONAL ASSEMBLY OCCUPANT LOAD 1000 OR MORE
GROUP F: INDUSTRIAL
USE OF CHARACTER OF OCCUPANCY
GROUP E: BUSINESS AND MERCANTILE GROUP J: AGRICULTURAL ACCESSORY
MOVING _____________________
RAISING _____________________________
ACCESORY BUILDING STRUCTURE _______
OTHERS (specify) _____________________
____________________________________
RENOVATION ________________
CONVERSION ________________
REPAIR _____________________
(see page 13/NCSO manual
1
22 3
4
5 Demolition
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 15/148
Application for Building Permit Application for Building Permit
• Treatment of Data/Information Entries
Box 1 – Detail of Application
Note: a) Relevant only for the use of the BuildingOfficial and LGU,
b) Not among the data to be encoded by
NCSO.
LAST NAME FIRST NAME MI TINOwner/Applicant
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 16/148
Application for Building Permit Application for Building Permit• Treatment of Data/Information Entries
Box 1 – Detail of Application
FOR OWNERSHIP OWNEDBY AN ENTERPRISE
FORM OFOWNERSHIP
Form of Ownership
Note: 1. Blank is not acceptable
2. Entry Instruction when name is an enterprise:
“Corp” or “Inc” - - Corporation“Proprietor”, “Prop” or “Owner” - Single Prop.
“Partners”, “Limited”, “Associates” -Partnership
“Cooperative” or “Coop” - - Cooperative“If name of a person” - - Private Individuals
fA li ti f B ildi P it
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 17/148
Application for Building Permit Application for Building Permit• Treatment of Data/Information Entries
Box 1 – Detail of Application
FOR OWNERSHIP OWNEDBY AN ENTERPRISE
FORM OFOWNERSHIP
Form of Ownership
Note: Form of Ownership
1. Private Individuals & Households 2. Single Proprietor
3. Partnership 4. Government Corporation
5. Private Corporation 6. Cooperative
7. Association 8. Local Government9. National Government 10. Others (Specify)
A li ti f B ildi P itA li ti f B ildi P it
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 18/148
Application for Building Permit Application for Building Permit• Treatment of Data/Information Entries
Box 1 – Detail of Application
NO. STREET BARANGAY CITY/MUN. ZIP CODE TEL. NO.
Address of Owner/Applicant
Note: 1. For the use of the Building Official & LGU
2. ZIP Code shall be indicated per 1993 PSTANDARD
GEOGRAPHIC CODE (see Appendix 7, NCSO
Manual for reference)
A li ti f B ildi P itA li ti f B ildi P it
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 19/148
Application for Building Permit Application for Building Permit• Treatment of Data/Information Entries
Box 1 – Detail of Application
LOT NO. BLK NO. TCT NO. TAX DEC. NO.
STREET ___________ BARANGAY ________ CITY/MUN. OF
________ ZC_________________
Location of Construction
Note: 1. For the use of the Building Official & LGU
2. ZIP Code shall be indicated per 1993 PSTANDARDGEOGRAPHIC CODE (see Appendix 7, NCSO
Manual for reference) corresponding to the
City/Municipality where the construction is located3. Example: Tagum, Davao 23192
A li ti f B ildi P itA li ti f B ildi P it
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 20/148
Application for Building Permit Application for Building Permit• Treatment of Data/Information Entries
Box 1 – Detail of ApplicationScope of Work
Note: 1. There should be check mark corresponding to one of thenumbers from 1 to 5. “Other” should be specified.
2. For “SoW” = 1 (New Construction), total cost, total
floor area and number of storey should be non-zero.
3. For “SoW = 2(Additions), total cost and total area
should be non-zero. Then, verify the number of storey.
Accept number of storey = 0, if total floor area is 1 to 15
square meters.
4. For “SoW” = 3 (Repair), 4 (Renov.), 5 (Demolition),there should be non-zero entries in total cost while total
floor area and number of storey should be zero.
NBCNBC –– (New) IRR(New) IRR
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 21/148
NBCNBC (New) IRR(New) IRR
Box 1 – To be filled-up by the applicant;
OTHERS (specify) ________________
OCCUPANCY CLASSIFIED__________________________ TOTAL ESTIMATED COST P___________________________
NUMBER OF UNITS _______________________________ PROPOSED DATE OF CONSTRUCTION __________________
TOTAL FLOOR AREA __________________SQUARE METERS EXPECTED DATE OF COMPLETION _____________________
GROUP A: RESIDENTIAL DWELLINGS
APPLICATION NO.
OWNER/APPLICANT LAST NAME FIRST NAME M.I. TIN
FOR CONSTRUCTION OWNED BY AN ENTERPRSE FORM OF OWNERSHIP
ADDRESS NO STREET BARANGAY CITY/MUNICIPALITY ZIP CODE TELEPHONE NO.
LOCATION OF CONSTRUCTION LOT NO._________ BLK NO ________ TCT NO ________ TAX DEC NO ________
STREET _______________ BARANGAY _______________ CITY /MUNICIPALITY OF _______________________
SCOPE OF WORK
GROUP C: EDUCATIONAL, RECREATIONAL
GROUP B: RESIDENTIAL HOTEL APARTMENT
NEW CONSTRUCTION
ERECTION ______________ ADDITION ______________
ALTERATION ___________
GROUP D: INSTITUTIONAL
GROUP G: INDUSTRIAL STORAGE AND HAZA RDOUS
GROUP H: RECREATIONAL ASSEMBLY OCCUPANT LOAD LESS THAN 10
GROUP I: RECREATIONAL ASSEMBLY OCCUPANT LOAD 1000 OR MORE
GROUP F: INDUSTRIAL
USE OF CHARACTER OF OCCUPANCY
GROUP E: BUSINESS AND MERCANTILE GROUP J: AGRICULTURAL ACCESSORY
MOVING _____________________
RAISING _____________________________
ACCESORY BUILDING STRUCTURE _______ OTHERS (specify) _____________________
____________________________________
RENOVATION ________________
CONVERSION ________________ REPAIR _____________________
(see page 13/NCSO manual
1
22 3
4
5 Demolition
A li ti f B ildi P itApplication for B ilding Permit
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 22/148
Application for Building Permit Application for Building Permit• Treatment of Data/Information Entries
Box 1 – Detail of Application Number of Units
Note: 1. The number of buildings covered by the building permitshould be indicated.
2. If the building permit is only for one building, then the
entry is 1.
3. If the building permit is for 5 separate buildings, then
the entry is 5.
4. If the building is an apartment/row house/accessoria
consisting of many doors, then the number of units
is still 1.
Application for Building PermitApplication for Building Permit
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 23/148
Application for Building Permit Application for Building Permit
• Treatment of Data/Information Entries Box 1 – Detail of Application: Type of
Use/Occupancy
Use or Type of Occupancy (of the NSO Manual)
Note: 1. There should be a check mark in one of the code
numbers from 10 to 74.
2. “Others” should be properly specified. If the type of
occupancy indicated in “others” is one listed on the
NCSO Manual use the corresponding codenumber.
NBCNBC Classification of all building by use/occupancyClassification of all building by use/occupancy
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 24/148
NBCNBC – – Classification of all building by use/occupancyClassification of all building by use/occupancy
ADMINISTRATION AND ENFORCEMENT
IRR VII – Classification and Gen. Requirements of
all Building by Use or Occupancy / PD 1096
• Ten (10) GroupsA B C D E F G H I J
R
e s i d e n t i a l
R e s . ,
H o t e l , A p t
.I n s t i t u t i o
n a l
H
a z a r d o u s / S t or a g e
A
s s e m b l y , OL < 1 0 0 0
A
s s e m b l y , OL > 1 0 0 0
A c c e s s or y S t r u c t .
I n d u s t r i a l
E
d u c . &R e c
r e a t i on
B
u s i n e s s / M e r c a n t i l e
GR
O
UP
DIV.(25) 2 1 2 3 3 1 3145
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 25/148
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 26/148
NBCNBC –– Example NCSO Type of OccupanciesExample NCSO Type of Occupancies
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 27/148
NBCNBC Example NCSO Type of OccupanciesExample NCSO Type of Occupancies
ADMINISTRATION AND ENFORCEMENT
Use or Type of Occupancy
• Residential: 11 – Single, 12 – Duplex13 – Row house/Accessoria , 14 – Quadruplex
15 – Residential Condo. 10 – Staff Houses
• Commercial:
22 - Store
Bakery, Department Store, Grocery, Shopping Center, Supermarket, Sari- Sari
Store, Video Rental, Other Business Store.
23 – Hotel/Motel
Inns, Pension houses
NBCNBC –– Example NCSO Type of OccupanciesExample NCSO Type of Occupancies
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 28/148
NBCNBC Example NCSO Type of OccupanciesExample NCSO Type of Occupancies
ADMINISTRATION AND ENFORCEMENT
Use or Type of Occupancy• Commercial:
24 – Office Condominium/Business/Office
Transportation Office, Radio & TV
Broadcasting & Transmitting Studios
25 – Restaurants, Etc.Cabarets, Day & Night Clubs, Disco
pads/houses, Bar & Cocktail Lounges, Beer
Gardens, Music Lounges, Night Club
26 – Shop
Beauty Parlor, Photo Developing Shop, Engraving Shop, Laundry Shop, Painter
Sho
NBCNBC –– Other USE/Other USE/OccuppanciesOccuppancies
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 29/148
NBCNBC Other USE/Other USE/OccuppanciesOccuppancies
ADMINISTRATION AND ENFORCEMENT
IRR VII: Other Grouping not mentioned in this Section
• The Secretary (DPWH) will issue farther groupclassification if the Code allows (after
amendment, ex. BP 220)
• Occupancy not expressly indicated shall adoptthe nearest it most nearly resembles.
