SULTANATE OF OMAN MINISTRY OF TRANSPORT AND COMMUNICATIONS DIRECTORATE GENERAL OF ROADS & LAND TRANSPORT MUSCAT UPGRADING OF FALAJ AL QABAIL ROUNDABOUT TENDER NO. 51/2012 MONTHLY PROGRESS REPORT NO. 10 OCTOBER 2014 CONSULTANT: RENARDET S.A. & PARTNERS CONSULTING ENGINEERS LLC. P.O. Box 579, Muscat, P.C. 100, Sultanate of Oman CONTRACTOR: CONSOLIDATED CONTRACTORS CO. LLC P.O. Box 614, Muscat, P.C. 100, Sultanate of Oman

description

Monthly progress report for a major interchange project in Sultanate of Oman for the month of October 2014.

Transcript of FQI-MPR-2014-10

  • SULTANATE OF OMAN

    MINISTRY OF TRANSPORT AND COMMUNICATIONS DIRECTORATE GENERAL OF ROADS & LAND TRANSPORT

    MUSCAT

    UPGRADING OF FALAJ AL QABAIL ROUNDABOUT TENDER NO. 51/2012

    MONTHLY PROGRESS REPORT NO. 10

    OCTOBER 2014

    CONSULTANT:

    RENARDET S.A. & PARTNERS CONSULTING ENGINEERS LLC. P.O. Box 579, Muscat, P.C. 100, Sultanate of Oman

    CONTRACTOR:

    CONSOLIDATED CONTRACTORS CO. LLC P.O. Box 614, Muscat, P.C. 100, Sultanate of Oman

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report October 2014

    RENARDET S.A. & PARTNERS Page 1

    Table of Contents

    1. PROJECT PARTICULARS .............................................................................................................................................. 2

    2. SCOPE OF WORK ....................................................................................................................................................... 3

    3. TYPICAL CROSS SECTIONS .......................................................................................................................................... 4

    4. SITE VISITS/ MEETINGS .............................................................................................................................................. 6

    5. ENGINEERS SITE STAFF ............................................................................................................................................. 7

    6. PROGRESS S-CURVE ................................................................................................................................................... 8

    7. STATUS OF MAJOR ACTIVITIES ................................................................................................................................ 10

    8. BRIDGE SUB-STRUCTURE PROGRESS SCHEDULE ...................................................................................................... 11

    9. MSE WALLS PROGRESS SCHEDULE ........................................................................................................................... 12

    10. BOX CULVERTS PROGRESS SCHEDULE ...................................................................................................................... 15

    11. PROGRESS STATUS OF UTILITY CROSSING DUCTS .................................................................................................... 19

    12. PROJECT STRIP CHART ............................................................................................................................................. 23

    13. FINANCIAL STATUS OF PAYMENTS .......................................................................................................................... 29

    14. DETAILS OF EQUIPMENT AVAILABLE AT SITE ........................................................................................................... 30

    15. DETAILS OF MANPOWER AVAILABLE AT SITE .......................................................................................................... 32

    16. QA/QC REPORTS ...................................................................................................................................................... 34

    17. STATUS OF MATERIAL APPROVALS .......................................................................................................................... 39

    18. ENGINEERS COMMENTS ......................................................................................................................................... 40

    19. DETAILS OF CORRESPONDENCE DURING THE MONTH ............................................................................................. 41

    20. PROGRESS PHOTOGRAPHS ...................................................................................................................................... 42

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report October 2014

    RENARDET S.A. & PARTNERS Page 2

    1. Project Particulars

    Client: Ministry of Transport & Communications

    P.O. Box 684, Muscat, Postal Code 113

    Directorate General of Roads

    Sultanate of Oman.

    Consultant: Renardet S.A & Partners L.L.C.

    P.O. Box 579, Muscat, Postal Code 100

    Sultanate of Oman.

    Contractor: Consolidated Contractors Company L.L.C.

    P.O. Box 614, Muscat, Postal Code 100

    Sultanate of Oman.

    Project Commencement Date: 30.10.2013

    Mobilization Period: 60 Days

    Construction Period: 548 Days

    Completion date: 29.06.2015

    Original Contract Value:

    (Including Contingencies) R.O. 17,884,403.000

    Amount of Contingencies: R.O. 1,402,155.613

    Original Contract Value:

    (Excluding Contingencies) R.O. 16,482,247.387

    Planned Physical Progress for September

    2014 8.49%

    Actual Physical Progress for September

    2014 6.20%

    Planned physical progress cumulative up to

    end of September 2014

    48.35%

    Achieved physical progress cumulative up

    to end of September 2014 45.39%

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report October 2014

    RENARDET S.A. & PARTNERS Page 3

    2. Scope of Work

    This project is located in Batinah Region on existing Batinah Highway in the Wilayat Sohar and

    consists of construction of an interchange in place of existing roundabout along with allied works.

    Total length of the project along Batinah highway is about 4.0 km which shall be converted from four

    lanes to six lanes with tapering back to 4lanes, all as shown on plans. Also included in the scope of

    work is the construction of service roads, pedestrian underpasses.

    The work also includes expropriation of properties, relocation/protection of services (sewerage,

    telephone, electricity, water, irrigation) road lighting works and traffic signals.

    Major items within the scope of work consist of but not limited to the following:

    Removal of existing asphalt surface, extension of existing embankment and earthwork to

    achieve the designed profile and gradient.

    Removal of existing drainage structures and construction of new ones including protection

    works as shown on construction drawings and as directed.

    Expropriation of open/built up properties and removal of existing structures thereupon.

    Construction of interchange ramps, Box Girder Bridge, roundabout, pedestrian underpasses and

    service roads.

    Provision of new street lighting system/traffic signals and removal/disposal of existing street

    light poles including conductors/cables, transformers, feeder pillars, foundations etc., all for the

    proper completion of the job.

    Construction of earthen embankment/sub grade, sub-base, aggregate base course, bituminous

    base course and bituminous wearing course as per details on the construction drawings.

    Installation of road side furniture (traffic signs, road marking etc.) and protection works on

    embankment slopes.

    Relocation/Protection of existing LT, 11KV and 33KV transmission lines and allied items

    (transformers etc.) as per the requirements of concerned authority.

    Relocation/Protection of existing utilities (sewerage, telephone, electricity, water lines and

    irrigation) as per the requirements of concerned authorities.

    Provision of ducts for future utilities as per the requirements of utility operator.

    Construction of concrete safety barriers, fixing of guard rails and paving tiles.

    Provision of traffic diversion in coordination with concerned authorities.

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report October 2014

    RENARDET S.A. & PARTNERS Page 4

    3. Typical Cross Sections

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report October 2014

    RENARDET S.A. & PARTNERS Page 5

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report October 2014

    RENARDET S.A. & PARTNERS Page 6

    4. Site visits/ Meetings

    S. No. Details of Site Visit/ meeting Date Final Outcome/ Decisions

    1 Meeting with Dr. Ramadan, Director

    of Planning, Sohar Municipality

    14.10.2014 Land owner of Plot adjacent to

    Sohar Airport Access Road details

    are obtained.

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report October 2014

    RENARDET S.A. & PARTNERS Page 7

    5. Engineers Site Staff

    S.

    No. Name Designation

    Date of

    Joining

    1. Roberto Benigni Head Supervision Projects

    2. Muneer Abdul Resident Engineer 19.03.2014

    3. Hussein Shah Material Engineer 04.01.2014

    4. Ernesto B. Paredes Bridge Engineer 16.04.2014

    5. Sande H Tangaras Civil Engineer 08.06.2014

    6. Danilo Quantity Surveyor 19.06.2014

    6. Mohamed Safie Land Surveyor 04.01.2014

    7. Aseef Iqbal Site Inspector 10.02.2014

    8. Alaa Aldin Abdelfatah Site Inspector 30.03.2014

    9. Walid Samy Abdoh Mostafa Material Inspector 01.04.2014

    10. Haneefa Mohmmed Al Zadjali Secretary 13.04.2014

  • 6. Progress S-Curve

    2013

    Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

    0.01 0.25 1.42 4.23 7.25 10.06 9.42 9.73 10.21 9.79 8.49 5.72 4.55 3.56 2.79 3.83 3.55 3.47 1.67 - - - -

    0.11 0.14 0.23 0.28 1.71 3.18 6.84 9.16 9.14 9.08 8.49 7.90 8.08 6.71 6.25 4.68 3.59 3.34 4.42 3.29 1.64 1.11 0.62

    - 0.28 0.18 1.01 2.92 5.63 5.18 7.36 7.30 9.33 6.20 - - - - - - - - - - - -

    0.01 0.26 1.67 5.91 13.15 23.21 32.64 42.37 52.58 62.37 70.86 76.59 81.13 84.69 87.48 91.31 94.86 98.33 100.00 100.00 100.00 100.00 100.00

    0.11 0.25 0.48 0.76 2.47 5.64 12.48 21.64 30.78 39.87 48.35 56.26 64.34 71.05 77.31 81.99 85.59 88.93 93.35 96.64 98.27 99.38 100.00

    - 0.28 0.45 1.46 4.38 10.01 15.19 22.55 29.86 39.18 45.39

    CUMULATIVE PROGRESS

    CL14 Org Plan Cumulative %

    Actual Cumulative

    2014 2015

    MONTHLY PROGRESS

    CL14 Org Plan per Month %

    Actual per Month

    Revised Sch. per Month %

    Revised Sch. Cummulative %

    0.00

    20.00

    40.00

    60.00

    80.00

    100.00

    120.00

    -

    2

    4

    6

    8

    10

    12

    Dec

    Jan

    Fe

    b

    Ma

    r

    Apr

    Ma

    y

    Jun

    Jul

    Aug

    Sep

    Oct

    Nov

    Dec

    Jan

    Fe

    b

    Ma

    r

    Apr

    Ma

    y

    Jun

    Jul

    Aug

    Sep

    Oct

    2013 2014 2015

    % C

    um

    ula

    tive

    % M

    ON

    TH

    LY

    MONTHS

    UPGRADING OF FALAJ AL QABAIL ROUNDABOUT PROJECT - OMANMONTHLY CL 14 PLANNED VS. ACTUAL MANHOURS

    CL14 Org Plan per Month % Revised Sch. per Month % Actual per Month CL14 Org Plan Cumulative % Revised Sch. Cummulative % Actual Cumulative

  • REV.: 0

    PERIOD ENDING: Oct-14

    2013

    Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

    CL14 Plan % 0.30 8.67 19.23 26.89 31.77 36.64 41.51 46.39 51.26 56.13 61.01 65.88 70.76 75.63 80.50 85.38 90.25 95.13 100.00 100.00 100.00 100.00 100.00

    Revised Plan % 4.11 9.30 17.58 24.18 30.90 35.16 38.97 42.78 46.60 50.41 54.23 58.04 61.86 65.67 69.48 73.30 77.11 80.93 84.74 88.56 92.37 96.18 100.00

    Actual - 6.62 13.03 22.36 37.31 43.00 44.11 51.21 56.24 60.13 65.67

    CL14 Plan % 0.00 0.00 0.38 20.37 47.70 48.33 48.33 48.33 48.33 48.33 48.33 48.33 48.33 59.91 77.84 90.27 94.93 100.00 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - - - 7.40 29.85 78.13 78.13 78.13 78.13 78.13 78.13 78.13 78.13 78.13 78.13 80.66 87.59 88.57 100.00 100.00 100.00

    Actual - 10.09 10.09 17.59 19.52 77.42 69.96 70.18 70.18 70.18 83.49

    CL14 Plan % 0.00 0.00 0.00 0.78 6.58 16.76 29.38 41.37 58.64 66.60 74.18 82.85 84.75 84.75 85.24 92.34 92.34 98.36 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - - - - - 3.32 12.89 28.83 43.89 60.03 74.82 90.03 95.24 95.95 95.95 96.09 98.30 99.46 99.54 100.00 100.00

    Actual - - - - 4.35 4.89 - 5.27 14.93 29.52 47.15

    CL14 Plan % 0.00 0.00 1.01 9.21 29.30 45.91 56.90 62.24 64.59 67.94 69.08 69.08 75.05 82.85 93.48 98.64 100.00 100.00 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - - - 4.26 8.17 16.03 32.68 53.13 67.05 67.47 67.47 67.90 68.32 68.32 68.32 81.11 93.02 97.11 100.00 100.00 100.00

    Actual - - - 5.00 5.00 53.23 62.16 74.91 78.29 91.86 98.62

    CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11.07 26.27 41.98 59.98 78.73 79.90 79.90 85.20 89.45 92.60 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - - - - - - - - - 3.58 17.42 31.37 51.32 75.82 75.82 75.82 75.82 87.25 87.25 98.60 100.00

