Investment in Electricity Markets – a Market and Model Perspective
-
Upload
marin-galic -
Category
Documents
-
view
217 -
download
0
Transcript of Investment in Electricity Markets – a Market and Model Perspective
-
8/11/2019 Investment in Electricity Markets a Market and Model Perspective
1/17
Selected topics in energy economics
Exercise 3
Investment in Electricity Markets a market and model
perspective
Student's name ID
Marin Galic -
Vienna, January 2014
-
8/11/2019 Investment in Electricity Markets a Market and Model Perspective
2/17
1
1. The problem to solve
Exercise3.1: Full load hours, contribution margin vs. fix costs
a)
Calculate the theoretical full load hours of the given power plants (Coal plant,
Combined Cycle Gas turbine (CCGT), Open Cycle Gas turbine (OCGT)) for the years 2006
to 2012. (see figure 1). The market prices for those years can be found in spotprices.xlsx.
Assume that the power plants will only produce, if the price is greater than the short run
marginal costs of production. Assume that the short run marginal costs are defined by the
fuel costs and CO2 costs. Data on monthly average costs of those inputs can be found in the
file Fuel_CO2_costs.xlsx. (You can also use yearly average costs for your calculations but
that should be stated in your report). All other relevant parameters are given in table 1.
Present your results graphically!
b)
Calculate the contribution margin in each year. We define the contribution margin as
gross income minus variable costs for each year. (see figure 1) Compare the contribution
margin to the yearly fix costs. The yearly fix costs consist of operation and maintenance costs
(O&M) and the yearly capital costs (annuity of investment = I). Note that both components
are independent of the actual production within a year. To calculate the annuities use a
discount rate of 5% and the technical life time given in table 1.
Present your results graphically! What is your interpretation of the results? Where those
power plants profitable between 2006 and 2012?
c)
What is the minimal yearly contribution margin at which you would decide to go in
operation for each power plant if you assume that the plant is already built? What is the
minimal expected yearly contribution margin at which you would decide to invest in a new
power plant? Which decision would you take in year 2012 for each type of power plant?
Interpret your results!
(We assume that the O&M costs are not to be paid if the plant does not operate throughout a
whole year)
-
8/11/2019 Investment in Electricity Markets a Market and Model Perspective
3/17
2
-
8/11/2019 Investment in Electricity Markets a Market and Model Perspective
4/17
3
Exercise 3.2: Investment model Scenario analyses of minimal system costs
a)
Convert the generation dispatch model (I nvestmodel_Exerci se.gms) to an investment
model. Add an investment term (annuity of the investment) and the O&M costs to the
objective function (Cost). Those additional costs are considered to be yearly fixed
capacity costs. As we only simulate one typical day in the model we divide those costs by
365 which approximately yields daily capacity costs (Ccapacity [/kWday]).
[MW] is the additional capacity for each power plant (j) and is to found by the
optimization model together with the optimal dispatch tjP, for each hour (t) and power plant
(j)
The constraint Output which limits the power output of each plant has to be adjusted to
consider new installed capacity.
Addition:
Definition of daily capacity costs for model calculations:
With Ias specific investment costs, as annuity factor and Opexas fixed yearly operation
and maintenancecosts (O&M) for each power plantj. Of course this is a simplification. Here
we assume the load pattern to be constant in all days of a year. We also assume the same
patterns and costs over the whole life time of the power plants. Think of possible implications.
-
8/11/2019 Investment in Electricity Markets a Market and Model Perspective
5/17
4
b)
Find the optimal solution for the following base scenario:
Base scenario:
CO2 price: 20 /t
Gas price: 25 /MWh
Coal price: 10 /MWh
PV installed capacity (Cap_PV): 0.1 GW
No existing capacity: Capold=0 for all power plants.
What is the optimal installed capacity of each power plant?
c)
Shadow prices and the costs of capacity:
Take a look at the shadow prices of demand. They can be found in the Gamsoutput file (*.lst)
or in the Gdxviewer. The shadow price of demand for each hour can be found under
equation (or SolEQU in the .lst file) and the demand equation. It is the value in the
column marginal. It reflects the marginal additional or reduced costs if the right hand side
of the equation is increased by the value 1. In this case it reflects the additional costs of a
demand increase of one MWh in hour t.
In theory this can be interpreted as the price of one MWh in hour t.
Try to explain the shadow price of demand in hour 3 and in hour 19. Why is the shadow price
of hour 19 so high? What are the components of this price?
d)
Scenario analysesthe influence of Photovoltaic and CO2 costs:
Calculate the optimal capacity mix for the following scenarios:
PV scenario: Installed capacity of PV from 0 to 1 GW with 0.2 GW steps
CO2 scenario: CO2 price from 0 to 30 /tCO2 with 5 steps (Installed capacity of PV
stays at 0.1 GW as in Base scenario.)
