1
Colorado Coordinated Planning GroupTEPPC UpdateAugust 9, 2012
CCCCCCPPPGGG
CCCCCCPPPGGG 2
CCPG Primary Transmission Participants
CCCCCCPPPGGG 3
CCPG – General Information
Forum for joint transmission planning Recognized WECC Sub-Regional Planning Group4-5 Open Meetings/YearFebruary, April, August (Joint with SWAT/Sierra), December
Denver TSGT OfficesOpen to All Interested StakeholdersMeeting Notices/Materials Posted at: WestConnect Website and WestConnect Transmission Planning - CCPG
CCCCCCPPPGGG 4
CCPG Sub-Region Footprint
CCCCCCPPPGGG 5
2012 CCPG Organization Chart
S te erin g C o m m itteeC h a ir: B lan e T a ylo r
F o o th illsC h a ir:Je re m y B ro w n rigg
D E E PC h a ir: C lif f B erth e lo t
W Y /S D C om m o n U seC h a ir: E ric E g ge
W e ste rn S lo peC h a ir: T B D
(T o t 2 A 20 1 0)
E a st S lo peR e fe r to La m ar
S LV
T o t 3
D e n ver-M e tro
S u b co m m itte esS p e cif ic G e o gra p h ic P o rtion
m u lt i-ye ar
L o ng R an geC h a ir: M a rk S to u t
1 0 -yr L & R
C o nce p tu a l P la nn ingC o -cha ir: In e z D o m ing u ez
C o -ch a ir: G e rry S te lle rn
S B 1 00C h a ir: T o m G re en
2 0 10 - L a m a r S tud ies
B a se C a se C oo rd ina tionC h a ir: T h ie n N g u yen
N E R C C om p lia n ceC h a ir: S h a w n C a rlson
V o ltag e C o ord ina tionC h a ir: R o y G ea rh a rt
S h o rt C ircu it D a ta B a seC h a ir: V aca nt
W o rk G ro u pse n tire fo o tp rin t
m u lt i-ye ar
A rch er In te rco nn e ctW E C C R a ting
S p o n sor: T S G T
W Y C O In te rt ieW E C C R a ting
S p o nso r: L S P o w er
H P XW E C C R e g ion a l P la n n ing
S p o n so rs : M u lt ip le
C o m m u n ica tionC h a ir: T o m G re en
T a sk F o rcesp o rtio n o r e n tire fo o tp rin t
1 -2 ye a r d u ra tion
W E C C T E P P CJe ff H e in
W E C C O T C P CJ im H irn ing
W e stC o nn e ctB o b E as ton
C P U CIn e z D om ing u ez
G E OC h ris W o rle y
L ia iso ns
O ve rsig h t C o m m itteeC h a ir: B lan e T a ylo r
V ice C h a ir: Je ff H e in
CCPG 2012 ORG CHART
CCCCCCPPPGGG 6
CCPG ActivitiesChair
Blane Taylor (Tri-State) 2011-2012
Studies:Work Groups:
Long Range (10-Year) Planning StudyConceptual (>10-year) Planning/Scenario AssessmentSenate Bill 100 StudiesNERC Compliance (TPL Adequacy Study)WECC Data CoordinationVoltage Coordination
Subcommittee Studies (Geographic)Foothills, Western Slope, Denver-metro, etc.
Sub-Regional Project Study ParticipationWCI, HPX, Tot 3, 5, 7 Expansion, Black Hills increased ERZ injection,
Western reliability improvements
Regulatory & Reliability ComplianceFederal, Regional, & State
CCCCCCPPPGGG 7
CCPG 2012 Activites
WestConnect RegionWestConnect 2013 Plan work ongoing
SB100 (State of Colorado) Lamar – Front Range (in planning),Pawnee – Daniels Park 345 KV Line – In Service Date 2019Missile Site 230 kV Switching Station (2010), Midway – Waterton 345 kV Line
(May-2011), Missile Site 345 kV Substation (Jan-2013), Pawnee – Smoky Hill 345 kV Line (Jan-2013)
Colorado Long-Range Transmission Planning Group
DEEP Subcommittee (2010)Douglas, Elbert, El Paso, Pueblo Counties (south-central CO)DEEP Report
Foothills Subcommittee (1980)North-Northwest of Denver Metro AreaFoothills Planning Group Reports
NERC ComplianceSubregional coordination on standards
CCCCCCPPPGGG 8
CCPG 2012 Activities (cont’d)
Conceptual Planning Group20-30 Year Plan3 Resource Scenarios (20-30 year horizon)
1000MW Import/ExportCarbon ReductionHigh load and 30% Renewableshttp://www.westconnect.com/documents_results.php?categoryid=130
Colorado Transmission Planning: Rule 3627 (Dkt# 10R-526E)Utilities 10-year plan & documentation filed by February 1, 2012Due every two years after thatMust include specific information included in Order C11-0492 http://www.westconnect.com/planning_ccpg_10_year_trans_plan.php
COPUC Scenario Analysis: System Reliability (Dkt# 12M-041E)Test resiliency of CO bulk power system5 Scenarios Proposed – 2 or 3 are desiredCOPUC receiving comments Final scenarios due September 2012http://www.westconnect.com/planning_ccpg_10_year_trans_plan.php
CCCCCCPPPGGG 9
On Deck
Joint SWAT-SSPG-CCPG MeetingAugust 22, 2012; Tri-State Offices
CCPG Meeting August 23, 2012; Tri-State Offices
Notices/Materials Posted at: www.westconnect.com
Contacts
Contact Phone Email
Blane Taylor(CCPG Chair)
303-254-6111 [email protected]
Jeff Hein(CCPG Vice-Chair)
303-571-7229 [email protected]
CCCCCCPPPGGG
Questions / Comments?Questions / Comments?