• Ancillary building/structures as fences over
1.80m height, water tanks, etc., shall be
treated as separate structures.
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 30/148
Fence: 5.80 m. boundary structure. M. Balara, Quezon City
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 31/148
Validity
Date issued
TIN
FULL-TIME INSPECTOR AND SUPERVISOR OF CONSTRUCTION WORKS (REPRESENTING THE OWNER)
______________________
ARCHITECT OR CIVIL ENGINEER
(Signed and Sealed over printed name)
Date ____________________
Address
PRC No.
PTR No.
issued at
Full Time Inspector
NBCDO MEMORANDUM NO. 1 s 2006
FullFull--Time Inspector Time Inspector
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 32/148
Place Issued Date Issued Place Issued
__________________________________ Date___________
(Signature over printed name)
CTC No. Date Issued CTC No.
APPLICANT WITH MY CONSENT: LOT OWNER
_______________________________ Date___________
(Signature over printed name)
Address Address
BOX 3 – ApplicantBOX 4 – Lot Owner
Box 3 & 4Box 3 & 4 – – Applicant/Owner Applicant/Owner
NBCNBC – – Other Definition / ItemsOther Definition / Items
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 33/148
ADMINISTRATION AND ENFORCEMENT
Total Estimated Cost –
Use: Table II.G.1 – Fixed Construction Cost
Proposed Date of Construction – Should be in numeric figures; Ex. June 19,
2006, should written as 061906.
Expected Date of Completion – Should be laterthan the proposed date of construction and
should also be written in numeric figures.
Total Floor Area – Should be reported in square
meter, and there should always be non-
zero entry for all types of new building
construction and additions to existing buildings.
ASSESSED FEES ASSESSED BY AMOUNT DUE DATE PAID OR NUMBER NSO
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 34/148
ASSESSED FEES ASSESSED BY AMOUNT DUE DATE PAID O.R. NUMBER NSO
FILING FEE
PROCESSING FEE
LOCATIONAL /ZONING OF LAND USE
LINE AND GRADE (Geodetic)
FENCING ARCHITECTURAL
CIVIL/STRUCTURAL
ELECTRICAL
MECHANICAL
SANITARY
PLUMBING
ELECTRONICS INTERIOR
ONE HALF (1/2) OF FIRE SERVICE FUND (FSF)
TOTAL
Date Issued ----------------------- 9
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 35/148
tat/matrix Data Generation
Permit Number ------------------
Blank
Blank
Blank
Blank
Blank
Form of Ownership & Eco Activity
Blank
Location of Construction
Scope of Work -------------------
Number of Units -----------------
Type of Occupancy -------------
Data Generation for Reporting Consolidation 10
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 36/148
Statistic Com liance/ ur oseStatistic Com liance/ ur ose Data Generation
p g
Statistic Requirements for NCSO data generation
1. Permit Number
• Blank is not acceptable
• approve building permits are numberedcontinuously from 1 every year as
follows;
Y Y M M N N N N N• First two cells for the year
•Next two cells for the month of issuance
• Next five cells for chronological numbering of
permits issued every year.
Note: Alpha entry will not be included in encoding.
Data Generation for Reporting Consolidation 11
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 37/148
tatistic om liance/ ur ose Data Generation
p g
Statistic Requirements for NCSO data generation
2. Date Issued
• Date of issued of building permit should be
written numeric figures.
• For Example: if the date of issuance is February
14, 2005, this should be -
0 2 1 4 0 5
M M D D Y Y
NBCNBC – – IRR/2005 Evaluation adviseIRR/2005 Evaluation advise
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 38/148
ADMINISTRATION AND ENFORCEMENT
The Building Permit – What’s new in its Terms & Cond.
The New (Old IRR II, Sect 1.8/ not on BP form)
Article 1723 of the civil CodeAccompanied by ancillary & accessory permits
Relocation Survey, Geodetic Engineer,
Notify adjacent property owner before excav.
No sidewalk Occupancy unless permitted
Protection of pedestrian
Keep logbook, subject for scrutiny of BO Notice of Construction to be submitted to BO
NBCNBC – – IRR/2005 Evaluation adviseIRR/2005 Evaluation advise
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 39/148
ADMINISTRATION AND ENFORCEMENT
The Building Permit –
What is a Building Permit / evaluation advises
check authenticity of the professional signatories both of the designer and in charge of work;
provide the NCSO one (1) copy of the issued
Building Permit to serve as indicator of progress
and development of the construction industry.
provide also a copy of notice of construction tocontractor industry association of the
Philippines, CIAP (if or whenever it is already
submitted by the applicant, indicating starts ofconstruction.
– – RequireRequire
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 40/148
ADMINISTRATION AND ENFORCEMENT
The Building Permit –
Requirement for the issuance of BP.
complete the required clearances;• Locational Clearance from local planning dept.
• Clearances from various authorities exercising
and enforcing regulatory function affecting
the project.
• Example: proposed hospital from DOH
proposed hotel from Dept of Tourism
proposed ind’l bldg from DENR
NBCNBC – – IRR/2005 Ancillary PermitIRR/2005 Ancillary PermitADMINISTRATION AND ENFORCEMENT
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 41/148
ADMINISTRATION AND ENFORCEMENT
List of various authorities exercising and enforcingregulatory functions affecting buildings/structures
DPWH/widening
ATO/height
HLURB/condo
LGU/zoningDOT/hotel
DENR/pollution
DOTC/ bus/train sta.DILG/Fire/asst.
PPA/ harbor works
DepEd/ school
DOH/sanitation
PHIVOCS/faults
LLDA/discharge
MWSS/source NWRB/ug source
DAR/ conversions
DA/ dairy agri hseDOLE/ safety
NHA/ housing
NCWDP/ social
NBCNBC – – IRR/2005 Ancillary PermitIRR/2005 Ancillary Permit
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 42/148
ADMINISTRATION AND ENFORCEMENT
The Ancillary Permits –
What is an Ancillary Permit
permits forms duly signed and sealed by the
corresponding professionals who prepared the
documents required for Building Permit
document involves; plans/drawings, specifications,
design analysis, etc. and the Ancillary PermitForm itself.
Ancillary Permit Forms (next slides)
NBCNBC – – (New) IRR(New) IRR
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 43/148
Building Permit and Ancillary Permits
Inter-disciplinary undertaking
to attain a goal or objective/stowards nation’s development.
C L I E N T
Discipline/Professionals& Stakeholders
1. Building Technical
2. Building Official
3. Owner/Applicant
4. LGU
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 44/148
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 45/148
NBCNBC – – (New) IRR, similar entries on Ancillaries(New) IRR, similar entries on Ancillaries
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 46/148
STAIRS WASH ROOMS AND TOILETS SWITCHES, CONTROLS, BUZZERS DRINKING FOUNTAINS
WALKWAYS LIFTS AND ELEVATORS HANDRAILS PUBLIC TELEPHONES CORRIDOORS RAMPS THRESHOLDS SEATING ACCOMODATIONS
DOORS, ENTRANCES & THRESHOLD PARKING AREAS FLOOR FINISHES OTHERS (Specify)_________
NUMBER AND WIDTH OF EXIT DOORS FIRE EXITS OTHERS (Spec ify)_____
WIDTH OF CORRIDOORS FIRE FIGTHING & SAFETY FACILITIES DISTA NCE TO FIRE EXIT SMOKE DETECTTORS
ACCESS TO PUBLIC STREET EMERGENCY LIGHTS
PERCENTAGE OF IMPERVIOUS SURFACE AREA _________________%PERCENTAGE OF UNPAVE SURFACE AREA ______ _____________%
OTHERS (Specify) __________________________________________
1. ARCHIT ECTURAL FACILIT IES AND OTHER FEATURES PURSUANT TO BATAS PAMBANSA BILA NG 334, REGARDING CERTAIN BUILDING,
INSTITUTIONS, ESTABLISHMENTS AND PUBLIC UTILITIES TO INSTALL FACILITIES AND OTHER DEVICES.
2. PERCENTAGE OF SITE OCCUPANCY 3. CONFORMANCE TO FIRE CODE OF THE PHILIPPINES ( PD 1185)
PERCENTAGE OF BUILDING FOOTPRINT _______________________%
Box 1 – Architectural Permit : (Ancillary Permit)
Similarly, Ancillaries contained basic information pertaining to technical as well as data necessary for the
BO to assess compliance with the National Building
Code and its IRR as reflected in the Plans & Spec.
NBCNBC – – IRR/2005 Accessory PermitIRR/2005 Accessory Permit
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 47/148
ADMINISTRATION AND ENFORCEMENT
The Accessory Permits –
What is an Accessory Permit
permits issued by BO for activities usually before
or during the processing of the application for
Building Permit;some of these permits has expiry period .
accessory permit forms (next slides)
NBCNBC – – Ancillary/ Accessory Diagram Ancillary/ Accessory Diagram
JURISDICTION TO VARIOUS
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 48/148
JURISDICTION TO VARIOUS
ANCILLARY ON ACCESSORYPERMITS
Ancillaries
Accessories
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 49/148
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 50/148
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 51/148
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 52/148
NBCNBC – – IRR/2005 Phases of ConstructionIRR/2005 Phases of Construction
ADMINISTRATION AND ENFORCEMENT
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 53/148
ADMINISTRATION AND ENFORCEMENT
Phases of Building Permit/Construction –
Pre – Construction Phase
Construction Phase
Post Construction Phase
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 54/148
NBCNBC – – IRR/2005 Pre Const/ Step 1IRR/2005 Pre Const/ Step 1
ADMINISTRATION AND ENFORCEMENT
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 55/148
ADMINISTRATION AND ENFORCEMENT
Phases of Building Permit/Construction –
Pre – Construction Phase/ Steps & Procedures in
Processing application for Building PermitStep 1 – Receiving
• documents check for completeness including
clearances,
• if found incomplete or deficient, advise
applicant to complete/correct or rectify,• requirements compliance, advise applicant to
pay the non-refundable application fee.