-
8/11/2019 Investment in Electricity Markets a Market and Model Perspective
6/17
5
Illustrate your results graphically!
Interpret your results!
What do you observe?
What are your conclusions for future developments of the installed capacity?
What kind of problems could arise if the market price is limited to the short run marginal cost
of the conventional power plants?
Sources:
GAMS download:http://www.gams.com/download/
All other files including the GAMS license can be found in TISS
http://www.gams.com/download/http://www.gams.com/download/http://www.gams.com/download/http://www.gams.com/download/ -
8/11/2019 Investment in Electricity Markets a Market and Model Perspective
7/17
6
3. Solution
3.1. Full load hours, contribution margin vs. fix costs
a)Theoretical full load hours have been calculated using spot prices of electrical energy,
fuel costs and CO2costs. CO2costs can be calculated using fuel emission factor (Table 1) and
CO2costs (in Excel, Fuel_CO2_costs.xl sx). Looking at the Table 1 it can be seen that fuel
emission factors are 0,2for CCGT and OCGT and 0,35for Coal Power Plant.
CO2costs have been calculated multiplying fuel emission factorand CO2_spot. For
example, in period January 2006, price of CO2 was 21,58 /t CO2:
In this period (for coal power plant):
Using Price of CO2, fuel costs and efficiency, we can calculate short run marginalcosts (SMC):
For example (coal power plant, same period):
Table 2. Example of CO2 and SMC costs calculation (January 2006)
Power plant fuel emission
factor
Price of CO2[/MWh]
fuel costs
[/MWh]
Short marginal
costs (SMC)
[/MWh]
CCGT 0,2 4,32 20,13 41,43
OCGT 0,2 4,32 20,13 61,11
Coal 0,35 7,55 7,74 38,24
-
8/11/2019 Investment in Electricity Markets a Market and Model Perspective
8/17
7
It has been assumed that each power plant will produce electrical energy only if spot
price of electrical energy will be higher than short run marginal costs. It is also assumed that
daily fuel price in a specific month is equal to the average monthly price of that month. Full
load hours of each power plant have been calculated comparing production costs with spot
prices. Results are presented on the Picture 1and in the Table 3.
Picture 1. Full load hours of each power plant in a specific year
Table 3. Full load hours for 2006 and 2012
Power plant full load hours
(2006) [h]
full load hours
(2012) [h]
CCGT 4769 3857
OCGT 2233 268
Coal 5963 6289
b)
Contri bution marginis defined as a gross incomeminus variable costsfor each year.
The final value of contribution margins are given in the table below. The whole calculation
can be found in the Excel file.
4769
2233
5963
3860
269
6289
0
1000
2000
3000
4000
5000
6000
7000
2006 2006 2006 2012 2012 2012
CCGT OCGT HC CCGT OCGT HC
Full load hours of each power plant in 2006 and 2012
-
8/11/2019 Investment in Electricity Markets a Market and Model Perspective
9/17
8
Table 4. Total contribution margin of each power plant in every year [/MWh]
2006 2007 2008 2009 2010 2011 2012
CCGT 119490,37 74154,82 154448,85 50203,09 70359,44 60657,11 39153,44
OCGT 51078,86 38304,74 49875,08 11171,92 7467,65 1581,22 4714,84
HC 152341,72 78536,88 146277,02 70356,62 80009,81 86733,62 92704,19
Picture 2. Contribution margin, variable costs and spot price of CCGT power plant in 2006
Picture 3. Contribution margin, variable costs and spot price of CCGT power plant in 2006
0
200
400
600
800
1000
CCGT 2006
MC contribution margin spot price
0
200
400
600
800
1000
OCGT 2006
MC contribution margin spot price
-
8/11/2019 Investment in Electricity Markets a Market and Model Perspective
10/17
9
Picture 4. Contribution margin, variable costs and spot price of HC power plant in 2006
Picture 5. Contribution margin, variable costs and spot price of CCGT power plant in 2012
Picture 6. Contribution margin, variable costs and spot price of OCGT power plant in 2012
0
200
400
600
800
1000
HC 2006
MC contribution margin spot price
0
50
100
150
200
CCGT 2012
Short run marginal cost (MC) Contribution margin Spot price
0
50
100
150
200
OCGT 2012
Short run marginal cost (MC) Contribution margin Spot price
-
8/11/2019 Investment in Electricity Markets a Market and Model Perspective
11/17
10
Picture 7. Contribution margin, variable costs and spot price of HC power plant in 2012
Compari son of contr ibuti on margin and yearly fi x costs
The yearly fix costs consist of operation and maintenance costs (O&M) and the yearly
capital costs (annuity of investment = I). Both components are independent of the actual
production within a year. To calculate the annuities there have been used a discount rate of
5% and the technical life time given in Table 1.
