Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM...

56
Five Year Conservation and Demand Management Plan 2014-2018 Prepared June 2014 by:

Transcript of Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM...

Page 1: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

Five Year Conservation and

Demand Management Plan

2014-2018

Prepared June 2014 by:

Page 2: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing
Page 3: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

Table of Contents

1 EXECUTIVE SUMMARY ................................................................................................. 1

2 KEY COMPONENTS ....................................................................................................... 3

3 HISTORICAL ENERGY MANAGEMENT ........................................................................... 6

4 CURRENT STATE OF CORPORATE ENERGY ................................................................... 7

5 CURRENT ENERGY CONCERNS ..................................................................................... 9

6 SCOPE OF THE CDM PLAN .......................................................................................... 11

7 ENERGY BASELINE AND CURRENT ENERGY PERFORMANCE ..................................... 13

8 MISSION AND VISION ................................................................................................. 17

9 GOALS AND OBJECTIVES ............................................................................................ 19

10 ENERGY MANAGEMENT TEAM .................................................................................. 21

11 FINANCIAL ASSESSMENT ............................................................................................ 22

12 CORPORATE ENERGY BUDGET ................................................................................... 24

13 ENERGY MANAGEMENT ACTIONS ............................................................................. 25

APPENDIX A Energy Data ............................................................................................... 31

APPENDIX B Energy Use Breakdown ............................................................................. 37

APPENDIX C Energy Conservation Measure Schedules ................................................. 43

APPENDIX D Dollars to $ense Workshop ......................................................................... 1

Page 4: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing
Page 5: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 1

1 EXECUTIVE SUMMARY

The Ontario Provincial Government has committed to help public agencies better understand and manage

their energy consumption. As part of this commitment, Ontario Regulation 397/11 under the Green

Energy Act 2009 requires public agencies, including municipalities, municipal service boards, school

boards, universities, colleges and hospitals to report on their energy consumption and greenhouse gas

(GHG) emissions annually beginning in 2013 and to develop and implement energy Conservation and

Demand Management (CDM) Plans starting in 2014.

The purpose of the Winchester District Memorial Hospital (WDMH) energy Conservation and Demand

Management Plan is to develop a framework for Winchester District Memorial Hospital to understand the

historical impact of its operations on greenhouse gas (GHG) emissions, and to take action by setting GHG

reduction targets. The first objective of this report was the development of an energy Conservation and

Demand Management Plan that addressed the facets of energy consumption in the Hospital. This included

the development of a GHG emissions inventory, benchmarking as Winchester District Memorial Hospital's

existing energy intensity performance relative to other hospitals, identifying potential energy efficiency

projects, and establishing a GHG emissions reduction target. This strategic approach to energy

management (“energy Conservation and Demand Management Plan”) supports Winchester District

Memorial Hospital’s Quality Improvement Plan 2013/2014 and the Strategic Plan 2013-2018.

Energy efficiency and the wise use of energy are two of the lowest cost options for meeting energy

demands, while providing many other environmental, economic and social benefits, including reducing

greenhouse gas (GHG) emissions, cost avoidance and savings. Along with the aforementioned benefits,

energy efficiencies and the wise use of energy also promote local economic development opportunities,

energy system reliability, improved energy supply security, and reduced price volatility.

There are a variety of low cost/no cost initiatives available to Winchester District Memorial Hospital which

can jump-start energy consumption and dollar savings. Simple actions such as turning lights and

appliances off, shutting off heaters in the summer, establishing efficient usage times, efficient production

requirements, and many other actions can result in energy savings. Such actions, along with energy

efficient capital and operating process improvements and project implementation, are key components

which are outlined within the energy Conservation and Demand Management Plan (CDM Plan).

Page 6: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 2

This CDM Plan is the culmination of a non-linear process involving the:

Integration of establishing a baseline for performance to be measured against,

Setting of future performance goals and objectives,

Continuous improvement through identification of energy conservation potential,

Strategic alignment of measure implementation and fiscal constraints, and

Evaluation, measurement and communication of results achieved.

This CDM Plan contains three perspectives: historical, current and future. It looks at “what we have

done”,” what we are doing”, and “what are we planning to do”.

Page 7: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 3

2 KEY COMPONENTS

The Big Picture

Sustainability is a concept which meets the needs of the present without compromising the ability of

future generations to meet their own needs. This is sometimes referred to as the “triple bottom line”.

Environmental Sustainability: Managing the effects of human activity so that they do not permanently harm the natural environment.

Economic Sustainability: Managing the financial transactions associated with human activities so that they can be sustained over the long term without incurring unacceptable human hardship.

Social/Cultural Sustainability: Allowing human activity to proceed in such a way that social relationships between people and the many different cultures around the world are not adversely affected or irreversibly degraded.

An energy Conservation and Demand Management Plan is the sum of measures planned and carried out

to achieve the objective of using the minimal possible energy while maintaining the comfort levels (in

offices or dwellings) and production rates (in factories). It can be applied to any process or building where

energy use is required. To make an efficient use of the energy and, as a consequence, to save it, the actions

are focused on:

Energy Conservation,

Energy Recovery,

Energy Substitution,

Corporate Goals and Objectives, and

Corporate Fiscal Management.

Analysis and Benchmarking

It is important to recognize the value of benchmarking and comparison as a starting point. By examining

the Hospital’s current energy consumption patterns and comparing them with others, a better

understanding of the opportunities and the pitfalls of energy conservation and sustainability planning as

experienced by other public agencies is gained. This exposure, combined with the information gleaned

from the energy audits, will allow WDMH to focus on strategies that have been proven successful

elsewhere and can be tailored to the unique nature of the Hospital.

It is apparent that energy conservation is being considered and implemented in most public sectors across

Ontario and Canada. . As well, the insights gained through their experiences with energy conservation

can be used as a springboard to further the WDMH’s sustainability strategies to encompass both

operational and policy improvements. Many public agencies are taking their understanding of

Page 8: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 4

environmental issues and conservation beyond energy consumption and recycling, by addressing the

more complex issues of water management, heat island effect, and light pollution, to name a few.

Regulatory Requirements

Under Ontario Regulation 397/11 (Part of the Green Energy Act, 2009), all public sector agencies must

now comply with mandatory reporting requirements. By 2013, all energy consumption at hospital

facilities will have to be recorded and submitted to the Ministry annually. By 2014, the requirements

become more stringent as the Hospital will have to submit a CDM Plan, which encompasses measures

taken to date with results, as well as a five year plan for further energy conservation measures to be

implemented. WDMH is well positioned to meet this requirement as an audit has been completed at its

facility, resulting in a compiled list of energy reduction projects, some of which are already implemented.

The full list is reviewed throughout this Plan while the implementation program is outlined later in this

report. This Plan itself is meant to serve as WDMH’s CDM Plan and will help assist WDMH to meet all of

its mandatory reporting requirements.

Key Factors and Constraints

It is important to both WDMH’s future and to its image in the public at large to understand the value of a

comprehensive CDM Plan. Many people around the world are beginning to embrace the notion that the

earth’s environment and precious resources need to be conserved. However, the necessary changes will

not happen overnight. To be successful, a comprehensive energy management plan should embrace long-

term thinking, taking advantage of “low hanging fruit” to achieve immediate cost savings which will be

redirected to more complex projects involving higher initial costs with larger net benefits.