    Actual 1.26 3.19

    CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.08 7.77 19.32 31.22 44.94 51.98 52.14 90.14 90.14 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - - - - - - - - - - - 0.08 8.44 22.42 46.57 51.97 51.97 86.66 90.05 93.03 100.00

    Actual

    CL14 Plan % 0.00 0.00 0.23 1.43 2.97 10.17 23.65 36.51 51.47 63.06 74.26 75.97 77.37 80.05 82.40 88.97 92.13 98.55 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - 0.26 2.64 7.33 20.62 35.14 50.06 62.76 68.40 72.78 74.07 74.67 83.42 84.04 84.30 87.32 95.58 98.11 99.44 100.00 100.00

    Actual - - - 0.48 1.26 5.59 14.93 27.72 40.08 55.38 66.20

    CL14 Plan % 0.00 0.00 4.02 15.21 34.62 57.89 69.26 81.40 83.38 83.46 84.50 92.89 99.96 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - - 2.77 7.75 13.76 22.09 29.64 39.02 49.64 59.51 71.33 85.14 87.00 93.50 100.00 100.00 100.00 100.00 100.00 100.00 100.00

    Actual - - - 0.01 6.05 14.73 18.14 22.33 26.30 30.75 34.14

    CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.38 1.21 2.63 3.42 4.23 5.50 6.08 6.08 34.35 99.38 99.76 99.76 100.00 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - - - - - - - - 61.45 74.69 90.19 94.70 94.70 94.70 94.70 94.70 98.41 100.00 100.00 100.00 100.00

    Actual - - - 2.50 17.74 14.39 13.24 16.19 16.72 27.56 21.22

    CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.80 17.87 43.85 61.59 72.98 81.15 83.94 84.42 85.35 92.86 96.39 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - - - - - - - - 7.02 20.33 38.29 50.60 59.52 72.89 81.07 83.55 86.89 90.26 95.34 98.27 100.00

    Actual - - - - - 2.61 4.98 6.42 8.31 10.67 12.36

    CL14 Plan % 0.00 0.00 0.00 4.43 17.23 33.36 49.13 65.07 80.79 93.82 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - - - 0.99 2.30 17.26 33.64 49.01 64.70 79.88 95.44 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00

    Actual - - - 6.16 9.87 17.63 25.69 35.90 49.03 65.95 72.27

    CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.17 0.79 1.43 5.65 13.41 21.84 30.56 32.94 70.94 75.04 94.02 96.43 100.00 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - - - - - 0.33 2.34 9.42 17.07 23.51 31.40 41.66 47.49 47.55 47.55 83.28 93.95 97.61 100.00 100.00 100.00

    Actual - - - 0.13 5.52 9.26 13.38 16.87 17.75 20.45 14.38

    Revised Plan 0.11 0.25 0.48 0.76 2.47 5.64 12.48 21.64 30.78 39.87 48.35 56.26 64.34 71.05 77.31 81.99 85.59 88.93 93.35 96.64 98.27 99.38 100.00

    Actual Cum - 0.28 0.45 1.46 4.38 10.01 15.19 22.55 29.86 39.18 45.39 - - - - - - - - - - - -

    2013

    Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

    0.01 0.25 1.42 4.23 7.25 10.06 9.42 9.73 10.21 9.79 8.49 5.72 4.55 3.56 2.79 3.83 3.55 3.47 1.67 - - - -

    0.11 0.14 0.23 0.28 1.71 3.18 6.84 9.16 9.14 9.08 8.49 7.90 8.08 6.71 6.25 4.68 3.59 3.34 4.42 3.29 1.64 1.11 0.62

    - 0.28 0.18 1.01 2.92 5.63 5.18 7.36 7.30 9.33 6.20

    0.01 0.26 1.67 5.91 13.15 23.21 32.64 42.37 52.58 62.37 70.86 76.59 81.13 84.69 87.48 91.31 94.86 98.33 100.00 100.00 100.00 100.00 100.00

    0.11 0.25 0.48 0.76 2.47 5.64 12.48 21.64 30.78 39.87 48.35 56.26 64.34 71.05 77.31 81.99 85.59 88.93 93.35 96.64 98.27 99.38 100.00

    - 0.28 0.45 1.46 4.38 10.01 15.19 22.55 29.86 39.18 45.39

    UPGRADING OF FALAJ AL QABAIL ROUNDABOUT - OMAN

    MANHOURS OVERALL PROJECT S-CURVE

    Item Description Wtd.

    %

    Plan/

    Actual

    2014

    C

    Clearing &

    Removal of

    Obstructions

    0.95

    2015

    B Road Diversions 2.73

    Budgeted

    Man-Hrs

    56,423

    19,558

    EStructural

    Excavation0.72

    D Embankment 3.5974,043

    14,821

    GBituminous

    Pavement3.57

    FSubbase &

    Aggregate Base2.4250,004

    73,724

    IConcrete for

    Bridge22.12

    H

    Concrete for

    Box Culvert

    /Underpas

    38.19788,138

    456,522

    L MSE walls 6.84

    J Drainage Works 1.50

    KIncidental

    Construction13.33

    30,920

    275,037

    141,190

    2014 2015

    MONTHLY PROGRESS

    CL14 Org Plan per Month %

    Actual per Month

    CUMULATIVE PROGRESS

    CL14 Org Plan Cumulative %

    Actual Cumulative

    MMEP Works &

    Ducts4.03

    TOTAL 100.000

    Revised Sch. per Month %

    Revised Sch. Cummulative %

    83,264

    2,063,644

  • 7. Status of Major Activities

    Sl. No.

    Description Unit BOQ Qty.

    (Revised)

    Actual Qty.

    % Completion

    1 Clearing & Grubbing M2 162,000 129,901 80.19%

    2 Borrow Excavation (to embankment)

    M3 340,000 108,670 31.96%

    3 Granular Sub-base M3 28,700 3,900 13.59%

    4 Concrete for Culverts M3 15,000 12,421 82.81%

    5 Concrete for Bridge M3 13,805 3,286 23.80%

    6 Steel reinforcement Fixing ton 4,900 2,063 42.10%

    7 Working Piles M3 2,826 2,826 100.00%

    8 Mortared Stone Riprap M3 5,210 0.00 0.00%

    9 MSE Walls M2 13,200 5,100 39.39%

    11 RCC Drainage Pipes LM 4,530 788 17.39%

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 11

    8. Bridge Sub-Structure Progress Schedule

    ACTIVITY AB1 L P1L P2L P3L P4L P5L AB2 L

    PEDESTAL/POT BEARING - - - - - - -

    PIER N/A - - - - - N/A

    2nd Lift - 13-Aug-14 19-Aug-14 24-Jul-14 29-Sep-14 4-Sep-14 -

    Height (m) - 6.920 6.920 6.920 6.920 6.920 -

    1st Lift - 23-Jul-14 7-Aug-14 29-Jun-14 15-Sep-14 10-Aug-14 -

    Height (m) - 1.153 1.210 1.440 1.248 1.225 -

    BIT. PAINTING - 28-May-14 26-Jun-14 17-May-14 4-Sep-14 23-Jun-14 -

    PILE CAP (Pier & Abut.) - 17-May-14 18-Jun-14 8-May-14 25-Aug-14 11-Jun-14 -

    F/P & BLINDING 21-Oct-14 11-May-14 11-Jun-14 1-May-14 17-Aug-14 3-Jun-14 -

    ACTIVITY AB1 R P1R P2R P3R P4R P5R AB2 R

    PEDESTAL/POT BEARING 16-Oct-14 14-Oct-14 14-Oct-14 16-Oct-14 - - -

    PIER N/A - - - - - N/A

    2nd Lift N/A 9-Jun-14 28-Jun-14 22-Jun-14 20-Sep-14 10-Jul-14 N/A

    Height (m) - 6.920 6.920 6.920 6.920 6.920 -

    1st Lift N/A 20-May-14 11-Jun-14 26-May-14 10-Sep-14 22-Jun-14 N/A

    Height (m) - 0.366 0.423 0.649 0.461 0.438 -

    BIT. PAINTING - 12-May-14 25-May-14 8-May-14 4-Sep-14 31-May-14 -

    PILE CAP (Pier & Abut.) 9-Oct-14 4-May-14 13-May-14 4/30/2014 27-Aug-14 20-May-14 -

    F/P & BLINDING 2-Oct-14 27-Apr-14 7-May-14 22-Apr-14 20-Aug-14 14-May-14 -

    PREVIOUSPREVIOUS

    MONTHTHIS MONTH

    SUB-STRUCTURE WORK PROGRESS (RHS)

    SUB-STRUCTURE WORK PROGRESS (LHS)

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 12

    9. MSE Walls Progress Schedule

    DATE Elevation DATE

    FROM TOFOUNDATION

    /BLINDINGFROM TO

    FOUNDATION

    /BLINDING

    22+702.653 22+760 2-Oct-14 22+718.936 22+810 17-Sep-14

    3-Oct-14 18-Sep-14

    22+760 22+825 30-Sep-14 22+810 22+893.032 9-Aug-14

    1-Oct-14 10-Aug-14

    22+825 22+840 13-Jul-14 22+893.032 22+976.294 13-Aug-14

    14-Jul-14 14-Aug-14

    22+840 22+880 6-Jul-14 22+976.294 23+040 18-Aug-14

    13-Jul-14 19-Aug-14

    22+880 22+908.387 10-Aug-14 23+040 23+088.046 26-Jul-14

    11-Aug-14 27-Jul-14

    22+908.387 22+969.478 3-Jul-14 23+088.046 23+130 21-Jul-14

    5-Jul-14 22-Jul-14

    22+969.478 23+000 4-Aug-14 23+130 23+191.774 7-Jul-14

    5-Aug-14 10-Jul-14

    23+000 23+025 20-Jul-14 23+191.774 23+270.800 26-Jun-14

    21-Jul-14 27-Jun-14

    23+025 23+070 17-Jul-14

    18-Jul-14

    23+070 23+140 30-Jun-14

    1-Jul-14 DATE

    23+140 23+164.573 16-Jun-14 FROM TOFOUNDATION

    /BLINDING

    17-Jun-14 23+270.762 (L) 23+270.800 (R ) 26-Jun-14

    23+164.573 23+237.536 23-Jun-14 27-Jun-14

    24-Jun-14

    23+237.536 23+270.762 17-Jun-14

    18-Jun-14

    PREVIOUSP R EVIOUS

    M ON T HTHIS MONTH

    El. 22.00

    El. 22.80

    El. 22.00

    El. 20.40

    El. 22.80

    MSE WALLS FOUNDATION AT APPROACH 1as of 31 OCTOBER 2014

    El. 21.20

    LOCATION (AB 1)

    Elevation

    Elevation

    LOCATION (LHS)

    El. 21.20

    El. 22.00

    El. 22.00

    LOCATION (RHS)

    El. 20.40

    El. 22.00

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 13

    DATE DATE

    FROM TOFOUNDATION

    /BLINDINGFROM TO

    FOUNDATION

    /BLINDING

    23+508.239 23+520 15-Sep-14 23+508.239 (L) 23+508.197 (R) 15-Sep-14

    16-Sep-14 16-Sep-14

    23+520 23+580.877 20-Aug-14

    21-Aug-14

    23+580.877 23+650 26-Aug-14

    27-Aug-14 DATE

    23+650 23+735 1-Sep-14 FROM TOFOUNDATION

    /BLINDING

    2-Sep-14 23+508.197 23+607.634 8-Sep-14

    23+735 23+790 19-Sep-14 9-Sep-14

    20-Sep-14 23+607.634 23+740 22-Sep-14

    23+790 23+827.635 - 23-Sep-14

    - 23+740 23+950.153 -

    El. 24.90 23+827.635 23+949.895 - -

    -

    PREVIOUSP R EVIOUS

    M ON T HTHIS MONTH

    LOCATION (RHS)

    El. 23.30El. 24.10

    El. 24.10

    Elevation

    El. 23.30

    Elevation

    MSE WALL FOUNDATIONS PROGRESS AT APPROACH 2as of 31 OCTOBER 2014

    El. 23.30

    LOCATION (LHS) LOCATION (AB 2)Elevation

    23+520 23+580.877 23+650 23+703 23+750 23+827.635 23+949.895

    34.500 - - - - - - -33.700 - - - - - - -32.900 - - - - - - -32.100 - - - - - - -31.300 - - - - - - -30.500 - - - - - - -29.700 - - - - - - -28.900 - - - - - - -28.100 - - - - - - -27.300 - - - - - - -26.500 - - - - - - -25.700 29-Oct-14 29-Oct-14 - - - - -24.900 13-Oct-14 13-Oct-14 26-Sep-14 26-Sep-14 - - -24.100 25-Sep-14 25-Sep-14 - - - - -23.300 - - - - - - -

    23+508.239 (L)23+508.197 (R )23+607.634 23+690 23+740 23+950.15333.700 - - - - - -32.900 - - - - - -32.100 - - - - - -31.300 - - - - - -30.500 - - - - - -29.700 - - - - - -28.900 - - - - - -28.100 - - - - - -27.300 - - - - - -26.500 - - - - - -25.700 - - - - - -24.900 16-Oct-14 16-Oct-14 15-Oct-14 15-Oct-14 - -24.100 30-Sep-14 30-Sep-14 9-Oct-14 - - -23.300 - - - - - -

    as of 31 OCTOBER 2014

    ELEV.AB 2 Face

    LHS (AB 2), from Sta. 23+508.239 to Sta. 23+949.895ELEV.

