Overview of US Contributions to the ITER Steady State Electrical ...
ITER Technical Overview
-
Upload
hanssinekr9050 -
Category
Documents
-
view
220 -
download
0
Transcript of ITER Technical Overview
-
8/3/2019 ITER Technical Overview
1/29
ITER: Technical Overview
W.Spears
ITER International Team
Ljubljana, 1st June, 2006
-
8/3/2019 ITER Technical Overview
2/29
1st June 2006 ITER Technical Overview - Ljubljana 2
ITER History
1988-1991 - (CDA) Conceptual Design Phase Start of common activities among EU,USSR, USA and JA.
Selection of machine parameters and objectives.
1992-1998 - (EDA) Engineering Design Phase
Developed design capable of ignition - large and expensive. The Parties (EU, JA, RF, US) endorsed design but could not afford to build it.
1999 2001 (EDA continues)
US withdraws from project.
Remaining Parties searched for less ambitious goal. New design: moderate plasma power amplification at about half the cost.
2001 - now (CTA and ITA)
End of EDA and start of negotiations on construction and operation.
4 site offers. 2003: US re-joins, China & South Korea are accepted as full partners.
Cadarache selected as ITER site in June 2005.
India joins in December 2005
-
8/3/2019 ITER Technical Overview
3/29
1st June 2006 ITER Technical Overview - Ljubljana 3
Technical Objectives
Q (ratio of fusion power to auxiliary heating power) 10(>5 in steady state). Possibility of controlled ignition.
Integrate the technologies essential for a fusion reactor (e.g.superconducting magnets, remote maintenance);
Test components for a future reactor (e.g. divertor and torusvacuum pumps, tritium breeding blanket modules).
Rely as far as possible on existing physics and tech. R&D.
Flexible operation range, with access to advanced modes.
Power flat top 300 s up to steady state.
Operation limited to ~30,000 pulses.
Average neutron flux > 0.5 MW/m2, fluence > 0.3 MWa/m2
Possible later installation of tritium breeding blanket.
Sufficiently reliable operation for nuclear testing.
Operate for ~ 20 years, using externally supplied tritium.
-
8/3/2019 ITER Technical Overview
4/291st June 2006 ITER Technical Overview - Ljubljana 4
ITER Plant
-
8/3/2019 ITER Technical Overview
5/291st June 2006 ITER Technical Overview - Ljubljana 5
Plant Systems
-
8/3/2019 ITER Technical Overview
6/291st June 2006 ITER Technical Overview - Ljubljana 6
Tokamak Building Complex
Hot Cell
TokamakAssembly Area
-
8/3/2019 ITER Technical Overview
7/29
JET
R=3m
Ip=4MAITERR=6.2m
Ip=15MA
-
8/3/2019 ITER Technical Overview
8/29
1st June 2006 ITER Technical Overview - Ljubljana 8
Shield
Magnet
System
Vacuum Vessel
Person
Tokamak
R=6.2 m
Ip=15 MA
Pfus=500 MW
Divertor
30 m
24 m
-
8/3/2019 ITER Technical Overview
9/29
1st June 2006 ITER Technical Overview - Ljubljana 9
Superconducting. Nb3Sn toroidal field (TF)coils produce confining/stabilizing toroidal field;
NbTi poloidal field (PF) coils position andshape plasma;
Modular Nb3Sn central solenoid (CS) coilinduces current in the plasma.
Correction coils correct error fields due tomanufacturing/assembly imperfections, andstabilize plasma against resistive wall modes.
TF coil case provides main structure of themagnet system and the machine core. PFcoils and vacuum vessel are linked to it. Allinteraction forces resisted internally.
TF coil inboard legs wedged together alongtheir side walls and linked at top and bottom
by two strong coaxial rings which providetoroidal compression
On the outboard leg, out-of-plane supportprovided by intercoil structures integrated withTF coil cases.
.
Magnet System
Magnet system weighs ~ 8,700 t.
-
8/3/2019 ITER Technical Overview
10/29
-
8/3/2019 ITER Technical Overview
11/29
1st June 2006 ITER Technical Overview - Ljubljana 11
CS Model Coil TF Model coil
Magnet EDA R&D
-
8/3/2019 ITER Technical Overview
12/29
1st June 2006 ITER Technical Overview - Ljubljana 12
Vacuum
Vessel
Blanket
Divertor
-
8/3/2019 ITER Technical Overview
13/29
1st June 2006 ITER Technical Overview - Ljubljana 13
Plasma Vacuum Vessel
Primary function
high quality vacuum for the plasma
first confinement barrier to radioactive materials
9 x 4 0vessel sectors.