Public agencies should realize that each of their circumstances is unique and they may not lend themselves

to ‘boiler plate’ solutions used in many private sector segments. Those who have met their goals have

utilized the advantages of the unique physical and non-physical attributes of their facilities, including

green power generation on large flat roofs and community gardens on their large properties. While it is

easy to be focused on the larger solutions, even seemingly small efforts can make a major long-term

impact on the overall goal. A good example of this is Energy Awareness training which encourages Staff

to take simple and effective actions such as turning off lights and computers when not in use.

Ongoing professional development is also a key factor in the success of a CDM Plan to ensure that Staff

Members understand their role in the greater goal. The CDM Plan and accompanying education should

be a required part of their daily activities.

While realities of budget restrictions are an important consideration in any planning activity, it is possible

to achieve energy savings while adhering to the financial constraints of a publicly-funded Hospital system.

It is clear that new technology and ideology changes have produced continued operational cost reductions

Page 9: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 5

while improving indoor comfort and environmental sustainability. These cost saving projects can often

fund themselves by avoiding the use of previously allocated funds. As long as the savings are reinvested,

these improvements can continue for the foreseeable future, ensuring a sustainable process. Many

industries have had environmental programs running for over a decade and continue to hit their 3%-5%

intensity reduction goals without sacrificing product quality.

Page 10: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 6

3 HISTORICAL ENERGY MANAGEMENT

Hospital operations commenced in March 2011. Historically, WDMH has addressed Energy Conservation

and Demand Management on a project-by-project basis through the activities of the Building Services

Team. Capital projects were implemented based on equipment’s expected useful life or in response to

equipment emergency breakdowns. Utility savings realized as a result of the implementation of these

individual projects have not historically been uniquely reported formally, but have been considered as a

component of general operations. Thus, they have been reported through utility expenses in the

Accounting System. Sustainability and long-term energy reduction goals, through this CDM Plan, will

become integral components of the business reporting system. Active participation in recycling programs

has addressed some of the environmental concerns faced by the Hospital.

Utility costs were viewed as a fixed overhead cost. The management of these costs relied on an exception-

based investigation approach. In other words, utility costs were only reviewed if a utility bill was much

higher, or lower, than typical.

In 2013, WDMH embarked upon a strategic energy auditing project. The purpose of this audit was to

identify and analyze potential energy conservation and demand management opportunities. These

efforts have been instrumental in assisting WDMH in aligning the CDM Plan with the Hospital’s Quality

Improvement Plan 2013/2014 and the Strategic Plan 2013-2018.

Historical Energy Reduction Projects Summary

Year Action Taken

2013

Detailed energy audit performed.

Heating and cooling set points were adjusted to lower energy consumption.

Updated controls for exterior parking lot lighting

Page 11: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 7

4 CURRENT STATE OF CORPORATE ENERGY

Energy Data Management

While WDMH has an admirable history of managing its energy consumption, the Ontario government has

required an increase in hospital energy management practices. This has resulted in the need to enhance

current practices and develop new approaches. To meet this need, WDMH will design a comprehensive

program for collecting and analyzing monthly energy billing information, and ensuring Staff is informed

about energy consumption. This effort will produce an energy costs and consumption database that will

be used for monitoring excessive variations, targeting facility follow-up evaluations, and highlighting areas

that could be candidates for improved conservation. These monitoring enhancements will improve

WDMH’s understanding of the bottom line impact of energy management.

Energy Supply Management

WDMH has currently adopted a strategy of procuring its energy through the HealthPro organization.

Electricity is secured from Hydro One Networks. The Hospital has chosen to contract its natural gas

through ECNG Energy L.P. from Union Gas. This strategy is reviewed annually during the budgeting

process.

Energy Use in Facilities

WDMH Staff Members have retained a great deal of knowledge with regard to their facility’s energy use.

This knowledge base has been enhanced by a series of comprehensive audits completed at WDMH’s

facility. Through the deployment of energy management software, WDMH Staff will be equipped with the

information necessary to make effective energy management decisions. This will make it possible to

implement an effective energy procurement process, pursue appropriate capital projects, and implement

successful conservation and demand management programs.

Equipment Efficiency

WDMH has pursued many measures to improve the energy efficiency of the Hospital’s equipment. Some

of these measures include:

Heating and cooling equipment retrofits,

Building envelope improvements,

Electrical systems upgrade, and

The pursuit of the feasibility of solar thermal and solar photovoltaic applications.

As the understanding of corporate energy consumption improves, WDMH Staff will be equipped with the

knowledge necessary to make informed decisions. This improved understanding will also reveal how

Page 12: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 8

simple actions like commissioning and maintenance procedures can improve existing equipment

efficiencies.

Organizational Integration

Day to day management of energy has been primarily the responsibility of the WDMH Building Services

Team. Current practices will be enhanced with future plans including:

The creation of an interdepartmental energy management team,

Improved energy monitoring and feedback, and

Interactive energy training and awareness.

Staff across all departments will be given the necessary tools to address corporate energy concerns such

as budgeting, procurement, conservation, and generation.

Prior to the development of the CDM Plan, VIP assessed WDMH’s energy management practices. This

assessment was completed by speaking to WDMH Staff and reviewing relevant hospital material. Upon

completion of this review, VIP determined that WDMH had provided Staff with a mandate to pursue

proper energy management, and through WDMH Staff ingenuity, WDMH was able to direct resources to

energy management. However, VIP also noted that if WDMH is to achieve the Ministry’s mandate, it will

require the development of this CDM Plan that will address WDMH’s energy information and energy

procurement needs.

Page 13: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 9

5 CURRENT ENERGY CONCERNS

Environmental, societal, and fiscal pressures accentuate the need for an energy Conservation and Demand

Management Plan (CDM Plan).

Environmental

Concerns surrounding energy consumption with regard to climate change and air pollution have been well

documented. Since 1990, Ontario’s greenhouse gas emissions have increased 14%. The Government of

Ontario estimates that 75% of Ontario’s greenhouse gas emissions are associated with the consumption

of fossil fuels for energy purposes. Increased smog and air pollution are also connected to the

consumption of energy. Ontario’s electricity generation is the Province’s second largest source of sulfur

dioxide and the third largest source of nitrogen oxides. These pollutants can cause irreparable harm to

human health.

Societal

The 2003 Blackout heightened societal concerns surrounding the stability and security of our energy

supply. Energy has been imbedded into most societal practices. If energy consumption is not managed

appropriately, the frequency of energy interruption and the subsequent societal disruption will increase.

Fiscal

The fossil fuels traditionally used for the generation of energy are no longer financially accessible or

environmentally acceptable. This has resulted in the promotion of renewable energy generation which

comes with an additional expense. Energy costs are also anticipated to increase as Ontario’s existing

energy infrastructure is taken off-line or refurbished. Coming off of the lows of the 2009 recession national

electricity and natural gas prices are 27% and 21% greater than they were at the start of the decade. It is

not anticipated that this upward trend will be altered in the short to medium future. The Province of

Ontario has recently projected an annual 3.5% to 7.9% increase in electricity costs over the next 20 years.

Natural gas is also projected to trend upward.