    RHS (AB 2), from Sta. 23+508.197 to Sta. 23+950.153

    MSE WALL PANELS FIXING AT APPROACH 2

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 14

    22+825 22+840 22+880 22+908.38 22+969.47 22+991 23+084 23+164.57 23+237.53 23+270.76

    34.800 - - - - - - - - - -34.000 - - - - - - - - - -33.200 - - - - - - - - - -32.400 - - - - - - - - - -31.600 - - - - - - - - - -30.800 - - - - - - - - - -30.000 - - - - - - - - - -29.200 - - - - - - - 19-Oct-14 1-Oct-14 1-Oct-1428.400 - - - - - - - 18-Oct-14 24-Sep-14 24-Sep-1427.600 - - - - - - - 20-Sep-14 18-Sep-14 18-Sep-1426.800 - - - - - - - 9-Sep-14 15-Sep-14 15-Sep-1426.000 - - - - - - 20-Oct-14 4-Sep-14 28-Aug-14 28-Aug-1425.200 - - - - - - 16-Sep-14 26-Aug-14 19-Aug-14 19-Aug-1424.400 - - - - 29-Oct-14 29-Oct-14 4-Sep-14 18-Aug-14 6-Aug-14 6-Aug-1423.600 - - - - 21-Sep-14 17-Sep-14 27-Aug-14 13-Aug-14 24-Jul-14 24-Jul-1422.800 - 22-Sep-14 22-Sep-14 22-Sep-14 11-Sep-14 24-Aug-14 9-Aug-14 28-Jul-14 - 13-Jul-1422.000 - 3-Sep-14 3-Sep-14 3-Sep-14 28-Aug-14 - - - - -21.200 - 28-Aug-14 28-Aug-14 28-Aug-14 - - - - - -

    20.400 - - - - - - - - - -

    22+810 22+893.03 22+976.29 23+035 23+088.04 23+191.77 23+270.8023+270.762

    (L)

    23+270.800

    (R )

    33.200 - - - - - - - - -32.400 - - - - - - - - -31.600 - - - - - - - - -30.800 - - - - - - - - -30.000 - - - - - - - - -29.200 - - - - - - 30-Sep-14 28-Sep-14 28-Sep-1428.400 - - - - - 30-Sep-14 24-Sep-14 24-Sep-14 24-Sep-1427.600 - - - - - 27-Sep-14 18-Sep-14 19-Sep-14 19-Sep-1426.800 - - - - - 13-Sep-14 13-Sep-14 11-Sep-14 11-Sep-1426.000 - - - 20-Oct-14 20-Oct-14 2-Sep-14 31-Aug-14 28-Aug-14 28-Aug-1425.200 - - - 18-Oct-14 18-Oct-14 24-Aug-14 18-Aug-14 18-Aug-14 18-Aug-1424.400 - - 23-Oct-14 20-Sep-14 20-Sep-14 13-Aug-14 6-Aug-14 7-Aug-14 7-Aug-1423.600 - - 25-Sep-14 8-Sep-14 8-Sep-14 9-Aug-14 24-Jul-14 24-Jul-14 24-Jul-1422.800 - 19-Oct-14 18-Sep-14 21-Aug-14 18-Aug-14 - 13-Jul-14 13-Jul-14 13-Jul-1422.000 - 23-Sep-14 26-Aug-14 - - - - - -21.200 - 4-Sep-14 - - - - - - -

    20.400 - - - - - - - - -

    PREVIOUSP R EVIOUS

    M ON T HTHIS MONTH

    RHS (AB 1), from Sta. 22+718.936 to Sta. 23+270.800

    LHS (AB 1), from Sta. 22+702.653 to Sta. 23+270.762

    MSE WALL PANELS FIXING @ APPROACH 1as of 31 OCTOBER 2014

    ELEV.

    ELEV.

    AB 1 Face

  • 10. Box Culverts Progress Schedule

    Rebars Concrete Rebars Concrete Rebars Concrete

    1 21+260 3 cells - 2.0 x 1.5 25.546 0 - - - - - - - -LHS Block 1 3 cells - 2.0 x 1.5 19.526 0 18-Oct-14 26-Oct-14 26-Oct-14 - - - - -RHS Block 2 3 cells - 2.0 x 1.5 14.473 0 - - - - - - - -RHS Block 3 3 cells - 2.0 x 1.5 6.000 0 - - - - - - - -

    2 21+485 1 cell - 2.0 x 1.5 39.750 0 - - - - - - - -Block 1a 1 cell - 2.0 x 1.5 3.000 0 - - - - - - - -Block 1b 1 cell - 2.0 x 1.5 17.290 0 1-Jul-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 1-Sep-14Block 2a 1 cell - 2.0 x 1.5 7.710 0 1-Jul-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 1-Sep-14Block 2b 1 cell - 2.0 x 1.5 10.000 0 21-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14Block 2C 1 cell - 2.0 x 1.5 11.730 0 - - - - - - - -

    3 21+838 2 x 4 cells (8) - 2.0 x 1.5 57.210 0 - - - - - - - -Block 1a 1 x 4 cells - 2.0 x 1.5 5.000 0 21-Jul-14 4-Sep-14 5-Sep-14 13-Oct-14 13-Oct-14 13-Oct-14 13-Oct-14 -Block 1b 1 x 4 cells - 2.0 x 1.5 17.600 0 3-Jul-14 4-Sep-14 5-Sep-14 13-Oct-14 13-Oct-14 13-Oct-14 13-Oct-14 -Block 2 1 x 4 cells - 2.0 x 1.5 22.600 0 3-Jul-14 20-Aug-14 20-Aug-14 30-Oct-14 30-Oct-14 30-Oct-14 30-Oct-14 -Block 3 1 x 4 cells - 2.0 x 1.5 11.970 0 - - - - - - - -

    Block 4a 1 x 4 cells - 2.0 x 1.5 5.000 0 21-Jul-14 10-Sep-14 12-Sep-14 18-Oct-14 19-Oct-14 18-Oct-14 19-Oct-14 -Block 4b 1 x 4 cells - 2.0 x 1.5 17.600 0 3-Jul-14 10-Sep-14 12-Sep-14 18-Oct-14 19-Oct-14 18-Oct-14 19-Oct-14Block 5 1 x 4 cells - 2.0 x 1.5 22.600 0 3-Jul-14 23-Sep-14 24-Sep-14 24-Oct-14 25-Oct-14 24-Oct-14 25-Oct-14 -Block 6 1 x 4 cells - 2.0 x 1.5 11.970 0 - - - - - - - -

    4 21+972.4 11 x 4 cel l s (44) - 3.0 x 2.0 57.629 0 - - - - - - - -Block 1 1 x 4 cells - 3.0 x 2.0 28.038 0 24-May-14 5-Jun-14 5-Jun-14 24-Jun-14 24-Jun-14 15-Jul-14 16-Jul-14 16-Aug-14Block 2 1 x 4 cells - 3.0 x 2.0 28.031 0 24-May-14 9-Jul-14 10-Jul-14 3-Aug-14 4-Aug-14 13-Aug-14 14-Aug-14 8-Sep-14Block 3 1 x 4 cells - 3.0 x 2.0 28.026 0 17-May-14 25-May-14 25-May-14 3-Jun-14 3-Jun-14 23-Jun-14 23-Jun-14 8-Sep-14Block 4 1 x 4 cells - 3.0 x 2.0 28.022 0 18-May-14 12-Jul-14 13-Jul-14 5-Aug-14 6-Aug-14 18-Aug-14 19-Aug-14 1-Oct-14Block 5 1 x 4 cells - 3.0 x 2.0 28.019 0 18-May-14 29-May-14 29-May-14 8-Jun-14 8-Jun-14 2-Jul-14 2-Jul-14 1-Oct-14Block 6 1 x 4 cells - 3.0 x 2.0 28.018 0 18-May-14 31-Jul-14 31-Jul-14 12-Aug-14 13-Aug-14 27-Aug-14 28-Aug-14 1-Oct-14Block 7 1 x 4 cells - 3.0 x 2.0 28.019 0 18-May-14 10-Jun-14 10-Jun-14 1-Jul-14 1-Jul-14 23-Jul-14 24-Jul-14 5-Oct-14Block 8 1 x 4 cells - 3.0 x 2.0 28.022 0 26-May-14 9-Aug-14 10-Aug-14 25-Aug-14 26-Aug-14 9-Sep-14 10-Sep-14 -Block 9 1 x 4 cells - 3.0 x 2.0 28.026 0 26-May-14 15-Jun-14 15-Jun-14 7-Jul-14 8-Jul-14 4-Aug-14 5-Aug-14 -

    Block 10 1 x 4 cells - 3.0 x 2.0 28.031 0 28-May-14 17-Aug-14 18-Aug-14 14-Sep-14 14-Sep-14 24-Sep-14 25-Sep-14 -Block 11 1 x 4 cells - 3.0 x 2.0 28.038 0 28-May-14 19-Jun-14 19-Jun-14 20-Jul-14 20-Jul-14 2-Sep-14 3-Sep-14 25-Sep-14

    RHS

    LHS

    RHS

    LHS

    LHS

    LHS

    RHS

    TYPE & DIMENSIONSTATIONBASE SLAB WALL

    NO.TOP SLAB Bituminous

    Paint (2 Coats)LENGTH (m) SKEW ( )

    F/P &

    BLINDING

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS

    Rebars Concrete Rebars Concrete Rebars Concrete

    Block 12 1 x 4 cells - 3.0 x 2.0 21.015 0 10-Aug-14 25-Aug-14 26-Aug-14 2-Sep-14 3-Sep-14 1-Oct-14 1-Oct-14 -Block 13 1 x 4 cells - 3.0 x 2.0 21.010 0 27-Jul-14 22-Sep-14 22-Sep-14 29-Sep-14 29-Sep-14 18-Oct-14 19-Oct-14 -Block 14 1 x 4 cells - 3.0 x 2.0 21.006 0 27-Jul-14 12-Oct-14 12-Oct-14 15-Oct-14 15-Oct-14 26-Oct-14 26-Oct-14 -Block 15 1 x 4 cells - 3.0 x 2.0 21.003 0 25-Jul-14 23-Aug-14 23-Aug-14 8-Sep-14 8-Sep-14 18-Sep-14 19-Sep-14 -Block 16 1 x 4 cells - 3.0 x 2.0 21.001 0 16-Jun-14 27-Jul-14 27-Jul-14 14-Aug-14 14-Aug-14 3-Sep-14 4-Sep-14 -Block 17 1 x 4 cells - 3.0 x 2.0 21.000 0 16-Jun-14 14-Sep-14 15-Sep-14 23-Sep-14 24-Sep-14 14-Oct-14 15-Oct-14 -Block 18 1 x 4 cells - 3.0 x 2.0 21.001 0 12-Jun-14 24-Oct-14 24-Oct-14 30-Oct-14 30-Oct-14 - - -Block 19 1 x 4 cells - 3.0 x 2.0 21.003 0 12-Jun-14 16-Sep-14 16-Sep-14 21-Oct-14 21-Oct-14 30-Oct-14 30-Oct-14 -Block 20 1 x 4 cells - 3.0 x 2.0 21.006 0 8-Jun-14 29-Sep-14 30-Sep-14 1-Oct-14 1-Oct-14 21-Oct-14 21-Oct-14 -Block 21 1 x 4 cells - 3.0 x 2.0 21.010 0 8-Jun-14 1-Sep-14 2-Sep-14 21-Sep-14 21-Sep-14 30-Sep-14 30-Sep-14 -Block 22 1 x 4 cells - 3.0 x 2.0 21.015 0 8-Jun-14 25-Jun-14 25-Jun-14 30-Jul-14 30-Jul-14 16-Sep-14 17-Sep-14 25-Sep-14

