Hale‘iwa Improvement District Project

58
Hale‘iwa Improvement District Project Hale‘iwa, North Shore, O‘ahu October 10, 2017 Public Informational Meeting Environmental Impact Statement Preparation Notice Waialua Elementary School 67-020 Waialua Beach Road Waialua, HI 96791 Department of Design and Construction City and County of Honolulu

Transcript of Hale‘iwa Improvement District Project

Page 1: Hale‘iwa Improvement District Project

Hale‘iwa Improvement District ProjectHale‘iwa, North Shore, O‘ahu

October 10, 2017

Public Informational MeetingEnvironmental Impact Statement Preparation Notice

Waialua Elementary School67-020 Waialua Beach Road

Waialua, HI 96791

Department of Design and ConstructionCity and County of Honolulu

Page 2: Hale‘iwa Improvement District Project

Meeting Purpose / Desired Outcomes

• Community and landowners understand the alternatives, issues and process.

• Obtain community and landowner input on the ID alternatives and on environmental, social and technical issues for evaluation in the EIS.

• Answer questions about the project, the ID and the EIS process.

2

Page 3: Hale‘iwa Improvement District Project

Introductions

City and County of HonoluluRobert Kroning, P.E., DDC Director Ann Shimatsu, P.E., DDC Project Manager, Civil DivisionBob Sarae, P.E., DDC Civil DivisionHarrison Rue, DPP, Community Building and TOD Administrator

R. M. Towill CorporationJimmy Yamamoto, P.E., Vice PresidentJim Niermann, AICP LEED AP, Principal PlannerGordon Ring, P.E., LEED AP, Principal EngineerMichele Leong, Planner

3

Page 4: Hale‘iwa Improvement District Project

Opening Remarks4

Page 5: Hale‘iwa Improvement District Project

Housekeeping

• Sign-in Sheet

• Meeting Documentation

• Comment Forms & Box

• Refreshments

• Restrooms

5

Page 6: Hale‘iwa Improvement District Project

Meeting Agenda

• Presentation by the Project Team.• Project Update

• Conceptual Alternatives for EIS

• EISPN Comment Period

• Full-group Discussion / Q & A

6

Page 7: Hale‘iwa Improvement District Project

Ground Rules

• Stick to the agenda.

• Save questions for the end. Reference slide #.

• Listen respectfully.

• Respond to ideas and issues, not individuals.

7

Page 8: Hale‘iwa Improvement District Project

Hale‘iwa Improvement District Project Area8

Page 9: Hale‘iwa Improvement District Project

Improvement District

City Council Resolution 09-338, CD11. Walkways2. Landscaping3. Undergrounding Utilities

ROH Chapter 14, Articles 23 to 29Establishes Improvement District Process

9

Page 10: Hale‘iwa Improvement District Project

Improvement District Process

• Costs shared by the City and adjacent landowners.

• Utility companies share a portion of utility costs.

• Basis for cost assessment may include:–Street frontage / lot area–Land use–Type of improvements–Assessed value of property

• The intent is to make it work.

10

Page 11: Hale‘iwa Improvement District Project

Complete Streets Ordinance

• Requires the City to employ a multi-modal approach to roadway projects.

• Goal is to balance needs of pedestrians, bicycles, transit and motor vehicles.

• Requires multi-modal traffic study.

• ROH Section 14-33

11

Page 12: Hale‘iwa Improvement District Project

12

Community Involvement, Agency Consultation

Background ResearchSpecial Studies

Community InterviewsAgency Consultation

Workshops#1 & #2

Prelim. AlternativesMulti‐modal Study

Final EIS Preparation

Design Meetings

Draft EIS

Pre‐Draft EIS Meeting(s) Alternatives Review

Community Involvement / EIS Process

Site Conditions AnalysisEngineering Analysis

Preliminary Design  Concepts

EIS Prep Notice

Draft EIS Meeting(s)Public Review Period 

Pre‐Final EIS MeetingID Alternative Final EIS / ROD

Page 13: Hale‘iwa Improvement District Project

Current Status

• EISPN Comment Period

• Conceptual Alternatives

• Multi-modal Traffic Study – in progress

• Agency Consultation – ongoing

• Special Studies for EIS – ongoing

13

Page 14: Hale‘iwa Improvement District Project

Key Feedback So Far

• Strong support for pedestrian improvements

• Preserve rural character and human scale

• Keep the ID improvements simple

• Preference to keep the road as-is, no left-turn lanes

• No strong preference for overhead vs. underground utilities (except costs)

• Parking – concern over loss of street frontage parking, support for centralized parking

• Concern about ID costs and allocation

• Concern about losing land to the project

• Construction impacts – hard on small businesses

14

Page 15: Hale‘iwa Improvement District Project

Hale‘iwa Improvement District15

Page 16: Hale‘iwa Improvement District Project

16Hale‘iwa Improvement District

Page 17: Hale‘iwa Improvement District Project

Existing Conditions• Two-lane, rural commercial street

• ROW width varies from 30’ to 50’

• No existing walkways except in isolated locations. No bike lanes.