WDMH, although a relatively new facility, has already experienced substantial patient growth and is

projected to grow into the future. As WDMH grows so will the Hospital’s environmental, societal, and

fiscal energy concerns. WDMH recognizes that proper energy management must be pursued if these

concerns are to be addressed.

Page 14: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 10

Growth in the Critical Care Centre is reflected in a decreasing patient days trend and an increasing

discharge volume.

Similar growth is being experienced in the Medical/Surgical area:

Page 15: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 11

6 SCOPE OF THE CDM PLAN

Winchester District Memorial Hospital

The WDMH facility is located at 566 Louise Street, Winchester, Ontario, and consists of a two-storey hospital with administrative

offices. The Hospital has an emergency ward, ECU, DI, rehabilitation, ambulatory area, haemodialysis, OH+S/IC ICT, continuing

care unit complex, maternity ward, surgical daycare unit, post-anaesthetic care, CSR, surgical suites, acute inpatient care unit,

cafeteria, pharmacy and administration and management offices.

The East wing of the building, which is the original hospital, was constructed circa 1947 and new wings D & Y were constructed

circa 2009. The building consists of two above grade levels. The facility has a mechanical room located at rooftop penthouse and

outside open parking.

Winchester District Memorial Hospital Facilities - General Information

Building Name Operation Type Address City

Postal

Code

Total Floor

Area

(m2)

Louise Harvey Dillabough Building Administrative Offices and related Facilities 550 Louise Street Winchester K0C 2KO 855.45

Winchester District Memorial Hospital - Admin Administrative Offices and related Facilities 566 Louise Street Winchester K0C 2KO 278.67

Winchester District Memorial Hospital - Main Facilities used for hospital purposes 566 Louise Street Winchester K0C 2KO 12,504.33

13,638.45

Page 16: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 12

Louise Harvey S. Dillabough Building

The Louise Harvey S. Dillabough facility is located at 550 Louise Street, Winchester, Ontario, and consists

of an old wing (North) and new wing (South). The old North wing of the building is a single story with a

basement used as a Staff boardroom and an administration office (diabetes education centre) on the

ground level, and a classroom, mechanical plant room and storage room in the basement. The new South

wing of the building is a single story which is used as a physician and surgeon’s clinic and medical

laboratory (known as Gamma Dynacare).

The North wing of the building, which is the original building, was constructed circa 1964 and the new

South wing was constructed circa 2009. The building has outside open parking.

Page 17: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 13

7 ENERGY BASELINE AND CURRENT ENERGY PERFORMANCE

Effectively managing energy requires implementing appropriate energy monitoring procedures. The

establishment of an accurate energy baseline is essential in this process. It will assist with energy

conservation and greenhouse gas reduction target setting, energy procurement and budgeting, bill

verification, energy awareness, and the selection and assessment of potential energy projects. WDMH,

like many hospitals, relies on its utility bills to establish its energy baseline.

Energy Audits were conducted on the two facilities in November 2013 by VIP Energy Services, Inc.

Winchester District Memorial Hospital

Louise Harvey S. Dillabough Building

The audits consist of a detailed analysis of historical consumption and demand information as well as a

walkthrough of the facility by a qualified energy auditor. Based on the auditor’s survey, a detailed

equipment list and an energy consumption breakdown have been created, as well as a comprehensive list

of potential energy conservation measures for each facility.

BASELINE PERFORMANCE (2011)

WDMH has elected to utilize the consumption data from 2011 to represent its baseline energy

consumption performance. Based on this information, and normalizing for weather conditions, the

baseline energy performance may be represented by a normalization analysis.

Winchester District Memorial Hospital Facilities - 2011 Energy

Building Name

Total Electricity

Consumption

(kWh)

Total Natural Gas

Consumption

(m3)

GHG

Emissions

(kg)

Energy

Intensity

(ekWh/m2)

Energy

Intensity

(GJ/m2)

Louise Harvey Dillabough Building 113,959 8,016 24,272 22 0.84

Winchester District Memorial Hospital - Admin 89,444 15,511 36,481 85 3.29

Winchester District Memorial Hospital - Main 4,013,514 695,999 1,636,956 85 3.29

4,216,917 719,526 1,697,709 81 3.13

Page 18: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 14

CURRENT PERFORMANCE (2012)

It is imperative to understand the energy characteristics of each facility. By understanding these values,

baselines can be established and future retrofits and improvements to the buildings can be monitored

and tracked to ensure that the intended benefits are fully realized. WDMH’s most recent energy

consumption inventory was completed in 2012. This inventory took into account the electricity and

natural gas consumption of WDMH facilities. In 2012 WDMH’s total energy use, including electricity and

natural gas, was 12,065,226 equivalent kilowatt hours (ekWh). This total consisted of 4,216,917 kWh of

electricity and 719,526 m3 of natural gas, which is equivalent to 8,013,982 ekWh. The 2012 combined total

cost of electricity and natural gas was $544,717.

Page 19: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 15

In all, WDMH has maintained its energy intensity from 2011 to 2012 indicating a stable energy utilization

from 3.13 GJ/m2 to 3.18 GJ/m2. Current consumption patterns are tracking well with the baseline

performance.

Building Name

Total Electricity

Consumption

(kWh)

Total Natural Gas

Consumption

(m3)

GHG

Emissions

(kg)

Energy

Intensity

(ekWh/ft2)

Energy

Intensity

(GJ/m2)

Louise Harvey Dillabough Building 37,870 6,378 15,088 11 0.44

Winchester District Memorial Hospital - Admin 87,491 16,299 37,815 87 3.37

Winchester District Memorial Hospital - Main 3,925,883 731,383 1,696,843 87 3.37

4,051,244 754,060 1,749,746 82 3.18

Winchester District Memorial Hospital Facilities - 2012 Energy

Page 20: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 16

BENCHMARKING

Market Sector

Energy Intensity (ekWh/ft2)

Sector Minimum Average Maximum No. of Organizations

Hospital 1.0 61 350 141

WDMH’s facilities have an average 82 ekWh/ft2 energy intensity, above the industry average based on the

Ministry of Energy’s 2011 Public Sector Energy Consumption Data. WDMH ranks 111th amongst the 141

hospitals in Ontario for energy intensity.

WDMH Facilities

The Louise Harvey Dillabough Building is primarily an office style facility and consumes significantly less

energy than the main hospital facility.

-

10

20

30

40

50

60

70

80

90

100

Louise Harvey DillaboughBuilding

Winchester DistrictMemorial Hospital - Admin

Winchester DistrictMemorial Hospital - Main

2012 Energy Intensity (ekWh/ft2)

Page 21: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 17

8 MISSION AND VISION

Our Mission

“The Winchester District Memorial Hospital provides local access to acute and complex

continuing care services requiring the expertise and technical support of an accredited hospital.”

Our Vision

“The Winchester District Memorial Hospital:

provides core hospital services to meet the current and evolving healthcare needs;

develops a range of services to meet the evolving healthcare needs of the

community through strengthening linkages with other local and regional service

providers;

plays an active role in enhancing the environment for patients, Staff and volunteers

through investments in people, technology and facilities; and

functions efficiently while adhering to established quality standards”.

WDMH addresses this vision through the application of foundational areas of focus: Commitment to

Quality, Working Together, Compassion and Respect. WDMH’s mission, vision and value set are outlined

in the Winchester District Memorial Hospital Strategic Plan 2013- 2018.

