TEPPC 11-19-09 SWAT Summary - R. Kondziolka 1
Robert Kondziolka Salt River Project
November 19, 2009Phoenix, Arizona
WECC TEPPC Meeting SWAT Update
Western Electricity Coordinating CouncilWestern Electricity Coordinating Council
Transmission Expansion Planning Policy CommitteeTransmission Expansion Planning Policy Committee
TEPPC 11-19-09 SWAT Summary - R. Kondziolka 2
SouthwestArea
Transmission
SWATSWAT
SWAT Footprint One of the WestConnect Sub-Regional Planning
Groups
SWAT Footprint One of the WestConnect Sub-Regional Planning
Groups
http://www.westconnect.com
TEPPC 11-19-09 SWAT Summary - R. Kondziolka 3
Transmission Projects in WECC Regional Planning, Path Rating Process, or Development
Palo Verde-North Gila II
ON-Line
SWIPGreat Basin Project
Navajo TransmissionProject Segment 1
SunZia
High Plain Express
Palo Verde–Devers IICalifornia Portion
Pinal West to Pinal CentralPinal Central to BrowningPinal Central to TortolitaTS9 to Pinnacle Peak
Palo Verde to Sun ValleySun Valley to TS9
SPPR
TransWest Express
Chinook
Zephyr
Santa Fe
Tres Amigas
South Line
TEPPC 11-19-09 SWAT Summary - R. Kondziolka 4
Palo Verde
Imperial Valley
North Gila
Miguel
Mira Loma
Serrano
Valley
Devers
Vincent
Lugo
Victorville
Adelanto
RinaldiToluca
Crystal
McCullough
Mead
Eldorado
Mohave
Marketplace
Rudd
Four
Corners
YavapaiMoenkopi
Kyrene
Jojoba
PerkinsWestwing
Navajo
Harry Allen
Saguaro
Cholla
Coronado
Nevada
California
Utah
Peacock
Liberty
500 kV line
345 kV line
Major Substation
Major Power Plants
Silver
King
To Intermountain
To Celilo
Sylmar
To Midway
+/- 500 kV DC line
Arizona
DPV2 Project
Harquahala
EHV Transmission Upgrades In Development
2009400MW
500kV Line Upgrade
2009625MWEnergized
2009625MWEnergized
2010600MW
TEPPC 11-19-09 SWAT Summary - R. Kondziolka 5
Status of Major New Transmission ProjectsProject Name Voltage Capacity
Proposed In-Service Sponsor Status
Pinal Central to Browning 500kV 1400MW 2011 - 2nd Qtr SRP In Construction
Pinal West to Pinal Central 500kV 1400MW 2014 - 2nd Qtr SRP In Design & ROW Acquisition
Palo Verde to TS5 (Sun Valley) 500kV 650MW 2014 - 2nd Qtr APS In Design & ROW Acquisition
TS5 (Sun Valley) to TS9 500kV 1200MW 2016 - 2nd Qtr APS In Design & ROW Acquisition
TS9 (Raceway) to Pinnacle Peak 500kV 1000MW 2010 – 4th Qtr APS In Construction
Arizona Gateway South (Double Circuit) 345kV 2000MW 2014 TEP In Perpetual Federal Permitting
Navajo Transmission Project 500kV 1500MW 2011 DPA In Path Rating Study Process
Palo Verde to North Gila II 500kV 1250MW 2014 - 2nd Qtr APS In Design & ROW Acquisition
Palo Verde to Devers II (California Only) 500kV 1200MW 2012 – 4th Qtr SCE In Siting & Permitting
TransWest Express (Bi-Pole DC) 600kV 3000MW 2015 Anschutz In Siting & Permitting & Path Rating
Chinook and Zephyr (Bi-Pole DC) 500kV 6000MW 2015 TransCan In Siting & Permitting
Pinal Central to Tortolita 500kV 1200MW 2014 - 2nd Qtr TEP In Siting & Permitting
Easrtern Nevada Transmission Intertie 500kV 2000MW 2011 - 4th Qtr NVEnergy In Siting & Permitting & Path Rating
Great Basin Energy Project (SWIP) 500kV 1650MW 2012 - 4th Qtr LS Power In Siting & Permitting & Path Rating
Project kV MW 20XX ID I
SunZia Southwest Trans Project (2 Circuits) 500kV 3000MW 2013 SW Power In Path Rating Process & Permitting
High Plains Express Initiative (2 Circuits) 500kV 3500MW 2016 - 2017 Xcel Feasibility Studies
TEPPC 11-19-09 SWAT Summary - R. Kondziolka 6
SWAT 2009 Progress • CRT Subcommittee
– DPV2, Harcuvar Project, El Dorado Valley – RMR Studies for Yuma and Mohave counties
• SATS Subcommittee– 2009 study work finalized
• Short Circuit Work Group– Perfecting database and implementing small areas– Expanding area to include southern California
• NM Subcommittee– Focusing efforts through Renewable Transmission Task Force– Wind collector and integration system
• SWAT Renewable Transmission Task Force – ARRTIS (Arizona Renewable Resource and Transmission
Identification Subcommittee) – Report Approved– Finance Subcommittee – Report Approved– Definition of Renewable Transmission Project
TEPPC 11-19-09 SWAT Summary - R. Kondziolka 7
SWAT 2009 Progress• CATS HV Subcommittee
– 2009 Study Report Finalized and Approved
– Development of corridors with cities and county
• CATS EHV Subcommittee– 2009 Study Report Finalized and Approved
– Development of ACC BTA Studies
• Transmission Corridor Planning Work Group
• Common Corridor Structure Separation Task Force– Report Approved
BLM Arizona Restoration Design Energy Projects Western’s Transmission Infrastructure Program (TIP & WARP) Arizona Corporation Commission Biennial Transmission
Assessment April & June workshops on transmission lines to support renewables Utilities filed reports identifying top 3 renewable transmission projects
TEPPC 11-19-09 SWAT Summary - R. Kondziolka 8
TEPPC 11-19-09 SWAT Summary - R. Kondziolka 9
TEPPC 11-19-09 SWAT Summary - R. Kondziolka 10
TEPPC 11-19-09 SWAT Summary - R. Kondziolka 11
TEPPC 11-19-09 SWAT Summary - R. Kondziolka 12
SWAT Organization Chart
TEPPC 11-19-09 SWAT Summary - R. Kondziolka
Josh Johnston
Proposed Changes11/3/09
Consolidate into one subcommittee
Convert to subcommittee
El Dorado Valley Study Group
TEPPC 11-19-09 SWAT Summary - R. Kondziolka 14
Western Electricity Coordinating CouncilWestern Electricity Coordinating Council
Transmission Expansion Planning Policy CommitteeTransmission Expansion Planning Policy Committee
Robert E. KondziolkaRobert E. [email protected]
(602) 236-0971(602) 236-0971
Questions?Questions?