March 14, 2008 TEPPC 031408Mtg WestConnect Subregional Planning Update Jerry D. Smith WestConnect...
-
Upload
alexis-carll -
Category
Documents
-
view
218 -
download
0
Transcript of March 14, 2008 TEPPC 031408Mtg WestConnect Subregional Planning Update Jerry D. Smith WestConnect...
March 14, 2008
TEPPC 031408Mtg
WestConnect Subregional Planning Update
Jerry D. SmithWestConnect Planning Manager
TEPPC 031408Mtg 2
WestConnect Subregional Planning Groups
ColoradoCoordinated
PlanningGroup
SouthwestArea
Transmission
CCPGCCPG
SWATSWAT
SIERRASIERRANew Area ?
CCPG and SWAT act as WestConnect technical planning work groups for WestConnect planning area•Coordinate Base Cases for use by all study participants
•Define subregional study plans, provide study resources, and perform studies
•Provide forum for coordination and peer review of planning studies and 10-year plans
TEPPC 031408Mtg 3
2007 WestConnectSubregional Planning Participants
13 WestConnect Project Agreement for Subregional Transmission Planning Members
15 Other Participating Utilities
15 Governmental Entities
29 At large Industry Participants
TEPPC 031408Mtg 4
Status of WestConnectSubregional Planning Process
2007 Planning Cycle concluded – Annual Planning Meeting 1/17/08– Ten Year Plan and Planning Report approved
by Planning Mgmt Comm / Steering Comm
2008 Planning Cycle has commenced– 2013 & 2018 Base Case being coordinated– Annual Adequacy Study of Plan this summer– Biennial Long Range Study conclude in 2009– SWAT and CCPG will oversee Other Studies
TEPPC 031408Mtg 5
Jun Jul Aug Sep Oct Nov DecJan Feb Mar Apr MaySep Oct Nov Dec Jan Feb Mar Apr
Database Preparation
Request WindowStudy Plan Development
Study Execution
Analysis
Report PreparationReport Approvals
Historical Data Analysis
2007 2008 2009
2008 Synchronized Study Plan
TEPPC
WESTCONNECT
BASE CASE 2013 & 2018
EXHIBIT 5
EXHIBIT 9
EXHIBIT 10
EXHIBIT 12
EXIHIBIT 13
NREL STUDY
SCWG
SUBREGIONAL PLANING GROUPS
NREL
SCWG
CRT
AZNM
CCPG
SPPG
SATS
ADEQUACY STUDY
BIENNIAL L. R. STUDY
CATS-EHV
CATS-HV
TO BE DETERMINED
NM STUDY GRP
Request Window
Report Preparation
EXHIBIT 4
TEPPC 031408Mtg 6
WestConnect Annual Adequacy Study
Purpose – test the adequacy of most recently published WestConnect Transmission Plan (excluding conceptual projects)
A WestConnect-wide study utilizing the 5th and 10th year coordinated base cases
Perform traditional N-0, N-1 and N-2 contingency outagesEstablish reliability risk of potential corridor outages with
planned transmission projects in 10th yearComplete studies by August joint CCPG/SWAT meeting Deficiencies in plan noted with sufficient lead time for
subregional planning participants to investigate solutions for inclusion in the 2008 WestConnect Transmission Plan
TEPPC 031408Mtg 7
WestConnect Biennial Long Range Study
Purpose – Biennially explore conceptual long range transmission needs within WestConnect Planning Area.
A Westconnect –wide study of contemporary issues facing the industry in the 10th year and beyond.
Utilizes the 10th year coordinated base case with load forecasts and generation scenarios representative of the study time period. Study limited to power flow and only considers N-1 outages.
Initial study has two fold objective:– Provide traditional transmission reliability oriented studies in
response to the TEPPC economic transmission study results,
– Study WestConnect-wide integration of renewable energy projects
Complete initial study in 2009
TEPPC 031408Mtg 8
Colorado Energy Resource Zones
TEPPC 031408Mtg 9
Stage 5+Integration with High Plains Express
WillardWillardWillard
Ft. CraigFt. CraigFt. Craig
BABABA
BelenBelenBelen
GladstoneGladstoneGladstone
VL TapVL TapVL Tap
Total WindGuadalupe/Willard/Duran:
> 4000 MW (?)
• Build HPX 500 kV lines (may not need two circuits from Guadalupe to Ft Craig)
• Install 500/230 kV transformer at Gladstone• Install 500/345 kV transformer at Guadalupe• Install 500/345 kV transformer Ft Craig• Install 500/345 kV transformer at Duran
100
200
DuranDuranDuran
>1000
250
>1000
150
400
Existing 345 kV line
New station
Existing station
Proposed wind project
Existing or committed wind project
Existing 115 kV line
New 345 kV line
1200
NM Wind Collector System Integrated with HPX
TEPPC 031408Mtg 10
Conceptual Transmission for Renewables
TEPPC 031408Mtg 11
2008-2017 Plan Summary
Type Project
No. Projects
Total
MilesEstimated Cost
(2008 $M)
Planned 106 4,636 6,969
Conceptual 22 4,256 6,204
TOTAL 128 8,892 $ 13,173
TEPPC 031408Mtg 12
2008-2017 Plan Cost
Figure 2 – Cost Distribution by Voltage Class
Estimated Cost Breakdown by Voltage Class
77%
5%
15%3%
500 kV 345 kV 230 kV Below 230 kV
TEPPC 031408Mtg 13
Planned Projects by Year
WestConnect Planned Transmission Projects and Transmission Investment by Year
0
5
10
15
20
25
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 orTBD
In-Service Date
Nu
mb
er
of
Pro
ject
s
$0
$500
$1,000
$1,500
$2,000
$2,500
Mill
ion
s (2
00
8 D
olla
rs)
Number of Planned Projects Estimated Cost (2008 Dollars)
TEPPC 031408Mtg 14
Conceptual Projects by Year
WestConnect Conceptual Transmission Projects and Transmission Investment by Year
0
1
2
3
4
5
6
7
8
2011 2012 2013 2014 2015 2016 2017 2018 orTBD
In-Service Date
Nu
mb
er
of
Pro
ject
s
$0
$1,000
$2,000
$3,000
$4,000
$5,000
$6,000
Mill
ion
s (2
00
8 D
olla
rs)
Number of Conceptual Projects Estimated Cost (2008 Dollars)
TEPPC 031408Mtg 15
Planned Projects by State
StateNo.
ProjectsTotal
MilesEstimated Cost
(2008 $M)
Arizona 66 1,403 2,331
California 10 759 1,593
Colorado 16 1,892 2,016
Nevada 5 415 864
New Mex. 4 117 141
Texas 5 50 24
Multi-State 0 0 0
TOTAL 106 4,636 $ 6,969
TEPPC 031408Mtg 16
Conceptual Projects by State
StateNo.
ProjectsTotal
MilesEstimated Cost
(2008 $M)
Arizona 15 286 185
California 1 18 27
Colorado 0 0 0
Nevada 1 31 70
New Mex. 2 71 122
Texas 0 0 0
Multi-State 3 3,850 5,800
TOTAL 22 4,256 $ 6,204