The CDM Plan has been developed to address the fiscal, societal, and environmental costs and risks

associated with energy consumption. Proper energy management will allow WDMH to display leadership,

improve the delivery of services, and enhance the overall quality of life with respect to the patient services

provided.

The CDM Plan outlines key actions that must be pursued to make this vision a reality. The completion of

these actions will assist WDMH to meet its energy conservation and greenhouse gas emission reduction

targets. Achieving these goals will assist WDMH in securing a strong energy management reputation and

will allow for cost savings that can benefit WDMH, its employees, and its patients.

It is acknowledged that, for this vision to come to fruition, energy management at WDMH must become

an inclusive process. Recognizing that energy affects everyone differently, this Plan was created to

address a variety of energy related concerns, while capturing innovative and relevant actions that will lead

to meaningful change.

This CDM Plan will allow energy management to be incorporated into all WDMH activities, including

organizational and human resource procedures, procurement practices, financial management and

investment decisions, and facility capital, operations, and maintenance.

Page 22: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 18

Overview

This CDM Plan is designed to meet the current energy needs and obligations of WDMH. The intent is to

guide WDMH in the development of an energy management foundation. This will be a living Plan that will

evolve as WDMH’s energy needs are revealed and better understood.

WDMH’s approach to energy management is three pronged. It begins with:

Elimination of waste,

Improving efficiencies, and

Optimizing energy supply.

Prior to pursuing these actions, WDMH must be aware of the facility and Staff behaviours that influence

energy consumption. Once encapsulated, this knowledge must be dispersed throughout the organization,

allowing for the development of a culture of sustainability.

An improved understanding of corporate energy consumption will require improvements in energy

management and awareness. Energy awareness campaigns will strive to make energy a tangible asset that

Staff Members can appreciate when it is being consumed or wasted. In addition to increasing energy

awareness, this energy Plan will integrate energy efficiency into the capital and operational decision

making of the organization.

Page 23: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 19

9 GOALS AND OBJECTIVES

It is of critical importance to improve energy efficiency and reduce our operating costs. Equally important

is displaying our commitment to the environment through the reduction of greenhouse gases, while

improving our air quality. It is also important that these actions are carried out without adversely

impacting WDMH’s operations. All WDMH Staff will have an essential role in the success of this energy

management Plan. It will be the responsibility of the Energy Management Team to ensure that energy

management measures are properly communicated and effectively implemented. An Energy Mandate for

WDMH has been developed and is an integral component of this CDM Plan.

WDMH’s CDM Plan was completed to help support the following Strategic Directions and Priorities:

Strengthen our current patient care and rural health education programs,

o Strengthen the volume, quality and efficiency of our current clinical services and enhance our academic programs,

o Continue to support the ongoing professional development needs of our Staff, physicians and volunteers,

Fill key gaps in our communities’ needs through collaboration,

o Develop and improve coordination, access and quality of palliative care services by working with key partners,

o Develop an integrated approach to meet the health needs of seniors and improve their quality of life,

o Continue to collaborate with local and regional partners to support the broader health and care needs of our communities,

Develop and implement a rural population health research program,

o Develop and implement a plan to advance WDMH’s research program and increase our research capabilities, and

o Enhance capabilities to understand and apply evidence to support quality decision making.

The primary objective of this Plan is to improve the management of WDMH’s energy consumption to

support these Strategic Directions and Priorities. Part of this objective is setting a conservation target that

will see WDMH reduce its 2011 energy consumption by 3% by the end of 2018. Recognizing that WDMH

is a growing hospital, WDMH energy conservation target will be intensity based. It is also the objective of

this Plan to improve WDMH’s understanding of energy consumption which is essential for WDMH to meet

its corporate energy management goals.

Page 24: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 20

Measurements of Success

The measurements of success will be based on a variety of indicators:

Reaching the CDM Plan’s energy conservation target,

Achieving the savings outlined in the Plan’s budget section, and

Imbedding energy management in WDMH’s capital and operations decision making process.

WDMH will follow the guidelines set out by the International Process Measurement and Verification

Protocol (IPMVP) to determine the energy conservation and demand management performance.

Reporting Standards

The CDM Plan will allow for the monitoring and reporting that is necessary for WDMH to meet the

regulatory requirements of the Green Energy Act. Regular energy monitoring and feedback to the

Ministry, WDMH Management and Staff will improve knowledge and help make energy consumption a

tangible asset, making possible appropriate behavioural changes. The intent of monitoring and reporting

on energy consumption is to make energy management transparent and the consumer accountable. The

Ministry will be provided with annual updates on the state of energy management at WDMH. Energy

consumption feedback provided to Staff will be imbedded into WDMH’s regular business.

Page 25: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 21

10 ENERGY MANAGEMENT TEAM

Historically, WDMH has addressed Energy Conservation and Demand Management on a project-by-

project basis through the activities of the Building Services Team. Strategic directives have been provided

by the Hospital’s Senior Executive Team.

This CDM Plan outlines a commitment to integrate Energy Conservation and Demand Management into

the operations of the Hospital, as indicated in the covering letter from the Senior Vice President of

Corporate Services. Within the duration of the CDM Plan, CDM planned activities will become an integral

component of the annual budgeting process. A collaborative effort will be undertaken to achieve this

integration, involving:

Internal Staff (which may include but will not be limited to Facilities Management, Finance, and Procurement),

Advisement from the Ministry of Energy and Ministry of Health, and

Consultations with Energy Management experts.

Page 26: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 22

11 FINANCIAL ASSESSMENT

The energy Conservation and Demand Management Plan’s financial assessment philosophy is to treat

fiscal resources as if they were energy assets. Therefore, financial investments follow the same three

pronged approach used for the management of energy:

Elimination of waste,

Improving efficiencies, and

Optimizing energy supply.

The initial costs and savings estimates for the proposed process improvements, program implementation,

and projects are broken down as follows:

Opportunity at WDMH Total

Savings Cost

Payback Period (years)

Building Re-Commissioning - Detail Engineering Study

$67,476 $80,000 0.6

McQuay BAS Upgrade $3,512 $14,500 3.5

Upgrade and Integrate all Split A/C with Single Variable Refrigerant Flow Unit (VRF)

$6,085 $42,000 5.7

Install Energy Recovery Ventilation(ERV)for Exhaust Fans

$2,719 $38,000 12.9

Building Envelop Insulation $4,214 $25,000 5.5

Lighting Upgrade $1,630 $28,500 16.9

Install Load Managing Device for Vending Machine $580 $3,000 4.0

OPA Feed-in Tariff $35,000 $227,500 6.5

Upgrade All Standard Efficient Motors to Super Premium Efficiency Motors

$6,901 $69,850 9.8

Replace Old Hot Water Baseboard Heater (East Wing)

$25,506 $28,000 1.1

Install Solar Thermal Panel for DHW Pre-Heating $2,152 $8,800 4.1

Install Combined Heat & Power Unit (CHP) $186,382 $600,000 1.9

Hot Water Pipes & Joints Insulation for Steam Boiler

$189 $6,200 32.9

Install Water Aerators $3,669 $1,800 0.5

Install Low Flush Toilets $1,688 $13,300 7.9

Energy and Resource Awareness $24,044 $52,034 1.3

TOTAL $371,747 1,238,484 2

Page 27: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 23

Opportunity at Louise Harvey Dillabough Building Savings Cost Payback Period (years)

