Grid Island

download Grid Island

of 27

Transcript of Grid Island

  • 8/11/2019 Grid Island

    1/27

    Power Research & Development Consultants Pvt. Ltd.1

    Application of Electrical Transient

    Studies to Enhance the Success Rateof Grid Islanding

    R. Nagaraja

    Power Research & Development Consultants Pvt. Ltd.

    No. 4, Ist B Main, Ist N Block,

    Rajajinagar

    Bangalore560012

  • 8/11/2019 Grid Island

    2/27

    Power Research & Development Consultants Pvt. Ltd.2

    Major mind boggling problem in the industrial system -

    How quickly the faults can be isolated without affecting the

    production.

    Grid synchronization is essential for process industries with CPP

    What is the success rate of getting islanded from the grid for

    major disturbances in the grid

    Addresses the issues in grid islanding

    How to incorporate state of the art numerical relays to enhance

    the success rate of grid islanding.

    Introduction

  • 8/11/2019 Grid Island

    3/27

    Power Research & Development Consultants Pvt. Ltd.3

    Liberalization and de-regulation in the power sector

    more and more industries setting up the captive power plants.

    Why grid connection?

    Operation becomes impossible without the grid support for

    varying and bulk loads

    One more source of power supply for system emergencies

    Third party power transfer

    Introduction

  • 8/11/2019 Grid Island

    4/27

    Power Research & Development Consultants Pvt. Ltd.4

    Application of state of the art numerical relays in the

    industrial system - Grid islanding has been more simplified

    Setting calculations of the relays are very important to have

    maximum success rate of islanding.

    The success rate of grid islanding -

    Following the grid disturbance the islanding should occur only if

    the grid could not survive.

    After the islanding all the generators within the plant should

    survive

    There should not be any un-called tripping in the plant

    Introduction

  • 8/11/2019 Grid Island

    5/27

    Power Research & Development Consultants Pvt. Ltd.5

    The presentation addresses the following issues

    System behaviour during different types of disturbances

    The application of numerical relays to track the system

    disturbance

    Arriving at proper relay settings based on simulation studies

    Post islanding measures to minimize the production loss

    Maximization of the pyramid like functions of the numerical

    relay i.e. protection, monitoring and control.

    Introduction

  • 8/11/2019 Grid Island

    6/27

    Power Research & Development Consultants Pvt. Ltd.6

    Grid Islanding

    Grid islanding scheme

    Single or a set of protective relays

    Connected at the islanding bus

    Will sense the disturbance in the grid

    Trip command is issued to the islanding breaker whenever the

    grid disturbance exceeds a set limit.

    By opening the islanding breaker, the CPP and CPP side loads

    are isolated from the grid.

  • 8/11/2019 Grid Island

    7/27

    Power Research & Development Consultants Pvt. Ltd.7

    Grid Islanding

    The load on the grid side will survive if the grid survives

    If the grid is not surviving following the disturbance, only part

    of the plant load on the grid side gets affected.

    The process of disconnecting the CPP from the utility system iscalled islanding of the CPP.

    Grid islanding scheme helps both the utility as well as the CPP.

  • 8/11/2019 Grid Island

    8/27

    Power Research & Development Consultants Pvt. Ltd.8

    Grid IslandingBenefits to Utility

    The utility, which has the responsibility to maintain the grid,normally do not want an additional independent power source

    (CPP) in their grid network, when the grid is disturbed.

    Since the power source is not in their control, it will complicate

    utilitys methods of dealing with the disturbed grid.

    While the utility is in the process of solving the grid

    disturbance, they do not like to have another power source

    which they do not control and which may add to thedisturbance.

  • 8/11/2019 Grid Island

    9/27

    Power Research & Development Consultants Pvt. Ltd.9

    Grid IslandingBenefits to Utility

    Once the CPP is disconnected from the grid, it becomes easier

    for the utility to locate the source of disturbance and rectify the

    same.

    The main idea is that the utility eliminates the possibility of theCPP feeding the disturbance.

    Hence the utility will insist on installing the Grid islanding

    scheme in the CPPs premises, before allowing the CPP to beconnected to grid.

  • 8/11/2019 Grid Island

    10/27

  • 8/11/2019 Grid Island

    11/27

    Power Research & Development Consultants Pvt. Ltd.11

    Grid IslandingBenefits to CPP

    It is strongly advisable to disconnect the CPP from the grid, when the grid is

    disturbed.

    The main reason is that the DG or the TG of CPP may get damaged due to

    grid disturbances resulting in heavy repair costs and shut downs.

    It is necessary to protect the CPP generators from grid disturbances.

    It is also better to disconnect the CPP units from utility whenever the utility

    fails, by opening the islanding breaker.

    If not, the CPP which is running will experience a severe jolt when theutility power comes back. This will cause extreme damage to CPP

    generators.

  • 8/11/2019 Grid Island

    12/27

    Power Research & Development Consultants Pvt. Ltd.12

    What are grid disturbances?

