Gas Turbine Maintenence Aspects

download Gas Turbine Maintenence Aspects

of 38

Transcript of Gas Turbine Maintenence Aspects

  • 8/12/2019 Gas Turbine Maintenence Aspects

    1/38

    Heavy-Duty Gas TurbineOperatingand MaintenanceConsiderations

    YDERABAD

  • 8/12/2019 Gas Turbine Maintenence Aspects

    2/38

    2HDGT.PPT/

    HYDERABAD GT INSPECTIONS

    Running Inspections

    Standby Inspections

    Shutdown Inspections

  • 8/12/2019 Gas Turbine Maintenence Aspects

    3/38

    Running Inspection DataParameters to be monitored -Summary

    Speed

    Load

    Fired Starts

    Fired Hours

    Site Barometric Reading

    Temperatures

    Inlet Ambient

    Compressor Discharge

    Turbine Exhaust

    Turbine Wheelspace

    Lube Oil Header

    Lube Oil Tank

    Bearing Drains

    Exhaust Spread

    Pressures

    Compressor Discharge

    Lube Pump(s)

    Bearing Header

    Cooling Water

    Fuel

    Filters (Fuel, Lube, Inlet Air)

    Vibration Data for Power Train

    Generator

    Output Voltage

    Phase Current

    VARS

    Load

    Start-Up Time

    Coast-Down Time

    Field Voltage

    Field Current Stator Temp.

    Vibration

    HYDERABAD

  • 8/12/2019 Gas Turbine Maintenence Aspects

    4/38

    4HDGT.PPT/

    HYDERABAD

    RUNNING INSPECTIONSOPERATIONAL DIAGNOSTICS

    Start up

    Increased Startup time

    Jaw clutch disengagement at a lower speed

    Higher vibrations during critical speeds

    - Indicative of unhealthy starting means /turbine bearings

  • 8/12/2019 Gas Turbine Maintenence Aspects

    5/38 5HDGT.PPT/

    HYDERABAD Critical speedsTypical (Fr-5P)

    First critical1900 rpm

    Second critical3250 rpm

    Third critical5200 to 5600 rpm

    Critical speedsTypical (Fr-6B)

    First critical1650 to 1880 rpm

    Second critical3260 to 3900 rpmThird critical7050 to 7350 rpm

  • 8/12/2019 Gas Turbine Maintenence Aspects

    6/38 6HDGT.PPT/

    HYDERABAD Critical speedsTypical (Fr-9E)

    First critical980 rpm

    Second critical1300 rpm

    Third critical2300 rpm

    Critical speedsTypical (Fr-6FA)

    First critical 1840 rpm

    Second critical 4743 rpm

  • 8/12/2019 Gas Turbine Maintenence Aspects

    7/38 7HDGT.PPT/

    HYDERABAD

    RUNNING INSPECTIONSOPERATIONAL DIAGNOSTICS

    Load Limitation / Hunting

    Unable to maintain load

    Unable to increase load

    - Indicative of clogged hydraulic filters and / ordamaged fuel pump and / orrelief valve

    RUNNING INSPECTIONS

  • 8/12/2019 Gas Turbine Maintenence Aspects

    8/38 8HDGT.PPT/

    HYDERABAD

    RUNNING INSPECTIONSOPERATIONAL DIAGNOSTICS

    Combustion Trouble / exhaust spread

    Increasing trend in exhaust temperature spread

    Changing pattern of exhaust temp. spread with load

    - Indicative of unequal fuel distribution tofuel nozzles

    RUNNING INSPECTIONS

  • 8/12/2019 Gas Turbine Maintenence Aspects

    9/389HDGT.PPT/

    HYDERABAD

    RUNNING INSPECTIONSOPERATIONAL DIAGNOSTICS

    Lower Loads under similar conditions

    Higher Exhaust Temperature under similar

    conditions

    - Indicative of compressor fouling

  • 8/12/2019 Gas Turbine Maintenence Aspects

    10/381HDGT.PPT/

    HYDERABAD STANDBY INSPECTION

    Inspections carried out during Off-peakperiods when Unit is not running for a longduration

    Check Battery system, Oil levels, instrument calibrations,replacement of various filters & servicing of accessorysystems etc.