HVAC-Control System - Deadband Reset $418 $200 0.5

Lighting Upgrade $759 $760 1.0

Install Demand Control for DHW Pump $174 $1,000 5.8

Install Programmable Thermostats for Baseboard Heaters $1,181 $2,400 2.0

Replace Existing Water Coolers with Energy Star Water Coolers $1,134 $1,200 1.1

Replace Domestic Hot Water Heater $157 $2,200 14.0

Install E-Film to Improve Window Insulation $215 $4,600 21.4

Install Water Aerators $124 $700 5.6

Energy and Resource Awareness $489 $6,007 12.3

TOTAL $4,653 $19,067 4.1

The listed costs and savings are for the inaugural year of a process, program, or project. If initiated and

monitored effectively, it can be anticipated that these savings can be sustained. It should also be noted

that the price of energy is anticipated to increase, whereas the costs of capital projects will likely decrease

with advancements in technology. This could potentially lead to increased savings and decreased costs in

the later years of the Plan. The potential for avoided costs adds to the relevance of a plan of this nature.

This fiscal assessment does not take into account the economic benefits of achieving all of the corporate

energy management goals. Due to the difficulty in quantifying the economic value of extended equipment

longevity, improved comfort and productivity, and climate change mitigation, it should not be discounted.

Page 28: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 24

12 CORPORATE ENERGY BUDGET

The following budget was derived from the planned actions within the CDM Plan. Each year’s estimated

cumulative savings have also been displayed. These projected costs and savings do not consider the

human resource expenditures.

Prior to requesting funding for energy actions, WDMH will consult with utility representatives and/or

energy consultants, allowing WDMH to schedule project launch dates in parallel with applicable incentive

funding programs. The projects may be moved forward or delayed based on changes to incentive

programs as well as changes to the CDM Plan. However, WDMH will not make significant alterations to

the Plan in a quest for incentive funding. This is not a prudent approach to planning. Actions will be

pursued only when they coincide with the WDMH’s objectives and are appropriate to be pursued at that

time.

As WDMH continues to evolve and its energy needs become greater it will be essential to reassess and

clarify as necessary the financial indicators that are applied to investment analysis and prioritization of

proposed energy projects. Energy efficiency projects must be weighted appropriately relative to other

investment needs. There will also be a need to develop procedures for the annual allocation of capital

resources for energy efficiency measures in the capital budget.

Page 29: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 25

13 ENERGY MANAGEMENT ACTIONS

The economic feasibility of proposed actions played a large role in the prioritization of the processes,

programs, and projects. Equally important in this prioritization exercise was the evaluation of WDMH’s

internal capacity to complete the proposed initiatives. Recognizing the need to develop WDMH’s internal

capacity, the initial years of the Plan focus heavily on processes and programs. The implementation of the

recommended processes and programs will result in an improved understanding and awareness of energy

consumption. This will allow for improved decision making and greater success with future energy projects

(See Appendix C for the CDM Plan timeline). As these actions are completed, the Energy Management

Team will meet to discuss monitoring results and how they can be used to enhance the Plan. The CDM

Plan is intended to be a living document. Anticipated improvements in knowledge and capacity will result

in enhancement of the proposed actions.

Annual Reporting

An Annual Conservation and Demand Management Plan Update Report will be provided that details

WDMH’s activities and results relating to this 2014-2018 Energy Conservation and Demand Management

(CDM) Plan. The Report will describe the CDM Plan related activities that have happened in the previous

year and will focus on linking actions to results. In addition, the Report will take a forward view of the

upcoming year to lay out the roadmap and identify any changes or adjustments that should be considered

based on what the current market conditions are. The overarching goal of the report is to make the 5 year

CDM Plan a living document that is reviewed and updated on a yearly basis.

Future Energy Projects

Energy projects at WDMH were evaluated prior to the development of the CDM Plan. WDMH Staff

Members have advocated for some ambitious energy initiatives that were investigated and determined

to be not feasible for a variety of reasons. It is anticipated that as WDMH grows and energy management

practices improve these actions will be reassessed.

Page 30: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 26

Future Energy Reduction Projects Summary

Year Action Planned - Hospital

2014

Energy awareness training.

BAS functional performance testing.

Primary heating and cooling equipment functional performance testing

Kitchen hood controls upgrade

2015

Conference room lighting upgrade

Installation of occupancy sensors

Water aerator installation

2016

Cogeneration study to be conducted

Replacement of motors with high efficiency models

Energy awareness training.

2017 To be established in future budgeting activity

2018 To be established in future budgeting activity

Future Energy Reduction Projects Summary

Year Action Planned - Louise Harvey Dillabough Building

2014 Energy awareness training.

E1 lighting upgrade.

2015 E4 and W1 lighting upgrade

2016 Energy awareness training.

2017 To be established in future budgeting activity

2018 To be established in future budgeting activity

Renewable Energy

Feasibility and promotion of renewable energy technologies will be examined throughout the duration of

the CDM Plan. These technologies have not yet been incorporated into the CDM Plan but will be included

when and where it made sense to do so, strategically or fiscally.

Page 31: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 27

Purchasing Practices

Traditionally, purchasing practices in the public sector were designed to favour equipment or physical

retrofits at the lowest cost in order to ensure the highest possible financial responsibility. As energy

conservation best practices emerged, it was revealed that there is a major issue in doing this. Almost all

wasteful energy consuming equipment is less expensive than their energy conserving counterparts. The

practice in itself does not encourage energy efficiency, as most energy intensive alternatives such as

standard efficiency motors are less costly than their higher efficiency counterparts. When dealing with

energy intensive hardware, the initial capital cost is only a fraction (5%-10%) of the total lifecycle cost.

The practice of ‘low bidder wins’ purchasing limits the Staff when trying to make the right environmental

decision. Making a specific amount of money available to include the conservation upgrades allows the

Hospital to take advantage of necessary investments in order to reduce their impact on the bottom line

after the cost of purchase. For example, when purchasing a motor, all suppliers will specify standard

efficiency motors. An energy smart buyer will know that 90%+ of the motor’s lifecycle cost is in its energy

use. Therefore, buying a premium efficiency motor at a small incremental cost has a payback of less than

three years. Missing this opportunity translates into a long-term financial increase. In fact, the incremental

cost between a less efficient and a more efficient alternative is often less than 5% of the capital cost. That

5% capital cost difference is often recuperated in less than three years. This allows Staff to make the right

environmental decision based on industry best financial practices.

Energy Management and Information Systems

An Energy Management and Information System (EMIS) is an important element of a comprehensive

Energy Management Program (EMP), as it helps to ensure that the full benefits of other energy

conservation efforts are achieved and sustained. In fact, a quality EMIS can reduce energy use and cost

by at least 5%. (Reference: Office of Energy Efficiency, National Resources Canada). Current industry and

international standards, such as the International Performance Measurement & Verification Protocol

(IPMVP), use an average of an 8%-10% reduction in energy consumption and costs. VIP Energy Services

has documented a conservation average of 17% over customers served to date. However, in order to be

as conservative as possible in its financial calculations, VIP generally uses NRCan's conservative numbers

(5%) to ensure objectivity in the investment matter. The savings from an EMIS result from the following

measured impacts:

Early detection of poor performance,

Support for optimal decision making,

Effective performance reporting,

Auditing of historical performance,

Identification and justification of energy projects,

Page 32: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 28

Evidence of implementation success,

Support for energy budgeting and accounting, and

Provision of energy data to other systems (such as Building Automation Systems, BAS).