10
CCCCCCPPPGGG
SUPPLEMETAL SLIDES
More detailed information on issues presented previously.
CCCCCCPPPGGG 12
CPUC Rule 3627Docket 10R-526E
Requires Regulated Utilities to File 10-Year Transmission Plan10-Year Plan, 2-year cycle, starting Feb 201220-Year Plan, 2 year cycle, starting Feb 2014
Use CCPG as ForumNon-jurisdictional plans provided for information on utility
maintained websiteStakeholder Participation
actively solicit input from stakeholders, including government agencies, to identify alternative solutions
Reporting includes:Methodologies, load forecasts, related studies & reports,
transmission case data, stakeholder comments All Facilities >100kVPUC will hold workshops and a consolidated hearing.
Commission will render a decision regarding the “adequacy” of plans and process
Transmission Planning DecisionTransmission planning Recommended Rules
CCCCCCPPPGGG 13
2012 Study Scopes – Work GroupsWork Group: Long Range Transmission Planning Group
Purpose:Develop Coordinated 10 Year Transmission PlansConsider RPS & up to 30% RenewableConsider New PUC Rules
Work Group: SB100Purpose:
Meet requirements of Colorado Senate Bill 100 Identify “Energy Resource Zones”Plan Transmission to Serve the ERZ’sFile CPCN’s with COPUC
Work Group: Conceptual Planning (on-goingPurpose:
Develop Conceptual Transmission Plans beyond 10 YearsCoordinated with Advisory Group3 Resource Scenarios Evaluated (1)Import/Export of 1000 MW, (2)Carbon Reduction, (3)High Load
CCCCCCPPPGGG 14
2012 Study Scopes – Work GroupsWork Group: NERC Compliance
Purpose:Help Meet NERC TPL-001,2,3,4 RequirementsSteady State, Transient and Voltage PerformanceNear (5 year) & Far (10year) WindowsConsider RPS & up to 30% Renewable
Work Group: Area CoordinationPurpose:
Address Issues associated with preparation of cases for WECC Annual Study Program
Rocky Mountain Area CoordinatorWork Group: Voltage Coordination
Purpose:Prepare Guidelines for System Modeling
Work Group: Short Circuit Data BasePurpose:
Prepare a Short Circuit Data Base
CCCCCCPPPGGG 15
2012 Study Scopes (cont.)Subcommittees
Purpose:Analyze transmission requirements for specific regions within the CCPG
FootprintFoothills, DEEP, Tot 3, Wyoming Joint, Denver-Metro, SECO, SWCO, Front
Range, etcCCPG - Colorado Long-Range Transmission Planning Group |
WestConnect
LiaisonsPurpose:
Provide Information on Other Areas of Interest:OTC, TEPPC, PUC, GEO, etc.
CCCCCCPPPGGG 16
Regional Project Task Forces
High Plains Express InitiativeStage 2 CompletedStage 3 InitiatedWECC Regional Planningwww.highplainsexpress.com
CCCCCCPPPGGG
PSCo 10-Year Transmission Plan & 20-Year Scenario Assessment
10-Year Transmission Plan & 20-Year Scenario Assessmentwww.oatioasis.com/PSCO/PSCOdocs/PSCO_2011_10-
20_year_plan_Final.pdfCore reliability projects Clean Air Clean Jobs ActSB-100 Transmission Plan (9 proposed projects*)
o Missile Site 230 kV Switching Station (2010), Midway – Waterton 345 kV Line (May-2011), Missile Site 345 kV Substation (Jan-2013), Pawnee – Smoky Hill 345 kV Line (Jan-2013),
o San Luis Valley – Calumet – Comanche Project. CPCN granted Sept 2011. (Project may not be needed based on 2011 ERP)
o Lamar – Front Range (2018-2019) A CPCN may be filed in 2012o Pawnee – Daniels Park 345 KV Line – In Service Date 2019o Lamar – Vilas 230 kV Line – In Service Date TBDo Ault – Cherokee 230 kV Line – In Service Date TBD
CCCCCCPPPGGG 18
New Lamar-Comanche 345 kV & Lamar - Missile Site 345 kV ISD 2016
New San Luis Valley-Calumet-Comanche 230 & 345 kV lines ~ ISD 2013
New Midway-Waterton 345 kV ~ISD 2011
New Lamar –Vilas 345 kV ISD 2016
New Pawnee-Daniels Park 345 kV -2nd circuit ~ISD 2016
New Missile Site 230 kV ISD 2010) & 345 kV (ISD 2013)
New Ault-Cherokee 230 kV ~ISD 2015
New Pawnee-Smoky Hill 345 kV, ISD 2013
SB-100 Transmission Plan
CCPG - Senate Bill 100 Colorado