• proceed/forward to Line & Grade Section.
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 56/148
NBCNBC – – IRR/2005 Pre ConstructionIRR/2005 Pre Construction
Phases of Building Permit/Construction –
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 57/148
g
Verify compliance with the requirements ofapplication for Building Permit.
Conduct site inspection for verification of
submitted documents & site conditions
If construction/activities had already been started,
imposed per procedure fines & surchargesRecommend rectification if misrepresentation is
committed per observation. Ex. Actual lot/site
different from submitted documents.
Pre – Evaluation of Application for Bldg Permit
Adm Adm && Enf Enf – – Evaluation/ Processing definedEvaluation/ Processing defined
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 58/148
Evaluation –
– the process of assessing compliance of a
proposed project (construction) withexisting regulation or law/s promulgated
for the purpose of protecting the public
against excessive or lacking of
requirements of what is necessary.
– since it is a process, it is usually
termed: Processing
Adm Adm && Enf Enf – – Tools for Evaluation ProcessTools for Evaluation Process
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 59/148
Evaluation – Tools for use in Evaluation;
- Forms, documents & clearances
submitted by the applicant,
- Referral Codes, literature & standards so
authorized by the Secretary,
- Review of related literature/s
- Computer/s (records, existing structures)
- Localized evaluation forms
Adm Adm && Enf Enf – – Evaluation Sheet (Sample), Arch.Evaluation Sheet (Sample), Arch.
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 60/148
Adm Adm && Enf Enf – – Evaluation Sheet (Sample),Evaluation Sheet (Sample), StructStruct..
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 61/148
NBCNBC – – IRR/Pre Const. Step 1, Line & GradeIRR/Pre Const. Step 1, Line & Grade
ADMINISTRATION AND ENFORCEMENT
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 62/148
ADMINISTRATION AND ENFORCEMENT
Phases of Building Permit/Construction –
Pre – Construction Phase/ Steps & Procedures in
Processing application for BP (cont’d)Line and Grade verification;
• established line and grade on all sides of the lot
based on the technical description of TCT.
• Indicate physical & environmental constraints,
Ex. Road & widening, River/creek, etc.• access to the site or property.
• foundation encroaching public property.
NBCNBC – – IRR/ Pre Const. Step 2, Arch.IRR/ Pre Const. Step 2, Arch.
ADMINISTRATION AND ENFORCEMENT
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 63/148
ADMINISTRATION AND ENFORCEMENT
Phases of Building Permit/Construction –
Pre – Construction Phase/ Steps & Procedures in
Processing application for BP (cont’d)Step 2 – Architectural Section
• compliance to type/s of occupancy/use
• Compliance to setback/easement, parking and
accessibility, light and ventilation;
• if found deficient, return with statement oferror/corrections for compliance,
• resubmitted corrected docs found complied
substantially, proceed to other sections
FEB. 25, 1983 OCT. 3, 1984IRR /EFFECT
PRES MARCOS
NEW PROPOSED
BP 344BP 344 – – HistogramHistogram
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 64/148
PRES MARCOS
SIGNED THIS ACT
BP 344SCOPE
ALL BLDG &
STRUCTPERMIT
-IRR 1: SCOPE & APP
-IRR 2: MIN REQ’MENTS
-IRR 3: SPECIFIC REQ.
-IRR 4: TRANSPORT REQ
-IRR 5: ADM & ENF
A P P L I C A
T I O N -CONSTRUCTN
-REPAIR
-RENOVATION
-CHANGE OCCUP
INCORPORATED
IN DESIGN &FACILITIES
INSTALLATION
EXISTING
a) PRIMARY
FUNCTION
b) 10% OF TOTAL
NUMBER
c) INGRESS/EGRESS
d) PARKING AREAS
a) WORK TO BE
DONE AT
PRIMARY
FUNCTION
b) USE OF
ELEVATOR/LEVEL
c) 10% LIMIT ONFUNCTION ROOM
d) NOT EFFECT
STRUCTURAL
e) COST NOT MORE
THAN 20% /BLDG
f) NO LEGAL EFFECT
B O T H
PRIVATE PUBLIC
NON-
ISSUANCE
WHEN NOT
TO ISSUE
VIOLATION BY
CONSTITUTE
-OWNER
-CONTRACTOR
-ARCHITECT
-ENGINEER
-BLDG OFF’L
NON-COMPLIANCE-STAIRS
-WALKWAYS-CORRIDORS-DOORS/ENTR -WASH/REST RM-LIFTS/ELEV-RAMP-PARKING-SWITCHES/-HANDRAILS
-THRESHOLDS-FLOOR FINISHES-DRINKING FOUN-PUB TELEPHONE-SEATING CAPACITY
EDUC INST
AIRPORTS
SHOPS/EST
SPORT CX
RECREA CX
PAKINGPUB TRANS
STREETS
HIGHWAY
PED XING
BP 344BP 344 -- Determination of Violation / MagnaDetermination of Violation / Magna CartaCarta
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 65/148
PERMIT
A
P P L I C A T I O N
INCORPORATED
IN DESIGN &
FACILITIES
INSTALLATION
NON-ISSUANCE
WHEN
NOT
TO ISSUE
VIOLATION BY
CONSTITUTE
-OWNER
-CONTRACTOR
-ARCHITECT
-ENGINEER
-BLDG OFF’L
NON-COMPLIANCE
-STAIRS
-WALKWAYS
-CORRIDORS
-DOORS/ENTR
-WASH/REST RM
-LIFTS/ELEV
-RAMPS, ETC.
Determination of violations
a) IRR 5, Section 2 : Adm & Enf.
MAGNA CARTA /Disabled Per.
Penalty:
1st violation: P50T to 100 T or/w 6 Moin prison up to 2 yrs or both.
2nd violation: P100 to 200T or/w 2 Yrs
in prison up to 6 yrs or both.
Abused: not less than 6 Mo in prison &
imposed P5T to P50T or both.
BP 344BP 344 – – Determination of violation/ BP 344 provisionDetermination of violation/ BP 344 provision
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 66/148
PERMIT
A
P P L I C A T I O N
INCORPORATED
IN DESIGN &
FACILITIES
INSTALLATION
NON-ISSUANCE
WHEN
NOT
TO ISSUE
VIOLATION BY
CONSTITUTE
-OWNER
-CONTRACTOR
-ARCHITECT
-ENGINEER
-BLDG OFF’L
NON-COMPLIANCE
-STAIRS
-WALKWAYS
-CORRIDORS
-DOORS/ENTR
-WASH/REST RM
-LIFTS/ELEV
-RAMPS, ETC.
Determination of violations
b) IRR Section 4.
BP 344 /Disabled Per.
Penalty:
6 Mo. In prison and fine of P2Tto P5T or both.
BP 344BP 344 – – Jurisdiction of PenaltyJurisdiction of Penalty
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 67/148
PERMIT
A
P P L I C A T I O N
INCORPORATED
IN DESIGN &
FACILITIES
INSTALLATION
NON-ISSUANCE
WHEN
NOT
TO ISSUE
VIOLATION BY
CONSTITUTE
-OWNER
-CONTRACTOR
-ARCHITECT
-ENGINEER
-BLDG OFF’L
NON-COMPLIANCE
-STAIRS
-WALKWAYS
-CORRIDORS
-DOORS/ENTR
-WASH/REST RM
-LIFTS/ELEV
-RAMPS, ETC.
Jurisdiction of Penalty
a) Based on the New IRR. – the BO can
deny the application for BuildingPermit. The applicant can make appeal.
b) In both cases, non-compliance can be
filed in civil court for imposition of
penalty.
