spokesperson remarks CMPB MICE NEWS

12
1 MICE CMPB Alain Blondel 19 April 2007 spokesperson remarks CMPB MICE NEWS

description

spokesperson remarks CMPB MICE NEWS. Aspirational MICE Schedule now (~unchanged since march 2006). m. beam line + detector commissionning starts August 2007!. 1 October 2007. STEP I. STEP II. December 2007. STEP III. March 2008. PHASE I. STEP IV. Early 2009. STEP V. - PowerPoint PPT Presentation

Transcript of spokesperson remarks CMPB MICE NEWS

Page 1: spokesperson remarks CMPB MICE NEWS

1MICE CMPB Alain Blondel 19 April 2007

spokesperson remarksCMPB

MICE NEWS

Page 2: spokesperson remarks CMPB MICE NEWS

2MICE CMPB Alain Blondel 19 April 2007

Aspirational MICE Schedule now (~unchanged since march 2006)

1 October 2007 STEP I

December 2007

STEP III

STEP II

STEP IV Early 2009

STEP V Summer 2009

STEP VI 2010

PHASE II

R&D

beam line + detectorcommissionning starts August 2007!

PHASE I

March 2008

Page 3: spokesperson remarks CMPB MICE NEWS

3MICE CMPB Alain Blondel 19 April 2007

NEWS (Ia)

1. Since March 25, Malcolm Ellis is keeping a MICE NEWS page. http://hep04.phys.iit.edu/cooldemo/news/weeklydigest.html

2. MICE Installations/commissionning/operations group will have first in-person meeting on 12 June (day before the collaboration meeting) meanwhile…Reports at Video conferences (1/month) are already organized according to main MICE subsystems. Visits to RAL by Gregoire (CKOV, TOF shield) Graulich (DAQ) ABross (Tracker, detectors) are organized.

3. Prof. Gail Hanson has been awarded a grant from the NSF, 133k$

X 3 years effective 15th April. Will hire a post doc to work on MICE (mostly at RAL). A matching contribution from GH startup fund at University of Riverside (400k$) is associated.

4. Transfer of 200k€ to INFN for TOF is taking place ( Vittorio)

Page 4: spokesperson remarks CMPB MICE NEWS

4MICE CMPB Alain Blondel 19 April 2007

5. EU notice for MICE AFC modules has gone out in EU official journal

MICE Absorber Focus Coil Modules (REF 2020RE) – NUTS code:UKJ14 Two complete assemblies with an option for a third. It is expected that delivery will be required during October 2008.

6. ICST coupling coil discussions are advancing well. Technical review and visit involving MICE and NFMCC officials is

organized in week of 15 May at Harbin

7. Steve Virostek (LBNL) and Wing Lau (Oxford) have accepted o act as deputy MICE project managers to relieve P.

Drumm

8. MICE spokesperson election has taken place… AB reelected for 3 years

NEWS (Ib)

Page 5: spokesperson remarks CMPB MICE NEWS

5MICE CMPB Alain Blondel 19 April 2007

NEWS (II)

TARGET. Review 9 March at Daresbury Lab.-- test in fall 2006 OK, but only with 10A (55 needed) driver and rep rate of once per 64/50 sec. -- Recommended that present system be upgraded to ensure efficient recovery of thetarget at full performance after dip in the beam. (new processor will be developed in parallel)

Milestones: Start long run target test in AprilRamp to 55A by 1st of MayInstall in ISIS by 22 JuneComplete reliability demonstration by mid september.

Beam line and hall preparation:See Pauls presentation. Aim to have everything in place for closure on August 1st. (upstream magnets and stands, PSI solenoid, Shielding of area)

Page 6: spokesperson remarks CMPB MICE NEWS

6MICE CMPB Alain Blondel 19 April 2007

NEWS (III)

CKOVICKOV construction jobs are being spawned in parallel -

Aerogel containers + mirrors - Mississippi PMT enclosures - IIT Light boxes - U. Iowa

Some progress on the lexan mirror forming has been made. The PMT base redesign work has begun at Fermilab. Aerogel order is out to Matsushita (Panasonic) - Dan. PMT checking in Trieste is started. ON TRACK for CKOV at RAL in JULY

TOFFirst batch of H6553MOD Hammamatsu PMT assemblies for TOF1 delivered to INFN Milano Bicocca. Magnetic tests of PMTs going on. Design of lightguides and PMT support collars for TOF0/1 have been finalised. Production of lightguides has started. ONTRACK for TOF0/TOFI at RAL in August. Updated PID dimensions updated in G4MICE.

KL calorimeterProduction on going at Roma III (funding advanced by KLOE) Expected delivery date: october 2007

SW calorimeter: Batch of scintillator shipped from FNAL -- first prototype layer being assembled at Trieste. (P. Chimenti) aim is to have SW in MICE in 2008

Page 7: spokesperson remarks CMPB MICE NEWS

7MICE CMPB Alain Blondel 19 April 2007

Light guide scintillator assembly for TOF

Page 8: spokesperson remarks CMPB MICE NEWS

8MICE CMPB Alain Blondel 19 April 2007

NEWS (IV)

Tracker-- Station production is going well. -- Following the visit to G-Tech, the waveguide production has started. -- The first production cryostat has now achieved the desired performance following improvements to the way the thermal links are prepared. It is anticipated that even on 50Hz power in the UK, there will be sufficient margin for the cryostat to operate. -- Cosmic ray test of station 5 at FNAL proceeding -- DAQ within MICE framework progressing well. Commissionning of first tracker expected to start in June at RAL. Tracker will be part of Step I (beam commissionning period)

Spectrometer solenoidWinding of the center coil for the first magnet now ~80% complete2nd finished coil former at Wang & leak-checked4th cryocooler arrived at Wang At least 1 month schedule slip due to late delivery of coil former Wang is in the process of updating the fabrication schedule – extended shifts being consideredSchedule of magnetic measurements at RAL being addressed now. EXPECTED delivery at RAL 1 december 2007.

Page 9: spokesperson remarks CMPB MICE NEWS

9MICE CMPB Alain Blondel 19 April 2007

Tracker construction:

Station fabrication keeping pace, perhaps a week or so behind schedule

Awaiting polishing check before final polish. Hence last step in production not done for stations 2 to 6

Waveguide production a little behind scheduleTracker team need to take stock

Assembly and QA of mechanical assembly can take placeTest of tracker 1 is likely to be delayed by ~weeks (less than a

month)

Page 10: spokesperson remarks CMPB MICE NEWS

http://alephwww.cern.ch/~bdl/lepc/lepc.ppt

10

Winding of one of the middle layers of the spectrometer solenoid center coil

3/28/07

Page 11: spokesperson remarks CMPB MICE NEWS

11MICE CMPB Alain Blondel 19 April 2007

PublicationsA MICE web page has been set up with uptodate MICE publication list

Page 12: spokesperson remarks CMPB MICE NEWS

12MICE CMPB Alain Blondel 19 April 2007

Conclusions

MICE is working hard to match schedule of Phase I !

first beam in August, operation of stepI in October StepII in december.

many places to worry and work hard about, but no sign of delay at this moment.