MICE News 29 March 2006

4
1 MICE VC Alain Blondel 9 - 03 - 2003 MICE News 29 March 2006 1. From Executive board in Osaka: 1.1 The Electron-Muon-CALorimeter (EMCAL*) will proceed for test with small size (65-80 cm width) KLOE light module. (more on EMCAL size today) 1.2 fiber tracker responsibility will be shifted from Malcolm Ellis to Takashi Matsushita 1.3 CM15 will be in Fermilab 8-11 June 2006 local organisers: Alan Bross and Malcolm Ellis Programme committee Jean-Sebastien Graulich and Jim Norem (have agreed) 1.4 A list of Items and plans for VCs was issued (thus the rich agenda today) http://dpnc.unige.ch/users/blondel/MICE/Exec-board/wrap-up-cm14-to- CM15.doc see also executive board actions http://dpnc.unige.ch/users/blondel/MICE/Exec-board/web/MICE-Executive- actions.htm *) pronounce E-M-Cal

description

MICE News 29 March 2006. From Executive board in Osaka: 1.1 The Electron-Muon-CALorimeter (EMCAL * ) will proceed for test with small size (65-80 cm width) KLOE light module. (more on EMCAL size today) 1.2 fiber tracker responsibility will be shifted from Malcolm Ellis to Takashi Matsushita - PowerPoint PPT Presentation

Transcript of MICE News 29 March 2006

Page 1: MICE News 29 March 2006

1MICE VC Alain Blondel 9 - 03 - 2003

MICE News 29 March 2006

1. From Executive board in Osaka: 1.1 The Electron-Muon-CALorimeter (EMCAL*) will proceed for test with small

size (65-80 cm width) KLOE light module. (more on EMCAL size today)

1.2 fiber tracker responsibility will be shifted from Malcolm Ellis to Takashi Matsushita

1.3 CM15 will be in Fermilab 8-11 June 2006local organisers: Alan Bross and Malcolm EllisProgramme committeeJean-Sebastien Graulich and Jim Norem (have agreed)

1.4 A list of Items and plans for VCs was issued (thus the rich agenda today)http://dpnc.unige.ch/users/blondel/MICE/Exec-board/wrap-up-cm14-to-

CM15.doc

see also executive board actions http://dpnc.unige.ch/users/blondel/MICE/Exec-board/web/MICE-Executive-

actions.htm

*) pronounce E-M-Cal

Page 2: MICE News 29 March 2006

2MICE VC Alain Blondel 9 - 03 - 2003

MICE NEWS (CTD)

2. Committees

2.1 The Last MUTAC meeting happened at Fermilab on 16-17 March (--> comment by M. Zisman or D. Kaplan)

2.2 The next Funding Agency Committee will meet on 10 April at Warwick

2.3 other news? (US funding request, Italy etc…)

2.4 There is a (rumor of possible) proposal of change of status of PPARC

Page 3: MICE News 29 March 2006

3MICE VC Alain Blondel 9 - 03 - 2003

NEWS -- IIIThe ISIS shut down has been delayed

NEW « FIRST BEAM DATE » FOR MICE: 1 October 2007

(this is infortunate for outside university groups for whom summer is^’special’)

15 March: The IMC has agreed yesterday to start the long shutdown in December 2006.  This means that there will be an extra cycle 2006/5 this year, starting on 14 November and ending on 18 December 2006.

During the long shutdown, the new EPB to the second target station will be installed and the problems with some of the magnets in EPB1 will be addressed.  This work and more will go on from January 2007 to August 2007.  During September 2007 there will be commissioning of part of the EPB2 and TS1 with beam.  The first user cycle 2007/1 is expected to start on 1 October 2007.Every effort should be made to carry out all proposals submitted & accepted in the current call before the end of 2006, so that we go with a clean slate into the long shutdown.  There will be no Call for Proposals in October 2006.  The proposal round in April 2007 with FAPs in June 2007 will determine the programme from October 2007 onwards.  The user community will be informed of this in the current call for proposals.

Page 4: MICE News 29 March 2006

4MICE VC Alain Blondel 9 - 03 - 2003

Thus we have *450* days to data taking

However:this increases the pressure on us to do everyting swiftly once we have the beam: less time for phase I and II!

Preparations (DAQ, reconstruction, Software, procedures and detectors) hace to be prepared longer in advance…