Guidelines for Battery Electric Vehicles in the … Guidelines for Battery Electric Vehicles in the...
Transcript of Guidelines for Battery Electric Vehicles in the … Guidelines for Battery Electric Vehicles in the...
www.cmic-ccim.org
Guidelines for Battery Electric Vehicles
in the Underground - Mine Design
April 30th, 2017
Presented By: Alain Richard Cheryl Allen
Electrical Engineer Principal Engineer – Ventilation
BESTECH Vale Ontario Operations
www.cmic-ccim.org
Introduction
• Alain Richard– 6 years with BESTECH– Power System Studies
– Feasibility Study
– Ventilation Control System
Studies
– Electrical Design on the
Onaping Depth project
• Cheryl Allen– 30+ years in mining
– 16 years with Vale
– Mining Engineer
– Ventilation Design
– Research Studies
– BEV for Sudbury mine
projects
www.cmic-ccim.org
Agenda
• Introduction and Intent
• Mine Layout and Infrastructure
• Personnel Movement
• Other Electric Equipment
• Charging Infrastructure
• Ventilation and Cooling
www.cmic-ccim.org
Introduction and Intent
• First assumption: BEV mines will be different
than diesel mines
• Second assumption: Greenfield and brownfield
mines have different opportunities to
incorporate BEVs
• Intent: This is not a mine design 101 but rather
points to ponder when designing a BEV mine
www.cmic-ccim.org
Mine Layout and Infrastructure
• Anticipated challenges to address:– Range limitation on a single charge
– Emerging technology (depending on the vehicle size)
– Different design questions/requirements
– Changing perspective of mine owners, operators and
designers
– Shift in maintenance resources
www.cmic-ccim.org
Ore/Waste Handing System (OWHS)
• OWHS large energy consumer
• Multiple design trade-offs required
• Need to ensure BEVs do not have a negative
impact on the OWHS
• Impact of downhill haulage
• Impact of uphill haulage
www.cmic-ccim.org
Regenerative Braking – the good
• Diesel vehicles convert all kinetic energy into heat
• With BEV it is possible to convert some of the kinetic energy back into electric energy while generating some heat
• Potential advantage:– Longer BEV range – Smaller Batteries
– Higher efficiency – Reduced heat production
www.cmic-ccim.org
Regenerative Braking – the bad
• Dis-advantage:– Need proper planning and/or vehicle design to
prevent overcharging
– Might need braking resistor and/or regular brake
system
– Mine design may reduce full potential from
regenerative braking• Ex. Brownfield mine
– Experience is required to fully understand the
potential
www.cmic-ccim.org
Vehicle Parking
• Typically not a constraint in the design for a
diesel fleet
• With BEV, parking will be based on the charging
strategy and needs to be carefully laid out
• Change in workforce culture
www.cmic-ccim.org
Vehicle Parking
• A mine monitoring system would ideally track
the location and status of every BEV throughout
the day
• Need to remove the chance of a worker starting
a shift with a discharged battery
www.cmic-ccim.org
Personnel Movement
• Whether the mine is shaft access or portal
access, changing to BEV needs to consider not
just the movement of ore/waste, but also of
people.
www.cmic-ccim.org
Shaft Access
• Near shaft parking– Access vehicles via walking
– Requires sufficient parking locations and chargers
near shaft
• Mining level parking– Such as Jumbo, Bolter…
– Need to transport workers to vehicles
www.cmic-ccim.org
Shaft Access
• Personnel carriers – Access personnel carriers via walking
– Transport workers to the mining levels or distributed
parking locations
• Combination– Find the best balance for the application
www.cmic-ccim.org
Ramp Access
• Group travelling is strongly encouraged– Increase efficiency of travel
• Long uphill travels -> very demanding on
batteries
• Long downhill travels -> could be problematic
with regenerative braking
www.cmic-ccim.org
Equipment Groups
• Charge-while operating equipment group
(Tethered)
• Load Haul Dump (LHD) Machines
• Alternate haulage methods
• Auxiliary Vehicles
www.cmic-ccim.org
Tethered Equipment
• Vehicles that are typically plugged into AC power while performing work– Bolters– Scalers– Jumbos…
• Move with diesel or battery power
• Charging via AC cables– Similar to some residential BEVs– Smaller battery
www.cmic-ccim.org
Tethered Equipment
• Without an on-board charger– Ensure charger access
– Potentially more chargers required
– Larger battery
• Key to review the duty cycle of the battery
www.cmic-ccim.org
Other Electric Equipment
• Load Haul Dump (LHD) Machines– Mine-level grades, charging philosophy, fully tethered,
hybrid-powered, inductive charging, trolley-assist
charging
• Alternate haulage methods– Conveyors, electric-powered trains, trolleys,
monorails, RailVeyorTM and continuous haulage
systems
www.cmic-ccim.org
Charging Infrastructure
• Production is dependent on capacity to have
fully charged batteries
• Dependable charging infrastructure that fit for
purpose
www.cmic-ccim.org
Design Prerequisites
• Questions to ponder:– Shifts per day?
– Duration per shift?
– Equipment expectation?
– Equipment capacity?
– Number of chargers?
– Types of chargers?
– Opportunity charging?