When looking at performance reports, an EMIS facilitates ensuring that upgrades or changes actually meet

forecasted savings, as well as the quantification of losses or gains. However, it is important to note that

placing meters to isolate individual retrofit projects determined by their scope is generally cost ineffective

and typically does not allow incorporation of out-of-scope project factors that directly affect equipment

performance.

A one-time, comprehensive metering solution allows for a much more cost effective view, while enabling

accountability to 90% of the planned projects budgeted to date. Reporting can be the most essential part

of this plan as multiple portions of the organization rely on this data to make periodic decisions. The

Finance Team can use this information to verify billing accuracy and other potential costs, such as

construction back-charges. Energy Conservation Managers generally look at this data for building

performance, future opportunity and functional trending. Project Managers rely on this information to

ensure that vendors are supplying and meeting contractual obligations. Collecting the information in any

EMIS program is really only the first step, as the data must then be used to instigate change and push

action. This can only be done through analysis and warning systems built on baseline information. In order

for an EMIS system to function properly, communication loops must also be established between

departments for the maximum benefit to be realized. These systems can be as simple as an online Data

Storage, Retrieval and Reporting System using billing data to form the basis and baselines for future

comparison.

Building Re-Commissioning

Building re-commissioning, or retro-commissioning, refers to the optimization of the current automation,

controls and energy consuming systems. As buildings age, both the functionality of the equipment and

the functions that they serve can undergo significant changes. A re-commissioning program generally

focuses on ensuring that the equipment operations are modified to include any new or deleted duties.

The following is a list of common problems found in re-commissioning projects that result in increased

energy costs:

Inefficient scheduling of HVAC equipment,

Simultaneous heating and cooling,

Economizer sequences not optimized,

Incorrect airflow and water balance,

Malfunctioning sensors or incorrect calibration,

Fan VFD control overridden,

Page 33: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 29

Supply air static pressure set-points not optimized,

Boiler controls not operating efficiently,

Balancing dampers and valves not installed or installed in poor or unusable locations,

Incorrectly piped water coils,

Process or space classification changes (lab space to office, etc.),

Incomplete or incorrect control component installation,

Control sequence incorrectly implemented,

Substituted control components,

Incomplete installations (missing control valve, actuators, etc.), and

Testing, adjusting, and balancing (TAB) not completed or only partially completed.

National Resources Canada (NRCan) has published several guidelines for costing and expected returns

from re-commissioning projects. Building re-commissioning is an increasingly important practice, not only

from an energy standpoint, but also from a comfort and safety perspective as well. The more complex

building controls and ventilation become, the more risk there is that one or more components fail or

deliver incorrect measurements.

Current practices in re-commissioning indicate that the cost to complete these initiatives is between $2.90

and $4.50/m2. Expected savings from the projects are typically between $1.00 and $4.00/m2, depending

on the starting efficiency of the building, creating very attractive paybacks in this area.

Energy and Resource Awareness (ERA) Programs

Independent studies done by organizations such as Natural Resources Canada (NRCan) and the Ontario

Hospital Association (OHA) show that initiatives directed at Staff and facility users, in particular ERA

Programs, can lead to significant savings on their own. In fact, the OHA reports indicate that dedicated,

consistent Energy Awareness Programs are proven to be the most effective way to reduce energy usage

with no capital costs and minor operational expenses. A conservative estimate of savings for an effective

ERA Program can be as high as 5%-7% of annual utilities spending.

An effective ERA Program is designed to assist organizations to attain energy savings by promoting a

fundamental shift in the personal philosophies of Staff and facility users towards reducing their energy

use. The Program utilizes community-based social marketing to develop influential communication

materials and in-house displays that are carefully designed to inform and motivate employees to

effectively decrease energy consumption. In many cases, an ERA Program has proven to be the most

effective way to lower energy usage without any capital costs and minimal operational expenses. A typical

ERA Program would include features such as:

A detailed ERA Program written plan including a GANTT chart,

Page 34: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 30

The creation of a program email address for suggestions and concerns and access to ERA experts to answer questions,

A customized identity and marketing program,

Training and support for an Energy Steward Team,

ERA displays with various relevant conservation themes, and

Annual Marketing Effectiveness Reports and Feedback system.

A continuous and consistent ERA Program is not only an effective way to lower energy use within a facility,

but can also serve to be an effective marketing tool to spread the word that the Hospital is a community

leader in energy conservation and environmental sustainability.

To embark upon this education journey, WDMH joined forces with NRCAN to provide a two-day Dollars

to $ense Spot the Savings Workshop, in March of 2014. A copy of the invitation to attend the session is

provided in Appendix D. The workshop was geared toward identifying a learning opportunity to: identify

the seven steps to understanding energy use in the Hospital: identify energy conservation opportunities

and prioritize them; and, evaluate the advantages of energy efficiency.

Page 35: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 31

APPENDIX A

Energy Data

Page 36: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 32

Page 37: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 33

ENERGY CONSUMPTION

Page 38: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 34

Page 39: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 35

Page 40: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 36

Page 41: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 37

APPENDIX B

Energy Use Breakdown

Page 42: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 38

Page 43: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 39

ENERGY USE BREAKDOWN

The occupancy of the WDMH, on average, was 300 persons (including Staff and patients) and being a

hospital did not vary significantly over the course of the analysis period. Hence, the seasonal patterns of

energy consumption remain fairly constant. Monthly consumption data was obtained from Hydro One

Networks Inc. electricity bills, and from Union Gas bills.

Electricity

Based on the horsepower or kilowatt rating of the equipment and estimated hours of operation, the

energy mass balance of electricity usage indicates that the HVAC system uses the most electricity. The

HVAC accounts for the highest electricity consumption of 58.21% followed by Ward equipment at 10.44%,

Lighting at 5.61%, Cafeteria at 4.98%, Boiler Equipment at 4.83%, Appliances at 4.80%, Exhaust Fans at

3.68%, Air Compressors at 2.30%, Elevators at 1.72%, Office Equipment at 1.54%, Domestic Hot Water

Pumps at 1.28%, Work shop equipment at 0.45%, Duct/Unit Heaters at 0.12% and Process pumps/Other

at 0.04%.

Electricity is the primary source for cooling and can be partly interpreted based on seasonal consumption.

Apart from the baseload, it is evident that the electricity consumption for the year is dependent upon

seasonal demand for cooling.

* Note: Total sum value of percentages may not be 100% due to rounding. See the appendix with listed equipment values for

exact figures.

Page 44: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 40

Natural Gas

Natural gas is used for heating and for the provision of domestic hot water (DHW). As natural gas is used

primarily for heating, it can be interpreted based on seasonal consumption. It is evident that natural gas

consumption for the year is based on seasonal demand for heating the space.

Various factors, in addition to weather, could affect consumption levels:

Patient Occupancy,

Reduction in working/operating hours from last year,

Improvement in building envelope,

Keeping doors closed, and

Improved maintenance and operating procedures.