    4 21+972.4 11 x 4 cells - 3.0 x 2.0 57.629 0 - - - - - - - -Block 23 1 x 4 cells - 3.0 x 2.0 6.635 0 - - - - - - - -Block 24 1 x 4 cells - 3.0 x 2.0 6.782 0 - - - - - - - -Block 25 1 x 4 cells - 3.0 x 2.0 6.819 0 - - - - - - - -Block 26 1 x 4 cells - 3.0 x 2.0 7.217 0 - - - - - - - -Block 27 1 x 4 cells - 3.0 x 2.0 7.975 0 - - - - - - - -Block 28 1 x 4 cells - 3.0 x 2.0 8.571 0 - - - - - - - -Block 29 1 x 4 cells - 3.0 x 2.0 9.267 0 - - - - - - - -Block 30 1 x 4 cells - 3.0 x 2.0 9.949 0 - - - - - - - -Block 31 1 x 4 cells - 3.0 x 2.0 10.260 0 - - - - - - - -Block 32 1 x 4 cells - 3.0 x 2.0 10.262 0 - - - - - - - -Block 33 1 x 4 cells - 3.0 x 2.0 10.265 0 - - - - - - - -

    5 22+655 2 x 4 cells (8) - 2.0 x 2.0 95.482 45 R - - - - - - - -(9 cells) 1 cell - 2.0 x 2.0 - - - - - - - -Block 1 1 x 4 cells - 2.0 x 2.0 9.675 45 R - - - - - - - -Block 2 1 x 4 cells - 2.0 x 2.0 32.711 45 R 30-Jun-14 6-Aug-14 7-Aug-14 1-Sep-14 2-Sep-14 1-Sep-14 2-Sep-14 13-Oct-14Block 3 1 x 4 cells - 2.0 x 2.0 32.711 45 R 24-Jun-14 21-Jul-14 21-Jul-14 17-Aug-14 18-Aug-14 17-Aug-14 18-Aug-14 13-Oct-14Block 4 1 x 4 cells - 2.0 x 2.0 20.315 45 R 11-Sep-14 12-Oct-14 13-Oct-14 22-Oct-14 22-Oct-14 22-Oct-14 22-Oct-14 -Block 5 1 x 4 cells - 2.0 x 2.0 19.035 45 R - - - - - - - -Block 6 1 x 4 cells - 2.0 x 2.0 32.711 45 R 29-Jun-14 27-Jul-14 28-Jul-14 13-Sep-14 14-Sep-14 13-Sep-14 14-Sep-14 13-Oct-14Block 7 1 x 4 cells - 2.0 x 2.0 32.711 45 R 24-Jun-14 28-Aug-14 28-Aug-14 24-Sep-14 26-Sep-14 24-Sep-14 26-Sep-14 13-Oct-14Block 8 1 x 4 cells - 2.0 x 2.0 10.95 45 R - - - - - - - -Block 9 1 cell - 2.0 x 2.0 25.03 45 R - - - - - - - -

    Block 10 1 cell - 2.0 x 2.0 32.711 45 R 28-Jun-14 20-Aug-14 23-Aug-14 2-Oct-14 3-Oct-14 2-Oct-14 3-Oct-14 13-Oct-14Block 11 1 cell - 2.0 x 2.0 32.711 45 R 29-Jun-14 3-Aug-14 4-Aug-14 2-Oct-14 3-Oct-14 2-Oct-14 3-Oct-14 13-Oct-14Block 12 1 cell - 2.0 x 2.0 4.960 45 R - - - - - - - -

    6 23+492 1 x 4 cells (4) - 3.0 x 2.0 79.065 15 R - - - - - - - -(5 cells) 1 cell - 3.0 x 2.0 - - - - - - - -

    BASE SLAB WALL TOP SLAB Bituminous Paint (2 Coats)

    NO. STATION TYPE & DIMENSION LENGTH (m) SKEW ( )F/P &

    BLINDING

    RHS

    LHS

    RHS

    RHS

    RHS

    LHS

    RHS

    LHS

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS

    Rebars Concrete Rebars Concrete Rebars Concrete

    Block 1 1 x 4 cells - 3.0 x 2.0 6.457 15 R - - - - - - - -Block 2 1 x 4 cells - 3.0 x 2.0 31.546 15 R 24-Jun-14 9-Jul-14 9-Jul-14 30-Jul-14 30-Jul-14 16-Aug-14 17-Aug-14 6-Sep-14Block 3 1 x 4 cells - 3.0 x 2.0 31.546 15 R 24-Jun-14 14-Jul-14 15-Jul-14 3-Aug-14 3-Aug-14 21-Aug-14 21-Aug-14 6-Sep-14Block 4 1 x 4 cells - 3.0 x 2.0 7.982 15 R 9/172014 23-Sep-14 24-Sep-14 28-Sep-14 28-Sep-14 1-Oct-14 2-Oct-14 18-Oct-14Block 5 1 cell - 3.0 x 2.0 7.039 15 R - - - - - - - -Block 6 1 cell - 3.0 x 2.0 31.546 15 R 24-Jun-14 5-Aug-14 5-Aug-14 9 & 20/8/2014 9 & 23/8/2014 28-Aug-14 28-Aug-14 4-7/9/2014Block 7 1 cell - 3.0 x 2.0 31.546 15 R 24-Jun-14 6-Aug-14 6-Aug-14 11 & 25/8/2014 11 & 26/8/2014 31-Aug-14 1-Sep-14 4-7/9/2014Block 8 1 cell - 3.0 x 2.0 5.525 15 R 17-Sep-14 28-Sep-14 28-Sep-14 2-Oct-14 2-Oct-14 11-Oct-14 11-Oct-14 18-Oct-14

    11-Oct-14 11-Oct-14 - - -7 23+756.5 1 cell - 2.0 x 1.5 67.550 0 - - - - - - - -

    Block 1 1 cell - 2.0 x 1.5 12.090 0 - - - - - - - -Block 2 1 cell - 2.0 x 1.5 20.180 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14

    Block 3a 1 cell - 2.0 x 1.5 14.430 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 3b 1 cell - 2.0 x 1.5 8.700 0 11-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 28-Aug-14Block 4 1 cell - 2.0 x 1.5 12.090 0 - - - - - - - -

    8 23+997 1 cell - 2.0 x 1.5 70.268 0 - - - - - - - -Block 1 1 cell - 2.0 x 1.5 16.128 0 - - - - - - - -

    Block 2a 1 cell - 2.0 x 1.5 4.933 0 - - - - - - - -Block 2b 1 cell - 2.0 x 1.5 13.860 0 8-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 3a 1 cell - 2.0 x 1.5 16.300 0 8-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 3b 1 cell - 2.0 x 1.5 4.942 0 10-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 31-Aug-14Block 4a 1 cell - 2.0 x 1.5 7.848 0 10-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 31-Aug-14Block 4b 1 cell - 2.0 x 1.5 6.197 0

    9 24+235 1 cell - 2.0 x 1.5 59.106 0 - - - - - - - -Block 1a 1 cell - 2.0 x 1.5 15.566 0 - - - - - - - -Block 1b 1 cell - 2.0 x 1.5 15.000 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 2a 1 cell - 2.0 x 1.5 8.900 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 2b 1 cell - 2.0 x 1.5 15.600 0 10-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 31-Aug-14Block 2c 1 cell - 2.0 x 1.5 4.020 0 - - - - - - - -

    10 24+570 1 cell - 2.0 x 1.5 51.953 0 - - - - - - - -LHS Block 1 1 cell - 2.0 x 1.5 25.846 0 14-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 31-Aug-14

    Block 2a 1 cell - 2.0 x 1.5 13.500 0 14-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 31-Aug-14Block 2b 1 cell - 2.0 x 1.5 12.587 0 - - - - - - - -

    Note: Precast RCBC were used for all 1 cell - 2.0m x 1.5m locations.

    PREVIOUSP R EVIOUS

    M ON T HTHIS MONTH

    NO. STATION TYPE & DIMENSION LENGTH (m) SKEW ( )F/P &

    BLINDING

    RHS

    LHS

    RHS

    RHS

    RHS

    BASE SLAB WALL TOP SLAB Bituminous Paint (2 Coats)

    LHS

    LHS

    LHS

    RHS

    LHS

    RHS

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS

    Rebars Concrete Rebars Concrete Rebars Concrete

    1 21+300 2 cells - 4.0 x 3.0 37.700 0 - - - - - - - -LHS Block 1 2 cells - 4.0 x 3.0 15.780 0 9-Oct-14 26-Oct-14 26-Oct-14 - - - - -RHS Block 2 2 cells - 4.0 x 3.0 21.900 0 - - - - - - - -

    2 24+300 2 cells - 4.0 x 3.0 44.051 0 - - - - - - - -LHS Block 1 2 cells - 4.0 x 3.0 21.620 0 22-Oct-14 - - - - - - -RHS Block 2 2 cells - 4.0 x 3.0 22.411 0 - - - - - - - -

    Rebars Concrete Rebars Concrete Rebars Concrete

    1 23+290, SOL-1 1 cells - 4.0 x 4.0 - 0 - - - - - - - -LHS Block 1 1 cells - 4.0 x 4.0 - 0 - - - - - - - -RHS Block 2 1 cells - 4.0 x 4.0 - 0 - - - - - - - -

    2 24+360, SOL-1 1 cells - 4.0 x 4.0 59.614 0 - - - - - - - -LHS Block 1 1 cells - 4.0 x 4.0 9.000 0 - - - - - - - -LHS Block 2 1 cells - 4.0 x 4.0 20.777 0 15-Sep-14 1-Oct-14 1-Oct-14 19-Oct-14 19-Oct-14 30-Oct-14 30-Oct-14 -RHS Block 3 1 cells - 4.0 x 4.0 22.777 0 - - - - - - - -RHS Block 4 1 cells - 4.0 x 4.0 7.000 0 - - - - - - - -

    3 0+050, SOL-3 1 cells - 4.0 x 4.0 83.223 0 - - - - - - - -LHS Block 1 1 cells - 4.0 x 4.0 17.721 0 - - - - - - - -LHS Block 2 1 cells - 4.0 x 4.0 17.721 0 - - - - - - - -LHS Block 3 1 cells - 4.0 x 4.0 17.721 0 - - - - - - - -RHS Block 4 1 cells - 4.0 x 4.0 30.000 0 - - - - - - - -

    PREVIOUSPREVIOUS

    MONTHTHIS MONTH

    WALLNO.

    LENGTH (m) SKEW ()F/P &

    BLINDINGTYPE & DIMENSION

    PEDESTRIAN UNDERPASS PROGRESS SCHEDULE (BARREL)

    TYPE & DIMENSION LENGTH (m)SKEW

    ( )

    TOP SLABBituminous

    Paint (2 Coats)STATION

    STATIONBASE SLAB WALL

    F/P &

    BLINDING

    BASE SLAB

    NO.

    VEHICLE UNDERPASS PROGRESS SCHEDULE (BARREL) As of 31 OCTOBER 2014

    TOP SLABBituminous

    Paint (2 Coats)

  • 11. Progress Status of Utility Crossing Ducts

    DRAWING NO.