CCGT
Investment costs (I0) = 950 000 /MW
O&M costs (IO&M) = 28 000 /MWa
Calculating the yearly capital costs (annuity of investment = I) we have:
Ccapital costs
= I0*
Where is given by:
where: r = interest rate (5%)
L = lifetime of the power plant (Table 1.)
In this case: L = 35 years and = 0,06
So, we have:
Ccapital costs
= 58 018 /MWa
IO& M= 28 000 /MWa
0
50
100
150
200
HC 2012
Short run marginal cost (MC) Contribution margin Spot price
-
8/11/2019 Investment in Electricity Markets a Market and Model Perspective
12/17
11
Using the same formulas and data from Table 1, we can calculate fix costs for OCGT
and HC power plants:
OCGT
Ccapital costs
= 26 040 /MWa
IO& M= 17 000 /MWa
HC
Ccapital costs
= 96 159 /MWa
IO& M= 36 000 /MWa
Final fix costs can be calculated using formula:
where Tis full load hours (Table 3).
Total fix costs [/MWh] are given in the table below.
Table 5. Fix costs of each power plant according to full load hours
2006 2007 2008 2009 2010 2011 2012
CCGT 18,03691 30,80874 14,75437 21,8764 14,58427 15,891 22,28446
OCGT 19,27452 37,65529 17,06582 45,21008 37,42609 122,9714 160
HC 22,16317 40,94145 23,48658 25,33237 21,07463 19,90047 21,01431
Table 6. Comparison (difference) of contribution margin in each year and yearly fix costs
2006 2007 2008 2009 2010 2011 2012
CCGT 33 472,37 -11863,18 68430.85 -35 814,91 -15658,56 -25360,89 -46864,56
OCGT 8038,86 -4735,26 6835,08 -31868,08 -35572,35 -41458,78 -38325,16
HC 20 182, 72 -53 622,12 14 118,02 -61802,38 -52149,19 -45 425,38 -39 454,81
Looking at the Table 6, it can be seen difference between contribution margin and
yearly costs. As we can see, CCGT power plant is profitable only in 2006. OCGT and HC
power plants are profitable in 2006 and 2008. Summing total money flow in these 7 years, it
can be seen that all three power plants are not profitable1.
If we assume that there are no O&M costs (because power plant does not operate
through the whole year), we get new results shown in the table below:
1If we are calculating with the constant fix costs (investment costs and O&M costs) for each year
-
8/11/2019 Investment in Electricity Markets a Market and Model Perspective
13/17
12
Table 7. Total money flow withouth O&M costs (only contribution marge and investment costs)
2006 2007 2008 2009 2010 2011 2012
CCGT 61 472 16 136 96 430 - 7 815 12 341 2639 -18 865
OCGT 25 038 12 264 23 835 -14 869 -18 573 -24 459 -21 326
HC 56 182 -17 623 50 118 - 25 803 -16 150 -9 426 -3 455
Excluding O&M costs, HC power plant is becoming profitable during these 7 years
(with the welfare of 33 843 ), but CCGT and OCGT power plants are still unprofitable.
Picture 8. Contribution margin and fix costs of CCGT power plant in 2006
Picture 9. Contribution margin and fix costs of OCGT power plant in 2006
0
5
10
15
20
25
30
35
2006 2007 2008 2009 2010 2011 2012
contribution margin and fix costs for CCGT
Contribution margin Fix costs
0
50
100
150
200
2006 2007 2008 2009 2010 2011 2012
contribution margin and fix costs for OCGT
Contribution margin Fix costs
-
8/11/2019 Investment in Electricity Markets a Market and Model Perspective
14/17
13
Picture 10. Contribution margin and fix costs of HC power plant in 2006
c)
If power plants are already built and if we want to go in operation, minimum total
welfare should cover at least investment costs. Because of the non-operating power plant has
more costs than a power plant that operate and cover at least investment costs. But let us
assume that we want to go in operation if all costs (variable costs, investment and O&M
costs) are being covered. Min imum contr ibution margins in th is case should be at least
equal or greater than fi x yearl y costs.
Thinking about the building of new power plant, we must have yearl y contr ibuti on
margin that covers investment and O&M costs. We also must consider the in terest rate.
Making a calculation using the interest rate and Net present value, we will decide to invest in
new power plant if the NPV is higher than 0.