Note: BO cannot imposeimprisonment term to violator of
BP 344
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 68/148
PROCESSING APPLICATION FOR BLDG PERMITS
USING THE CODE PROCEDURES
LAND USE AND
ZONING
ISSUANCE OF BUILDING PERMIT
PAYMENT OF
FEES
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 69/148
NBC - IRR/ Administration & Enforcement 69
NBCNBC – – (NR)IRR(NR)IRR BP Processing Flow BP Processing Flow Administrative & Enforcement
REQUIRED
CLEARANCES
MUNICIPAL
TREASURER
VERIFICATION OF
ZONING & OTHER
CLEARNCES
FINAL EVALUATION
AND
RECOMMENDATION
LINE AND GRADE
(GEODETIC)
ARCHITECTURAL
INTERIOR/
ACCESSIBILITY
PLUMBING
SANITARY
ELECTRICAL
ELECTRONICS &
COMMUNICATION
MECHANICAL
OTHERS
(SPECIFY, REPAIR)
CIVIL/
STRUCTURAL
ZONING
BUILDING
OFFICIAL
APPLICATION
REALEASE
TRUE COPY TCT
TAXDEC & RCPT
(LEASE CNTRCT)
SETS OF PLANS& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
1 2 3
4
5
6
7
8
9
11 12
10
13
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 70/148
NBC - IRR/ Administration & Enforcement 70
NBCNBC – – (NR)IRR(NR)IRR BP Processing Flow BP Processing Flow Administrative & Enforcement
REQUIRED
CLEARANCES
VERIFICATION OF
ZONING & OTHER
CLEARNCES
LINE AND GRADE
(GEODETIC)
ARCHITECTURAL
INTERIOR/
ACCESSIBILITY
APPLICATION
TRUE COPY TCT
TAXDEC & RCPT
(LEASE CNTRCT)
SETS OF PLANS& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
1 2 3
Receiving:
-Completeness of documents per Section 302/ App for BP
- Incomplete/deficient return to applicant for compliance
- Complied w/ req., pay filing fee
Line & Grade:
- Set L&G per TCT
- Easements & Access
- Determine pay items
Archi tectural:
-Types of Occupancy/Use
- Setback/Easements/parking/ Accessibility & L& Vent’n
- Fire Protection requirements, Exi ts, Occupancy Loads
- Floor & Premises Areas, Projections, Heights
- Determine pay items
- Sect 804/ Courts & Yards, min horizontal distance not less than 2m for
Architectural Processing Section
BO Evaluation of Compliance
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 71/148
NBC - IRR/ Administration & Enforcement 71
NBCNBC – – (NR)IRR(NR)IRR BP Processing Flow BP Processing Flow
REQUIRED
CLEARANCES
VERIFICATION OF
ZONING & OTHER
CLEARNCES
LINE AND GRADE
(GEODETIC)
ARCHITECTURAL
INTERIOR/
ACCESSIBILITY
APPLICATION
TRUE COPY TCT
TAXDEC & RCPT
(LEASE CNTRCT)
SETS OF PLANS& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
1 2 3
1 & 2 sty bldg., 1.5m on cluster bldg.
1.5m 1.5m
Courts
B ui l d i n g
pr o p er
Building proper
BO Evaluation of Compliance
Architectural Processing Section
BO Evaluation of Compliance
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 72/148
NBC - IRR/ Administration & Enforcement 72
NBCNBC – – (NR)IRR(NR)IRR BP Processing Flow BP Processing Flow Administrative & Enforcement
REQUIRED
CLEARANCES
VERIFICATION OF
ZONING & OTHER
CLEARNCES
LINE AND GRADE
(GEODETIC)
ARCHITECTURAL
INTERIOR/
ACCESSIBILITY
APPLICATION
TRUE COPY TCT
TAXDEC & RCPT
(LEASE CNTRCT)
SETS OF PLANS& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
1 2 3
- Sect 806/ Room Minimum Size and Dimension
a) Human habitation shall be 6 sq m., 2m least dimensionb) Kitchen shall be 3 sq m., 1.5m least dimension
c) Toilet shall be 1.2 sq m., 0.9m least dimension
BO Evaluation of Compliance
1. Sect 804/ Courts & Yards
BO Evaluation of Compliance
Architectural Processing Section
BO Evaluation of Compliance
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 73/148
NBC - IRR/ Administration & Enforcement 73
NBCNBC – – (NR)IRR(NR)IRR BP Processing Flow BP Processing Flow Administrative & Enforcement
REQUIRED
CLEARANCES
VERIFICATION OF
ZONING & OTHER
CLEARNCES
LINE AND GRADE
(GEODETIC)
ARCHITECTURAL
INTERIOR/
ACCESSIBILITY
APPLICATION
TRUE COPY TCT
TAXDEC & RCPT
(LEASE CNTRCT)
SETS OF PLANS& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
1 2 3
- Sect 805/ Ceiling Heights
a) Artificial Ventilation, ceiling height not less than:
2.7m – 1st floor
2.4m – 2nd floor2.1m – 3rd floor and up
b) Natural Ventilation; 2.7m – any floor
c) Mezzanine Height; 1.8m – above & below floor
BO Evaluation of Compliance
1. Sect 804/ Courts & Yards
2. Sect 806/ Room Minimum Size and Dimension
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 74/148
NBC - IRR/ Administration & Enforcement 74
BUILDING
SECTION
Artificial Ventilation Room
Ceiling Ht. not less than
2.70 m – 1st floor
2.40 m – 2
nd
storey2.10 m – 3rd and up
Natural Ventilation Room
2.70 m – Any Floor
Mezzanine Ht.1.80 m – Above / Below
Int. Beam
DefinitionsDefinitions – – Floor Level / 15Floor Level / 15
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 75/148
NBC - IRR/ Administration & Enforcement 75
Storey Ht.Ceiling Ht.
Storey – Portion of a building/structure includedbetween the uppermost surface (or finished
level) of any floor and the uppermost surface
(or finished level) of the next floor above(or ceiling or roof above) or below it (Glossary).
First Storey – storey the floor of which is at/or abovethe level of the sidewalk, the remaining storeys
being numbered in regular succession upward.
The Code (PD 1096) Compliance / 20The Code (PD 1096) Compliance / 20
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 76/148
NBC - IRR/ Administration & Enforcement 76
PD 1096 Sect 807:
Air Space Requirement in Determining Size of Rooms:
Air Space shall be as follows;
– School rooms :• Volume- - - - - - - 3.00 cu. m.
• Floor area/person - - 1.00 sq. m
– Workshops, Factories, and Offices:
• Volume - - - - - - - 12.00 cu. m.
• Floor area/person - - - 1.00 sq. m.
– Habitable rooms:
• Volume - - - - - - - 14.00 cu. m.
• Floor area/person - - - 1.00 sq. m.
- Sect 808/ Window Openings for any room without artificial ventilation sy
stem shall be
Architectural Processing Section
BO Evaluation of Compliance
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 77/148
NBC - IRR/ Administration & Enforcement 77
NBCNBC – – (NR)IRR(NR)IRR BP Processing Flow BP Processing Flow Administrative & Enforcement
ARCHITECTURAL
INTERIOR/
ACCESSIBILITY
3
stem shall be
a) 10% (least) of floor area, no less than 1.0 sq m.
b) 1/20 of toilet, bath or laundry room areac) Shall open di rectl y to;
- court w/in property
- yard with regular setback
- public street or alley, not FW
- open water courses, not FW
1. Sect 804/ Courts & Yards
2. Sect 806/ Room Minimum Size and Dimension
3.Sect 805/ Ceiling Heights
- Sect 1207/ Design Requirements;
Architectural Processing Section
BO Evaluation of Compliance
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 78/148
NBC - IRR/ Administration & Enforcement 78
NBCNBC – – (NR)IRR(NR)IRR BP Processing Flow BP Processing Flow Administrative & Enforcement
ARCHITECTURAL
INTERIOR/ACCESSIBILITY
3
a) Occupants Loads and Exits Req.
b) Width & Arrangement of Exi ts;
c) Exit Door swing shall be in the direction of exit travel when serving
hazardous areas or with occupant load of 50 or more.
d) Exit shall be openable inside without the use of a key. . .
1. Sect 804/ Courts & Yards
2. Sect 806/ Room Minimum Size
and Dimension
3.Sect 805/ Ceiling Heights
4. Sect 808/ Window Openings
Architectural Figures Architectural Figures
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 79/148
Refer to Table VII.G.3/p301-IRR for Residential and Commercial
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 80/148
Architectural Figures Architectural Figures
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 81/148
The Ozone DiscoThe Ozone Disco
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 82/148
NBC - IRR/ Administration & Enforcement 82
THE OZONE DISCO
a) Architectural Failure
b) Electrical Failure
c) Structural Failure
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 83/148
LAND USE AND
ZONING
Civil/Structural Section
BO Evaluation of Compliance
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 84/148
NBC - IRR/ Administration & Enforcement 84
NBCNBC – – (NR)IRR(NR)IRR BP Processing Flow BP Processing Flow Administrative & Enforcement
REQUIRED
CLEARANCES
VERIFICATION OF
ZONING & OTHER
CLEARNCES
LINE AND GRADE
(GEODETIC)
ARCHITECTURAL
INTERIOR/
ACCESSIBILITY
CIVIL/
STRUCTURAL
APPLICATION
TRUE COPY TCT
TAXDEC & RCPT
(LEASE CNTRCT)
SETS OF PLANS& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
1 2 3
4
Sect 708/ Min Requirements; (pd 1096)
a) Foundation: Footings shall be of sufficient size and strength to supp
ort the load of the dwelling and shall be at least;
- 250mm thick
- 600mm below ground level
b) Post of wooden construction shall be per Table 708-A, each post sh
all be anchored to such footing by straps and bolt of adequate size.