    OF

    SETOUT/

    EXCV/BE

    NO. Stages DIA TYPE WAYS LAYING CONCRETE BACKFILL

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT 9/24/14 9/24/14 10/18/14 UTL-LAY- 104 UTL-CON-131A

    MIDDLE

    RIGHT

    LEFT 5/15/14 5/15/14 5/18/14 6/12/14 UTL-LAY- 81 UTL-CON- 65 UTL-BF- 01

    MIDDLE 6/11/14 6/11/14 6/12/14 7/10/14 UTL-LAY- 104 UTL-CON- 83 UTL-BF- 20

    RIGHT

    LEFT 5/19/14 5/19/14 5/20/14 6/4/14 UTL-LAY- 87 UTL-CON- 66 UTL-BF- 03

    MIDDLE 6/14/14 14/06/14 6/14/14 6/21/14 UTL-LAY- 108 UTL-CON- 84 UTL-BF- 21

    RIGHT

    LEFT 5/19/14 5/19/14 5/20/14 5/31/14 UTL-LAY- 85 UTL-CON- 63 UTL-BF- 02

    MIDDLE 6/15/14 6/15/14 6/15/14 UTL-LAY- 107UTL-CON- 85

    RIGHT

    LEFT 5/20/14 5/20/14 5/25/14 6/4/14 UTL-LAY- 86 UTL-CON- 64 UTL-BF- 05

    MIDDLE 6/15/14 6/15/14 6/15/14 7/8/14 UTL-LAY- 109UTL-CON- 87 UTL-BF- 23

    RIGHT

    LEFT 5/25/14 5/25/14 5/25/14 6/4/14 UTL-LAY- 90 UTL-CON-68 UTL-BF- 07

    MIDDLE 6/16/14 6/16/14 6/17/14 7/10/14 UTL-LAY- 111UTL-CON- 88 UTL-BF- 28

    RIGHT

    LEFT 6/17/14 6/17/14 6/18/14 7/9/14 UTL-LAY- 112UTL-CON- 89 UTL-BF- 33

    MIDDLE 7/20/14 7/20/14 7/21/14 7/27/14 UTL-LAY- 131UTL-CON- 106UTL-BF-44

    RIGHT

    LEFT 6/19/14 6/19/14 6/19/14 7/6/14 UTL-LAY- 114UTL-CON- 92 UTL-BF- 31

    MIDDLE 7/20/14 7/20/14 7/21/14 7/17/14 UTL-LAY- 132UTL-CON- 107UTL-BF-46

    RIGHT

    LEFT 6/19/14 6/19/14 6/19/14 7/5/14 UTL-LAY- 113 UTL-CON- 91 UTL-BF- 30

    MIDDLE 7/20/14 7/20/14 7/21/14 7/17/14 UTL-LAY- 133UTL-CON- 108UTL-BF-45

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT 5/26/14 5/26/14 5/26/14 6/8/14 UTL-LAY- 88 UTL-CON- 69 UTL-BF- 08

    MIDDLE 6/11/14 6/11/14 6/11/14 7/22/14 UTL-LAY-106 UTL-CON- 81 UTL-BF-26

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT 6/16/14 6/16/14 6/16/14 7/20/14 UTL-LAY- 102UTL-CON- UTL-BF-19

    MIDDLE 7/8/14 7/8/14 7/9/14 7/27/14 UTL-LAY- 125UTL-CON-99 UTL-BF-42

    RIGHT

    LEFT 5/25/14 5/25/14 5/26/14 6/14/14 UTL-LAY- 91 UTL-CON- 71 UTL-BF- 06

    MIDDLE 11/06/201 6/11/14 6/11/14 6/23/14 UTL-LAY- 105UTL-CON- 82 UTL-BF- 25

    RIGHT

    LEFT 5/27/14 5/27/14 5/27/14 6/17/14 UTL-LAY- 92 UTL-CON- 72 UTL-BF- 09

    MIDDLE

    RIGHT

    LEFT 5/28/14 5/28/14 5/28/14 6/17/14 UTL-LAY- 93 UTL-CON- 70 UTL-BF- 10

    MIDDLE

    RIGHT

    3

    2

    3

    3

    3

    2

    2

    2

    3

    1

    1

    3

    4

    3

    200

    200

    200

    150

    300

    900

    UPVC

    UPVC

    UPVC

    UPVC

    UPVC

    UPVC

    UPVC

    UPVC

    UPVC

    150

    150

    RC

    UPVC

    UPVC

    UPVC

    19 CCC/FQI/EL/13

    CCC/FQI/EL/0820

    23+060

    23+210

    23+240

    150

    150

    BACKFIL

    LING

    RFI REF.S.

    NO.CHAINAGE

    PIPE

    2

    2UPVC

    INSTALL

    ATION

    CONCRE

    TE

    1CCC/FQI/IR/06

    SERVICE ROAD-30+030 200 UPVC

    2CCC/FQR/IR/11

    SOL-20+150 300

    2

    3

    2

    4CCC/FQR/WA/0

    5 SR-10+600 300 UPVC

    5 CCC/FQI/EL/01

    9 CCC/FQI/EL/03 21+880

    CCC/FQI/EL/04 22+260

    11

    300 UPVC

    7 CCC/FQI/EL/02 21+660

    10

    150

    6 CCC/FQI/IR/01 21+460

    UPVC

    8 CCC/FQI/IR/02 21+780 300

    CCC/FQI/EL/05 22+510 150

    14

    CCC/FQI/IR/05

    JUNCTION

    CROSSING

    22+587 LHS

    12 CCC/FQI/IR/03

    21+360 150 UPVC

    18 CCC/FQI/EL/07

    15 CCC/FQI/EL/06

    22+520

    13

    CCC/FQI/IR/04

    JUNCTION

    CROSSING

    22+520 LHS

    CCC/FQI/WA/01

    CCC/FQI/WA/02

    JUNCTION16

    17

    23+008 LHS

    23+020

    22+760

    150

    23CCC/FQR/IR/10

    SOL-30+300 200 UPVC

    CCC/FQI/SL/01 21+160 150 UPVC 44A

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 20

    DRAWING NO.

    OF

    SETOUT/

    EXCV/BE

    NO. Stages DIA TYPE WAYS LAYING CONCRETE BACKFILL

    LEFT 5/29/14 5/29/14 5/29/14 6/17/14 UTL-LAY- 94 UTL-CON- 73 UTL-BF- 11

    MIDDLE 7/30/14 8/12/14 7/30/14 8/26/14 UTL-LAY-142 UTL-CON- 115UTL-BF-48

    RIGHT

    LEFT 5/29/14 6/2/14 6/2/14 6/17/14 UTL-LAY- 95 UTL-CON- 75 UTL-BF- 15

    MIDDLE 7/14/14 7/14/14 7/14/14 8/20/14 UTL-LAY- 124UTL-CON- 102UTL-BF- 36

    RIGHT

    LEFT 5/29/14 6/2/14 6/2/14 6/17/14 UTL-LAY-97 UTL-CON- 76 UTL-BF- 13

    MIDDLE 7/14/14 7/14/14 7/15/14 8/20/14 UTL-LAY- 127UTL-CON- 101UTL-BF- 38

    RIGHT

    LEFT

    MIDDLE 8/10/14 8/11/14 8/11/14 8/26/14 UTL-LAY-149AUTL-CON- 120AUTL-BF- 58

    RIGHT 10/27/14 10/27/14 UTL-LAY- 206UTL-CON- 153

    LEFT 5/29/14 6/2/14 6/3/14 6/19/14 UTL-LAY- 98 UTL-CON- 77 UTL-BF- 14

    MIDDLE 8/6/14 8/6/14 8/9/14 8/13/14 UTL-LAY- 134-R1UTL-CON- 109AUTL-BF- 53

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT 6/3/14 6/4/14 6/4/14 6/23/14 UTL-LAY- 99 UTL-CON- 78 UTL-BF- 16

    MIDDLE 8/11/14 8/11/14 8/19/14 8/26/14 UTL-LAY-140 R1UTL-CON-114UTL-BF- 52

    RIGHT

    LEFT 6/4/14 6/5/14 6/10/14 23/06/201 UTL-LAY- 100UTL-CON- 79 UTL-BF- 17

    MIDDLE 7/23/14 7/24/14 8/19/14 8/26/14 UTL-LAY-139 UTL-CON-112-R1UTL-BF- 47

    RIGHT

    LEFT 6/9/14 6/9/14 6/10/14 6/23/14 UTL-LAY- 101UTL-CON- 80 UTL-BF- 18

    MIDDLE 8/6/14 8/6/14 8/6/14 8/26/14 UTL-LAY-138-R1UTL-CON-111-BUTL-BF- 56

    RIGHT

    LEFT 7/5/14 7/5/14 7/5/14 8/19/14 UTL-LAY- 123UTL-CON- 94 UTL-BF- 39R1

    MIDDLE

    RIGHT

    LEFT 7/16/14 7/16/14 7/17/14 UTL-LAY- 130UTL-CON- 105

    MIDDLE 10/27/14 10/27/14 10/27/14 10/27/14 UTL-LAY-190R1UTL-CON- 148UTL-BF- 72

    RIGHT

    LEFT 9/14/14 9/14/14 10/14/14 10/20/14 UTL-LAY- 166UTL-CON-125UTL-BF-81

    MIDDLE 10/27/14 10/27/14 10/27/14 UTL-LAY- 205UTL-CON- 150

    RIGHT

    LEFT 9/16/14 9/20/14 UTL-LAY- 173

    MIDDLE 10/27/14 10/27/14 10/27/14 UTL-LAY- 203UTL-CON- 149

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT 5/21/14 5/21/14 5/21/14 6/4/14 UTL-LAY- 89 UTL-CON- 67 UTL-BF- 04

    MIDDLE 6/16/14 6/16/14 6/18/14 7/10/14 UTL-LAY- 110UTL-CON- 90 UTL-BF- 29

    RIGHT

    LEFT 5/29/14 5/31/14 5/31/14 6/17/14 UTL-LAY- 96 UTL-CON- 74 UTL-BF- 12

    MIDDLE 7/10/14 7/10/14 8/13/14 8/26/14 UTL-LAY- 120 R1UTL-CON- 95 UTL-BF- 49

    RIGHT

    LEFT 7/21/14 8/4/14 8/5/14 UTL-LAY-137-R1UTL-CON- 118

    MIDDLE 8/8/14 8/9/14 8/9/14 9/22/14 UTL-LAY-148AUTL-CON- 117UTL-BF- 57

    RIGHT 9/16/14 9/16/14 9/16/14 UTL-LAY-172 UTL-CON- 126

    LEFT 7/7/14 7/8/14 7/8/14 UTL-LAY-103AUTL-CON-98

    MIDDLE 8/12/14 8/13/14 8/14/14 8/15/14 UTL-LAY-150 UTL-CON-122AUTL-BF- 37A

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT 7/9/14 7/9/14 7/9/14 UTL-LAY- 116UTL-CON-100

    MIDDLE 8/12/14 8/13/14 8/14/14 9/25/14 UTL-LAY-151 UTL-CON-121UTL-BF-81

    RIGHT 10/12/14 10/13/14 10/12/14 UTL-LAY-187 UTL-CON-137

    LEFT 7/2/14 7/3/14 7/3/14 UTL-LAY-122 UTL-CON-93R1

    MIDDLE 7/10/14 7/10/14 7/14/14 UTL-LAY-126 UTL-CON-103

    RIGHT 7/22/14 7/22/14 7/23/14 8/20/14 UTL-LAY-136 UTL-CON-110UTL-BF- 50

    LEFT 8/30/14 8/31/14 9/14/14 9/30/14 UTL-LAY-158 UTL-CON-96 UTL-BF-64

    MIDDLE

    RIGHT

    4

    4

    3

    1

    3

    2

    3

    2

    3

    2

    24+220

    24+340

    24+520

    UPVC

    UPVC

    UPVC150

    23+820

    23+900

    23+980

    24+000

    24+020

    24+120

    37CCC/FQI/OMAN

    TEL.1

    33

    CCC/FQI/OMAN

    TEL.2100

    150

    38 0+140 SOL-3

    22+810 100

    100

    21+870

    23+580

    24+720

    150

    100

    100

    150

    UPVC

    UPVC

    UPVC

    UPVC300

    150

    300

    UPVC

    UPVC

    RC

    UPVC

    RC

    UPVC

    UPVC

    UPVC

    150

    CCC/FQI/IR/0726

    34

    35

    36

    CCC/FQI/EL/14

    CCC/FQI/IR/08

    CCC/FQI/EL/15

    CCC/FQI/EL/16

    CCC/FQI/IR/09

    CCC/FQI/EL/17

    CCC/FQI/NAW.2

    CCC/FQI/NAW.3

    CCC/FQI/NAW.4

    CCC/FQI/EL/1227

    24 CCC/FQI/EL/11

    CCC/FQI/EL/0921

    CCC/FQI/WA/0425

    23+560

    CCC/FQI/EL/1022

    CCC/FQI/WA/0323

    150

    150

    600

    24+820

    24+960

    25+160

    28

    29

    30

    31

    32

    223A 23+960 UPVC

    2

    3

    1

    2

    600

    300

    150

    150

    3

    3

    UPVC

    2

    4

    22+080

    UPVC

    UPVC

    UPVC

    UPVC 4

    39CCC/FQI/SL/03

    Rev A22+820 150 UPVC

    S.

    NO.CHAINAGE

    PIPEINSTALL

    ATION

    CONCRE

    TE

    BACKFIL

    LING

    RFI REF.

    4

    40 CCC/FQI/SL/04 22+990

    41 CCC/FQI/SL/02 4

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 21

    DRAWING NO.