Many ports for access:
-Diagnostics
-Maintenance
-Heating systems
-Fuelling/Pumping
-Inspection-Test Blankets
Double wall
Water cooled
-
8/3/2019 ITER Technical Overview
14/29
1st June 2006 ITER Technical Overview - Ljubljana 14
Blanket
440 blanket modules withdetachable faceted first wall (FW)
with Be armour on a water-cooled
copper substrate, attached to a
SS shielding block.
Blanket cooling channels are
mounted on the vessel.
Design strongly affected by needto resist electromagnetic forces.
Initial blanket acts solely as a
neutron shield, and tritium
breeding experiments are carriedout on test blanket modules
inserted and withdrawn at radial
equatorial ports.
Inlet/outlet
manifolds
First wall
panel
Hole to fit
flexible support
Flexiblesupports
Vessel
Shieldblock
Shear key
Gripping
hole
Electrical strap
-
8/3/2019 ITER Technical Overview
15/29
1st June 2006 ITER Technical Overview - Ljubljana 15
Divertor
54 cassettes.
Target and divertor floor form a V which traps
neutral particles, protecting the target plates,
without adversely affecting helium removal.
Large openings between the inner and outer
divertor balance heat loads in the inboard and
outboard channels.
Design uses C at the vertical target strike
points. W is the backup. C is best able to
withstand large power density pulses (ELMs,
disruptions), but produces tritiated dust and T
co-deposited with C which has to be
periodically removed. The choice can be made
at the time of procurement.
Vertical target (W part)
Dome (W)
Vertical target (C part)
-
8/3/2019 ITER Technical Overview
16/29
1st June 2006 ITER Technical Overview - Ljubljana 16
Heating/Current Drive
High energy (1 MeV D-) ion beams +
radio frequency heating tuned to key
plasma frequencies (ion, electroncyclotron, lower hybrid).
RF systems modular and
interchangeable in equatorial ports.
EC used in upper ports.
2 main beam-lines, with room for
third.
Initial installation 73 MW with room
for expansion to 130 MW.
Steerable mirror
Front shield
Waveguides Windows
Electron Cyclotron System
Equatorial Port Plug
E l f EDA R&D
-
8/3/2019 ITER Technical Overview
17/29
1st June 2006 ITER Technical Overview - Ljubljana 17
Examples of EDA R&D
Payload ~ 4 t, Arm length ~ 6m
Vehicle Manipulator System For Blanket Maintenance
-
8/3/2019 ITER Technical Overview
18/29
1st June 2006 ITER Technical Overview - Ljubljana 18
-
8/3/2019 ITER Technical Overview
19/29
1st June 2006 ITER Technical Overview - Ljubljana 19
A bl
-
8/3/2019 ITER Technical Overview
20/29
1st June 2006 ITER Technical Overview - Ljubljana 20
Assembly
Lower cryostat, tokamak gravitysupports, lower PF and correction
coils, TF pre-tensioning rings, etc.,
placed in the pit.
40 sectors of vessel + 2 TF coils,thermal shields, etc., assembled
together on-site and moved to pit.
Sectors welded in opposition to
minimise distortions. TF coil pre-tensioning rings installed. Machine
datum established. Clean
conditions in-vessel.
In-vessel components installed andaligned. PF/correction coils and
cryostat above equator installed.
External installations proceed in
parallel.
Pl Ph i I
-
8/3/2019 ITER Technical Overview
21/29
1st June 2006 ITER Technical Overview - Ljubljana 21
MHD Stability
Heat Confinement
Steady State Operation
Control of Plasma Purity
Exploration of the new physics with adominant -particles plasma self heating
Plasma Physics Issues
E i i /T h l Ch ll
-
8/3/2019 ITER Technical Overview
22/29
1st June 2006 ITER Technical Overview - Ljubljana 22
Engineering/Technology Challenges
Change of extent of fusion research.
Many new problems to solve.
Millions of parts with very complex
interfaces and ensuing knock-on effects.
