Municipal Wastewater Treatment Design Lee

download Municipal Wastewater Treatment Design Lee

of 30

Transcript of Municipal Wastewater Treatment Design Lee

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    1/30

    Municipal wastewater treatment design:

    Lecture by Y. Lee, PhD Candidate U of Manitoba

    What do you need to know?

    Influent characteristic of wastewater Effluent limit (very strict not so strict)

    Flow and population BOD removal plant (not so strict)

    Biological nutrient removal (BNR)wastewater treatment plant (very strict)

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    2/30

    Landfill

    Screens Grit

    removal Primary

    clarifier

    Activated sludgeSecondary

    clarifier

    Land

    application orfurther

    treatment

    Return activated

    sludge

    Filtrati

    onatio

    n

    Disinfection

    Final effluent

    Waste activated

    sludge

    Thickener

    Thickener return

    Dewatering

    return

    Digester return

    Digester

    Primary sludge

    Dewatering

    1

    10

    8

    11

    5

    4

    6

    9

    7

    3

    2

    12

    13

    Filtration return

    Typical schematic of municipal wastewater

    treatment

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    3/30

    Bar Screens (coarse)

    Removal of large objects (i.e. rags, paper, plastic, etc)

    Vertical or inclined steel bars equally spaced across a

    channel, mechanically cleaned. Design criteria

    Opening between bars = 6-38mm (25mm typical)

    Dimensions based on velocity and peak design flow rate Typical velocity through rack openings

    Quantity of screenings = 20 m3 /106 m3 of wastewater (average), &36 m3 /106 m3 of wastewater (maximum)

    NOTE:

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    4/30

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    5/30

    Grit removal

    Removal of grit, consisting of sand, gravel, cinder orother heavy solid material

    Design criteria HRT=2-5min (3min is typical)1) Establish the peak hourly flow rate for design

    2) Peak flowrate = Q* 2.75

    3) Grit chamber volume = peak flowrate * HRT*1/24) Dimensions: Depth = 2-5m; length-to-width ratio (2.5:1) - (5:1)

    5) Air supply requirement

    Assume 5 ft3/min of air per foot of grit chamber length

    6) Grit quantity (m3

    /1000m3

    of influent):-Separate sewer system 0.004-0.037

    -Combined sewer system 0.004-0.18

    NOTE: (you need at least 2 chambers)

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    6/30

    Primary clarifier

    Design criteria

    Surface overflow rate

    At average flow = 30-50m3/m2/d

    Then, determine area of clarifiers

    Determine the number of clarifiers

    Diameter of each clarifier ranges from 10-40m

    Using HRT = 1-2.5 h, calculate the volume of each

    clarifier, depth must be between 3-6m

    (even number of clarifiers and same dimensions)

    Check for peak flows (overflow rate must be between

    70 -130m3/m2/d)

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    7/30

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    8/30

    Primary clarifier

    Primary sludge

    50-65% removal of influent TSS (60% typical) BOD (35%)

    N =? P =?

    Sludge production 60% influent TSS (influent, Q (m3/d) * TSS (mg/L) * 0.6)

    4-12% solids concentration (typical 5% solid)

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    9/30

    Biological nutrient (N & P) treatment Removal of nitrogen

    Nitrification (aerobic) Denitrification (anoxic)

    Removal of phosphorous

    Phosphorous release (anaerobic)

    Phosphorous uptake (aerobic)

    COD removal occurs simultaneously

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    10/30

    Biological nutrient (N & P) treatment

    Removal of nitrogen (both nitrification and

    denitrification are required) Nitrification (aerobic)

    Conversion of NH4 to NO3

    Rate limiting process Nitrifying bacteria grow very slowly

    SRT of approximately 10 days is required (i.e. if it is BOD

    removal plant then SRT of only 2-3 day is required)

    HRT will increase in order to provide nitrifying bacteria

    enough contact time with food ( influent wastewater) (e.g.

    HRT of 10 hours) (i.e. if it is BOD removal plant then HRT of

    only 4 hour is enough)

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    11/30

    Biological nutrient (N & P) treatment

    Removal of nitrogen

    Denitrification (anoxic) Conversion of NO3 to N2 gas by denitrifying

    bacteria

    Occurs in the absence of oxygen

    Nitrate becomes the terminal electron acceptor

    Requires large amounts of carbon to be present

    clarifieranoxicstage

    aerobic

    stage

    WAS

    influent

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    12/30

    Biological nutrient (N & P) treatmentPhosphorus Removing Mechanism

    Facultative bacteria Energy

    Acetate plusfermentation

    products

    PO43-

    Substrate

    Acinetobacter spp.

    Anaerobic

    (Phosphorusremovingbacteria, slow

    grower)

    Aerobic

    PHB

    PO43-

    PHBEnergy

    BOD+O2

    New biomass

    +

    CO2 + H2O

    Poly-P

    Poly-P

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    13/30

    Biological nutrient (N & P) treatment

    Removal of phosphorous (Bio-P bacteria)

    Both bio-P bacteria and denitrifying bacteria require COD as

    carbon substrate

    Bio- P bacteria are not compatible with denitrifying bacteria

    Thus, requires low NO3 in anaerobic reactor and high COD (i.e.

    sometimes external carbon source is added into the reactors in

    order to increase the COD concentration in the reactor)