Based on the BTU ratings of each piece of equipment and usage, the energy mass balance of natural gas

indicates that the Boilers use the most natural gas with a consumption of 74.74%; followed by the DHW

supply at 17.39%, HVAC (for RTU & MAU) at 7.11%, and the Cafeteria/Kitchen at 0.76%.

* Note: Total sum value of percentages may not be 100% due to rounding. See the appendix with listed equipment values for

exact figures.

Page 45: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 41

Water

The energy mass balance of water usage indicates that 32.63% of water is used by Wards for different

activities followed by Sinks at 25.02%, the Cafeteria/Kitchen (including cooking) at 16.31%, HVAC

(including humidifiers) at 10.88%, Water Closets at 10.45%, Showers at 2.54% and Boilers (makeup water)

at 2.18%.

* Note: Total sum value of percentages may not be 100% due to rounding. See the appendix with listed equipment values for

exact figures.

Page 46: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 42

Page 47: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 43

APPENDIX C

Energy Conservation Measure Schedules

Page 48: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

P a g e 44

Page 49: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

Page | 1

Winchester District Memorial Hospital Energy Management Strategies

Annual Energy Savings Annual Cost Savings Estimated Installation Costs

EMS # Opportunity Electricity (kWh/yr)

Electricity Demand (kW/yr)

Natural Gas

(m3/yr)

Water (m3/yr)

Electricity ($.0848 /kWh)

Demand ($13.06

/kW)

Natural Gas ($.1318

/m3)

Water ($2.11 /m3)

Total Savings

Cost Incentives Cost with Incentives

Payback Period with

Incentives (years)

Total Energy Savings (GJ/yr)

tCO2e Savings

E01 Building Re-Commissioning - Detail Engineering Study

533,426 0 168,715 0 45,233 0 22,243 0 $67,476 $80,000 $40,000 $40,000 0.6 1,915 578.71

E02 McQuay BAS Upgrade 23,174 0 11,733.0 0 1,965 0 1,547 0 $3,512 $14,500 $2,317 $12,183 3.5 86 37.14

E03 Upgrade and Integrate all Split A/C with Single Variable Refrigerant Flow Unit (VRF)

71,765 0 0 0 6,085 0 0 0 $6,085 $42,000 $7,176 $34,824 5.7 244.9 16.00

E04 Install Energy Recovery Ventilation(ERV)for Exhaust Fans

29,883 0 1,404 0 2,534 0 185 0 $2,719 $38,000 $2,988 $35,012 12.9 103 10.49

E05 Building Envelop Insulation 19,162 0 19,638 0 1,625 0 2,589 0 $4,214 $25,000 $1,916 $23,084 5.5 76 57.79

E06 Lighting Upgrade 19,227 0 0 0 1,630 0 0 0 $1,630 $28,500 $961 $27,539 16.9 66 4.29

E07 Install Load Managing Device for Vending Machine 6,843 0 0 0 580 0 0 0 $580 $3,000 $684 $2,316 4.0 23 1.53

E08 OPA Feed-in Tariff 0 0 0 0 0 0 0 0 $35,000 $227,500 $0 $227,500 6.5 0 0.00

E09 Upgrade All Standard Efficient Motors to Super Premium Efficiency Motors

78,800 17 0 0 6,682 219 0 0 $6,901 $69,850 $2,075 $67,775 9.8 269 17.57

F01 Replace Old Hot Water Baseboard Heater (East Wing)

0 0 193,464 0 0 0 25,506 0 $25,506 $28,000 $0 $28,000 1.1 109 527.19

F02 Install Solar Thermal Panel for DHW Pre-Heating 0 0 16,320 0 0 0 2,152 0 $2,152 $8,800 $0 $8,800 4.1 9.2 44.47

F03 Install Combined Heat & Power Unit (CHP) 0 0 0 0 183,163 3,219 0 0 $186,382 $600,000 $240,000 $360,000 1.9 0 0.00

F04 Hot Water Pipes & Joints Insulation for Steam Boiler

0 0 1,430 0 0 0 189 0 $189 $6,200 $0 $6,200 32.9 0.8 3.90

W01 Install Water Aerators 0 0 0 1,739 0 0 0 3,669 $3,669 $1,800 $0 $1,800 0.5 0 0.00

W02 Install Low Flush Toilets 0 0 0 800 0 0 0 1,688 $1,688 $13,300 $0 $13,300 7.9 0 0.00

B01 Energy and Resource Awareness 198,968 0 35,043 1,210 16,872 0 4,620 2,552 $24,044 $52,034 $20,815 $10,407 1.3 699 139.86

TOTAL 981,247 17 447,747 3,749 $266,371 $3,439 $59,031 $7,909 $371,747 1,238,484 $318,932 $919,552 2 3,600 1,439

Page 50: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

Page | 2

Louise Harvey Dillabough Building Energy Management Strategies

Annual Energy Savings Annual Cost Savings Estimated Installation Costs

EMS # Opportunity Electricity (kWh/yr)

Electricity Demand (kW/yr)

Natural Gas

(m3/yr) Water (m3/yr)

Electricity ($.1287/kWh)

Demand ($0/kW)

Natural Gas ($.2314/m3)

Water ($2.11/m3)

Total Savings Cost Incentives

Cost with Incentives

Payback Period with

Incentives (years)

Total Energy Savings (GJ/yr)

tCO2e Savings

E01 HVAC-Control System - Deadband Reset 3,000 0 140 0 $386 $0 $32 $0 $418 $200 $0 $200 0.5 1.05 1.05

E02 Lighting Upgrade 5,898 0 0 0 $759 $0 $0 $0 $759 $760 $0 $760 1.0 1.32 1.32

E03 Install Demand Control for DHW Pump 617 0 407 0 $79 $0 $94 $0 $174 $1,000 $0 $1,000 5.8 1.25 1.25

E04 Install Programmable Thermostats for Baseboard Heaters 9,180 0 0 0 $1,181 $0 $0 $0 $1,181 $2,400 $0 $2,400 2.0 2.05 2.05

E05 Replace Existing Water Coolers with Energy Star Water Coolers 8,813 0 0 0 $1,134 $0 $0 $0 $1,134 $1,200 $0 $1,200 1.1 1.97 1.97

F01 Replace Domestic Hot Water Heater 0 0 678 0 $0 $0 $157 $0 $157 $2,200 $0 $2,200 14.0 1.85 1.85

F02 Install E-Film to Improve Window Insulation 1,458 0 119 0 $188 $0 $28 $0 $215 $4,600 $0 $4,600 21.4 .65 0.34

W01 Install Water Aerators 0 0 0 59 $0 $0 $0 $124 $124 $700 $0 $700 5.6 0.00 0.00

B01 Energy and Resource Awareness 2,868 0 330 21 $369 $0 $76 $44 $489 $6,007 $0 $6,007 12.3 1.54 1.54

TOTAL 31,835 0 1,674 80 $4,097 $0 $387 $168 $4,653 $19,067 $0 $19,067 4.1 12 11.3

Page 51: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

Page | 3

Winchester District Memorial Hospital Projected Energy Conservation Savings and investment

EMS # Savings 2013-2014 2014-2015 2015-2016 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021 2021-2022 2022-2023 Total

E01 Building Re-Commissioning - Detail Engineering Study 67,476 66,127 64,804 63,508 62,238 60,993 59,773 58,578 57,406 56,258 617,161