    Put the unit on ratcheting / barring gear for atleast 30 mindaily

    Crank the Turbine once in a Fortnight to drive awayMoisture

    Run the Gas Turbine FSNL once every month to avoidcorrosion to turbine wheel dovetails

  • 8/12/2019 Gas Turbine Maintenence Aspects

    11/38

    A Maintenance Program should:

    Optimize owners maintenance costs

    Maximize equipment availability

    PERIODIC SHUTDOWN INSPECTIONSHYDERABAD

  • 8/12/2019 Gas Turbine Maintenence Aspects

    12/38

    Factors Affecting Maintenance Planning andMaintenance Program

    Maintenance

    Program

    ManufacturersRecommendedMaintenance

    Program

    Diagnostics

    Availability

    Need

    On-Site

    Maintenance

    Capability

    DesignFeatures

    Utilization

    Need

    DutyCycle

    Environment

    Cost ofDowntime

    Type of

    Fuel

    Expert

    Systems

    Reserve

    Requirements

    HYDERABAD

  • 8/12/2019 Gas Turbine Maintenence Aspects

    13/38

    Case 2

    1,000 Hrs/Yr

    400 Starts/Yr

    HGP at 3 years, not 24 years

    Case 1

    8,000 Hrs/Yr

    160 Starts/Yr

    HGP at 3 years

    Because not all customers operate their gas turbines the similarl

    not all customer maintenance programs are the same.

    BHEL Provides Guidance for Customer Maintenance Planning

    HYDERABAD

  • 8/12/2019 Gas Turbine Maintenence Aspects

    14/38

    Maintenance Cost and Equipment LifeAre Influenced by Key Service Factors

    Fuel

    Firing Temperature

    Steam/Water InjectionCyclic Effects (Start-up rate, number of trips)

    Air Quality

    Service Factors Different From the Reference Condition*

    Can Increase Maintenance Cost & Reduce Maintenance Intervals

    HYDERABAD

  • 8/12/2019 Gas Turbine Maintenence Aspects

    15/38

    Potential Failure Modes

    Continuous Duty Application Creep Deflection Creep Rupture Corrosion Oxidation Erosion. High-Cycle Fatigue.

    Hot-Gas-Path Components

    Cyclic Duty Application

    Thermal Mechanical Fatigue Rubs/Wears.

    HYDERABAD

  • 8/12/2019 Gas Turbine Maintenence Aspects

    16/38

  • 8/12/2019 Gas Turbine Maintenence Aspects

    17/38

    1HDGT.PPT/

    HYDERABAD

    Operation of Gas Turbine inExtended lean-lean base

    mode in DLN-1 units has amaintenance factor of 10

  • 8/12/2019 Gas Turbine Maintenence Aspects

    18/38

    Maintenance Factor Definition

    IDEAL INTERVAL = Interval for Continuous Base Loadon Clean Natural Gas

    RECOMMENDED

    INTERVAL = Ideal Interval determined fromapplication of maintenance factors

    HYDERABAD

  • 8/12/2019 Gas Turbine Maintenence Aspects

    19/38

    Maintenance Factors Summary

    Maintenance Requirements are Based on an IndependentCount of Hours and Starts

    Certain Operating Factors Reduce Maintenance Intervals

    Peak Load

    Steam/Water Injection >2.2% Liquid Fuel

    Trips From Load

    Fast Starts

    Exceeding BHEL Specification Limits can SignificantlyIncrease Maintenance Factors and Reduce Component Life

    Equations for Establishing Application Specific Hot GasPath Maintenance Intervals are Available

    HYDERABAD

  • 8/12/2019 Gas Turbine Maintenence Aspects

    20/38

  • 8/12/2019 Gas Turbine Maintenence Aspects

    21/38

    Exh.

    Temp.

    TimeStart-up Shutdown

    Light-offAcceleration

    Warm-up

    Full SpeedNo Load

    Full Speed

    No Load

    Load Ramp

    Base Load

    Fired Shutdown

    Trip

    Unload Ramp

    Turbine Start/Stop Cycle

    540 Deg C

    HYDERABAD

  • 8/12/2019 Gas Turbine Maintenence Aspects

    22/38

    % Load

    T

    rip

    Severity

    Fa

    ctor

    01

    2

    3

    4

    5

    67

    8

    9

    10

    0 20 40 60 80 100 120

    Base

    FSNL

    For trips during Start-up

    Acceleration, assume

    Trip Severity Factor = 2

    Maintenance Factor - Trips from Load

    HYDERABAD

  • 8/12/2019 Gas Turbine Maintenence Aspects

    23/38

    Heavy-Duty Gas Turbine

    CombustionHot-Gas-Path

    Major

    Shutdown Inspect ions

    Major inspectionHot-Gas-Path

    Inspection

    CombustionInspection

    Special Inspect ion s

    Borescope

    IGV Bushing insp.