Unprecedented size of the
super-conducting magnet andstructures.
Extremely high heat fluxes in first
wall components, & materials
under neutron irradiation
Remote Maintenance required.
-
8/3/2019 ITER Technical Overview
23/29
1st June 2006 ITER Technical Overview - Ljubljana 23
Organisation Challenges (1)
Forging one coherent project team across multiple cultures(and time zones) with industrial support.
Organisation Challenges (2)
-
8/3/2019 ITER Technical Overview
24/29
1st June 2006 ITER Technical Overview - Ljubljana 24
Magnet System
Cryogenie
& Vessel
Internals
Others
Power Supplies
Distribution &
& Diagnostics
CODAC
Cooling Water
Systems
Buildings
Assembly & R/H Cryostat & TS
EU
China
USA
India
RF
JapanS Korea
Organisation Challenges (2)
In-Kind?
Involve all the Parties in key fusion technology areas.
Share the cost of the device by value and not by currency.
Automatically ensure fair return Sharing: 5/11 EU (1/11 procured in Japan), 1/11 Others. (of which
10% centrally funded and 90% in-kind)
Procurement Sharing
-
8/3/2019 ITER Technical Overview
25/29
1st June 2006 ITER Technical Overview - Ljubljana 25
Procurement Sharing
Negotiation Status
-
8/3/2019 ITER Technical Overview
26/29
1st June 2006 ITER Technical Overview - Ljubljana 26
Negotiation Status
ITER Parties are now in the process of finalising the JointImplementation Agreement and its main instruments. Main Agreement Text
Staffing regulations Procurement and cost sharing
Intellectual Property Rights
Principles of Operation Programme
Resource Management Principles on management
November 2005: High level P Meeting, DG selected
December 2005: NSSG13/N Meeting , Finalisation of Drafts
May 2006: Ministerial Meeting to initial Agreement
November 2006: Agreement Formal Signature
Early 2007: Agreement enters into force
Continuing Design Process
-
8/3/2019 ITER Technical Overview
27/29
1st June 2006 ITER Technical Overview - Ljubljana 27
Continuing Design Process
In mid-2001 design finalised to extent allowing reasonablecost estimate to be made - ~ 5B + 5B during operation.
Continued design improvement since then, focussing onlong lead items (buildings/tunnels, magnets, vessel) andtheir interfaces.
Many improvements made to increase realism of costing
and to simplify design, operation or manufacture, reducerisk, or ease licensing.
Project infrastructure improvements to tighten up on
design change control and quality management -document and model management systems.
Strong emphasis now on licensing and preparation ofdocumentation for it. Design to be reviewed by new team
and then regularly as construction proceeds.
Schedule
-
8/3/2019 ITER Technical Overview
28/29
1st June 2006 ITER Technical Overview - Ljubljana 28
Schedule
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
ITER IOLICENSE TO
CONSTRUCT
TOKAMAK ASSEMBLY
STARTS
FIRST
PLASMA
BidContract
EXCAVATETOKAMAK BUILDING
OTHER BUILDINGS
TOKAMAK ASSEMBLY
COMMISSIONING
MAGNET
VESSEL
Bid Vendors Design
Bid
Install
cryostat
First sector Complete VVComplete
blanket/divertor
PFC Install CS
First sector Last sector
Last CSLast TFCCSPFC TFCfabrication start
Contract
Contract
2016
Construction License Process
Conclusions
-
8/3/2019 ITER Technical Overview
29/29
1st June 2006 ITER Technical Overview - Ljubljana 29
Conclusions
ITER is one of the most technologically, organisationally and politicallychallenging projects being undertaken today.
Nevertheless, a convincing design has been and continues to be developedable to meet its objectives, and the international infrastructure and the
organisation necessary to build it on the expected timescale is in theprocess of being set up.
ITER will be the proving ground for the key technologies necessary to makemagnetic fusion into a viable energy source.
The design phase has demonstrated the desirability of jointly implementingITER in a broad-based international collaborative frame with the stronginvolvement of Industry.
Procurement is split among the ITER Parties, but Europe provides 36% of
the hardware. This allows considerable opportunities for Europeanmanufacturers and service providers.
In its host role, Europe is well-placed to gain essential know-how from itsinvolvement in most systems, via installation and plant licensing.