ITER Technical Overview

download ITER Technical Overview

of 29

Transcript of ITER Technical Overview

  • 8/3/2019 ITER Technical Overview

    1/29

    ITER: Technical Overview

    W.Spears

    ITER International Team

    Ljubljana, 1st June, 2006

  • 8/3/2019 ITER Technical Overview

    2/29

    1st June 2006 ITER Technical Overview - Ljubljana 2

    ITER History

    1988-1991 - (CDA) Conceptual Design Phase Start of common activities among EU,USSR, USA and JA.

    Selection of machine parameters and objectives.

    1992-1998 - (EDA) Engineering Design Phase

    Developed design capable of ignition - large and expensive. The Parties (EU, JA, RF, US) endorsed design but could not afford to build it.

    1999 2001 (EDA continues)

    US withdraws from project.

    Remaining Parties searched for less ambitious goal. New design: moderate plasma power amplification at about half the cost.

    2001 - now (CTA and ITA)

    End of EDA and start of negotiations on construction and operation.

    4 site offers. 2003: US re-joins, China & South Korea are accepted as full partners.

    Cadarache selected as ITER site in June 2005.

    India joins in December 2005

  • 8/3/2019 ITER Technical Overview

    3/29

    1st June 2006 ITER Technical Overview - Ljubljana 3

    Technical Objectives

    Q (ratio of fusion power to auxiliary heating power) 10(>5 in steady state). Possibility of controlled ignition.

    Integrate the technologies essential for a fusion reactor (e.g.superconducting magnets, remote maintenance);

    Test components for a future reactor (e.g. divertor and torusvacuum pumps, tritium breeding blanket modules).

    Rely as far as possible on existing physics and tech. R&D.

    Flexible operation range, with access to advanced modes.

    Power flat top 300 s up to steady state.

    Operation limited to ~30,000 pulses.

    Average neutron flux > 0.5 MW/m2, fluence > 0.3 MWa/m2

    Possible later installation of tritium breeding blanket.

    Sufficiently reliable operation for nuclear testing.

    Operate for ~ 20 years, using externally supplied tritium.

  • 8/3/2019 ITER Technical Overview

    4/291st June 2006 ITER Technical Overview - Ljubljana 4

    ITER Plant

  • 8/3/2019 ITER Technical Overview

    5/291st June 2006 ITER Technical Overview - Ljubljana 5

    Plant Systems

  • 8/3/2019 ITER Technical Overview

    6/291st June 2006 ITER Technical Overview - Ljubljana 6

    Tokamak Building Complex

    Hot Cell

    TokamakAssembly Area

  • 8/3/2019 ITER Technical Overview

    7/29

    JET

    R=3m

    Ip=4MAITERR=6.2m

    Ip=15MA

  • 8/3/2019 ITER Technical Overview

    8/29

    1st June 2006 ITER Technical Overview - Ljubljana 8

    Shield

    Magnet

    System

    Vacuum Vessel

    Person

    Tokamak

    R=6.2 m

    Ip=15 MA

    Pfus=500 MW

    Divertor

    30 m

    24 m

  • 8/3/2019 ITER Technical Overview

    9/29

    1st June 2006 ITER Technical Overview - Ljubljana 9

    Superconducting. Nb3Sn toroidal field (TF)coils produce confining/stabilizing toroidal field;

    NbTi poloidal field (PF) coils position andshape plasma;

    Modular Nb3Sn central solenoid (CS) coilinduces current in the plasma.

    Correction coils correct error fields due tomanufacturing/assembly imperfections, andstabilize plasma against resistive wall modes.

    TF coil case provides main structure of themagnet system and the machine core. PFcoils and vacuum vessel are linked to it. Allinteraction forces resisted internally.

    TF coil inboard legs wedged together alongtheir side walls and linked at top and bottom

    by two strong coaxial rings which providetoroidal compression

    On the outboard leg, out-of-plane supportprovided by intercoil structures integrated withTF coil cases.

    .

    Magnet System

    Magnet system weighs ~ 8,700 t.

  • 8/3/2019 ITER Technical Overview

    10/29

  • 8/3/2019 ITER Technical Overview

    11/29

    1st June 2006 ITER Technical Overview - Ljubljana 11

    CS Model Coil TF Model coil

    Magnet EDA R&D

  • 8/3/2019 ITER Technical Overview

    12/29

    1st June 2006 ITER Technical Overview - Ljubljana 12

    Vacuum

    Vessel

    Blanket

    Divertor

  • 8/3/2019 ITER Technical Overview

    13/29

    1st June 2006 ITER Technical Overview - Ljubljana 13

    Plasma Vacuum Vessel

    Primary function

    high quality vacuum for the plasma

    first confinement barrier to radioactive materials

    9 x 4 0vessel sectors.