    A grid is said to be disturbed when

    there is an under voltage (U/V)there is over voltage (O/V)

    there is under frequency (U/F)

    there is over frequency (O/F)

    there is a rapid fall or rise in frequency

    ( +dF/dT ordF/dT )there is a power failure in the grid

    there is a fault in the grid

    there is vectorial shift in the voltage

  • 8/11/2019 Grid Island

    13/27

    Power Research & Development Consultants Pvt. Ltd.13

    -1.5

    0Volts

    T

    Voltage Vector Jump:

    Advantages

    Can operate more quickly than voltage/frequency protection

    Secure for single phase faults

    Applicable to conventional DGs

    Disadvantages

    Can be difficult to set

    Fails when P+jQ = 0

  • 8/11/2019 Grid Island

    14/27

    Power Research & Development Consultants Pvt. Ltd.14

    What are grid disturbances effect?

    It may happen that the CPP may experience a large variation in

    the power at the islanding breaker which is not within the

    acceptable limits.

    Continued low voltage of the grid will result in the operation ofCPP generators at low power factor.

    If compelled to work with low PF, the CPP generators will

    experience a reverse reactive power flow and this can damagethe generators.

  • 8/11/2019 Grid Island

    15/27

    Power Research & Development Consultants Pvt. Ltd.15

    How the relay operates?

    An over loaded grid will give rise to fall in frequency.

    A fault in the grid will give rise to fall in voltage.

    Loss of grid will result in sudden change in power at theislanding breaker.

    Loss of grid will also result in sudden change or vectorial shift

    in the voltage

    It is possible to detect each of the above symptoms by single

    numerical relay.

  • 8/11/2019 Grid Island

    16/27

    Power Research & Development Consultants Pvt. Ltd.16

    What else required at CPP?

    Pref

    Droop

    Wref

    +

    +

    +

    -W

    Chang over facility from constant power mode

    to constant frequency mode on grid islanding

  • 8/11/2019 Grid Island

    17/27

    Power Research & Development Consultants Pvt. Ltd.17

    Modes of operation : 2 MW deficit

    TG 2

    Grid

    Transformer

    Islanding

    Breaker

    CPP side load 13 MW

    12 MW

    import

    DGTG 1

    2 MW 4 MW5 MW

    Grid side load 10 MW

    2 MW

  • 8/11/2019 Grid Island

    18/27

    Power Research & Development Consultants Pvt. Ltd.18

    Load shedding logic

    < Set value

    CPP side sudden generation

    loading margin

    +

    -

    Grid to CPP

    side flow

    AND

    1

    Islanding breaker trip

    1

    Output of load

    management software

    Trip non essential loads

  • 8/11/2019 Grid Island

    19/27

    Power Research & Development Consultants Pvt. Ltd.19

    Modes of operation : 2 MW excess

    TG 2

    Grid

    GridTransformers ( 3 numbers)

    Islanding

    Breaker

    CPP side load

    13 MW

    12 MW

    import

    DGTG 1

    3 MW 5 MW7 MW

    Grid side load10 MW

    2 MW

  • 8/11/2019 Grid Island

    20/27

    Power Research & Development Consultants Pvt. Ltd.20

    System Considered for Simulation

    Sl no

    Description Values

    1. Grid/Source data 70 kV, 50 Hz system, 1000 MVA fault level,

    Inertia constant of 100 sec. on 100 MVA base

    2. Grid transformers 3 numbers of 70/6 kV, 7.5 MVA, 9% impedance

    3. Grid side load 10 MW at 0.85 pf

    4. CPP side load 13 MW at 0.85 pf

    5. Diesel generators 5/6 numbers, 6 kV, 1200 kW, 0.8 pf.

    6. Turbo generator 1 1 number, 6 kV, 4000 kW, 0.8 pf, back pressure

    7. Turbo generator 2 1 number, 6 kV, 6000 kW, 0.8 pf, back pressure

    8. CPP side load

    priority

    11 MW essential, 2 MW non essential

    9. Grid side load

    priority

    6 MW essential, 4 MW non essential.

    http://localhost/var/www/apps/conversion/tmp/instructor/island_paper.guihttp://localhost/var/www/apps/conversion/tmp/instructor/island_paper.gui
  • 8/11/2019 Grid Island

    21/27

    Power Research & Development Consultants Pvt. Ltd.21

    Loss of grid

    Loss of grid results in sudden shift in the voltage vector and hencea vector shift relay best suits the logic to find the loss of grid.

    The relay operation is instantaneous in nature and hence should

    not operate for momentary grid faults.

    Phase angle shift obtained at 6 kV bus of grid side for

    A. Loss of grid5 degrees

    B. Three phase fault in 70 kV2 degreesC. Three phase fault in 6 kV system - 0.2 degree

    Recommended voltage vector shift relay setting is 5 degrees.

  • 8/11/2019 Grid Island

    22/27

    Power Research & Development Consultants Pvt. Ltd.22

    Loss of grid

    In the absence of the vector shift relay, df/dt relay in conjunctionwith under frequency relay can be used.

    As frequency relay time setting has to be with a time delay,

    chances of successful islanding will not be 100%, as some of the

    drive auxiliaries and power plant auxiliaries may trip.

    Following the islanding, the non essential load of 2 MW on the

    CPP side is tripped immediately using the load manager software

    based on the logic that further cushion is not available.

    In the absence of the load manager software, the load will be

    tripped with further time delay.

  • 8/11/2019 Grid Island

    23/27

  • 8/11/2019 Grid Island

    24/27

    Power Research & Development Consultants Pvt. Ltd.24

  • 8/11/2019 Grid Island

    25/27

  • 8/11/2019 Grid Island

    26/27

    Power Research & Development Consultants Pvt. Ltd.26

  • 8/11/2019 Grid Island

    27/27