Following the Procurement Process

Administrative Services Office of Federal Grants and Program Compliance

Dale Butler FY14 Title I Summit

July 24, 2013

Page 2: Following the Procurement Process - Atlanta Public Schools · Following the Procurement Process ... If the vendor appears in the Lawson system, ... A process flow notification is

Step your way a to successful purchase!

Approved School wide Plan

Know your Budget (GL298)

Requisition - Process

Contract Process

Funds to support student success

Page 3: Following the Procurement Process - Atlanta Public Schools · Following the Procurement Process ... If the vendor appears in the Lawson system, ... A process flow notification is

Federal Funds can only be use to purchase those materials or services outlined in the grant guidelines and in the approved school wide plan. TRUE or FALSE A requisition for material or services should be entered as the first step in informing the Federal Grant Specialist and the Procurement Department that there is a need for materials or services? TRUE or FALSE For those items not available via district contract and the cost does not exceed $2,000.00 a quote is not needed. TRUE or FALSE If the vendor appears in the Lawson system, they are considered a contracted vendors. TRUE or FALSE Purchases of $25,000.00 or more must follow the formal solicitation process unless authorized by the Budget Center Manager. TRUE or FALSE

Test Your Knowledge

Page 4: Following the Procurement Process - Atlanta Public Schools · Following the Procurement Process ... If the vendor appears in the Lawson system, ... A process flow notification is

Requisition P-Card Lawson

•  $1 -$2,999.00 •  Included in Approved

Schoolwide Plan •  Place on Paper Requisition •  Signed and Dated •  Send to Federal Grant

Specialist •  Federal Grant Specialist

approves or rejects. •  If approved- order is placed

•  Use to purchase materials and services included in approved Schoolwide Plan.

•  Enter requisition for approval. •  Federal Grant Specialist

approves or rejects. •  If approved, it is routed to

procurement for processing •  Items are delivered •  Requestor must receive in

Lawson.

Page 5: Following the Procurement Process - Atlanta Public Schools · Following the Procurement Process ... If the vendor appears in the Lawson system, ... A process flow notification is

Requisition/Purchase Order P-Card Lawson

•  Items delivered to individual schools

•  Packing slip is sent to Federal Grant Specialist

•  Federal Grant Specialist reconciles P-Card Statement (monthly)

•  Vendor sends invoice to Accounts Payable

•  Invoice is entered in Lawson and matched for accuracy

•  Invoice is Paid •  BCM/Requestor run monthly

GL298 for outstanding PO’s or Requisitions.

•  Reviews 60 day open PO report monthly

Page 6: Following the Procurement Process - Atlanta Public Schools · Following the Procurement Process ... If the vendor appears in the Lawson system, ... A process flow notification is

Office of Federal Grants and Program Compliance Purchase Requisition

Page 7: Following the Procurement Process - Atlanta Public Schools · Following the Procurement Process ... If the vendor appears in the Lawson system, ... A process flow notification is

Lawson Requisition

Page 8: Following the Procurement Process - Atlanta Public Schools · Following the Procurement Process ... If the vendor appears in the Lawson system, ... A process flow notification is

STEPS FOR CONTRACTED SERVICES $2,000.00 OR LESS

1.  Forward completed Independent Contract to Administrative Services for review

Attn: Dale Butler/Grant Manager Go to:

http://www.atlanta.k12.ga.us/page/227 to download an Independent Contract form

2.  Contract is forwarded to the

following personnel for approval: •  Assistant Superintendent for

Administrative Services •  Deputy Superintendent for

Curriculum and Instruction

3.  Contract is forwarded to Procurement

•  Upon initial review, if template is an unaltered APS template, see # 4

•  If template is an altered APS template or vendor template, contract is forwarded to Legal for review and approval and then returned to Procurement for review and approval

4.  Contract is reviewed and approved by Procurement Officer or Director

5.  Upon approval, a PO is issued by Procurement and the contract is uploaded to Cobblestone

Page 9: Following the Procurement Process - Atlanta Public Schools · Following the Procurement Process ... If the vendor appears in the Lawson system, ... A process flow notification is