LAND USE AND
ZONING
Civil/Structural Section
BO Evaluation of Compliance
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 85/148
NBC - IRR/ Administration & Enforcement 85
NBCNBC – – (NR)IRR(NR)IRR BP Processing Flow BP Processing Flow Administrative & Enforcement
REQUIRED
CLEARANCES
VERIFICATION OF
ZONING & OTHER
CLEARNCES
LINE AND GRADE
(GEODETIC)
ARCHITECTURAL
INTERIOR/
ACCESSIBILITY
CIVIL/
STRUCTURAL
APPLICATION
TRUE COPY TCT
TAXDEC & RCPT
(LEASE CNTRCT)
SETS OF PLANS& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
1 2 3
4
Sect 708 PD 1096/ Minimum Requirements;
c) Floor Live Load shall be;
- 200 Kg/sq m for 1st floor,
- 150 Kg/sq m for 2nd floor
d) Roofs wind load shall be at least -120 Kg/Sq m of vertical
projection
LAND USE AND
ZONING
Civil/Structural Section
BO Evaluation of Compliance
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 86/148
NBC - IRR/ Administration & Enforcement 86
NBCNBC – – (NR)IRR(NR)IRR BP Processing Flow BP Processing Flow Administrative & Enforcement
REQUIRED
CLEARANCES
VERIFICATION OF
ZONING & OTHER
CLEARNCES
LINE AND GRADE
(GEODETIC)
ARCHITECTURAL
INTERIOR/
ACCESSIBILITY
CIVIL/
STRUCTURAL
APPLICATION
TRUE COPY TCT
TAXDEC & RCPT
(LEASE CNTRCT)
SETS OF PLANS& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
1 2 3
4
- Written reports of Geotechnical Engineer shall be
submitted w/ the application for BP.
1. Sect 708/ Min Requirements;
Boring and Load Test (in accordance with NSCP) for the following;
- Building/structures of three (3) sty and higher,
- Lower bui lding/structures shall also be required on areas w/
potential geological/ geotechnical hazards, areas
LAND USE AND
ZONING
Civil/Structural Section
BO Evaluation of Compliance
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 87/148
NBC - IRR/ Administration & Enforcement 87
NBCNBC – – (NR)IRR(NR)IRR BP Processing Flow BP Processing Flow Administrative & Enforcement
REQUIRED
CLEARANCES
VERIFICATION OF
ZONING & OTHER
CLEARNCES
LINE AND GRADE
(GEODETIC)
ARCHITECTURAL
INTERIOR/
ACCESSIBILITY
CIVIL/
STRUCTURAL
APPLICATION
TRUE COPY TCT
TAXDEC & RCPT
(LEASE CNTRCT)
SETS OF PLANS& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
1 2 3
4
NSCP 2001, Sect 303.(1-4)
c) Provide data;
- soi l bearing capacity
- compressibili ty,- l iquefaction (PI) and - expansiv
eness/ASTM4546
or 4829, index 20 require
special design)
1. Sect 708/ Min Requirements;
Foundation Investigation:
a) shall be conducted at each site
b) CE shall make evaluation, evaluate, interpret results
2. Sect 302.5/ PD 1096 – Boring Test Requirement
LAND USE AND
ZONING
Civil/Structural Section
BO Evaluation of Compliance
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 88/148
NBC - IRR/ Administration & Enforcement 88
NBCNBC – – (NR)IRR(NR)IRR BP Processing Flow BP Processing Flow Administrative & Enforcement
REQUIRED
CLEARANCES
VERIFICATION OF
ZONING & OTHER
CLEARNCES
LINE AND GRADE
(GEODETIC)
ARCHITECTURAL
INTERIOR/
ACCESSIBILITY
CIVIL/
STRUCTURAL
APPLICATION
TRUE COPY TCT
TAXDEC & RCPT
(LEASE CNTRCT)
SETS OF PLANS& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
1 2 3
4
NSCP 2001, Sect 104.5
Foundation Investigation required
a) bldg falling under Categories ;
Cat I - Essential Facilities (Hospital, etc.)
Cat II -Hazardous Facilities (Struct w/ Toxic, or
Hazards contents)
Cat III – Special Occupancy (struct of publi c
assembly with more than 300 OL)
1. Sect 708/ Min Requirements;
2. Sect 302.5/ PD 1096 – Boring Test Requirement
3.Sect 302 PD 1096 - Jurisdiction
LAND USE AND
ZONING
Civil/Structural Section
BO Evaluation of Compliance
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 89/148
NBC - IRR/ Administration & Enforcement 89
NBCNBC – – (NR)IRR(NR)IRR BP Processing Flow BP Processing Flow Administrative & Enforcement
REQUIRED
CLEARANCES
VERIFICATION OF
ZONING & OTHER
CLEARNCES
LINE AND GRADE
(GEODETIC)
ARCHITECTURAL
INTERIOR/
ACCESSIBILITY
CIVIL/
STRUCTURAL
APPLICATION
TRUE COPY TCT
TAXDEC & RCPT
(LEASE CNTRCT)
SETS OF PLANS& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
1 2 3
4
Sect 302 PD 1096- Foundation Investigation
NSCP 2001, Sect 304
Foundation Investigation required when using Table 304-1;
a) Assumption limitation
- Continuous Footing w/ load > 30 kN/m
- Isolated Footing with load > 250 kN.
b) Higher values set by Tab 304-1 on soil bearing capacity
in reference to min depth prescribed by
PD 1096
1. Sect 708/ Min Requirements;
2. Sect 302.5/ PD 1096 – Boring Test Requirement
3.Sect 302 PD 1096 - Jurisdiction
Compliance to NSCP / 7Compliance to NSCP / 7
2001 Edition (1972, 1981, 1986, 1992) NSCP
Ch 1 G
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 90/148
NBC - IRR/ Administration & Enforcement90
Chap 1 – Gen Req.
Table 304 – 1 Allowable Found. & Lateral Pressure
Class of Materials² Allowable Foundation
(ASTM Classification) Pressure³ ( kPa )
1. Massive Crystalline Bedrock 200
2. Sedimentary & Foliated Rock 100
3. Sandy Gravel /Gravel (GW & GP) 1004. Well Graded Sand . . (SW, SP, SM, etc) 75
5. Clay, Sandy Clay . . (CL, ML, MH & CH) 50
(See footnotes for application)
0 Df=300mm Qa=100kPa
Civil/Structural Section
2001 Edition (72, 81, 86, 92) NSCP
Chap 1 Gen Req
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 91/148
NBC - IRR/ Administration & Enforcement91
Dp Df
t
N
G
0. Df=300mm, Qa=100kPa
1.
2.
3.
t(min) = 250mm
Dp(min) = 600mm
Chap 1 – Gen Req.
Table 304 – 1 Allowable Found.
& Lateral Pressure
Footnotes of Table 304 – 1
All values of allowable foundation
pressure are for footings having a
minimum width of 300 mm and aminimum depth of 300 mm into
natural grade. Except as in footnote
7 below, increase of 20% is allowed
for each additional 300 mm ofwidth and/or depth to a maximum
value of three times the designated
value.
(+20%), Df=600mm, Qa=120kPa
(+20%), Df=900mm, Qa=140kPa
(+20%), Df=900mm, Qa=140kPa
Structural Evaluation SheetStructural Evaluation Sheet
2 R l i D ( i )
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 92/148
• 2. Regulation Data (min):
• Qa(assumed) = 140 (to 145) kPa
• SBC/Test = (if submitted as required)
• Pn (Designed) = Pn<250 kN /Isolated Footing
Pn<30 kN/m/Wall Footing
• Depth Footing = Dp = 600mm or
• Depth Foundation= Df = equal/least dimensionof footing base
• Thickness slab tf(min) = 250 mm.
3. What is the least assumed SBC allowed by the Code/NSCP
2001 Edition (1972 1981 1986 1992) NSCP
Civil/Structural Section
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 93/148
NBC - IRR/ Administration & Enforcement93
2001 Edition (1972, 1981, 1986, 1992) NSCP
Chap 1 – Gen Req. Foundation investigation (Sect. 104.5)Sect. 303. (1 to 4) – Report for Soil Investigation
a) plot showing location of all test boring b) description & classification of soil
encountered
c) Elevation of the water table, if encounteredd) Recommendations for;
foundation type & design criteria
bearing capacity, provision to mitigateexpansive soil, provision to mitigate liquefactionand soil strength, effects of adjacent loads
e) Expected total and differential settlement
Pre Fabricated Construction
Civil/Structural Sect
ion
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 94/148
NBC - IRR/ Administration & Enforcement 94
Pre – Fabricated Construction2001 Edition (1972, 1981, 1986, 1992) NSCP
Chap 1 – Gen Req. Sect. 107 – Structural Inspection,
Test and Structural ObservationSect. 107.7 Prefabricated Construction / 1 107.7.1 : Purpose is to
regulate materials and establish method of safe construction
where any structure or portion thereof is wholly or partially prefabricated.
Definitions ;
a) Prefab. Assy. – done prior to incorporation in the bldg.
b) Test of Materials – test to be made during prefabrication
c) Test of Assy. – test for durability & weather resistance
d) Connections – device used to connect prefab assy/Code req.
2001 Edition (1972 1981 1986 1992)
Civil/Structural Section
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 95/148
NBC - IRR/ Administration & Enforcement95
2001 Edition (1972, 1981, 1986, 1992) National Structural Code of the Phil.
Chap 1 – Gen Req. Sect. 107 – Structural Inspection, Test and Structural
Observation
Sect. 107.7 Prefabricated Construction / 2
107.7.6.(1-2) : Cert. and Inspection – as to inspection done and declare
compliance with the requirements of the Code.
107.7.6.3: Certifying Agency – to be acceptable under this Code, everycertificate of approval shall be made by an approved agency.
(Note: Reference is also made to Section 416 – Precast Concrete where test and
acceptance is also required by the Code)
Certification Issued, Prefab Structural, NSCP/13Certification Issued, Prefab Structural, NSCP/13
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 96/148
NBC - IRR/ Administration & Enforcement 96
DPWH / Office of the Secretary, Manila; Feb 14, 2007
Vasquez Building System Corp./ 1269 EDSA, QC.
This refers to your letter reply dated February
02, 2007 to our 16 January 2007 letter regarding our
evaluation and recommendation on the VAZBUILT
Prefab Columns and Panel Systems, which as cited inYour letter is good only for a one-storey building system.