    Many ports for access:

    -Diagnostics

    -Maintenance

    -Heating systems

    -Fuelling/Pumping

    -Inspection-Test Blankets

    Double wall

    Water cooled

  • 8/3/2019 ITER Technical Overview

    14/29

    1st June 2006 ITER Technical Overview - Ljubljana 14

    Blanket

    440 blanket modules withdetachable faceted first wall (FW)

    with Be armour on a water-cooled

    copper substrate, attached to a

    SS shielding block.

    Blanket cooling channels are

    mounted on the vessel.

    Design strongly affected by needto resist electromagnetic forces.

    Initial blanket acts solely as a

    neutron shield, and tritium

    breeding experiments are carriedout on test blanket modules

    inserted and withdrawn at radial

    equatorial ports.

    Inlet/outlet

    manifolds

    First wall

    panel

    Hole to fit

    flexible support

    Flexiblesupports

    Vessel

    Shieldblock

    Shear key

    Gripping

    hole

    Electrical strap

  • 8/3/2019 ITER Technical Overview

    15/29

    1st June 2006 ITER Technical Overview - Ljubljana 15

    Divertor

    54 cassettes.

    Target and divertor floor form a V which traps

    neutral particles, protecting the target plates,

    without adversely affecting helium removal.

    Large openings between the inner and outer

    divertor balance heat loads in the inboard and

    outboard channels.

    Design uses C at the vertical target strike

    points. W is the backup. C is best able to

    withstand large power density pulses (ELMs,

    disruptions), but produces tritiated dust and T

    co-deposited with C which has to be

    periodically removed. The choice can be made

    at the time of procurement.

    Vertical target (W part)

    Dome (W)

    Vertical target (C part)

  • 8/3/2019 ITER Technical Overview

    16/29

    1st June 2006 ITER Technical Overview - Ljubljana 16

    Heating/Current Drive

    High energy (1 MeV D-) ion beams +

    radio frequency heating tuned to key

    plasma frequencies (ion, electroncyclotron, lower hybrid).

    RF systems modular and

    interchangeable in equatorial ports.

    EC used in upper ports.

    2 main beam-lines, with room for

    third.

    Initial installation 73 MW with room

    for expansion to 130 MW.

    Steerable mirror

    Front shield

    Waveguides Windows

    Electron Cyclotron System

    Equatorial Port Plug

    E l f EDA R&D

  • 8/3/2019 ITER Technical Overview

    17/29

    1st June 2006 ITER Technical Overview - Ljubljana 17

    Examples of EDA R&D

    Payload ~ 4 t, Arm length ~ 6m

    Vehicle Manipulator System For Blanket Maintenance

  • 8/3/2019 ITER Technical Overview

    18/29

    1st June 2006 ITER Technical Overview - Ljubljana 18

  • 8/3/2019 ITER Technical Overview

    19/29

    1st June 2006 ITER Technical Overview - Ljubljana 19

    A bl

  • 8/3/2019 ITER Technical Overview

    20/29

    1st June 2006 ITER Technical Overview - Ljubljana 20

    Assembly

    Lower cryostat, tokamak gravitysupports, lower PF and correction

    coils, TF pre-tensioning rings, etc.,

    placed in the pit.

    40 sectors of vessel + 2 TF coils,thermal shields, etc., assembled

    together on-site and moved to pit.

    Sectors welded in opposition to

    minimise distortions. TF coil pre-tensioning rings installed. Machine

    datum established. Clean

    conditions in-vessel.

    In-vessel components installed andaligned. PF/correction coils and

    cryostat above equator installed.

    External installations proceed in

    parallel.

    Pl Ph i I

  • 8/3/2019 ITER Technical Overview

    21/29

    1st June 2006 ITER Technical Overview - Ljubljana 21

    MHD Stability

    Heat Confinement

    Steady State Operation

    Control of Plasma Purity

    Exploration of the new physics with adominant -particles plasma self heating

    Plasma Physics Issues

    E i i /T h l Ch ll

  • 8/3/2019 ITER Technical Overview

    22/29

    1st June 2006 ITER Technical Overview - Ljubljana 22

    Engineering/Technology Challenges

    Change of extent of fusion research.

    Many new problems to solve.

    Millions of parts with very complex

    interfaces and ensuing knock-on effects.