In the year 2012 all power plants are not making any profit. Their looses (L) are:
LCCGT= 18 865 /MW
LOCGT= 21 326 /MW
LHC= 3 455 /MW
But if we decide not to operate with these three power plants in 2012, looses will be
higher because we will not be able to cover investment costs. So, if power plants are shuttled
0
10
20
30
40
50
2006 2007 2008 2009 2010 2011 2012
contribution margin and fix costs for HC
Contribution margin Fix costs
-
8/11/2019 Investment in Electricity Markets a Market and Model Perspective
15/17
14
down in 2012, they will not have any O&M or variable costs but they will have investment
costs for that year:
ICCGT= 58 018 /MW
IOCGT= 26 040 /MW
IHC= 96 159 /MW
These uncovered investment costs are higher than costs that we have during the
operation, so we think it is better for these three power plants to operate during 2012.
Exercise 3.2: Investment model
Scenario analyses of minimal system costs
a)
This part of exercise has been done in the GAMS-code. The result is given in the folder below.
* suggestion: copy this file on the computer and then open it using WordPad orNotePad.
Exercise3_part_a.lst
Solution a). File that constrain solution 3.2.a (Solution and the code can be seen in this file)
b)
Optimal install ed capacity
Accordint to the base scenario, we have determined the optimal capacity of each
power plant. The results are given in the file below.
Exercise_3_b.lst
Ex_3_b_.gms
Solution b). Files that constrain solution 3.2.b
c)
Shadow price at the hour 3 is 42.500/MWhand at the hour 19 is 48.356 /MWh.
Looking at the demand, we can see that in hour 3 it was 640 MWh and in the hour 19it was 1550 MWh. During these two hours we didnt have any electrical energy from the PV
-
8/11/2019 Investment in Electricity Markets a Market and Model Perspective
16/17
15
modules. Wind power plants were producing 210 MWh (at the hour 3) and 150 MWh (at the
hour 19).
Because of the higher demand at the hour 19, we must have higher electricity
production, what means that we have to operate with the more expensive power plants to
cover whole demand during that period (production of an additional MWh determine the price
of the electrical energy (marginal cost)).
Components of this price are production costs (fuel costs, CO2costs and O&M costs).
d)
PV scenar io
Tabela 8. Output of each power plant in 12th hour [MWh]
Output of each power plant [MWh] in 12th
hour
Power plant for PV = 0.2 for PV = 0.4 for PV = 0.6 for PV = 0.8 for PV = 1
HC 600 600 600 480 320
CCGT 360 200 40 0 0
OCGT 0 0 0 0 0
PV 160 320 480 650 800
Wind 100 100 100 100 100
Picture 11. Output of each power plant in 12th hour [MWh]
Increasing the power of PV modules, less amount of energy produced by HC, CCGT
and OCGT is needed. This also effects at the price of electrical energy. As the price of an
additional MWh determines the price of electrical energy, we can conclude that increasing the
PV power, price of electrical energy will be crashed. For example in the case with PV = 0,2
0
100
200
300
400
500
600
700
800
900
PV = 0,2 GW PV = 0,4 GW PV = 0,6 GW PV = 0,8 GW PV = 1 GW
Outpu
tofeachpowerplant[MWh]
Output of each power plant in hour 12
HC
CCGT
OCGT
PV
Wind
-
8/11/2019 Investment in Electricity Markets a Market and Model Perspective
17/17
16
GW, price was determinate by CCGT power plant (because this power plant is the most
expensive operating power plant in this hour). Increasing PV power (case with PV = 1 GW),
CCGT power plant does not operate any more, so the most expensive power plant in this case
is HC power plant which determines the price of electrical energy (energy is now cheaper
than in case with PV = 0,2 GW).
CO2scenar io
Table 9. Price of electrical energy in a specific hour according to the different CO2 price
hour
CO2_p=
0 /tCO2
CO2= 5
/tCO2
CO2= 10
/tCO2
CO2= 15
/tCO2
CO2= 20
/tCO2
CO2= 25
/tCO2
CO2= 30
/tCO2
6 25 29,375 33,75 38,125 42,5 46,875 51,25
12 42,373 44,068 45,763 47,458 49,153 50,847 52,542
19 62,5 65 67,5 70 72,5 75 77,5
Picture 12. Price of electrical energy in a specific hout according to the different CO2 costs
Increasing CO2price, short run marginal costs are also being increased. This effect on
marginal costs (they are getting higher), i.e. it effects on the price of electrical energy (it is
also getting higher).
0
10
20
30
40
50
60
70
80
90
Priceofelectricalenergyinaspecifichour
/MWh
Marginal costs of electrical energy in a specific hour
hour 6
hour 12
hour 19