Page 1: Micromegas NSW issues Tasks list. Scope  Preparation of New Small Wheel project  Set up task sharing => proto-Collaboration (MoU)  Project leader &

Micromegas NSW issues

Tasks list

Page 2: Micromegas NSW issues Tasks list. Scope  Preparation of New Small Wheel project  Set up task sharing => proto-Collaboration (MoU)  Project leader &

Scope Preparation of New Small Wheel project

Set up task sharing => proto-Collaboration (MoU) Project leader & project management TDR (2012/13)

Layout & integration Chamber design, industrialization, and work in institutes Electronics production Trigger/DAQ Software issues

Simulation Analysis

Page 3: Micromegas NSW issues Tasks list. Scope  Preparation of New Small Wheel project  Set up task sharing => proto-Collaboration (MoU)  Project leader &

Chamber design Layout & integration into ATLAS

Layout & contact to NSW design engineers Chamber design & realization

Design of multilayer Design of spacer & support structure Alignment

MM design optimization Board layout & production aspects Connectivity

Page 4: Micromegas NSW issues Tasks list. Scope  Preparation of New Small Wheel project  Set up task sharing => proto-Collaboration (MoU)  Project leader &

Industrialization

Production engineer Organization of production in industry and institutes

Planning Procurement Follow-up

Quality assurance policy

Page 5: Micromegas NSW issues Tasks list. Scope  Preparation of New Small Wheel project  Set up task sharing => proto-Collaboration (MoU)  Project leader &

Electronics & services Trigger/DAQ system Front-end electronics (on-chamber)

Design, system layout Procurement Testing

DCS Services

HV system LV/cooling

Test sites & procedures

Page 6: Micromegas NSW issues Tasks list. Scope  Preparation of New Small Wheel project  Set up task sharing => proto-Collaboration (MoU)  Project leader &

Software & analysis issues System simulation Data preparations Monitoring Analysis s/w, integration into Athena framework ???

Page 7: Micromegas NSW issues Tasks list. Scope  Preparation of New Small Wheel project  Set up task sharing => proto-Collaboration (MoU)  Project leader &

TDR & Module0 (2013?)

TDR Expected in 2013 (?) Editor ?

Module 0 Design Planning & follow-up Production Assembly Evaluation