FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

48
FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006

Transcript of FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

Page 1: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - NCSX Central Solenoid Support Structure

Fred Dahlgren

Joe Rushinski

6 Sept 2006

Page 2: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Charge:

Does the coil structure provide adequate support for the PF1a coils with sufficient margins of safety?

Have the interfaces with other sub-systems been defined and are they compatible?

Are the drawings and supporting documents complete and ready for sign-off?

Has the analysis been documented and checked?

Are the cost, procurement and assembly schedule consistent with the program schedule and budget?

Page 3: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

Design Description:

•The structure consists of solution annealed 304L stainless weldments fabricated mainly from 1/4”, 3/8”, 1/2” and 3/4” thick plate (µ < 1.02).

•The individual structural segments are 120 degrees with G-11CR insulating plates, bushings, and washers between the adjacent segments.

•A mid-plane sub-assembly will space the top & bottom PF1A coils (re-claimed from NSTX), at ± 40 cm from the mid-plane.

•The top and bottom sub-assemblies will have six 3/4” tie rods with nuts and belleville washers and will provide a 12,000 lb. axial pre-load clamping force on the two PF1A coils. The bellevilles’ will accommodate up to 0.015” of differential thermal contraction/expansion (~ 0.007” amount required).

•Twelve radial support arms (6-top & 6-bottom) will attach the solenoid structure to the main coil structure.

•All bolting materials (nuts, bolts, washers, etc.) will be 316 stainless.

FDR - Central Solenoid Support Structure - 9/6/06

Page 4: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

PF1a Coil Modification: Water fittings & tubes must be re-worked & re-insulated

Coil Description: 48 turn double layer spiral wound, 0.787” square CDA107 drawn Cu conductor with 0.354 dia. coolant hole. Insulation: 0.026” thk. CTD112P w/0.0065” Kapton-1/2-lapped (0.052” turn to turn) & 0.054” thk. ground wrap.

Coil Dimensions:

12.8” I.D.

16.26” O.D.

21.08” axial length

48 turns

Cu area: 0.52 sq.in.

Hole dia.: 0.354”

Leads: 12.6” & 16.9”

Fabr. Details see:

NSTX-SPEC-13-041

Page 5: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

PF1a Coil/Structure Assembly - Pre-assembled

Page 6: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

111.5”

Page 7: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Assembly will have ~55” clearance for lift

Page 8: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

Materials:

304L solution annealed plates

ER316LN weld filler

316L nuts, bolts, washers, & rods

G10/11CR insulating plates @ 120 deg.

G10/11CR washers & bushings

Copper tubing

Brass Swagelok (B-600 series) tube fittingsInterfaces:

Cryogen cooling lines connect to top & bottom LN2 feed/return lines. Pressure & flow requirements defined, connecting lines (with insulating breaks) to cryogen supply & return plenums are needed. Four thermocouples are required to monitor coil inlet/outlet.

Bus pads at the top & bottom locations are defined. Bus connection to power supply are needed. Bus interface defined, scenario A.1.3.4 defines the current & voltage requirements.

Top & bottom mounting pads bolt to same threaded holes to be used for permanent solenoid supports. Loading @ support interface defined.

Page 9: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

*

* From Allegheny Ludlum Technical Data Blue Sheet

Page 10: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

2/3rd Yield allowable @80K = 46.6ksi

304L Properties*

* From Allegheny Ludlum Technical Data Blue Sheet

Page 11: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Cooling analysis:

Cooling Analysis Shows < 1 deg.K rise per pulse & no ratcheting

Plot of the PF1a exit temperature vs. time

DP = 10 psi

Qdot = 1.14 GPM

AMPS = 19.3 kA

ESW = 0.16 sec.

Rep.Rate = 900 sec.

0.787

Ø 0.354

Page 12: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

FEA Model of PF1A & Supporting Structure:

• A 1/6th-Upper half Nastran linear FEA model was used.

• PF1A coil modeled as discrete turns with insulating layers (CHEXA & CPENTA).

• Structural components modeled with plate elements (CQUAD4 & CTRIA3).

• Tie rods modeled with solid elements (CHEXA & CPENTA).

• Bolts modeled with CBAR elements attaching plates & adjacent weldments.

• EM loads on PF1A determined from dforce7b (Biot-Savart - U.C. code).

• Symmetry boundary conditions were applied (toroidal, vertical and rotational).

• Coil top & bottom surfaces not permitted to slide radially (rel. to supports).