Based on the Technical Brochure you submitted,
That contains among other information . . .
Acting Exec Dir., NBCDO
The Code (PD 1096) Compliance / 24The Code (PD 1096) Compliance / 24
PD 1096 Sect 1210 (e): Tower and Spires (Roof
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 97/148
NBC - IRR/ Administration & Enforcement 97
PD 1096 Sect 1210 (e): Tower and Spires (RoofStructures): Least x-sectional area exceed 10 sq m;
– Supporting frames shall extend directly to the ground
– Shall be constructed entirely of incombustible materials
– Shall withstand wind load in any direction in addition to any
other loads.
Note: application of the above installations can be useful in
communication tower, cell site, and roof sign structures
Sign(2) Structures CollapsesSign(2) Structures Collapses
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 98/148
NBC - IRR/ Administration & Enforcement 98
The Millenyo Challenges the Billb
oards
LAND USE AND
ZONING
Civil/Structural Section
BO Evaluation of Compliance
1. Sect 708/ Min Requirements;
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 99/148
NBC - IRR/ Administration & Enforcement 99
NBCNBC – – (NR)IRR(NR)IRR BP Processing Flow BP Processing Flow Administrative & Enforcement
REQUIRED
CLEARANCES
VERIFICATION OF
ZONING & OTHER
CLEARNCES
LINE AND GRADE
(GEODETIC)
ARCHITECTURAL
INTERIOR/
ACCESSIBILITY
CIVIL/
STRUCTURAL
APPLICATION
TRUE COPY TCT
TAXDEC & RCPT
(LEASE CNTRCT)
SETS OF PLANS& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
1 2 3
4
NSCP /Excerpt for PD 1096
Minimum size for Column constituting the principal support of a floor or roof shall
have a dimensions of at least
a) 25cm diameter for spiral column
w/ 6- 16mmØ RSB
b) 20cm least x-dimension for anytied column (600sq cm w/ 4- 16mmØ RSB
c) RSB shall be between (0.01- 0,08) of gross secti onal area.4. Sect 302 PD 1096- Foundation Investigation
2. Sect 302.5/ PD 1096 – Boring Test Requirement
3.Sect 302 PD 1096 - Jurisdiction
Civil/Structural Section
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 100/148
NBC - IRR/ Administration & Enforcement 100
Area = 60000 sq mm
300 mm
200 mm
250 mmSpiral Colum
n
NSCP on Concrete:
Limiting Dimension of Column:
Civil/Structural Section
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 101/148
NBC - IRR/ Administration & Enforcement 101
Limiting Dimension of Column:
Equivalent circular column – As an exception to the general
procedure of utilizing the full gross area of the column section, it shall
be permissible to design a circular column and to build it with a square,octagonal, or other shaped section of the least lateral dimension, in
such case, the allowable load, the gross area considered, and the
required percentage of reinforcement shall be taken as those of the
circular column.
16 mm Ф RSB
(minimum size)
Abandoned Construction Abandoned Construction
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 102/148
NBC - IRR/ Administration & Enforcement 102
MRT-Ayala Project, North Ave/Edsa, Quezon City
Compliance by NSCP / 2Compliance by NSCP / 2
2001 Edition (1972, 1981, 1986, 1992) NSCPChap 1 Gen Req on Analysis (Sect 104 4)
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 103/148
NBC - IRR/ Administration & Enforcement103
( , , , )Chap 1 – Gen Req. on Analysis (Sect. 104.4)
Consideration of Analysis focus of rationality of equilibrium,stability, geometric compatibility, materials properties;
Distribution of Horizontal Shear (lateral force)
Stability Against Overturning
Sec 206.6 for Retaining Wall
Sec 207 for Wind Loading
Sec 208 for Seismic Loading
Self Straining Forces (caused by settlements, temp., etc)
Anchorage (roof to wall/column, column to foundation)
MUNICIPAL CIVIL/
LAND USE AND
ZONING
4
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 104/148
NBC - IRR/ Administration & Enforcement 104
NBCNBC – – (NR)IRR(NR)IRR BP Processing Flow BP Processing Flow Administrative & Enforcement
REQUIRED
CLEARANCES
MUNICIPAL
TREASURER
VERIFICATION OF
ZONING & OTHER
CLEARNCES
LINE AND GRADE
(GEODETIC)
ARCHITECTURAL
INTERIOR/
ACCESSIBILITY
PLUMBING
SANITARY
ELECTRICAL
ELECTRONICS &
COMMUNICATION
MECHANICAL
OTHERS
(SPECIFY, REPAIR)
CIVIL/
STRUCTURAL
APPLICATION
TRUE COPY TCT
TAXDEC & RCPT
(LEASE CNTRCT)
SETS OF PLANS
& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
1 2 3
4
5
6
7
8
9
Could be less processing time for simpleor more complicated for large structures.
CIVIL/
LAND USE AND
ZONING
4
Fi l E l i b h Chi f P i U i
FINAL EVALUATION AND RECOMMENDATION
Chief Processing Section
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 105/148
NBC - IRR/ Administration & Enforcement 105
NBCNBC – – (NR)IRR(NR)IRR BP Processing Flow BP Processing Flow
FINAL EVALUATION
AND
RECOMMENDATION
PLUMBING
SANITARY
ELECTRICAL
ELECTRONICS &
COMMUNICATION
MECHANICAL
OTHERS
(SPECIFY, REPAIR)
STRUCTURAL4
5
6
7
8
9
10
• Final Evaluation by the Chief Processing Unit
• Recommendations to the Building Official
• Prepare Order of Payment including Fire
Service Fund Fee
CIVIL/
LAND USE AND
ZONING
ISSUANCE OF BUILDINGPERMIT
PAYMENT
OF FEES
4
2. Review O/P including
FS Fund per T- II.G.1
All in Order, forward
f l l
After recording, releasesto the applicant,
By Owner/Applicant
Properly informed
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 106/148
NBC - IRR/ Administration &
Enforcement
106
NBCNBC – – (NR)IRR(NR)IRR BP Processing Flow BP Processing Flow Administrative & Enforcement
REQUIRED
CLEARANCES
MUNICIPAL
TREASURER
RECEIVINGV
ERIFICATION OF
CLEARNCES
FINAL EVALUATION
AND
RECOMMENDATION
LINE AND GRADE
(GEODETIC)
ARCHITECTURAL
INTERIOR/
ACCESSIBILITY
PLUMBING
SANITARY
ELECTRICAL
ELECTRONICS &
COMMUNICATION
MECHANICAL
OTHERS
(SPECIFY, REPAIR)
STRUCTURAL
BUILDING
OFFICIAL
APPLICATI
ON
REALEASE
TRUE COPY TCTTAXDEC & RCPT(LEASE CNTRCT)
SETS OF PLANS
& SPECIFICATN
(A/S, S/P, E & M)GOV’T & EXEMP
1 2 3
4
5
6
7
8
9
11 12
10
13
1. refer one set of plans/
specs to the BFP c/o
City/Mun. Fire Marshall,to act in 5 days.
for payment to local
treasurer’s office
• Signs/issues BuildingPermitand accompanying
Ancillary/Accessory Permits
upon presentation of
Official Receipts and Fire
Safety Check issued byThe BFP & Forward all
processed/signed documents
for Recording and
Releasing Section.
pp
MUNICIPAL
TREASURER
CHIEF, PROCESSING
DIVISION
(Recommendation)
CHIEF, PROCESSING
DIVISION
(Recommendation)
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 107/148
NBC - IRR/ Administration & Enforcement
107NBCNBC – – (NR)IRR(NR)IRR BP Processing Flow (SOME1)BP Processing Flow (SOME1)
REQUIRED
CLEARANCES
VERIFICATION OF
ZONING & OTHER
CLEARNCES
ASSESSMENT
OF FEES
LINE AND GRADE
(GEODETIC)
PLUMBING
SANITARY
ELECTRICAL
MECHANICAL
CIVIL/
STRUCTURAL
ARCHITECTURAL
BUILDING
OFFICIAL
APPLICATION
65
REALEASE
TRUE COPY TCT
TAXDEC & RCPT
(LEASE CNTRCT)
SETS OF PLANS
& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
DEPUTY
DEPUTY
DEPUTY
DEPUTY
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 108/148
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 109/148
NBCNBC – – IRR/2005 Pre Const/ Summon ApplicantIRR/2005 Pre Const/ Summon ApplicantADMINISTRATION AND ENFORCEMENT
Phases of Building Permit/Construction – Pre – Construction Phase/ Steps & Procedures in
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 110/148
Pre Construction Phase/ Steps & Procedures in
Processing application for BP (cont’d)
The Building Official actions on BP application;• can invite/summon , in writing, the applicant
or his designer to amplify ambiguous
items on plans/specifications/
• in the exercise of Sect. 306 of PD, Re: non-
issuance, suspension or revocation ofBuilding Permit, applicant can make an
Appeal to the Secretary of DPWH within
15 days upon receipt of such action.