• Buildings located near roadway

• Accustomed street-front parking

• Trees and utilities located near roadway

• Bus service through town – 13 bus stops

• Congested conditions during daytime (visitor traffic, busses)

• 60-foot road widening setback

17

Page 18: Hale‘iwa Improvement District Project

• Low-Speed Road• Drainage – maintain exist. flow pattern• Multi-modal design - improve experience for

pedestrians, bicyclists and transit• Consider Complete Streets features • Dimension Guidelines

– 22’ Roadway– 6’ Walkway (8’ at bus stops and commercial core)– 5’ Bike lane (If Provided)– 4’ Buffer for landscaping, drainage and furniture

• Overhead and Underground Utilities

Design Criteria18

Page 19: Hale‘iwa Improvement District Project

• Conceptual Alternatives– Alt 1 – 65’-69’ ROW– Alt 2 – 42’ ROW– Alt 3 – 52’ to 56’

• Complete Streets Treatments– Raised Crosswalk– Bike Lanes– Furniture zone / buffer– Traffic Circles

• Parking – perpendicular, parallel, angled

19Design Summary

Page 20: Hale‘iwa Improvement District Project

20Typical Road Sections65’ to 69’ ROW

Dimensions may be modified in final design.

Page 21: Hale‘iwa Improvement District Project

21Typical Road Sections42’ ROW

Dimensions may be modified in final design.

Page 22: Hale‘iwa Improvement District Project

22Typical Road Sections52’ to 56’ ROW

Dimensions may be modified in final design.

Page 23: Hale‘iwa Improvement District Project

Alternative 1: 65’ to 69’ ROW 23

Page 24: Hale‘iwa Improvement District Project

Alternative 1: 65’ to 69’ ROW 24

Page 25: Hale‘iwa Improvement District Project

25Alternative 2: 42’ ROW

Page 26: Hale‘iwa Improvement District Project

26Alternative 2: 42’ ROW

Page 27: Hale‘iwa Improvement District Project

27Alternative 3: 52’ to 56’ ROW

Page 28: Hale‘iwa Improvement District Project

28Alternative 3: 52’ to 56’ ROW

Page 29: Hale‘iwa Improvement District Project

Complete Streets• The City is required by ordinance to consider

complete streets principles in transportation project planning

• Improves mobility for all street users.

• Good for business.

• Features that might work in Hale‘iwa:– Bicycle Facilities– Raised Crosswalks– Furniture Zone / Buffer– Parklets– Traffic Circles

29

Page 30: Hale‘iwa Improvement District Project

Bicycle Facilities

• 5-ft. wide bike lane, separated from walkway

• Sharrows – share the travel lane with motor vehicles

• Improve bicycling convenience and comfort to encourage less reliance on motor vehicles

• Connect to regional bike path system

• Equitable access for kids, teens, workers

30

Page 31: Hale‘iwa Improvement District Project

Bicycle Facilities31

Page 32: Hale‘iwa Improvement District Project

Raised Crosswalks

• Table-top crosswalk across travel lane.

• Raised intersection.

• Provides traffic calming (speed table).

• Improves visibility for drivers and pedestrians.

• Creates landmark.

32

Page 33: Hale‘iwa Improvement District Project

Raised Crosswalks33

Page 34: Hale‘iwa Improvement District Project

Furniture Zone / Buffer

• 4-foot wide area to provide separation from travel way and pedestrian walkway.

• Used for:– Landscaping – Drainage– Utilities– Street Furniture (benches, signs, trash cans)

34

Page 35: Hale‘iwa Improvement District Project

Furniture Zone / Buffer35

Page 36: Hale‘iwa Improvement District Project

Furniture Zone / Buffer36

Page 37: Hale‘iwa Improvement District Project

Furniture Zone / Buffer37

Page 38: Hale‘iwa Improvement District Project

Parklet

• Parklet– Seating, landscape features, shade/shelter.– Provides social/respite space, creates a

landmark.– Can be customized to fit into available space,

minimizing impacts to the adjacent area.

38

Page 39: Hale‘iwa Improvement District Project

39

Parklet

Page 40: Hale‘iwa Improvement District Project

40

Parklet

Page 41: Hale‘iwa Improvement District Project

Traffic Circles

• Eliminates stop-control, allows continuous flow.• Alternative to left turn lanes.• Allows cars to make a U-turn instead of left turns.• Improves motor vehicle movement and

pedestrian access into adjacent properties.• Minimizes turn conflicts.• Creates a landmark/entry feature.