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    14/30

    Biological nutrient (N & P) treatment

    Reactor configurations

    clarifierAnaerobic

    stageanoxic

    stage

    aerobic

    stage

    clarifierAnaerobic

    stageanoxic

    stage

    aerobic

    stage

    anoxic

    stage

    aerobic

    stage

    clarifierAnaerobic

    stageanoxic

    stage

    anoxic

    stageaerobic

    stage

    a) A2O

    b) 5-stage

    Bardenpho

    c) MUCT

    WAS

    WAS

    WAS

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    15/30

    Reactor configurations

    50-100--Anaerobic recycle, % ofinfluent

    100-600400-600100-300

    Internal recycle, % of

    influent

    80-10080-10020-50RAS, % of influent

    9.0-22.09.5-23.04.5-8.5Total

    -0.5-1.0-Second aerobic

    2.0-4.02.0-4.0-Second anoxic

    4.0-12.04.0-12.03.5-6.0First aerobic

    2.0-4.02.0-4.00.5-1.0First anoxic

    1.0-2.01.0-2.00.5-1.5Anaerobic

    HRT, hours

    2000-50002000-50002000-4000MLSS, mg/L

    10-3010-404-27SRT, days

    0.1-0.20.1-0.20.15-0.25

    F:M, kg TBOD/kg

    MLVSS/d

    MUCT5-stage

    Bardenph

    o

    A2/0Parameter

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    16/30

    Oxygen requirements

    Oxygen requirements= carbonaceous BOD removal + NH4 removal

    by nitrifiers= (total mass of BOD L utilized -1.42 (mass of

    organisms wasted)) + (nitrification)

    = Q (BOD in BOD out) / + (4.5 *Q (TKN in-TKN out))

    NOTE : f = 0.45-0.68

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    17/30

    Secondary clarifier

    Circular clarifier/ rectangular clarifier

    Design calculation

    Surface overflow rate At average flow the rate should be less than the design criteria

    of 15 m3/m2*d

    Then, determine area of clarifiers

    Determine the number of clarifiers

    Diameter of each clarifier ranges from 10-40m

    Using HRT = 2-4 h, calculate the volume of each clarifier, depthmust be between 3-6m

    (even number of clarifiers and same dimensions)

    Check for peak flows (overflow rate should be less than the designcriteria of 40 m3/m2*d

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    18/30

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    19/30

    Number of clarifier required

    Area or clarifier

    Diameter

    Detention time (HRT) Volume of each clarifier

    Overflow rate and solid loading rate

    Primary and secondary clarifier

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    20/30

    Sludge treatment

    Thickening

    Anaerobic digester

    Dewatering

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    21/30

    Mass balance

    Primary

    ClarifierAnaero-

    bic

    Secondary

    Clarifier

    Thickener

    Anaerobic

    Digester

    Dewatering

    Centrifuge

    Anoxic Aerobic Anoxic Aerobic

    Sludge cake

    RAS=60%

    Internal Recycle=200%

    Q1 Q2

    Q3

    Q4 Q5

    Q6

    Q7Q8

    Q9

    Q10

    Q11

    Q12

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    22/30

    Sludge production

    Primary clarifier (removal of TSS 60%) (Q3)

    Thus, sludge production from primary sludge

    = conc of TSS (mg/L) * (Q inQ reactor) Waste activated sludge

    Required to know the yield of biomass

    Y obs = Y/(1+kd *SRT)

    Then, sludge production rate

    = Y obs * Q (S inS out) = ? Kg/d portion of this lost inthe effluent

    Thus, sludge produced entering thickening(Q6)

    = the overall sludge production lost in effluent

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    23/30

    Sludge treatment

    Thickening (combined primary and waste

    activated sludge) Used to concentrate solids and reduce the volume.

    Methods: Gravity thickening, dissolved air flotation,

    and centrifugation Design criteria

    Influent solid concentration = 0.5-2%

    Thickened solid concentration = 4.0 -6% Hydraulic loading (m3/m2*d) =4-10 (not less than the 9)

    Solid loading (kg/m2*d)=25-80 ( not to exceed 47)

    HRT= 24 h

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    24/30

    Anaerobic digester

    Stabilization of biodegradable particulate organicmater

    Simply CSTR; HRT=SRT, no recycle

    Mesophilic (35oC) most common, thermophilic(55oC) sometimes used

    Design criteria: HRT = 15-20 days, 20 days common

    Diameter 10-40m, sidewall depth 5-10m

    Volume based on solids production from combined primaryand waste activated sludge

    Achieve 60% reduction of VS in primary, 30-50% ofsecondary

    Converted to methane gas, ~0.37m3/kg VS destroyed

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    25/30

    Dewatering

    Depend on type of sludge, % solids in final

    product (sludge cake) are different. For rotary vacuum filters

    Feed solids percent (3-7%)

    Cake solid percent (18-25%)

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    26/30

    UV disinfection

    Design criteria

    Required intensity=1.16mW/cm2

    (USEPA,1986) Resident time = 60s (recommended)

    Determine the volume of disinfection basin

    = the peak design flow * HRT(provide at least 2 basin)

    Dosage = intensity * HRT

    Then, determine UV density = actual intensity *absorbance coefficient

    Then, calculate how many lamps are required.

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    27/30

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    28/30

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    29/30

    Typical municipal wastewater treatment plant layout

    Landfill

    Riverscreen Grit

    removalPrimary

    clarifier

    Activated sludge

    system

    Final

    clarifier

    disinfection

    thickeningAnaerobic

    digester

    Belt filter

    press

  • 8/12/2019 Municipal Wastewater Treatment Design Lee

    30/30

    Wastewater facility design criteriaPlant capacity

    flow

    average flow:

    peak flow:

    BOD (kg/d)Nitrogen (kg/d)

    Phosphorous (kg/d)

    Screen

    number:

    dimension:

    design velocity:

    Grit removalnumber:

    dimension:

    volume:

    air requirement:

    Primary clarifier

    number:

    dimension:

    surface loading rate:

    BNRvolume:

    dimension:

    MLVSS

    F/M

    SRT

    HRT

    total oxygen requirementFinal clarifier

    number:

    dimension:

    surface loading rate:

    Solid loading rate: