Grid Island
Transcript of Grid Island
-
8/11/2019 Grid Island
1/27
Power Research & Development Consultants Pvt. Ltd.1
Application of Electrical Transient
Studies to Enhance the Success Rateof Grid Islanding
R. Nagaraja
Power Research & Development Consultants Pvt. Ltd.
No. 4, Ist B Main, Ist N Block,
Rajajinagar
Bangalore560012
-
8/11/2019 Grid Island
2/27
Power Research & Development Consultants Pvt. Ltd.2
Major mind boggling problem in the industrial system -
How quickly the faults can be isolated without affecting the
production.
Grid synchronization is essential for process industries with CPP
What is the success rate of getting islanded from the grid for
major disturbances in the grid
Addresses the issues in grid islanding
How to incorporate state of the art numerical relays to enhance
the success rate of grid islanding.
Introduction
-
8/11/2019 Grid Island
3/27
Power Research & Development Consultants Pvt. Ltd.3
Liberalization and de-regulation in the power sector
more and more industries setting up the captive power plants.
Why grid connection?
Operation becomes impossible without the grid support for
varying and bulk loads
One more source of power supply for system emergencies
Third party power transfer
Introduction
-
8/11/2019 Grid Island
4/27
Power Research & Development Consultants Pvt. Ltd.4
Application of state of the art numerical relays in the
industrial system - Grid islanding has been more simplified
Setting calculations of the relays are very important to have
maximum success rate of islanding.
The success rate of grid islanding -
Following the grid disturbance the islanding should occur only if
the grid could not survive.
After the islanding all the generators within the plant should
survive
There should not be any un-called tripping in the plant
Introduction
-
8/11/2019 Grid Island
5/27
Power Research & Development Consultants Pvt. Ltd.5
The presentation addresses the following issues
System behaviour during different types of disturbances
The application of numerical relays to track the system
disturbance
Arriving at proper relay settings based on simulation studies
Post islanding measures to minimize the production loss
Maximization of the pyramid like functions of the numerical
relay i.e. protection, monitoring and control.
Introduction
-
8/11/2019 Grid Island
6/27
Power Research & Development Consultants Pvt. Ltd.6
Grid Islanding
Grid islanding scheme
Single or a set of protective relays
Connected at the islanding bus
Will sense the disturbance in the grid
Trip command is issued to the islanding breaker whenever the
grid disturbance exceeds a set limit.
By opening the islanding breaker, the CPP and CPP side loads
are isolated from the grid.
-
8/11/2019 Grid Island
7/27
Power Research & Development Consultants Pvt. Ltd.7
Grid Islanding
The load on the grid side will survive if the grid survives
If the grid is not surviving following the disturbance, only part
of the plant load on the grid side gets affected.
The process of disconnecting the CPP from the utility system iscalled islanding of the CPP.
Grid islanding scheme helps both the utility as well as the CPP.
-
8/11/2019 Grid Island
8/27
Power Research & Development Consultants Pvt. Ltd.8
Grid IslandingBenefits to Utility
The utility, which has the responsibility to maintain the grid,normally do not want an additional independent power source
(CPP) in their grid network, when the grid is disturbed.
Since the power source is not in their control, it will complicate
utilitys methods of dealing with the disturbed grid.
While the utility is in the process of solving the grid
disturbance, they do not like to have another power source
which they do not control and which may add to thedisturbance.
-
8/11/2019 Grid Island
9/27
Power Research & Development Consultants Pvt. Ltd.9
Grid IslandingBenefits to Utility
Once the CPP is disconnected from the grid, it becomes easier
for the utility to locate the source of disturbance and rectify the
same.
The main idea is that the utility eliminates the possibility of theCPP feeding the disturbance.
Hence the utility will insist on installing the Grid islanding
scheme in the CPPs premises, before allowing the CPP to beconnected to grid.
-
8/11/2019 Grid Island
10/27
-
8/11/2019 Grid Island
11/27
Power Research & Development Consultants Pvt. Ltd.11
Grid IslandingBenefits to CPP
It is strongly advisable to disconnect the CPP from the grid, when the grid is
disturbed.
The main reason is that the DG or the TG of CPP may get damaged due to
grid disturbances resulting in heavy repair costs and shut downs.
It is necessary to protect the CPP generators from grid disturbances.
It is also better to disconnect the CPP units from utility whenever the utility
fails, by opening the islanding breaker.
If not, the CPP which is running will experience a severe jolt when theutility power comes back. This will cause extreme damage to CPP
generators.
-
8/11/2019 Grid Island
12/27
Power Research & Development Consultants Pvt. Ltd.12
What are grid disturbances?
A grid is said to be disturbed when
there is an under voltage (U/V)there is over voltage (O/V)
there is under frequency (U/F)
there is over frequency (O/F)
there is a rapid fall or rise in frequency
( +dF/dT ordF/dT )there is a power failure in the grid
there is a fault in the grid
there is vectorial shift in the voltage
-
8/11/2019 Grid Island
13/27
Power Research & Development Consultants Pvt. Ltd.13
-1.5
0Volts
T
Voltage Vector Jump:
Advantages
Can operate more quickly than voltage/frequency protection
Secure for single phase faults
Applicable to conventional DGs
Disadvantages
Can be difficult to set
Fails when P+jQ = 0
-
8/11/2019 Grid Island
14/27
Power Research & Development Consultants Pvt. Ltd.14
What are grid disturbances effect?
It may happen that the CPP may experience a large variation in
the power at the islanding breaker which is not within the
acceptable limits.
Continued low voltage of the grid will result in the operation ofCPP generators at low power factor.
If compelled to work with low PF, the CPP generators will
experience a reverse reactive power flow and this can damagethe generators.
-
8/11/2019 Grid Island
15/27
Power Research & Development Consultants Pvt. Ltd.15
How the relay operates?
An over loaded grid will give rise to fall in frequency.
A fault in the grid will give rise to fall in voltage.
Loss of grid will result in sudden change in power at theislanding breaker.
Loss of grid will also result in sudden change or vectorial shift
in the voltage
It is possible to detect each of the above symptoms by single
numerical relay.
-
8/11/2019 Grid Island
16/27
Power Research & Development Consultants Pvt. Ltd.16
What else required at CPP?
Pref
Droop
Wref
+
+
+
-W
Chang over facility from constant power mode
to constant frequency mode on grid islanding
-
8/11/2019 Grid Island
17/27
Power Research & Development Consultants Pvt. Ltd.17
Modes of operation : 2 MW deficit
TG 2
Grid
Transformer
Islanding
Breaker
CPP side load 13 MW
12 MW
import
DGTG 1
2 MW 4 MW5 MW
Grid side load 10 MW
2 MW
-
8/11/2019 Grid Island
18/27
Power Research & Development Consultants Pvt. Ltd.18
Load shedding logic
< Set value
CPP side sudden generation
loading margin
+
-
Grid to CPP
side flow
AND
1
Islanding breaker trip
1
Output of load
management software
Trip non essential loads
-
8/11/2019 Grid Island
19/27
Power Research & Development Consultants Pvt. Ltd.19
Modes of operation : 2 MW excess
TG 2
Grid
GridTransformers ( 3 numbers)
Islanding
Breaker
CPP side load
13 MW
12 MW
import
DGTG 1
3 MW 5 MW7 MW
Grid side load10 MW
2 MW
-
8/11/2019 Grid Island
20/27
Power Research & Development Consultants Pvt. Ltd.20
System Considered for Simulation
Sl no
Description Values
1. Grid/Source data 70 kV, 50 Hz system, 1000 MVA fault level,
Inertia constant of 100 sec. on 100 MVA base
2. Grid transformers 3 numbers of 70/6 kV, 7.5 MVA, 9% impedance
3. Grid side load 10 MW at 0.85 pf
4. CPP side load 13 MW at 0.85 pf
5. Diesel generators 5/6 numbers, 6 kV, 1200 kW, 0.8 pf.
6. Turbo generator 1 1 number, 6 kV, 4000 kW, 0.8 pf, back pressure
7. Turbo generator 2 1 number, 6 kV, 6000 kW, 0.8 pf, back pressure
8. CPP side load
priority
11 MW essential, 2 MW non essential
9. Grid side load
priority
6 MW essential, 4 MW non essential.
http://localhost/var/www/apps/conversion/tmp/instructor/island_paper.guihttp://localhost/var/www/apps/conversion/tmp/instructor/island_paper.gui -
8/11/2019 Grid Island
21/27
Power Research & Development Consultants Pvt. Ltd.21
Loss of grid
Loss of grid results in sudden shift in the voltage vector and hencea vector shift relay best suits the logic to find the loss of grid.
The relay operation is instantaneous in nature and hence should
not operate for momentary grid faults.
Phase angle shift obtained at 6 kV bus of grid side for
A. Loss of grid5 degrees
B. Three phase fault in 70 kV2 degreesC. Three phase fault in 6 kV system - 0.2 degree
Recommended voltage vector shift relay setting is 5 degrees.
-
8/11/2019 Grid Island
22/27
Power Research & Development Consultants Pvt. Ltd.22
Loss of grid
In the absence of the vector shift relay, df/dt relay in conjunctionwith under frequency relay can be used.
As frequency relay time setting has to be with a time delay,
chances of successful islanding will not be 100%, as some of the
drive auxiliaries and power plant auxiliaries may trip.
Following the islanding, the non essential load of 2 MW on the
CPP side is tripped immediately using the load manager software
based on the logic that further cushion is not available.
In the absence of the load manager software, the load will be
tripped with further time delay.
-
8/11/2019 Grid Island
23/27
-
8/11/2019 Grid Island
24/27
Power Research & Development Consultants Pvt. Ltd.24
-
8/11/2019 Grid Island
25/27
-
8/11/2019 Grid Island
26/27
Power Research & Development Consultants Pvt. Ltd.26
-
8/11/2019 Grid Island
27/27