    HYDERABAD

  • 8/12/2019 Gas Turbine Maintenence Aspects

    24/38

    Base Line Recommended Inspection IntervalsBase Load - Gas Fuel - Dry

    Factors That Can Reduce Maintenance IntervalsFuel

    Load Cycle

    Steam/Water Injection

    Peak Load Operation

    Trips from Load

    Start Cycle

    HGP Hardware Design

    Type of

    Inspection

    Combustion

    Hot-Gas Path

    Major

    Hours/Starts

    12000/800

    MS32/52/51

    Upgrade

    (Standard)

    Eliminated/1200

    48000/2400

    8000/900

    24000/900

    48000/2400

    12000/1200

    24000/1200

    48000/2400

    MS6BStandard

    DLN1MS6FA & 9FA

    DLN2

    MS9E

    Standard

    & DLN1

    8000/450

    24000/900

    48000/2400

    HYDERABAD

  • 8/12/2019 Gas Turbine Maintenence Aspects

    25/38

    Maintenance InspectionsCombustion Inspection - Key Elements

    Foreign Objects

    Abnormal Wear

    Cracking

    Liner Cooling Hole Plugging TBC Coating Condition

    Oxidation/Corrosion/Erosion

    Hot Spots/Burning

    Missing Hardware

    Clearance Limits

    Borescope Compressor andTurbine

    Potential Actions:Inspect for:Key Hardware

    Combustion Liners

    Combustion Covers

    Fuel Nozzles

    Transition PiecesCross Fire Tubes

    Flow Sleeves

    Check Valves

    Spark Plugs

    Flame Detectors

    Flex Hoses

    Repair/Refurbishment

    Liners

    Cracking/Erosion/Wear

    TBC Repair

    Transition PiecesWear

    TBC Repair

    Distortion

    Fuel Nozzles

    Plugging

    Erosion/Wear

    Cross Fire TubesWear/Burning

    Criteria: Op. & Instr. Manual TILs

    Service Engineers

    Inspection

    Methods: Visual

    LP

    Borescope

    Availability of On Site

    Spares Is Key to

    Minimizing Downtime

    WORK SCOPE:

    HYDERABAD

    i i

  • 8/12/2019 Gas Turbine Maintenence Aspects

    26/38

    Maintenance InspectionsHot Gas Path Inspection - Key Elements

    Foreign Objects Damage

    Oxidation/Corrosion/Erosion

    CrackingCooling Hole Plugging

    Remaining Coating Life

    Nozzle Deflection/Distortion

    Abnormal Deflection/Distortion

    Abnormal Wear

    Missing HardwareClearance Limits

    Potential Actions:Inspect for:Key Hardware

    Nozzles (1,2,3)

    Buckets (1,2,3)

    Stator Shrouds

    IGVs & Bushings

    Compressor Blading

    (Borescope)

    Repair/Refurbishment

    Nozzles

    Weld Repair

    Reposition

    Recoat

    Buckets

    Strip & Recoat

    Weld Repair

    Blend

    Criteria: Op. & Instr. Manual TILs

    Service Engineers

    Inspection

    Methods: Visual

    LP

    Borescope

    WORK SCOPE: Combust ion Inspect ion wo rk scope +

    Availability of On Site

    Spares Is Key to

    Minimizing Downtime

    HYDERABAD

    i i

  • 8/12/2019 Gas Turbine Maintenence Aspects

    27/38

    Maintenance InspectionsGT Major Inspection - Key Elements

    Foreign Objects Damage

    Oxidation/Corrosion/Erosion

    Cracking

    Leaks

    Abnormal Wear

    Missing Hardware

    Clearance Limits

    Potential Actions:Inspect for:Key Hardware

    Compressor Blading

    Turbine Wheels Dovetails

    Journal and Seal Surfaces

    Bearing Seals

    Inlet System

    Exhaust System

    Repair/Refurbishment Stator Shrouds

    Oxidation/Corrosion/Erosion Buckets

    Coating DeteriorationFOD/Rubs/CrackingTip Shroud DeflectionCreep Life Limit

    Nozzles Deterioration IGV Bushings Wear

    Bearings/Seals Boring/Wear Compressor Blades

    Corrosion/ErosionRubs/FOD

    Criteria: Op. & Instr. Manual TILs

    Service Engineers

    Inspection

    Methods: Visual

    LP

    Borescope

    WORK SCOPE: Combust ion Inspect ion Work Scope +HotGas Path Inspect ion Work Scope +