41

Page 42: Hale‘iwa Improvement District Project

Traffic Circles – Hale`iwa Road42

Page 43: Hale‘iwa Improvement District Project

Traffic Circles – Hale`iwa Road43

Page 44: Hale‘iwa Improvement District Project

Parking

• Space availability – ROW, physical constraints.• Safety / integration of parking with walkway

design. • Convenience / business needs (customers,

loading, deliveries).• Design:

– Perpendicular– Parallel– Angled

44

Page 45: Hale‘iwa Improvement District Project

Parking45

Page 46: Hale‘iwa Improvement District Project

Parking46

Street frontage parking: Parallel parking.

Pā‘ia, Maui Makawao, Maui

Page 47: Hale‘iwa Improvement District Project

Parking47

Street frontage parking: angled parking.

San Francisco, CA Makawao, Maui

Reverse angle “safety” parking Nose-in angle parking

Page 48: Hale‘iwa Improvement District Project

48

• 13 Bus stops – create breaks in traffic that facilitate left turns and pedestrian crossings.

• 3 bus stops are candidates for removal due to low ridership and proximity to adjacent bus stops.

B B

BB B

BB

BB B

BB

B

Bus Stops

Page 49: Hale‘iwa Improvement District Project

Alternatives Cost Comparison49

• Cost categories:– Construction mobilization/demobilization– Demolition– Utility Relocation – electrical/telcom, water, lighting– Paving, Concrete Walkways & Driveways– Drainage improvements– Landscaping and street furnishings– Land acquisition– Tie-in to property frontage– Building retrofit

Page 50: Hale‘iwa Improvement District Project

Order of magnitude costs (subject to change pending design):Alternatives Cost Comparison

50

Cost Category Alternative 1 Alternative 2 Alternative 3

Construction Mob, Traffic Control $3,250,000 $1,710,000 $2,375,000Travel way Construction $5,650,000 $1,500,000 $1,500,000Bike Lane Construction $1,120,000 $0 $1,120,000Walkway Construction $3,030,000 $2,440,000 $2,590,000Furniture Zone – landscaping & features $600,000 $300,000 $300,000Utility Relocation $4,340,000 $1,990,000 $2,530,000Drainage Improvements $6,425,000 $2,560,000 $3,000,000Contingency (20%) $4,885,000 $2,100,000 $2,685,000

Total $29,300,000 $12,600,000 $16,100,000

Does not include costs for:• Land / Easement Acquisition• Building Upgrades / Retrofit• Tie-ins to existing property frontageUndergrounding Electrical cost estimate = $14,200,000Traffic Circle cost estimate = $600,000 (excluding land acquisition and

property adjustments)

Page 51: Hale‘iwa Improvement District Project

Basis for ID Cost Allocation51

• Street frontage / lot area• Land use / zoning• Type of improvements• Value of existing, impacted improvements• Assessed market value of property• Utility company cost-share

Page 52: Hale‘iwa Improvement District Project

Project Schedule52

Complete Project Alternative Designs for Inclusion in EIS

Summer 2018

Complete EIS Summer 2019

Complete Preliminary ID Report Fall 2020

Council Action on the Preliminary ID Report

2021

Key Project Milestones:

Page 53: Hale‘iwa Improvement District Project

Q & A

• Listen respectfully.• Respond to ideas and issues, not

individuals• One person speaks at a time.• Allow everyone to speak once before

speaking a second time.• Keep comments and discussion concise

and to the point.

53

Page 54: Hale‘iwa Improvement District Project

Q & A54

Page 55: Hale‘iwa Improvement District Project

What’s Next?

• EISPN Comment Period – October 23, 2017• Finalize multi-modal study and alternatives.• Prepare Draft EIS for publication Fall 2018.• Work with City agencies to review alternatives.• Next community meeting summer 2018.

55

Page 56: Hale‘iwa Improvement District Project

EISPN Comments Due:October 23, 2017

Ms. Ann Shimatsu, P.E., Project ManagerDepartment of Design and Construction

City and County of Honolulu650 South King Street, 15th Floor

Honolulu, HI 96813

56

Page 57: Hale‘iwa Improvement District Project

Contact:

James Niermann, AICP, LEED APPlanning Project Coordinator

Email: [email protected]

Phone: (808) 842-1133

R. M. Towill Corporation2024 North King Street Suite 200

Honolulu, Hawaii 96819

57

Page 58: Hale‘iwa Improvement District Project

MAHALO

Department of Design and ConstructionCity and County of Honolulu