Morcott Water Treatment Works Extensions and Rutland Water Habitats Creation 17 March 2010.
-
date post
22-Dec-2015 -
Category
Documents
-
view
240 -
download
1
Transcript of Morcott Water Treatment Works Extensions and Rutland Water Habitats Creation 17 March 2010.
Morcott Water Treatment Works Extensions and Rutland Water Habitats Creation 17 March 2010
Agenda • Scheme Driver
• Background
• The scheme - scope
• Schedule
• Commercial
• Photographs
3
Scheme Driver
• Forecast population growth and industrial water demand
REQUIRING
• Additional treatment capacity at Wing WTW
• Strategic mains to Wing and into supply
REQUIRING
• Habitat creation works for Rutland Water
4
Wing wtw extension - background
• Need affirmed by 1995-97 Drought
• Planning application prepared and submitted in 2000 for a 90 Ml/d extension to the wtw capacity with environmental assessment to challenge the impact of abstraction on affected European sites
• Appropriate Assessment required under the Habitats Regulations by Natural England & Rutland County Council. (Planning Authority)
• Planning permission withheld due to “adverse impact upon Rutland Water SPA, Ramsar and SSSI sites”
• Advice that AWS should consider ‘mitigation measures’ to be able to secure planning permission
• Planning application for WTW re submitted and planning application for Habitats Creation Work submitted 2005 and approved 2007
5
Manton
Edith Weston
Egleton
Empingham
Upper Hambleton
Water levelMargin (drawdown zone)
Whitwell
ProposedLagoons
ProposedLagoons
Rutland Water reservoir 50% full
6
Manton
Edith Weston
Egleton
Empingham
Upper Hambleton
Water levelMargin (drawdown zone)
Whitwell
ProposedLagoons
ProposedLagoons
Rutland Water reservoir 30% full
7
Wing Sub Programmes Statistics
• Direct population served 500,000 people
• Overall population served approx. 1 million people
• Current Plant Design 270 Ml/d
• Geographical areas served Peterborough
directly Corby
Wellingborough
KetteringNorthamptonMilton Keynes
8
Ruthamford Water Resource Zone
GRAFHAM
WING
PETERBOROUGH
BEDFORSHIRE
BUCKINGHAMSHIRE
HERTFORDSHIRE
NORTHAMPTONSHIRE
CAMBRIDGESHIRE
LEICESTERSHIRE
Kettering
St Neots
HANNINGTON
BEANFIELD
EMPINGHAM
RUTLAND
LINCOLNSHIRE
OXON
MILTON KEYNES
MiltonKeynes
PITSFORD
Leicester
Peterborough
Corby
Huntingdon
Wellingborough
Northampton
Bedford
District BoundaryAW Regional Boundary
Strategic Water Supply Mains
Water Treatment WorksPumping Stations
Market Harborough
9
The Scheme - scope
New Empingham to WingRaw Water Pipeline
(7.5km; 1,000mm diameter)
New Wing to BeanfieldPotable Water Pipeline
(15.5km; 1,000mm diameter)
New Raw Water Draw(700m, 800mm diameter)
New EmpinghamPumping Station
(90 Ml/d)
New Beanfield to HanningtonPotable Water Pipeline(18.0 Km; 900mm diameter)
Hannington Reservoir
Wing WTW
Existing EmpinghamPumping Station
Existing WingPumping Station(new pumps)
Existing BeanfieldPumping Station(new pumps)
Existing Draw Off
To Peterborough
(7.5km; 1,000mm diameter)
(15.5km; 1,000mm diameter)
Rutland HabitatsMitigation
New MorcottWTW
(18.0 Km; 900mm diameter)
(new pumps)
(new pumps)
(Connection works)
10
Rutland Habitats Mitigation Works
We are herex
11
Scope – Empingham to Wing Pipeline
• DN 1000 Raw Water Pipeline
• Approx. 7.5km long
Existing twin DN 1100 steel
pipeline
Proposed DN 1000 DI pipeline
12
• DN 1000 Potable Water Pipeline
• Approx. 15.5km
Scope – Wing to Beanfield Pipeline
Existing DN 1100/1400 steel pipeline
Proposed DN 1000 DI pipeline
13
Scope –Beanfield to Hannington Pipeline
Existing DN 1400 steel / DN 1200 concrete pipeline
Proposed DN 900 DI pipeline
• DN 900 Potable Water Pipeline
• Approx. 18.5km
14
Existing Wing WTW and Location of New Extension
15
Schedule
Now
Main Construction02/08
Area B complete 12/08
Area A complete: 04/09
Area D complete: 03/10
Area C complete: 10/10
Rutland Habitats Mitigation
Morcott WTW and associated works
Pipelines
Dec 06 Jun 07 Dec 07 Jun 08 Dec 08 Jun 09 Dec 09 Jun 10 Dec 10
Main Construction02/08
complete: 03/10
Main Construction09/07 02/08
Empingham to Wing complete: 04/09
Wing to Beanfield complete: 09/09
Beanfield to Hannington complete: 03/10
Design Development
EnablingWorksDesign Development
EnablingWorksDesign Development
09/07
09/07
EnablingWorks
Area D complete:
03/10
16
Approved programme costs £117m
Wing Extensions£57 million Wing
Mains£29 million
Rutland£11 million
AWS £16 million (main cost centres indicated below)
GTM
JN Bentley
Carillion
Programme Management Support and Design£5 million
Mott Macdonald
£15 million (main cost centres indicated below)
Land “Planning
Conditions” Capitalisedoverhead
Project Management
RiskPower
connectionOps
AWS
17
• Risk share - inflation.
• Steel prices.
• Rise in fuel prices.
• Procurement of labour, equipment and plant.
Financial challenges
18
Environmental and Archaeological costs
• Rutland Habitats - £17m
• Pipelines – Archaeology - £1.05m
- Environmental - £0.9k
• Water Treatment Works - Environmental - £30k
• Total - £19.98m (17.1% of programme)
19
Any questions??????