    Unprecedented size of the

    super-conducting magnet andstructures.

    Extremely high heat fluxes in first

    wall components, & materials

    under neutron irradiation

    Remote Maintenance required.

  • 8/3/2019 ITER Technical Overview

    23/29

    1st June 2006 ITER Technical Overview - Ljubljana 23

    Organisation Challenges (1)

    Forging one coherent project team across multiple cultures(and time zones) with industrial support.

    Organisation Challenges (2)

  • 8/3/2019 ITER Technical Overview

    24/29

    1st June 2006 ITER Technical Overview - Ljubljana 24

    Magnet System

    Cryogenie

    & Vessel

    Internals

    Others

    Power Supplies

    Distribution &

    & Diagnostics

    CODAC

    Cooling Water

    Systems

    Buildings

    Assembly & R/H Cryostat & TS

    EU

    China

    USA

    India

    RF

    JapanS Korea

    Organisation Challenges (2)

    In-Kind?

    Involve all the Parties in key fusion technology areas.

    Share the cost of the device by value and not by currency.

    Automatically ensure fair return Sharing: 5/11 EU (1/11 procured in Japan), 1/11 Others. (of which

    10% centrally funded and 90% in-kind)

    Procurement Sharing

  • 8/3/2019 ITER Technical Overview

    25/29

    1st June 2006 ITER Technical Overview - Ljubljana 25

    Procurement Sharing

    Negotiation Status

  • 8/3/2019 ITER Technical Overview

    26/29

    1st June 2006 ITER Technical Overview - Ljubljana 26

    Negotiation Status

    ITER Parties are now in the process of finalising the JointImplementation Agreement and its main instruments. Main Agreement Text

    Staffing regulations Procurement and cost sharing

    Intellectual Property Rights

    Principles of Operation Programme

    Resource Management Principles on management

    November 2005: High level P Meeting, DG selected

    December 2005: NSSG13/N Meeting , Finalisation of Drafts

    May 2006: Ministerial Meeting to initial Agreement

    November 2006: Agreement Formal Signature

    Early 2007: Agreement enters into force

    Continuing Design Process

  • 8/3/2019 ITER Technical Overview

    27/29

    1st June 2006 ITER Technical Overview - Ljubljana 27

    Continuing Design Process

    In mid-2001 design finalised to extent allowing reasonablecost estimate to be made - ~ 5B + 5B during operation.

    Continued design improvement since then, focussing onlong lead items (buildings/tunnels, magnets, vessel) andtheir interfaces.

    Many improvements made to increase realism of costing

    and to simplify design, operation or manufacture, reducerisk, or ease licensing.

    Project infrastructure improvements to tighten up on

    design change control and quality management -document and model management systems.

    Strong emphasis now on licensing and preparation ofdocumentation for it. Design to be reviewed by new team

    and then regularly as construction proceeds.

    Schedule

  • 8/3/2019 ITER Technical Overview

    28/29

    1st June 2006 ITER Technical Overview - Ljubljana 28

    Schedule

    2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015

    ITER IOLICENSE TO

    CONSTRUCT

    TOKAMAK ASSEMBLY

    STARTS

    FIRST

    PLASMA

    BidContract

    EXCAVATETOKAMAK BUILDING

    OTHER BUILDINGS

    TOKAMAK ASSEMBLY

    COMMISSIONING

    MAGNET

    VESSEL

    Bid Vendors Design

    Bid

    Install

    cryostat

    First sector Complete VVComplete

    blanket/divertor

    PFC Install CS

    First sector Last sector

    Last CSLast TFCCSPFC TFCfabrication start

    Contract

    Contract

    2016

    Construction License Process

    Conclusions

  • 8/3/2019 ITER Technical Overview

    29/29

    1st June 2006 ITER Technical Overview - Ljubljana 29

    Conclusions

    ITER is one of the most technologically, organisationally and politicallychallenging projects being undertaken today.

    Nevertheless, a convincing design has been and continues to be developedable to meet its objectives, and the international infrastructure and the

    organisation necessary to build it on the expected timescale is in theprocess of being set up.

    ITER will be the proving ground for the key technologies necessary to makemagnetic fusion into a viable energy source.

    The design phase has demonstrated the desirability of jointly implementingITER in a broad-based international collaborative frame with the stronginvolvement of Industry.

    Procurement is split among the ITER Parties, but Europe provides 36% of

    the hardware. This allows considerable opportunities for Europeanmanufacturers and service providers.

    In its host role, Europe is well-placed to gain essential know-how from itsinvolvement in most systems, via installation and plant licensing.