MUNICIPAL
TREASURER
CIVIL/
STRUCTURAL
LAND USE AND
ZONING
ISSUANCE OF BUILDING PERMIT
PAYMENT OF
FEES
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 111/148
NBCNBC – – (NR)IRR BP Processing Flow, NBC1(NR)IRR BP Processing Flow, NBC1 Administrative & Enforcement
REQUIRED
CLEARANCES
TREASURER
VERIFICATION OF
ZONING & OTHER
CLEARNCES
FINAL EVALUATION
AND
RECOMMENDATION
LINE AND GRADE
(GEODETIC)
ARCHITECTURAL
INTERIOR/
ACCESSIBILITY
PLUMBING
SANITARY
ELECTRICAL
ELECTRONICS &
COMMUNICATION
MECHANICAL
OTHERS
(SPECIFY, REPAIR)
STRUCTURAL
BUILDING
OFFICIAL
APPLICATIO
N
64
REALEASE
TRUE COPY TCT
TAXDEC & RCPT
(LEASE CNTRCT)
SETS OF PLANS
& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
ENDORSEMENT T O PROPER AUTHORITIES
MUNICIPAL
TREASURER
CHIEF, PROCESSING
DIVISION
(Recommendation)
CHIEF, PROCESSING
DIVISION
(Recommendation)
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 112/148
NBCNBC – – (NR)IRR BP Processing Flow (Districts)2(NR)IRR BP Processing Flow (Districts)2 Administrative & Enforcement
REQUIRED
CLEARANCES
VERIFICATION OF
ZONING & OTHER
CLEARNCES
ASSESSMENT
OF FEES
LINE AND GRADE
(GEODETIC)
PLUMBING
SANITARY
ELECTRICAL
MECHANICAL
CIVIL/
STRUCTURAL
ARCHITECTURAL
BUILDING
OFFICIAL
APPLICATIO
N
65
REALEASE
TRUE COPY TCT
TAXDEC & RCPT
(LEASE CNTRCT)
SETS OF PLANS
& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
DEPUTY
DEPUTY
DEPUTY
DEPUTY
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 113/148
Flow more3Flow more3
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 114/148
Flow more4Flow more4
inspection
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 115/148
Flow more5Flow more5
11
2
34
5
6
71
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 116/148
Flow more7Flow more7
NBCNBC – – (New) IRR Process Concept, Diagram(New) IRR Process Concept, Diagram
Diagram representation of the evaluation process,
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 117/148
INPUT
SUPPORT
EVALUATIONPROCESS
OUTPUT
-Conforming / Code
-- Deficient / correct
-- Re-design use IRR
-- Shift to non-conforming / BP 220
Knowledge and
Expertise of thedesigner/profes.
Institute Strategic
measure to meet Code
requirement by both
designer & evaluator.
FEEDBACK
NBCNBC
– –
IRR/2005 Pre ConstructionIRR/2005 Pre Construction
Phase, DefinitionsPhase, DefinitionsADMINISTRATION AND ENFORCEMENT
Phases of Building Permit/Construction –
D fi iti R l t t E l ti / i
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 118/148
Definitions Relevant to Evaluation/processing
Storey – bet. succ. floor surfaces or floor/roof Level, (or Split) – (refer to elevations)
Roof Deck – (required to have parapet vs flr. levelPenthouse – simply a floor level/area > 6 sqm.
Mezz & Loft (with open floor), Flat (multi living)
Soil Bearing Cap. or Pressure (w/c is up or down)
Existing building – (covered by legal permit)
Height of Building – (references: sidewalk or lot
NBCNBC
– –
IRR/2005 ConstructionIRR/2005 Construction
PhasePhaseADMINISTRATION AND ENFORCEMENT
Phases of Building Permit/Construction –
C t ti Ph
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 119/148
Construction Phase
conduct periodic inspection on the on-goingconstruction;
Can examine & sign in logbook as prescribed in
terms and conditions of permit issued;
evaluate installations of safety devises for
protection of pedestrianevaluate installations of safety devises for
protection of pedestrian as well as workers
no changes on issued plans unless BO authorized.
NBCNBC
– –
IRR/2005 PostIRR/2005 Post
ConstructionConstructionADMINISTRATION AND ENFORCEMENT
Phases of Building Permit/Construction –
P t C t ti Ph A li t b it t OBO
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 120/148
Post Construction Phase: Applicant submit to OBO
Certificate of Completion;
Construction Logbook, signed and certified
completed according to the permit issued,as-built plans and specification, including the
reflected on plans amendatory permit/s issued,
test and samples of specimen (if so required by the
OBO).
NBCNBC – – IRR/2005 Post Const/ OBO actionIRR/2005 Post Const/ OBO action
ADMINISTRATION AND ENFORCEMENT
Phases of Building Permit/Construction – Post Construction Phase: OBO action on submitted
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 121/148
Post Construction Phase: OBO action on submitted
documents for application for Cert of Occupancy
endorse one copy of as-built plan submitted with
request to conduct final inspection pursuant to
PD 1185; to act within five (5) daysundertakes Final Inspection, verification or review
based on Certificate of Completion, etc.
pursuant to Sect 303 of PD 1096.assess fees for payment.
all in order, BO issue the Certificate of Occupancy
NBCNBC – – IRR/2005 Post Const/OBO further IRR/2005 Post Const/OBO further
ADMINISTRATION AND ENFORCEMENT
Phases of Building Permit/Construction – Post Construction Phase: OBO further action
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 122/148
Post Construction Phase: OBO further action
A partial Certificate of Occupancy maybe issued, provided the remaining construction will not
posed hazards to the occupant/s
Building with already issued Certificate ofOccupancy may be further issued Certificate of
Occupancy due to changes in use, whether
partly or wholly.
Inspection of Mech. Installation with Mechanical
Engineer commission by the applicant,
NBCNBC – – IRR/2005 AnnualIRR/2005 Annual
InspectionInspectionADMINISTRATION AND ENFORCEMENT
Annual Building Inspection –
Insp. & Enf. Division Team effort composed of
h i l i f diff di i li
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 123/148
technical inspectors of different disciplines
Notification to building owner required before theactual inspection,
Consolidated report backed by picture/s if possible
prepared by the team after inspection, withassessment of fees submit to Chief, E & I D in
turns forward to BO for disposition,
BO approves recommendation and assess fees
issued the Certificate of Annual Inspection.
Non payment of inspection fee on time adds 25%surcharge.
NBCNBC – – IRR/2005 Annual Insp. PortfolioIRR/2005 Annual Insp. PortfolioADMINISTRATION AND ENFORCEMENT
Annual Building Inspection – Portfolio of Findings
Findings can indicate;
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 124/148
• Unauthorized substantial changes made to the
building/structure (no building permit)
BO shall issue the necessary Order/s
corresponding to the violation/s for compliance
by the owner/occupant.
• Change of Occupancy without Certificate of
Change of Occupancy/Use,
• Demolition/removal without appropriate
demolition or removal permit
VIOLATIONS -
SECTION 211 -
Implementing Rules and Regulation:
In the implementation of the provisions of the Code,
the Secretary shall formulate necessary rules and regulations
and adopt design and construction standards and criteria for
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 125/148
NBCNBC – – (NR)IRR(NR)IRR ViolationsViolations-- illustration 2 illustration 2 Administration & Enforcement
SECTION 212
-
Administrative Fines:
and adopt design and construction standards and criteria for
buildings and other structures. Such standards, rules and
regulation shall take effect after their publication once a weekfor three consecutive weeks in a newspaper of general
circulation
For the violation of any of the provisions of this Code
or any of the rules or regulations issued there under, theSecretary is hereby empowered to prescribed and impose
fines not exceeding ten thousand pesos.
VIOLATIONS -
A. Initiation of action usually arises from a complaint and/or findings of
violation involving the following;
Activities/
ViolationsCompliance
Type
Violation
Fine, upon
determination
NBCNBC – – (Rev) IRR(Rev) IRR
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 126/148
126 126
Administration & Enforcement
1. Erecting, constructing,
altering, repairing, moving,
converting, installing or
demolishing a private or
private building/structurewithout building and/or
demolition permit.
Sect. 301 Grave
ViolationP 10,000.00
Note: Defiance to undergo administrative proceeding for compliance, the
case can be filed in Civil Court under other remedies.
VIOLATIONS -
A. Initiation of action usually arises from a complaint involving the
following;
Activities/
Violations ComplianceType
Violation
Fine, upon
determination
NBCNBC – – (Rev) IRR(Rev) IRR
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 127/148
127 127
2. Making any alteration, addition,
conversion or repair in any
building/ structure
appurtenances thereto
constructed or installed before
the adoption of the Code
whether public or private
without permit.
Sect.
2101
Grave
ViolationP 10,000.00
Note: Decision is subject for Appeal.
VIOLATIONS -
A. Initiation of action usually arises from a complaint involving the
following;
Activities/
ViolationsCompliance
Type
Violation
Fine, upon
determination
NBCNBC – – (Rev) IRR(Rev) IRR
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 128/148
128 128
3. Unauthorized change,
modification or alteration
during construction in the
duly submitted plans and
specifications on which the
building permit is based.
Sect. 304Grave
ViolationP 10,000.00
Note: Decision is subject for Appeal.
VIOLATIONS -
A. Initiation of action usually arises from a complaint involving the
following;
Activities/
Violations ComplianceType
Violation
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 129/148
129 129
4. Non-compliance with the
work stoppage order or
notice and/or orders to effect
necessary correction in plans
and specifications founddefective.
Sect. 207Grave
ViolationP 10,000.00
Note: Decision is subject for Appeal.
VIOLATIONS -
A. Initiation of action usually arises from a complaint involving the
following;
Activities/
Violations ComplianceType
Violation
Fine, upon
determination
NBCNBC – – (Rev) IRR(Rev) IRR
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 130/148
130 130
5. Non-compliance with order todemolish building/structure
declared to be nuisance,
ruinous or dangerous.Sect. 215
Grave
ViolationP 10,000.00
Note: (sometimes political & economic (squatters?)