    Availability of On Sit

    Spares Is Key to

    Minimizing Downtim

    HYDERABAD

    E ti t d R i / R l t C l

  • 8/12/2019 Gas Turbine Maintenence Aspects

    28/38

    2HDGT.PPT/

    HYDERABADEstimated Repair/ Replacement Cycles

    Repair Replacement

    Starts Hours

    Liners CI 5CI 3CI

    TPs CI 6CI 4CI

    Fuel Nozzles CI 3CI 2CI

    N#1,2,3 HGPI 3HGPI 3HGPIB#1 HGPI 3HGPI 2HGPI

    B#2,3 HGPI 4HGPI 3HGPI

    Shroud#1 HGPI 2HGPI 2HGPI

    Shroud#2,3 HGPI 4HGPI 3HPGI

    Typical and informative only. Depends upon GT type and size

    R i / R l t C l Lif E t i

  • 8/12/2019 Gas Turbine Maintenence Aspects

    29/38

    2HDGT.PPT/

    HYDERABAD

    FIRST STAGE NOZZLE WEAR - PREVENTIVE MAINTENANCELIFE EXTENSION

    Repair/ Replacement CyclesLife Extension

    Without repair

    Repaired Nozzle

    Min AcceptabilityStandard

    NozzleCondition

    Severe Deterioration

    New Nozzle

    Acceptance Standard

    First repair

    2nd repair

    3rd repairRepaircostexceeds

    replacementcost

    10,000 20,000 30,000 40,000 50,000 60,000 70,000 80,000

    Operating Hours

    SPARE PARTS PLANNING CONSIDERATIONS

  • 8/12/2019 Gas Turbine Maintenence Aspects

    30/38

    3HDGT.PPT/

    HYDERABADSPARE PARTS PLANNING - CONSIDERATIONS

    Repair / replacement intervals

    Cost

    Procurement cycle time

    Repair cycle time Vs. Inspection down time

    Shelf life

    Storage facilities

    Environment

    Transport facilities

    Borescope Inspection

  • 8/12/2019 Gas Turbine Maintenence Aspects

    31/38

    3HDGT.PPT/

    HYDERABAD Borescope Inspection

    BORESCOPE INSPECTION CRITERIAACCESS AREA INSPECT FOR

    Compressor Blades Foreign object damage

    Dirt buildup

    Corrosion

    Tip Erosion

    Trailing Edge thinning

    Stator blade root erosion

    Tip clearances

    Borescope Inspection

  • 8/12/2019 Gas Turbine Maintenence Aspects

    32/38

    3HDGT.PPT/

    HYDERABAD

    BORESCOPE INSPECTION CRITERIAACCESS AREA INSPECT FOR

    Combustion Carbon build-up

    (Liner and transition piece) Hot spots

    Cracking

    Bulging

    Wear

    Missing metal or thermal

    barrier coating

    Borescope Inspection

    Borescope Inspection

  • 8/12/2019 Gas Turbine Maintenence Aspects

    33/38

    3HDGT.PPT/

    HYDERABAD

    BORESCOPE INSPECTION CRITERIAACCESS AREA INSPECT FOR

    Turbine Nozzles Foreign object damage

    Corrosion

    Blocked cooling holes

    Cracks

    Trailing edge bowing

    Erosion

    Burning

    Borescope Inspection

    Borescope Inspection

  • 8/12/2019 Gas Turbine Maintenence Aspects

    34/38

    3HDGT.PPT/

    HYDERABAD Borescope Inspection

    BORESCOPE INSPECTION CRITERIAACCESS AREA INSPECT FOR

    Turbine buckets Foreign object damage

    Corrosion

    Blisters

    Erosion

    Cracks

    Tip clearance

    Missing metal

    Borescope Inspection

  • 8/12/2019 Gas Turbine Maintenence Aspects

    35/38

    3HDGT.PPT/

    HYDERABAD Borescope Inspection

    BORESCOPE

    RIGID BORESCOPE

    FLEXIBLE BORESCOPE

    VIGV Bushing Inspection

  • 8/12/2019 Gas Turbine Maintenence Aspects

    36/38

    3HDGT.PPT/

    HYDERABAD VIGV Bushing Inspection

    1. Set vanes to full open position

    2. Set up dial indicator to

    measure motion normal to the

    vane chord. Position the

    indicator to read as close to the

    vane inner button as possible

    3. Deflect vane in a tangentia

    direction (perpendicular to the

    air flow direction) to both sides

    of the bushing clearance and

    record full dial indicator

    reading.

    AirflowDirection

    VIGV

    VIGV in fullyOpen Position

    84

    DialIndicator

    VIGV Bushing Inspection

  • 8/12/2019 Gas Turbine Maintenence Aspects

    37/38

    3HDGT.PPT/

    HYDERABAD VIGV Bushing Inspection

    DOWN TIME REDUCTION

  • 8/12/2019 Gas Turbine Maintenence Aspects

    38/38

    3HDGT.PPT/

    HYDERABAD

    SPECIAL DESIGN FEATURES FOR EASY MAINTENANCE

    Casings are horizontally split

    With upper half of casings removed, it is possible to removenozzles and inspect buckets without removing rotor

    All bearing housings are horizontally split and bearings can be

    replaced without removing the rotor. Large blades are moment weighed and sequenced to avoid

    rebalancing of rotor after site replacement.

    Components like governing components, fuel nozzles,

    combustion components are mounted type for easy maintenance All major accessories are separate assemblies and are accessible

    for inspection and maintenance.

    DOWN TIME REDUCTION