    OF

    SETOUT/

    EXCV/BE

    NO. Stages DIA TYPE WAYS LAYING CONCRETE BACKFILL

    LEFT 9/7/14 9/7/14 10/14/14 10/27/14 UTL-LAY-162 UTL-CON-124UTL-BF-69

    MIDDLE 9/15/14 9/15/14 UTL-LAY-162R1

    RIGHT 10/27/14 10/28/14 10/27/14 10/30/14 UTL-LAY-207 UTL-CON-152UTL-BF-92

    LEFT 9/16/14 9/17/14 9/30/14 10/16/14 UTL-LAY-174 UTL-CON-127UTL-BF-83

    MIDDLE 10/14/14 10/18/14 10/14/14 UTL-LAY-188 UTL-CON-138

    RIGHT 10/27/14 10/27/14 10/27/14 UTL-LAY-204 UTL-CON-151

    LEFT 10/2/14 10/2/14 10/2/14 UTL-LAY-184 UTL-CON-135

    MIDDLE

    RIGHT

    LEFT 10/2/14 10/2/14 10/2/14 UTL-LAY-164 R1UTL-CON-134

    MIDDLE

    RIGHT

    LEFT 10/2/14 10/2/14 10/2/14 UTL-LAY-185 UTL-CON-136

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    DRAWING NO.

    OF

    SETOUT/

    EXCV/BE

    NO. Stages DIA TYPE WAYS LAYING CONCRETE BACKFILL

    LEFT 9/4/14 9/28/14 UTL-LAY-159-BUTL-CON-132

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT 9/16/14 9/17/14 9/30/14 10/18/14 UTL-LAY-167 UTL-CON-128UTL-BF-78

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    UPVC 2

    5

    UPVC 2

    UPVC 6

    Existing

    Road front

    SOL-3 Ch.

    150 UPVC

    Buraimi Road (SOL-3)

    CCC/FQI/SL/13

    UPVC 2

    CCC/FQI/SD/07

    CCC/FQI/SD/08

    CON

    C PI

    PECO

    NC

    PIPE

    21+500

    21+560

    2

    Setting Out

    , Excavation

    and Laying

    of UPVC

    Street

    Lighting

    150

    42 CCC/FQI/EL/19 23+740 150

    150CCC/FQI/SL/01

    0+130 150

    21+620 450

    0+140 150

    1CCC/FQI/Omant

    el/020+138.348 110

    45 CCC/FQI/SD/09

    2

    24+850

    450

    46 CCC/FQI/SD 23+400 600

    CON

    C PI

    PE

    UPVC 2-4WAY

    UPVC 4

    42

    43

    44

    450

    CON

    C PI

    PE

    S.

    NO.CHAINAGE

    PIPE

    2ACCC/FQI/Omant

    el/024UPVC

    INSTALL

    ATION

    CONCRE

    TE

    BACKFIL

    LING

    RFI REF.S.

    NO.CHAINAGE

    PIPE

    INSTALL

    ATION

    CONCRE

    TE

    BACKFIL

    LING

    RFI REF.

    6

    CCC/FQI/SL/14

    CCC/FQI/SL/15

    CCC/FQI/SL/16

    CCC/FQI/SL/17

    0+415 1503

    4

    Existing

    Road front

    SOL-3 Ch.

    150

    UPVC 2

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 22

    DRAWING NO.

    OF

    SETOUT/

    EXCV/BE

    NO. Stages DIA TYPE WAYS LAYING CONCRETE BACKFILL

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    DRAWING NO.

    OF

    SETOUT/

    EXCV/BE

    NO. Stages DIA TYPE WAYS LAYING CONCRETE BACKFILL

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    DRAWING NO.

    OF

    SETOUT/

    EXCV/BE

    NO. Stages DIA TYPE WAYS LAYING CONCRETE BACKFILL

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    SERVICE ROAD-01

    CCC/FQI/SL/07 0+530 150 UPVC

    4

    6CCC/FQI/OMAN

    TEL/060+648.103 100 UPVC

    4

    CCC/FQI/SL/10

    0+550

    100 UPVC 4

    4

    0+472.8

    CCC/FQI/SL/06 UPVC150

    CCC/FQI/OMAN

    TEL/04

    5CCC/FQI/OMAN

    TEL/05100 UPVC

    1

    0+060 4

    3 CCC/FQI/SL/08 0+600 100 UPVC 4

    2

    2

    SERVICE ROAD-02

    1 1+050 150 UPVC 2

    CCC/FQI/SL/12 1+530 150 UPVC 2

    S.

    NO.CHAINAGE

    PIPE

    2

    2

    3

    3 CCC/FQI/SL/08

    1 CCC/FQI/SL/23 0+020 150 UPVC 6

    2 CCC/FQI/SL/24 0+120

    S.

    NO.CHAINAGE

    PIPE INSTALL

    ATION

    CONCRE

    TE

    BACKFIL

    LING

    RFI REF.

    INSTALL

    ATION

    CONCRE

    TE

    BACKFIL

    LING

    RFI REF.

    S.

    NO.CHAINAGE

    PIPE INSTALL

    ATION

    CONCRE

    TE

    BACKFIL

    LING

    RFI REF.

    SERVICE ROAD-03

  • 12. Project Strip Chart

  • SUBGRADE IN CUT COMPLETED 21+150-21+500 As of Oct 2014BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmSubgrade Layr 9Layr 8Layr 7Layr 6Layr 5Layr 4Layr 3Layr 2

    EMBANKMENT Layer 1 BED PREPRATION OGL SURVEY

    21+0

    00

    21+0

    20

    21+0

    40

    21+0

    60

    21+0

    80

    21+1

    00

    21+1

    20

    21+1

    40

    21+1

    60

    21+1

    80

    21+2

    00

    21+2

    20

    21+2

    40

    21+2

    60

    21+2

    80

    21+3

    00

    21+3

    20

    21+3

    40

    21+3

    60

    21+3

    80

    21+4

    00

    21+4

    20

    21+4

    40

    21+4

    60

    21+4

    80

    21+5

    00

    OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4layer 5layer 6layer 7layer 8layer 9Subgrade

    GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm

    21+500-22+000BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmsub gradeLayer 9Layer 8Layer 7Layer 6Layer 5Layer 4Layer 3Layer 2

    EMBANKMENT Layer 1BED PREPRATION OGL SURVEY

    21+5

    00

    21+5

    20

    21+5

    40

    21+5

    60

    21+5

    80

    21+6

    00

    21+6

    20

    21+6

    40

    21+6

    60

    21+6

    80

    21+7

    00

    21+7

    20

    21+7

    40

    21+7

    60

    21+7

    80

    21+8

    00

    21+8

    20

    21+8

    40

    21+8

    60

    21+8

    80

    21+9

    00

    21+9

    20

    21+9

    40

    21+9

    60

    21+9

    80

    22+0

    00

    OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4layer 5layer 6layer 7layer 8layer 9sub grade

    GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm

    RH

    S

    FQI PROJECT - PROGRESS STRIP CHART FOR ROAD WORKS

    LHS

    RH

    SLH

    S

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 25

    COMPLETED 22+000-22+500 As of Oct 2014BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayr 10 SUB GRADE LAYER Layr 9Layr 8Layr 7Layr 6Layr 5Layr 4Layr 3Layr 2EMBANKMENT Layer 1 BED PREPRATION OGL SURVEY

    22+0

    00

    22+0

    20

    22+0

    40

    22+0

    60

    22+0

    80

    22+1

    00

    22+1

    20

    22+1

    40

    22+1

    60

    22+1

    80

    22+2

    00

    22+2

    20

    22+2

    40

    22+2

    60

    22+2

    80

    22+3

    00

    22+3

    20

    22+3

    40

    22+3

    60

    22+3

    80

    22+4

    00

    22+4

    20

    22+4

    40

    22+4

    60

    22+4

    80

    22+5

    00

    OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4layer 5layer 6layer 7layer 8layer 9layer 10 SUBGRADEGSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm

    22+500-23+000BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayer 10Layer 9Layer 8Layer 7 5th layer of rock soil Layer 6 layer 15Layer 5Layer 4 4th layer roock soil Layer 3Layer 2EMBANKMENT Layer 1BED PREPRATION OGL SURVEY

    22+5

    00

    22+5

    20

    22+5

    40

    22+5

    60

    22+5

    80

    22+6

    00

    22+6

    20

    22+6

    40

    22+6

    60

    22+6

    80

    22+7

    00

    22+7

    20

    22+7

    40

    22+7

    60

    22+7

    80

    22+8

    00

    22+8

    20

    22+8

    40

    22+8

    60

    22+8

    80

    22+9

    00

    22+9

    20

    22+9

    40

    22+9

    60

    22+9

    80

    23+0

    00

    OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4 4th layer roock soil layer 5layer 6 layer 15layer 7 5th layer of rock soil layer 8layer 9layer 10 SUB GGSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm

    LHS

    RH

    SLH

    SR

    HS

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 26

    COMPLETED 23+000-23+500 As of Oct 2014BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayr 10 rock siol layer no 3Layr 9 5th layer of rock soil layer no 28Layr 8 layer 15 of embankmentLayr 7Layr 6Layr 5Layr 4Layr 3Layr 2EMBANKMENT Layer 1 BED PREPRATION OGL SURVEY

    23+0

    00

    23+0

    20

    23+0

    40

    23+0

    60

    23+0

    80

    23+1

    00

    23+1

    20

    23+1

    40

    23+1

    60

    23+1

    80

    23+2

    00

    23+2

    20

    23+2

    40

    23+2

    60

    23+2

    80

    23+3

    00

    23+3

    20

    23+3

    40

    23+3

    60

    23+3

    80

    23+4

    00

    23+4

    20

    23+4

    40

    23+4

    60

    23+4

    80

    23+5

    00

    OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4layer 5layer 6 layer 15 of embankmentlayer 7 5th layer of rock soil layer no 28layer 8 rock siol layer no 3layer 9layer 10GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm

    23+500-24+000BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayer 10Layer 9Layer 8Layer 7Layer 6Layer 5Layer 4 4th layer of Rock siolLayer 3 3rd layer of Rock siolLayer 2 2nd layer of Rock siolEMBANKMENT Layer 11st layer of Rock siolBED PREPRATION OGL SURVEY

    24+5

    00

    24+5

    20

    24+5

    40

    24+5

    60

    24+5

    80

    24+6

    00

    24+6

    20

    24+6

    40

    24+6

    60

    24+6

    80

    24+7

    00

    24+7

    20

    24+7

    40

    24+7

    60

    23+7

    80

    23+8

    00

    23+8

    20

    23+8

    40

    23+8

    60

    23+8

    80

    23+9

    00

    23+9

    20

    23+9

    40

    23+9

    60

    23+9

    80

    24+0

    00

    OGL SURVEY BED PREPRATION EMBANKMENT Layer 11st layer of rock siollayer 2 2nd layer of rock siollayer 3 3rd layer of rock siollayer 4 4th layer of rock siollayer 5layer 6layer 7layer 8layer 9layer 10GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm

    LHS

    RH

    SLH

    SR

    HS

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 27

    COMPLETED 24+000-24+500 As of Oct 2014

    BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayer 10Layer 9Layer 8Layer 7Layer 6Layer 5Layer 4Layer 3Layer 2

    EMBANKMENT Layer 1 BED PREPRATION OGL SURVEY

    24+0

    00

    24+0

    20

    24+0

    40

    24+0

    60

    24+0

    80

    24+1

    00

    24+1

    20

    24+1

    40

    24+1

    60

    24+1

    80

    24+2

    00

    24+2

    20

    24+2

    40

    24+2

    60

    24+2

    80

    24+3

    00

    24+3

    20

    24+3

    40

    24+3

    60

    24+3

    80

    24+4

    00

    24+4

    20

    24+4

    40

    24+4

    60

    24+4

    80

    24+5

    00

    OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4layer 5layer 6layer 7layer 8layer 9layer 10

    GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm

    24+500-25+000

    BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayer 10Layer 9Layer 8Layer 7Layer 6Layer 5Layer 4Layer 3Layer 2

    EMBANKMENT Layer 1BED PREPRATION OGL SURVEY

    24+5

    00

    24+5

    20

    24+5

    40

    24+5

    60

    24+5

    80

    24+6

    00

    24+6

    20

    24+6

    40

    24+6

    60

    24+6

    80

    24+7

    00

    24+7

    20

    24+7

    40

    24+7

    60

    24+7

    80

    24+8

    00

    24+8

    20

    24+8

    40

    24+8

    60

    24+8

    80

    24+9

    00

    24+9

    20

    24+9

    40

    24+9

    60

    24+9

    80

    25+0

    00

    OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4layer 5layer 6layer 7layer 8layer 9layer 10

    GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm

    LHS

    RH

    SLH

    SR

    HS

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 28

    COMPLETED 25+000-25+500 As of Oct 2014

    BWC 6 cm

    Tack Coat

    BBC 12 cm

    PRIME COAT

    ABC 2 ND 15 cm

    ABC 1 ST 15 cm

    GSB 20 cm

    Layr 10

    Layr 9

    Layr 8

    Layr 7

    Layr 6

    Layr 5

    Layr 4

    Layr 3

    Layr 2

    EMBANKMENT Layer 1

    BED PREPRATION

    OGL SURVEY

    25+0

    00

    25+0

    20

    25+0

    40

    25+0

    60

    25+0

    80

    25+1

    00

    25+1

    20

    25+1

    40

    25+1

    60

    25+1

    80

    25+2

    00

    25+2

    20

    25+2

    40

    25+2

    60

    25+2

    80

    25+3

    00

    25+3

    20

    25+3

    40

    25+3

    60

    25+3

    80

    25+4

    00

    25+4

    20

    25+4

    40

    25+4

    60

    25+4

    80

    25+5

    00

    OGL SURVEY

    BED PREPRATION

    EMBANKMENT Layer 1

    layer 2

    layer 3

    layer 4

    layer 5

    layer 6

    layer 7

    layer 8

    layer 9

    layer 10

    GSB 20 cm

    ABC 1 ST 15 cm

    ABC 2 ND 15 cm

    PRIME COAT

    BBC 12 cm

    Tack Coat

    BWC 6 cm

    LHS

    RH

    S

  • 13. Financial Status of Payments

    Sl. No. DESCRIPTIONPAYMENT FOR

    THE MONTH OF

    GROSS

    AMOUNT

    (R.O.)

    GROSS

    AMOUNT

    CLAIMED (R.O.)

    NET AMOUNT

    CLAIMED

    (R.O.)

    DATE

    SUBMITTED

    AMOUNT

    CERTIFIED (R.O.)DATE CERTIFIED

    AMOUNT

    RECEIVED

    (R.O.)

    DATE

    PAYMENT DUE

    DATE

    PAYMENT

    RECEIVED

    1PAYMENT APPLICATION No. 1

    (ADVANCE PAYMENT)Dec-13 1,648,225 1,648,225 1,648,225 23-Nov-13 1,648,225 29-Jan-14 1,648,225 28-Mar-14 6-Feb-14

    2 PAYMENT APPLICATION No. 2 Jan-14 2,291,277 643,052 514,442 12-Feb-14 514,442 02-Apr-14 513,608 30-May-14 10-Apr-14

    3 PAYMENT APPLICATION No. 3 Feb&Mar-14 2,808,644 517,367 504,147 06-Apr-14 434,917 03-May-14 414,674 30-Jun-14 6-Aug-14

    4 PAYMENT APPLICATION No. 4 Apr-14 3,315,692 507,048 417,900 08-May-14 407,538 05-Jun-14 395,257 2-Aug-14 6-Aug-14

    5 PAYMENT APPLICATION No. 5 May-14 4,109,460 793,768 650,802 05-Jun-14 445,708 04-Jul-14 374,172 31-Aug-14 6-Aug-14

    6 PAYMENT APPLICATION No. 6 Jun-14 4,293,764 184,304 382,116 15-Jul-14 382,116 16-Jul-14 418,721 12-Sep-14 9-Sep-14

    7 PAYMENT APPLICATION No. 7 Jul&Aug-14 5,749,546 1,455,782 1,164,626 14-Sep-14 1,123,023 18-Sep-14 1,123,023 15-Nov-14 27-Oct-14

    8 PAYMENT APPLICATION No. 8 Sep-14 6,857,752 1,108,206 928,167 21-Oct-14

    9 PAYMENT APPLICATION No. 9 Oct-14

    10 PAYMENT APPLICATION No. 10 Nov-14

    11 PAYMENT APPLICATION No. 11 Dec-14

    12 PAYMENT APPLICATION No. 12 Jan-15

    13 PAYMENT APPLICATION No. 13 Feb-15

    14 PAYMENT APPLICATION No. 14 Mar-15

    15 PAYMENT APPLICATION No. 15 Apr-15

    16 PAYMENT APPLICATION No. 16 May-15

    17 PAYMENT APPLICATION No. 17 Jun-15

    6,857,752 6,857,752 6,210,425 4,955,969 4,887,679 TOTAL AMOUNT (R.O.)

  • 14. Details of Equipment Available At Site

    Sl.

    No.CCC HIRED

    TOTAL

    AVAILABLE

    AT SITE

    1 COMPRESSOR

    2 AIR COMPRESSOR 2 1 3

    3 MILLER WELDING MECHINE 2 2

    4 GENERATOR 3 3

    5 CRANES -

    6 CRANES 30 TON / 25 TON / 70 TON 2 2 4

    7 VEHICLES H.D. -

    8 DIESEL TANKER -

    9 FLAT TRAILER 2 2

    10 HIAB TRUCK 2 2

    11 P/MOVER + TIPPING TRAILER 5 5

    12 TIPPER TRUCKS 11 4 15

    13 WATER TANKER 5000 & 10000 GAL 1 5 6

    14 EARTH MOVING PLANT

    15 BOBCAT 1 2 3

    16 EXCAVATOR 1 1

    17 JCB 4CX / 3CX 1 4 5

    18 SHOVEL / WHEEL LOADER 3 2 5

    19 DOZER D9N/D8R 2 2

    20 TELEHANDLER -

    21 CIVIL ENGINEERING EQUIPMENT

    22 GREENE STABILIZER PLANT 1 1

    23 DYNAPAC S/ROLLER -

    24 E/WORK ROLLER 1 3 4

    25 MOTOR GRADER 1 4 5

    26 TITAN PAVER MACHINE -

    27 TYRE / PTR ROLLER -

    28 PAVER MACHINE -

    29 L. D. VEHICLES & TRUCKS

    30 DYNA TRUCK 1 2 3

    31 MAINTENANCE TRUCKS 1 1

    32 ASHOK LEYLAND BUS 55 SEAT 5 5

    33 TOYOTA COASTER BUS 24 S 1 1

    34 TOYOTA COROLLA/CIVIC/YARIS 12 12

    35 TOYOTA PICKUP/ISUZU 5 8 13

    36 NISSAN PATHFINDER/X-TRAIL 5 5

    37 TOYOTA LAND CRUISER/FORTUNER 4 4

    38 Total 47 65 112

    DESCRIPTION

  • Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Total

    PLANNED TOTAL PER MONTH 47 68 87 95 93 107 110 108 102 100 98 87 82 79 77 66 53 41 1500

    REVISED PLANNED TOTAL PER MONTH 68 87 95 93 107 110 108 102 100 98 87 82 79 77 66 53 41

    PLANNED CUMULATIVE 47 115 202 297 390 458 545 640 733 840 950 1,058 1,160 1,260 1,358 1,445 1,527 1,606 1,683 1,749 1,802 1,843

    ACTUAL TOTAL PER MONTH 33 55 66 68 77 86 88 100 109 112 794

    ACTUAL CUMULATIVE 33 88 154 222 299 385 473 573 682 794

    2014 2015

    47

    68

    87

    95

    93

    10

    7 110

    10

    8

    10

    2

    100

    98

    87

    82

    79

    77

    66

    53

    41

    33

    55

    66 68

    77

    86 88

    10

    0

    10

    9 112

    68

    87

    9593

    107110

    108

    102100

    98

    87

    8279

    77

    66

    53

    41

    0

    20

    40

    60

    80

    100

    120

    Jan

    -14

    Feb-1

    4

    Mar-

    14

    Apr-

    14

    Ma

    y-1

    4

    Ju

    n-1

    4

    Ju

    l-14

    Aug

    -14

    Sep-1

    4

    Oct-

    14

    No

    v-1

    4

    Dec-1

    4

    Jan

    -15

    Feb-1

    5

    Mar-

    15

    Apr-

    15

    Ma

    y-1

    5

    Ju

    n-1

    5

    Ju

    l-15

    Aug

    -15

    Sep-1

    5

    Oct-

    15

    No

    . o

    f E

    QU

    IPM

    EN

    T

    PROJECT MONTHS

    PLANNED TOTAL PER MONTH

    ACTUAL TOTAL PER MONTH

    REVISED PLANNED TOTAL PER MONTH

  • 15. Details of Manpower Available At Site

    BUDGET ACTUAL BUDGET ACTUAL BUDGET ACTUAL

    A - MANAGEMENT *** 3 3

    B - COMMERCIAL STAFF * 9 1 10

    C - ENGINEERS 6 6

    D - FOREMAN & C/H 21 2 23

    E - ENGINEERING TECHNICIANS ** 23 6 29

    F - DAILY RATED EMPLOYEES :

    1 - SKILLED CRAFTSMEN 143 65 208

    2 - SEMI-SKILLED/UNSKILLED 506 53 559

    TOTAL AS OF END OF THE MONTH 0 711 0 127 0 838

    G - SUBCONTRACTORS

    Number of Personnel employed by Subcontractor on Company Work : 29

    STAFF & LABOUR

    EXPATRIATES NATIONALS TOTAL

  • 2013Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Total

    PLANNED TOTAL PER MONTH - ( DIRECT ) 6 34 186 375 586 791 792 799 794 793 701 480 381 269 246 307 307 305 149 8301

    565 756 754 750 700 652 667 554 516 387 297 276 365 271 135 92 51 7788

    PLANNED TOTAL PER MONTH - ( INDIRECT ) 5 23 36 50 52 57 59 59 60 61 63 61 61 57 51 47 44 35 30 914

    REVISED - PLANNED TOTAL PER MONTH-(INDIRECT) 63 84 84 83 78 72 74 61 57 43 33 31 40 30 15 10 6 862

    PLANNED TOTAL PER MONTH - ( DIRECT + INDIRECT ) 11 57 222 425 638 848 851 858 854 854 764 541 442 326 297 354 351 340 179 9215

    REVISED - PLANNED - ( DIRECT + INDIRECT ) 627 840 838 833 778 725 741 616 573 429 330 306 406 301 150 102 57 8651

    PLANNED CUMULATIVE 11 68 291 715 1,353 2,202 3,052 3,910 4,764 5,618 6,383 6,923 7,365 7,691 7,988 8,342 8,693 9,033 9,212 9,212

    ACTUAL TOTAL PER MONTH - ( DIRECT ) 322 365 550 581 603 691 709 756 734 773 767 6851

    ACTUAL TOTAL PER MONTH - ( INDIRECT ) 18 26 46 49 54 57 64 69 68 70 71 592

    ACTUAL TOTAL PER MONTH - ( DIRECT + INDIRECT ) 340 391 596 630 657 748 773 825 802 843 838 0 0 0 0 0 0 0 0 7443

    ACTUAL CUMULATIVE 340 731 1,327 1,957 2,614 3,362 4,135 4,960 5,762 6,605 7,443

    REVISED - PLANNED TOTAL PER MONTH - ( DIRECT )

    2014 2015

    11

    57

    222

    425

    638

    848

    851

    858

    854

    854

    764

    541

    442

    326

    297

    354

    351

    340

    179

    340

    391

    596 6

    30 657

    748 773

    825

    802 8

    43

    838

    0 0 0 0 0 0 0 00

    100

    200

    300

    400

    500

    600

    700

    800

    900

    Dec-1

    3

    Jan

    -14

    Feb-1

    4

    Mar-

    14

    Apr-

    14

    May-1

    4

    Ju

    n-1

    4

    Ju

    l-14

    Aug

    -14

    Sep-1

    4

    Oct-

    14

    Nov-1

    4

    Dec-1

    4

    Jan

    -15

    Feb-1

    5

    Mar-

    15

    Apr-

    15

    May-1

    5

    Ju

    n-1

    5

    Ju

    l-15

    Aug

    -15

    Sep-1

    5

    Oct-

    15

    No

    . o

    f M

    en

    PROJECT MONTHS

    PLANNED TOTAL PER MONTH - ( DIRECT + INDIRECT ) ACTUAL TOTAL PER MONTH - ( DIRECT + INDIRECT ) REVISED - PLANNED - ( DIRECT + INDIRECT )