STEPS FOR CONTRACTED SERVICES $2,000.00 OR LESS Continued

6.  A process flow notification is sent to requestor via Lawson

Following the 6 steps should yield;

Ø  Total Contract Execution

Ø  Speedy PO Delivery Ø  Timely Start of Services

Page 10: Following the Procurement Process - Atlanta Public Schools · Following the Procurement Process ... If the vendor appears in the Lawson system, ... A process flow notification is

STEPS FOR CONTRACTED SERVICES $2,001.00 to $25,000.00

1.  Initiator of grant should receive four quotes

(single or sole source approvals are not included)

2.  Forward completed Independent Contract with quotes to Administrative Services, Attn: Dale Butler, Grant Manager

Independent Contract form can be located/downloaded from the website http://www.atlanta.k12.ga.us/page/227

3.  Contract is forwarded to the following personnel for approval: •  Assistant Superintendent for

Administrative Services •  Deputy Superintendent for

Curriculum and Instruction

4.  Contract is forwarded to Procurement •  Upon initial review, if template is

an unaltered APS template, see # 5 •  If template is an altered APS

template or vendor template, contract is forwarded to Legal for review and approval and then returned to Procurement for review and approval

Page 11: Following the Procurement Process - Atlanta Public Schools · Following the Procurement Process ... If the vendor appears in the Lawson system, ... A process flow notification is

STEPS FOR CONTRACTED SERVICES $2,001.00 to $25,000.00 continued

5.  Contract is reviewed and approved by Procurement Officer or Director

6.  Upon approval, a PO is issued by Procurement and the contract is uploaded to Cobblestone

7.  A process flow notification is sent to requestor via Lawson

Following the 7 steps should yield;

Ø  Total Contract Execution

Ø  Speedy PO Delivery Ø  Timely Start of Services

Page 12: Following the Procurement Process - Atlanta Public Schools · Following the Procurement Process ... If the vendor appears in the Lawson system, ... A process flow notification is

SINGLE/SOLE SOURCE PURCHASE REQUEST

•  Sole source purchases are defined as those purchases of goods or services that can only be obtained from one source in the marketplace

•  Such goods or services will usually be of a unique nature and have performance characteristic and/or other attributes that can only be obtained from that source

•  Single source purchases are defined as those purchases of goods or services that, for a justifiable reason such as compatibility or standardization, are obtained from one source among others in a competitive marketplace

•  These are further defined as transactions valued under $2,000 for any item or group of items; or emergency purchases

Page 13: Following the Procurement Process - Atlanta Public Schools · Following the Procurement Process ... If the vendor appears in the Lawson system, ... A process flow notification is
Page 14: Following the Procurement Process - Atlanta Public Schools · Following the Procurement Process ... If the vendor appears in the Lawson system, ... A process flow notification is
Page 15: Following the Procurement Process - Atlanta Public Schools · Following the Procurement Process ... If the vendor appears in the Lawson system, ... A process flow notification is
Page 16: Following the Procurement Process - Atlanta Public Schools · Following the Procurement Process ... If the vendor appears in the Lawson system, ... A process flow notification is

Summary 1.  Know the content of your approved schoolwide plan

2.  Review your budget (GL298) frequently

3.  Your requisition is the first means in which you communicate a need for

services or material

4.  Know which requisition is required

•  P-Card

•  Lawson

5. For Services or items not on contract and do not meet the formal soliciting

requirements, you must start 60 days prior to services needed

6. For Services or items that must be formally solicited – contact procurement

within 120 days of service start date.

7. Follow the contract approval process

Note: Follow Up Often

Page 17: Following the Procurement Process - Atlanta Public Schools · Following the Procurement Process ... If the vendor appears in the Lawson system, ... A process flow notification is
Page 18: Following the Procurement Process - Atlanta Public Schools · Following the Procurement Process ... If the vendor appears in the Lawson system, ... A process flow notification is

Dale Butler Grants Manager

[email protected] 404 802-2796