– Charging philosophy
– Special needs? • Ex. grader
www.cmic-ccim.org
Charging Methods
• Simplified view of charging methods:
If battery running time > shift length -> shift-change charging
If battery running time ~ shift length -> shift-change charging + opportunity charging
If battery running time < shift length -> battery swapping or in-shift charging
• In reality, other factors will come into play and
affect the charging method
www.cmic-ccim.org
Charger Diversity
• Spectrum of possible scenarios– Dedicated charger per equipment
– Limited to a few types of chargers
– One size fits all
• To balance a successful implementation and
prevent limiting innovation, a few types of
chargers will likely be required for each mine
www.cmic-ccim.org
Opportunity Charging
• Scenario 1:
• Opportunity: 2×30 min. lunch break
+ 6×10 min. bio break = 2 h/day
• Typical shift-change: 2×2h = 4 h/day
– Conclusion:
• A dedicated opportunity charger would have half
the utilization than a shift-change charger
www.cmic-ccim.org
Opportunity Charging
• Scenario 2, staggered lunch breaks, dual purpose
chargers
• Opportunity: 4×30 min. lunch break
+ 6×10 min. bio break + 4h = 7 h/day
• Typical shift-change: 2×2h = 4 h/day
– Conclusion:
• A shared charger could have nearly double the
utilization than strictly a shift-change charger
www.cmic-ccim.org
Opportunity Charging
• Scenario 1, 50kW charger & 100kW battery
• 30 min. lunch = 25kW or 25% of charge
• Shift-change: 2h = 100kW or 100% of charge
– Conclusion:
• Interesting option to top-up the battery
www.cmic-ccim.org
Opportunity Charging
• Scenario 2, 100kW charger & 100kW battery
• 30 min. lunch = 50kW or 50% of charge
• Shift-change: 2h = 100kW or 100% of charge
– Conclusion:
• Interesting option to reduce battery size
• Can reduce “range anxiety”
www.cmic-ccim.org
Charging Stations
• Located near equipment; as recommended by
the OEMs
• For Mine Engineers, chargers can be viewed as
variable frequency drives
• Need to control:– Dust – Humidity – Heat
– Vibration – Percussion blast – Water
www.cmic-ccim.org
Swap-out Stations
• Goal of a swap-out station is to provide a full
charge in a short amount of time -> similar to
diesel re-fueling
• Proper planning of vehicle traffic is key to
prevent congestion
www.cmic-ccim.org
Swap-out Station Design
• Size of facility
• Crane system to remove and install batteries
– Must be compatible with all BEV types that use the
system
• Sufficient chargers in proximity
• Sufficient spare batteries
• Potential rockmass quality issues due to size of
excavation
www.cmic-ccim.org
Power Distribution Considerations
• Incoming voltage is typically 480-1,000V, 3 phase
• Typically have an isolating transformer
• Harmonic producing device
• Need to consider upstream transformer sizing:– Large enough to address the harmonics
– Prevent oversize due to the low utilization rate of
chargers, especially if using shift-change charging
www.cmic-ccim.org
Ventilation and Cooling
• Iterative approach between mine and ventilation
engineers
• Criteria to base the Ventilation design for BEVs– Temperature, dust, air velocity, clear blast gases
– Mine life, production profile, OWHS…
• Some differences:– No need to dilute diesel particulate
– Heat sources
www.cmic-ccim.org
Regulations
• Air quality is typically regulated by various
agencies:– Federal and local regulations
– Internal mining company standards
• The mine air volumes will be influenced by the
regulatory requirements
www.cmic-ccim.org
Equipment Fleet
• Need to know:– Quantity of each type of equipment
– Power rating for each type of equipment
– Anticipated utilization
• Need to work with manufacturers to determine
the heat generation
www.cmic-ccim.org
Heat Load
• Need to consider all heat sources:– All electrical equipment, including:
• Mine power centres, transformers, motors, VFD, chargers…
– Mobile equipment• Including batteries
– Auto compression
– Wall rock
– Any other sources
www.cmic-ccim.org
Heat Load – Chargers
• Typical heat losses from charging equipment are
5-10%, but should be obtained from vendors
• Depending on placement of chargers, hot spots
might be created in the mine– 1x50kW charger, rated 5% losses, operating will
generate 2.5kW of heat, which can easily be dealt with
– 4x400kW chargers, rated 10% losses, will generate
160kW of heat, which may be challenging to dissipate
www.cmic-ccim.org
Dust Control
• Reduced air volumes may not be sufficient to
remove dust contaminants, depending on
velocities
• Needs to be reviewed and may limit air volume
reductions
• Drift sizes, air volume and localized air
recirculation may need to be reconsidered
www.cmic-ccim.org
Blast Gas Clearing
• Time required depends on the air speed
• With a reduced airflow requirement, the time
required may become longer than desired
• Important to review the clearing times during
the design stage
• Considerations for capacity to increase airflow
duing blast clearing– VFD, louvers, automated ventilation control system
www.cmic-ccim.org
Air Monitoring
• Determine the real-time monitoring
requirements
• Place instruments accordingly
• Consider maintenance and access to the
equipment
• Typical sensors include:– Carbon monoxide, sulfur dioxide, nitrogen oxides,
dry-bulb temperature, humidity, air volume
• Dust is not commonly measured in real-time
www.cmic-ccim.org
Controlled Recirculation
• Typically limited due to the safety and health
implications in diesel mines
• BEV presents an opportunity to use controlled
full or partial recirculation
• If recirculation is part of the design, sufficient
fixed monitoring is required to ensure regulatory
compliance of air quality
www.cmic-ccim.org
Safety
• High level risk
assessment is
recommended to
understand the total
mine design risk with
BEV
• More detailed
assessments for critical
risks identified
• Include items such as:– Safety training
– Noise
– Power and voltage
– Air quality
– Heat
– Fire
– Geotechnical
www.cmic-ccim.org
Mine Design Conclusion
• Designing a BEV mine
offer multiple
opportunities
• Need to understand
the topics to be
explored and reviewed
prior to
implementation– Both greenfield and
brownfield mines
• BEV mine designers
need to ask themselves
new questions during
the design process of a
battery mine
www.cmic-ccim.org
Questions?
Thank you / Merci
Alain Richard Cheryl Allen
[email protected] [email protected]
705-675-7720 ext. 283 705-682-6857