E02 McQuay BAS Upgrade 3,512 3,442 3,373 3,305 3,239 3,175 3,111 3,049 2,988 2,928 32,121

E03 Upgrade and Integrate all Split A/C with Single Variable Refrigerant Flow Unit (VRF) 6,085 5,964 5,844 5,728 5,613 5,501 5,391 5,283 5,177 5,074 55,660

E04 Install Energy Recovery Ventilation(ERV)for Exhaust Fans 2,719 2,665 2,611 2,559 2,508 2,458 2,409 2,361 2,313 2,267 24,870

E05 Building Envelop Insulation 4,214 4,130 4,047 3,966 3,887 3,809 3,733 3,658 3,585 3,513 38,542

E06 Lighting Upgrade 1,630 1,598 1,566 1,535 1,504 1,474 1,444 1,415 1,387 1,359 14,912

E07 Install Load Managing Device for Vending Machine 580 569 557 546 535 525 514 504 494 484 5,307

E08 OPA Feed-in Tariff 35,000 34,300 33,614 32,942 32,283 31,637 31,004 30,384 29,777 29,181 320,123

E09 Upgrade All Standard Efficient Motors to Super Premium Efficiency Motors 6,901 6,763 6,628 6,495 6,366 6,238 6,113 5,991 5,871 5,754 63,121

F01 Replace Old Hot Water Baseboard Heater (East Wing) 25,506 24,995 24,496 24,006 23,525 23,055 22,594 22,142 21,699 21,265 233,283

F02 Install Solar Thermal Panel for DHW Pre-Heating 2,152 2,109 2,066 2,025 1,985 1,945 1,906 1,868 1,830 1,794 19,679

F03 Install Combined Heat & Power Unit (CHP) 186,382 182,655 179,002 175,422 171,913 168,475 165,105 161,803 158,567 155,396 1,704,720

F04 Hot Water Pipes & Joints Insulation for Steam Boiler 189 185 181 177 174 170 167 164 160 157 1,724

W01 Install Water Aerators 3,669 3,595 3,524 3,453 3,384 3,316 3,250 3,185 3,121 3,059 33,557

W02 Install Low Flush Toilets 1,688 1,654 1,621 1,589 1,557 1,526 1,495 1,465 1,436 1,407 15,439

B01 Energy and Resource Awareness 24,044 23,564 23,092 22,630 22,178 21,734 21,300 20,874 20,456 20,047 219,919

Total Savings $371,748 $364,313 $357,026 $349,886 $342,888 $336,030 $329,310 $322,724 $316,269 $309,944 $3,400,138

EMS # Cost (Investment) 2013-2014 2014-2015 2015-2016 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021 2021-2022 2022-2023 Total

E01 Building Re-Commissioning - Detail Engineering Study $80,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $80,000

E02 McQuay BAS Upgrade $14,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $14,500

E03 Upgrade and Integrate all Split A/C with Single Variable Refrigerant Flow Unit (VRF) $42,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $42,000

E04 Install Energy Recovery Ventilation(ERV)for Exhaust Fans $38,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $38,000

E05 Building Envelop Insulation $25,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $25,000

E06 Lighting Upgrade $28,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $28,500

E07 Install Load Managing Device for Vending Machine $3,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,000

E08 OPA Feed-in Tariff $227,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $227,500

E09 Upgrade All Standard Efficient Motors to Super Premium Efficiency Motors $69,850 $0 $0 $0 $0 $0 $0 $0 $0 $0 $69,850

F01 Replace Old Hot Water Baseboard Heater (East Wing) $28,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $28,000

F02 Install Solar Thermal Panel for DHW Pre-Heating $8,800 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,800

F03 Install Combined Heat & Power Unit (CHP) $600,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $600,000

F04 Hot Water Pipes & Joints Insulation for Steam Boiler $6,200 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,200

W01 Install Water Aerators $1,800 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,800

W02 Install Low Flush Toilets $13,300 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,300

B01 Energy and Resource Awareness $52,034 $0 $0 $0 $0 $0 $0 $0 $0 $0 $52,034

Total Cost (Investment) $1,238,484 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,238,484

Annual Surplus/Deficit -$866,737 $364,313 $357,026 $349,886 $342,888 $336,030 $329,310 $322,724 $316,269 $309,944 $2,161,653

Net Present Value (vs. 2% inflation) $1,850,076

Page 52: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

Page | 4

Louise Harvey Dillabough Building Projected Energy Conservation Savings and Investment

EMS # Savings 2013-2014 2014-2015 2015-2016 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021 2021-2022 2022-2023 Total

E01 HVAC-Control System - Deadband Reset 418 410 402 394 386 378 371 363 356 349 3,828

E02 Lighting Upgrade 759 744 729 715 700 686 673 659 646 633 6,944

E03 Install Demand Control for DHW Pump 174 170 167 163 160 157 154 151 148 145 1,588

E04 Install Programmable Thermostats for Baseboard Heaters 1,182 1,158 1,135 1,112 1,090 1,068 1,047 1,026 1,005 985 10,807

E05 Replace Existing Water Coolers with Energy Star Water Coolers 1,134 1,112 1,089 1,068 1,046 1,025 1,005 985 965 946 10,375

F01 Domestic Hot Water Heater 157 154 151 148 145 142 139 136 134 131 1,436

F02 Install E-Film to Improve Window Insulation 215 211 207 203 198 195 191 187 183 179 1,968

W01 Install Water Aerators 124 122 120 117 115 113 110 108 106 104 1,139

B01 Energy and Resource Awareness 489 480 470 461 451 442 434 425 416 408 4,476

Total Savings $4,653 $4,560 $4,469 $4,380 $4,292 $4,206 $4,122 $4,040 $3,959 $3,880 $42,560

EMS # Cost (Investment) 2013-2014 2014-2015 2015-2016 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021 2021-2022 2022-2023 Total

E01 HVAC-Control System - Deadband Reset $200 $0 $0 $0 $0 $0 $0 $0 $0 $0 $200

E02 Lighting Upgrade $760 $0 $0 $0 $0 $0 $0 $0 $0 $0 $760

E03 Install Demand Control for DHW Pump $1,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,000

E04 Install Programmable Thermostats for Baseboard Heaters $2,400 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,400

E05 Replace Existing Water Coolers with Energy Star Water Coolers $1,200 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,200

F01 Domestic Hot Water Heater $2,200 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,200

F02 Install E-Film to Improve Window Insulation $4,600 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,600

W01 Install Water Aerators $700 $0 $0 $0 $0 $0 $0 $0 $0 $0 $700

B01 Energy and Resource Awareness $6,007 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,007

Total Cost (Investment) $19,067 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,067

Annual Surplus/Deficit -$14,414 $4,560 $4,469 $4,380 $4,292 $4,206 $4,122 $4,040 $3,959 $3,880 $23,493

Net Present Value (vs. 2% inflation) $19,662

Page 53: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

Page | 1

APPENDIX D

Dollars to $ense Workshop

Page 54: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

Page | 2

Page 55: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

Page | 3

Page 56: Five Year Conservation and Demand Management Plan 2014-2018 Conservati… · P a g e 2 This CDM Plan is the culmination of a non-linear process involving the: Integration of establishing

Page | 4