  • 16. QA/QC Reports

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 35

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 36

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 37

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 38

  • 17. Status of Material Approvals

    Date

    Submitted

    CCC/FQI/REN/MAS/001 MAS/CCC/FQI/BBC/001 Bituminous Base Course Tarmac Zawawi LLC Oman 22/12/2013 Renardet APPROVED 01/04/2014 SO/FQI/CCC/087 07/04/2014

    CCC/FQI/REN/MAS/002 MAS/CCC/FQI/GTI/002 Geotechnical Investigation Swissboring & Company LLC 26/12/2013 Renardet APPROVED 02/02/2014 SO/FQI/CCC/015 12/02/2014

    CCC/FQI/REN/MAS/003 MAS/CCC/FQI/MSE/003 MSE Wall System Freyssinet Arabian Sea LLC 26/12/2013 Renardet APPROVED 02/02/2014 SO/FQI/CCC/014 12/02/2014

    CCC/FQI/REN/MAS/004 MAS/CCC/FQI/PVC/004 UPVC Pipes Amiantit Oman 26/12/2013 Renardet APPROVED 09/02/2014 SO/FQI/CCC/019 18/02/2014

    CCC/FQI/REN/MAS/005 MAS/CCC/FQI/HDPE/005 HDPE Pipes & Fittings Amiantit Oman 26/12/2013 Renardet APPROVED 09/02/2014 SO/FQI/CCC/020 18/02/2014

    CCC/FQI/REN/MAS/006 MAS/CCC/FQI/PW/006 Piling Works APCC LLC 26/01/2014 Renardet APPROVED 19/02/2014 SO/FQI/CCC/026 25/02/2014

    CCC/FQI/REN/MAS/007 MAS/CCC/FQI/MC/007 Bitnuminous Prime Coat (MC-70) Emirates Lube Oil Co. (Muscat) 30/01/2014 Renardet APPROVED 09/03/2014 SO/FQI/CCC/069 27/03/2014

    CCC/FQI/REN/MAS/008 MAS/CCC/FQI/RS/008 Reinforcing Steel Muscat Steel Industries 02/02/2014 Renardet APPROVED 20/03/2014 SO/FQI/CCC/063 24/03/2014

    CCC/FQI/REN/MAS/009-1 MAS/CCC/FQI/PT/009-1 Post Tensioning Work - Anchorage Freyssinet Arabian Sea LLC 22/02/2014 Renardet APPROVED 27/03/2014 SO/FQI/CCC/089 14/04/2014

    CCC/FQI/REN/MAS/009-2 MAS/CCC/FQI/PT/009-2 Post Tensioning Work - Duct Freyssinet Arabian Sea LLC 22/02/2014 Renardet APPROVED 27/03/2014 SO/FQI/CCC/090 14/04/2014

    CCC/FQI/REN/MAS/009-3 MAS/CCC/FQI/PT/009-3 Post Tensioning Work - Strand Freyssinet Arabian Sea LLC 22/02/2014 Renardet APPROVED 27/03/2014 SO/FQI/CCC/091 14/04/2014

    CCC/FQI/REN/MAS/010A-Rev.1 MAS/CCC/FQI/PB/010A-Rev.1 Bridge Pot Bearings Al Ammar International 07/05/2014 Renardet Not Approved --- REN/FQI/CCC/111 13/05/2014

    CCC/FQI/REN/MAS/010B MAS/CCC/FQI/PB/010B Bridge Pot Bearings Building Supplies & Services 11/05/2014 Renardet APPROVED 25/05/2014 REN/FQI/CCC/122 31/05/2014

    CCC/FQI/REN/MAS/011 MAS/CCC/FQI/HDPE/011 HDPE Water Pipes Amiantit Oman 22/02/2014 Renardet APPROVED 09/03/2014 SO/FQI/CCC/038 11/03/2014

    CCC/FQI/REN/MAS/012 MAS/CCC/FQI/RCBC/012 Single cell Precast Box Culvert Amiantit Oman 22/02/2014 Renardet APPROVED 25/03/2014 SO/FQI/CCC/064 26/03/2014

    CCC/FQI/REN/MAS/013 MAS/CCC/FQI/BP/013 Bituminous Paint Material (Rubberized) Al Inma Building Materilal LLC 02/03/2014 Renardet Not Approved 20/04/2014 REN/FQI/CCC/105 05/05/2014

    CCC/FQI/REN/MAS/013A MAS/CCC/FQI/BP/013A Bituminous Paint Material (Rubberized) Henkel Polybit Industries Ltd. 17/06/2014 Renardet APPROVED 03/07/2014 REN/FQI/CCC/146 13/07/2014

    CCC/FQI/REN/MAS/014A-Rev.1 MAS/CCC/FQI/EJ/014A-Rev.1 Bridge Expansion Joints Al Ammar International 07/05/2014 Renardet APPROVED 20/05/2014 REN/FQI/CCC/123 31/05/2014

    CCC/FQI/REN/MAS/015 MAS/CCC/FQI/RC/015 Reinforced Concrete Pipe (450,600,700mm dia) Amiantit Oman 02/03/2014 Renardet APPROVED 23/03/2014 SO/FQI/CCC/077 02/04/2014

    CCC/FQI/REN/MAS/016 B MAS/CCC/FQI/WS/016 B Water Stop G EE-25 Sika LLC Oman 25/03/2014 Renardet APPROVED 16/04/2014 REN/FQI/CCC/099 28/04/2014

    CCC/FQI/REN/MAS/017 MAS/CCC/FQI/TW/017 Telephone Works National Telephone Services 12/03/2014 Renardet APPROVED 17/03/2014 SO/FQI/CCC/082 03/04/2014

    CCC/FQI/REN/MAS/019 MAS/CCC/FQI/EW/019 Electrical Works United Engineering Projects 22/03/2014 Renardet APPROVED 29/05/2014 REN/FQI/CCC/131 16/06/2014

    CCC/FQI/REN/MAS/020 MAS/CCC/FQI/EC/020 MV & LV Cables United Engineering Projects 19/03/2014 Renardet APPROVED 27/03/2014 SO/FQI/CCC/083 03/04/2014

    CCC/FQI/REN/MAS/021 MAS/CCC/FQI/PS/021 Package Substation United Engineering Projects 22/03/2014 Renardet ---- ----

    CCC/FQI/REN/MAS/021A MAS/CCC/FQI/PS/021A Package Substation Voltamp Energy SAOG 16/09/2014 Renardet

    CCC/FQI/REN/MAS/022 MAS/CCC/FQI/LL/022 Street Lighting Luminaries Majees Lighting Industries LLC 27/03/2014 Renardet APPROVED 14/08/2014 REN/FQI/CCC/158 17/08/2014

    CCC/FQI/REN/MAS/023A MAS/CCC/FQI/LP/023A Street Lighting Poles (Mid-Hinged)Al Babtain Power &

    Telecomunication Co., S.Arabia22/05/2014 Renardet APPROVED 14/08/2014 REN/FQI/CCC/157 17/08/2014

    CCC/FQI/REN/MAS/024 MAS/CCC/FQI/FP/024 Street Lighting Feeder Pillar Stars Light LLC 27/03/2014 Renardet APPROVED 08/06/2014 REN/FQI/CCC/130 16/06/2014

    CCC/FQI/REN/MAS/025 MAS/CCC/FQI/JS/025 Joint Sealant (Polyseal) Al Inma Building Materilal LLC 27/03/2014 Renardet APPROVED 16/04/2014 REN/FQI/CCC/100 28/04/2014

    CCC/FQI/REN/MAS/026 MAS/CCC/FQI/GT/026 Geotextile Modern East Trading & Con. 21/05/2014 RenardetNo meet the

    HDS--- REN/FQI/CCC/119 27/05/2014

    CCC/FQI/REN/MAS/026A MAS/CCC/FQI/GT/026A Geotextile (Bonar NW16) Bonar Technical Fabrics 15/06/2014 Renardet APPROVED 14/08/2014 REN/FQI/CCC/159 17/08/2014

    CCC/FQI/REN/MAS/027 MAS/CCC/FQI/MS/027Masterseal 915

    (formerly known as Masterflow 410 Plus)OBasf The Chemical Company 10/08/2014 Renardet

    Required

    latest test

    Reports

    --- REN/FQI/CCC/166 24/08/2014

    CCC/FQI/REN/MAS/028 MAS/CCC/FQI/GG/028 Gully Gratings & Frames RBA Ferro Industries PVT. Ltd. 17/08/2014 Renardet APPROVED 25/09/2014 REN/FQI/CCC/192 15/10/2014

    CCC/FQI/REN/MAS/030 MAS/CCC/FQI/FLC/030 MasterRoc FLC 100 (Cable Grout Admixture) BASF-The Chemical Company 02/10/2014 Renardet

    CCC/FQI/REN/MAS/032 MAS/CCC/FQI/GR/032 Guardrails GK Wire Industries LLC 29/10/2014 Renardet

    CANCELLED

    Renardet

    Letter

    Dated

    Reference No. MAR No. Material/ Work Manufacturer/Supplier/

    Subcontractor

    Submitte

    d To

    Remarks

    By MOTC

    MOTC

    Comment

    s dated

    Via Renardet

    Letter Ref. No.

  • 18. Engineers Comments

    The Planned progress as per the revised Project Execution Program for the month of

    October is 8.49% and the Actual progress is 6.20% which shows 2.29% of delay

    during the month of October. The actual cumulative progress up to October is

    45.39% against Planned Cumulative Progress of 48.35% showing a lagging of

    3.00% . Though four working days are reduced during the month due to holidays,

    the delayed progress must be recovered in the coming month.

    MSE Wall works are commenced on Abutment No. 2 side, and progressing.

    Superstructure works are in progress in the Bridge and bottom slab of Bridge No. 1

    is casted.

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 41

    19. Details of Correspondence during the month

    S.

    No.

    Date

    ReceivedFrom

    Reference

    NoSubject

    Reply

    date

    Reference

    No.Remarks

    1

    10/1/2014 CCC

    FQI-REN-TR-

    258

    Shop Drawing for 4 way #

    150mm upvc Street Lighting

    Ducts at SOL-02 CH.0+130

    2 10/2/2014 CCC

    FQI-

    RENARDET/258 Project Road Signs

    3 10/2/2014 CCC

    FQI-

    RENARDET/257

    Monthly Progress Report

    No.9

    410/18/2014 CCC

    FQI-REN-TR-

    261

    Dimension & Details of 3

    Cell Box Culvert 3(2.0*1.5)

    Skew Angle 0 @ ch.21+260 10/18/2014 Approved

    5 10/19/2014 CCC

    FQI-

    RENARDET/261

    Confirmation of vethal

    Instruction ( CVI)

    6 10/19/2014 CCC

    FQI-REN-TR-

    267

    Bar Bending Schedule for

    Vehicular underpass at

    ch.21+300 block (1-2) LHS-

    RHS 11/2/2014

    Approved as

    Noted

    710/20/2014 CCC

    FQI-

    RENARDET/264 Hijra New Year

    8 20/10/201 CCC

    FQI-

    RENARDET/265

    Access gate for Flyover Box

    Girder -Test Certification of

    Materials 10/28/2014

    REN/FQI/CC

    C/193

    9 10/22/2014 CCC

    FQI-REN-TR-

    278

    Shop Drawing for

    Pedestrian underpass

    section Elavation

    Reinforcement Details 11/1/2014 Approved

    1010/29/2014 CCC

    FQI-

    RENARDET/269

    Additional Item - Friction

    slab for Barrier above MSE

    Wall

    11 10/29/2014 CCC

    CCC/FQI/REN/

    MAS/032

    Approval Guardrails MAR .

    NO. MAS/CCC/FOI/GR/032

    12 10/30/2014 CCC

    FQI-

    RENARDET/262

    Project monthly progress

    Videos & Pictures

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 42

    20. PROGRESS PHOTOGRAPHS

    Mu

    scat S

    ide A

    pp

    roa

    ch

    ge

    ttin

    g R

    ea

    dy

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 43

    Abutment No. 2 side Approach Works in Progress

    Scaffolding for LHS Flyover Superstructure in Progress

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 44

    Installation of Pot Bearings in Progress

    Concrete Pouring in Box Girder Bottom Slab

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 45

    Field Tests of Earthwork Filling in Progress

    Vehicular Underpass Works in Progress

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 46

    Earthworks for Soar Airport Approach Road in Progress

    Asphalt Wearing Course in Sohar Airport Approach Road

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 47

    Completed View of 9 Cells Box Culvert

    Status of 8 Cells Box Culvert Progress

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014

    RENARDET S.A. & PARTNERS Page 48

    44 Cells Box Culvert Works in Progress

    Pedestrian Underpass Works in Progress