Transcript of Metering Energy Consumption in Data Centres - Colin Love
![Page 1: Metering Energy Consumption in Data Centres - Colin Love](https://reader036.fdocuments.in/reader036/viewer/2022081413/547ea954b4795993508b4be5/html5/thumbnails/1.jpg)
Metering, Devolved Energy Budgeting and Charging for Energy Use
Colin Love
ULCC Data Centre Manager
![Page 2: Metering Energy Consumption in Data Centres - Colin Love](https://reader036.fdocuments.in/reader036/viewer/2022081413/547ea954b4795993508b4be5/html5/thumbnails/2.jpg)
Who are ULCC ?
• Wholly owned subsidiary of the University of London
• Receive no direct funding and so self-sufficient
• Operate own data centre facility (568sqM of IT space)
• Large number of external customers taking services
ranging from simple co-location hosting up to full
operating system & application management
• Not for profit organisation
![Page 3: Metering Energy Consumption in Data Centres - Colin Love](https://reader036.fdocuments.in/reader036/viewer/2022081413/547ea954b4795993508b4be5/html5/thumbnails/3.jpg)
Metering, Devolved Energy Budgeting and Charging for Energy Use
• What we meter, where and why
• Who we charge for power usage
• Why devolve energy budgeting
![Page 4: Metering Energy Consumption in Data Centres - Colin Love](https://reader036.fdocuments.in/reader036/viewer/2022081413/547ea954b4795993508b4be5/html5/thumbnails/4.jpg)
Electrical Distribution
• Single main panel for Data Centre and associated
equipment (plant kit) with dual grid feeds and standby
generator
• Dual feeds to dedicated plant equipment panel
• Dual UPS units running as 2N
• 4 PDUs within Data centre (2 per UPS), with discreet
A and B supplies to every cabinet
![Page 5: Metering Energy Consumption in Data Centres - Colin Love](https://reader036.fdocuments.in/reader036/viewer/2022081413/547ea954b4795993508b4be5/html5/thumbnails/5.jpg)
![Page 6: Metering Energy Consumption in Data Centres - Colin Love](https://reader036.fdocuments.in/reader036/viewer/2022081413/547ea954b4795993508b4be5/html5/thumbnails/6.jpg)
Power meters
DIRIS A40 Panel Meter Main Incomer
![Page 7: Metering Energy Consumption in Data Centres - Colin Love](https://reader036.fdocuments.in/reader036/viewer/2022081413/547ea954b4795993508b4be5/html5/thumbnails/7.jpg)
In rack power monitors
CL-Amp unit In rack PDU monitor
![Page 8: Metering Energy Consumption in Data Centres - Colin Love](https://reader036.fdocuments.in/reader036/viewer/2022081413/547ea954b4795993508b4be5/html5/thumbnails/8.jpg)
In rack PDU monitor
Close up Raw data
![Page 9: Metering Energy Consumption in Data Centres - Colin Love](https://reader036.fdocuments.in/reader036/viewer/2022081413/547ea954b4795993508b4be5/html5/thumbnails/9.jpg)
Why monitor power usage
• To ensure power demand doesn’t exceed availability
(limited power availability in the Data Centre)
• Understand PuE of the Data Centre so improvements
can be implemented
• To monitor and charge customers for excess power
usage where appropriate
• IT power loads are increasing, even with virtualisation
• Planning for the future – PuE, CRC, EUCoC
![Page 10: Metering Energy Consumption in Data Centres - Colin Love](https://reader036.fdocuments.in/reader036/viewer/2022081413/547ea954b4795993508b4be5/html5/thumbnails/10.jpg)
Improving Data Centre Efficiency
• Rack Containment
• More efficient cooling (in-row, free air, ECC fans)
• Higher temperatures in Data Centre (difficult in a co-
location environment due to legacy kit!!)
![Page 11: Metering Energy Consumption in Data Centres - Colin Love](https://reader036.fdocuments.in/reader036/viewer/2022081413/547ea954b4795993508b4be5/html5/thumbnails/11.jpg)
ULCC Data Centre 2
• Learnt from the original data centre
• Hot aisle-containment solution
• More efficient air conditioning, although still DX
because of building fabric limitations
• Metering is more focused, and more accurate in-rack
monitoring as greenfield site.
![Page 12: Metering Energy Consumption in Data Centres - Colin Love](https://reader036.fdocuments.in/reader036/viewer/2022081413/547ea954b4795993508b4be5/html5/thumbnails/12.jpg)
Devolved Energy Budgeting
• Why devolve
– Reduced space charges typically, but....
– The risks are higher overall costs
– Greater visibility of power usage
– Directly benefit from efficiency improvements
– Results in much closer involvement in energy
efficiency overall
![Page 13: Metering Energy Consumption in Data Centres - Colin Love](https://reader036.fdocuments.in/reader036/viewer/2022081413/547ea954b4795993508b4be5/html5/thumbnails/13.jpg)
The Future
• More sub-metering of supplies
• Networkable meters to provide trending data
• Better management software for the whole Data
Centre estate
• CRC challenges, EU Code of Conduct
![Page 14: Metering Energy Consumption in Data Centres - Colin Love](https://reader036.fdocuments.in/reader036/viewer/2022081413/547ea954b4795993508b4be5/html5/thumbnails/14.jpg)
Thank You
• Any Questions ???
• Contact Me: [email protected]
• GoodCampus/RECSO case study at
http://www.goodcampus.org/susteit/susteit-cases/