VIOLATIONS -
A. Initiation of action usually arises from a complaint involving the
following;Activities/
Violations Compliance
Type
Violation
Fine, upon
determination
NBCNBC – – (Rev) IRR(Rev) IRR
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 131/148
131 131Administration & Enforcement
6. Use or occupancy of a
building/structure without
Certificate of
Occupancy/Use even if
constructed under a valid building permit.
Compliance
Sect. 309
Violation
Less Grave
Violation
P 8,000.00
Note: (Mandatory/ often on residential)
VIOLATIONS -
A. Initiation of action usually arises from a complaint involving the
following;
Activities/
ViolationsCompliance
Type
Violation
Fine, upon
determination
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 132/148
132 132
7. Change in the existing use or
occupancy classification of a
building/structure or portion
thereof without thecorresponding Certificate of
Change of Use.
Sect. 309 Less Grave
Violation
P 8,000.00
Note: (Mandatory and subject of TUP/ medgen, St Agnes, Pandacan Oil
Depot)
VIOLATIONS -
A. Initiation of action usually arises from a complaint involving the
following;Activities/
ViolationsCompliance
Type
Violation
Fine, upon
determination
NBCNBC – – (Rev) IRR(Rev) IRR
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 133/148
133 133
Administration & Enforcement
8. Failure to post or display the
Certificate of Occupancy/
Use/ Operation in a
conspicuous place on the
premises of the building/structure/ appurtenances.
Violations
Sect. 309
Violation determination
Less Grave
ViolationP 8,000.00
Note: Mandatory
VIOLATIONS -
A. Initiation of action usually arises from a complaint involving the
following;
Activities/
Violations Compliance Type Violation
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 134/148
134 134
9. Change in the type of
construction of any building/
structure without an
amendatory permit.
Sect. 402
with Sect.
304
Grave
Violation
Note: Mandatory compliance to issued permit.
VIOLATIONS -
A. Initiation of action usually arises from a complaint and or findings (on
time the issuance of Building permit is still pending) involving thefollowing activities/violations
NBCNBC – – (Rev) IRR(Rev) IRR
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 135/148
135 135Administration & Enforcement
10. Non-compliance to pay thenecessary fees imposed as
fines and/or penalty, there
shall be;
a) Excav for foundation only.
b) foundations reinf. laid
c) const’n of superstructure
within 2m above ground
d) const’n of super structure
above 2m.
Compliance
Surcharge
Fine, upondetermination (prima
facie) to be added to
the Building Permit
Fees10%
For multiple building
construction in one lot,
building with most
development shall beused.
Surcharge
Surcharge
25%
50%
Surcharge 100%
NBCNBC – – IRR/2005 Assessment of Fees & otherIRR/2005 Assessment of Fees & other
ChargesCharges
ADMINISTRATION AND ENFORCEMENT
ASSESSMENT OF FEES & OTHER CHARGES
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 136/148
1. Basis of Assessment
• Type of Occupancy or Use of the Building
• Cost of Construction
• Floor Area, and
• Height.
NBCNBC – – IRR/2005 Assessment of Fees & otherIRR/2005 Assessment of Fees & other
ChargesChargesADMINISTRATION AND ENFORCEMENT
ASSESSMENT OF FEES & OTHER CHARGES
2. Cost of Construction uniform application
regardless of the following;
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 137/148
regardless of the following;
• Type of construction, and
Table II.G.1- Fixed Cost of Construction / sq m.
• Cost of construction
Location Group
All Cities/Mun. A,B,C,D,E,G,H,I F J
(Cost x 1000) P10 P 8 P 6
NBCNBC – – IRR/2005 Assessment of Fees & otherIRR/2005 Assessment of Fees & other
ChargesChargesADMINISTRATION AND ENFORCEMENT
Advantages of specified basic assessment reference,
Table II.G.1, Height and Use/Occupancy.
• Does not depend of submitted material of
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 138/148
• Does not depend of submitted material of
construction/ bill of materials submitted by designer, which in former days;
- Rich field of graft and corruption
- Source of “cashunduan” of what should be
adopted, usually favoring the applicant,
causing disadvantage to the governmentfor allowing collecting reduced fees.
- Repair, Cert of Occupancy & Fire Fund uses
cost of construction
ORGANIZATION AND ENFORCEMENT: Reports Generation
REPORTS;
1.
2.
REQUIREMENTS DUE DATE / AGENCY
QUARTERLYCIAP/ISSUED BP
Status BP issuedCopy start notice
1st
week/apr/jul/oct/janUpon issuance@ week
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 139/148
NBCNBC – – (NR)IRR(NR)IRR Organization & Enforcement Organization & Enforcement – – report generationreport generation Administration & Enforcement
3.
4.
5.
6.
7.
8.
NSO/ISSUED BPCOLLECTIONS
ANNUAL INSP.
OTHER 1(BP 344
OTHER 2
OTHER 3
Copy BP issuedFees, Fines & Char
Status Existg bldgs.
Compliance/ CO
End of @ monthEnd of @ month
15th day jan year follow
End of @ month
etc
etc
etc
etc
37
NBCNBC – – IRR/2005 Assessment of Fees & other ChargesIRR/2005 Assessment of Fees & other Charges
ADMINISTRATION AND ENFORCEMENT
Computation of Building Permit Fees (Hypothetical)
Use of Sidewalks and Erection of Scaffoldings:
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 140/148
Use of Sidewalks and Erection of Scaffoldings:
Ref. Sect. f and g, Schedule of Fees.
Features:
• Payment shall be per calendar month,
• Compliance with the safety and protective
requirement of IRR XI.
Adm Adm && Enf Enf (Safety Net)(Safety Net)
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 141/148
NBCNBC – – IRR/2005 Assessment of Fees & other ChargesIRR/2005 Assessment of Fees & other ChargesADMINISTRATION AND ENFORCEMENT
Computation of Building Permit Fees (Hypothetical)
Ground Preparation and Excavation Permit
F t
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 142/148
Features:
Excavations > 50.00 cu m and 2m in depthRequired: GP/EP
Solution: (Ref. Sect 304(4) – Processing BP
Sect 9(b)(i)(a to f) – Sched. of Fees
Form: NBC Form No. 8- 02 w/ cond.
Elements of Permit: With Cash BondFirst 50 cu m. - - - - - Php 50,000.00
+ in excess of 1st 50 cu m - - Php 300.00/cu m
NBCNBC – – IRR/2005 Assessment of Fees & other ChargesIRR/2005 Assessment of Fees & other ChargesADMINISTRATION AND ENFORCEMENT
Computation of Building Permit Fees (Hypothetical)
Ground Preparation and Excavation Permit
Features:
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 143/148
Features:
Excavations > 50.00 cu m and 2m in depthRequired: GP/EP
Limit of Permit:
Max Volume – 100.00 cu m.
& Depth – 3.00 m.
Duration – 30 days (or superseded bythe issuance of the
principal Building Permit)
ADMINISTRATION AND ENFORCEMENT
Computation of Building Permit Fees (Hypothetical)
Repairs Differentiated from Renovation/Alteration
Definitions:
NBCNBC – – IRR/2005 Assessment of Fees & other ChargesIRR/2005 Assessment of Fees & other Charges
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 144/148
Definitions:
Repair – dismantling/replacing dilapidated/deteriorated part/s of existing building
with same or equivalent material/s.
Fee – Ref. Sect 9(i), Schedule of Fees.
Renovation – Use of material/s different from
the original even if the original face ofthe structure is not changed.
Fee – Refer to original construction.
ADMINISTRATION AND ENFORCEMENT
Computation of Building Permit Fees (Hypothetical)
Accessories of Buildings/structures
S f W k (f ll i )
NBCNBC – – IRR/2005 Assessment of Fees & other ChargesIRR/2005 Assessment of Fees & other Charges
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 145/148
Scope of Works: (for all occupancies)
swimming pools , firewalls, concrete water
tanks, paved areas and the like;
Fee – Ref. Sect 8(d), Schedule of Fees.
Ex. Swimming pools (improvised from indigenous
materials such as rocks, cement flooring – Fee (50% of regular type/occupancy)
ADMINISTRATION AND ENFORCEMENTOther Provisions (On Fees computation)
Raising Permit: Ref. Sect 9(j) – Accessory Fee based on new usable area generated
D liti /M i P it
NBCNBC – – IRR/2005 Assessment of Fees & other ChargesIRR/2005 Assessment of Fees & other Charges
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 146/148
Demolition/Moving Permit:
Ref. Sect 9(k) – Accessory Fee
based on FA or dimension to be demolished.
* Related to Rule V, Fire Zone and Rule XI,
precautions/safety, traffic & utility clearances
Cemeteries, Mausoleum, columbarium, tombs, etc
construction – Ref. Sect 8(p).Certificate of Use: Group J, Div. 3 & Ancillaries –
bank/record vaults, swimming pools, towers, silos,
smoke stacks/chimney/ovens/kilns/furnaces/tanks, etc
Fees Silos, IRR II, Sect 8gFees Silos, IRR II, Sect 8g
8/15/2019 National Building Code PD 1096 - 148 pages.pdf
http://slidepdf.com/reader/full/national-building-code-pd-1096-148-pagespdf 147/148
Fees: Note/ for permanent or temporary (require removal)• Up to 10m in ht = P 2,400.00 + 150/m excess
• platform floor area @ /Section 3e (50% principal
bldg it serve)