• Model Summary:

Number of GRID Points = 21979 Number of CBAR Element = 57 Number of CHEXA Elements = 13232 Number of CPENTA Elements = 1696 Number of CQUAD4 Elements = 2287 Number of CTRIA3 Elements = 170

• Loading Conditions considered:

Gravity, EM, Thermal, Seismic

Page 13: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

3/4” Tie Rod / belleville washer, and bolted connection modeled

Page 14: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

PF1A Coil Model: CPENTA & CHEXA isotropic Cu & Epoxy Glass

Page 15: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Loads considered:

Gravity Loads with 1g & 2g vertical downward, B.C.: Symmetry & fixed at the upper bracket bolts (attached to the inner segmented ring castings which are assumed rigid).

Horizontal seismic loading using static 0.15g acceleration per the NCSX/IBC2000 criteria (h~15ft, Fp=0.108 x 1.369 = 0.147 ~ 0.15g).B.C.: Symmetry & fixed @ upper bracket bolts.

Thermally induced stress from cool down and temperature differentials using mean CTEs from R.T. to 77 oK. B.C.: Symmetry & fixed @ upper bracket bolts. (CTE-Cu from NIST data, CTE-304L from ITER data)

Electro-magnetic loading for coil day-1 scenario A.1.3.2: Ipf1a = 19,299 A & 23,500 A (simulates M.C. loading)Ipf4 = 3,141 AIpf6 = 241 AIpl = -26,068 A & 0.0 A(Ipl = 0.0 was highest loading)

B.C.: Symmetry & fixed @ upper bracket bolts.

Page 16: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

Vertical Displacements for a 1-g gravity: Max = 0.0025”

FDR - Central Solenoid Support Structure - 9/6/06

Page 17: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Peak Tresca stress - 1-g loading: 3.44 ksi @ mtg. bolt holes

Peak Tresca Stress: 3.44ksi

Page 18: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Vertical Displacements for (fault) 2g loading condition: -.005” max.

Page 19: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Tresca Z2 stress for a 2g loading condition (ie. if bottom supports loose or removed) Max Stress: 7ksi @ the mounting bolt holes

Page 20: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

Lateral 0.15g seismic displ. 0.002” at the middle of the tierod

Peak Tresca stress 2 ksi @ the bolt hole

Seismic (static) load 0.15g horizontal acceleration with top mtg. bracket fixed

Peak Tresca Stress 2.0ksi

FDR - Central Solenoid Support Structure - 9/6/06

Page 21: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Thermal Loading: Coil @ 80K & Structure @ R.T.(extreme case)

Max Vertical displacement: -0.085” @ the top of the coil

Page 22: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Need to avoid extreme thermal differentials during cooldown

Peak Tresca Stress 78.6 ksi >> yield stress & allowable

Page 23: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

A more realistic thermal loading assumes a temperature difference of 30 K and yields a relative vertical displacement of -0.012”. The differential rod & bellville to top plate shows about 0.005” - just over 50% of it’s linear range.

∂y ~0.005”

∂y (tot.): -0.0115”

Page 24: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Peak Tresca stress for a 30 K temperature differential: 15.6 ksi

Peak Tresca: 15.6 ksi

Page 25: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Tresca Peak Stress is 4.6 ksi in coil insulation for 30 oK temperature differential

Page 26: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

Baseline EM Loads assumed the 0.5T 1st Plasma Scenario

Coil EM Loading

No Plasma:

Fr = 4,369 lbs/in [5,660 lbs/in*]

Fz = -3,722 lbs (total) [-6,355 lbs*]

DFORCE7b result:

Hoop Stress(avg.)=1.27ksi [1.84ksi*]

Net Stress = 1.54ksi

With Ipl = -26,068 amps

Fr = 4,318 lbs/in

Fz = -3,647 lbs (total)

DFORCE7b result:

Hoop Stress (avg.)=1.25ksi

Net Stress = 1.53ksi

*For Ipf1a = 23,500 Amps

FDR - Central Solenoid Support Structure - 9/6/06

Page 27: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

EM Loading was calculated as J x B body forces at each coil turn.

Genforce subroutine added to DFORCE7b to generate Nastran Force input.

Equivalent discrete forces for the worst cases were applied at each of 6 interior element grid points. Centroidal currents (@ each turn) were assumed. The loading from the M.C. field was simulated by running a 23.5 kA PF1a current case, which duplicates the peak vertical loading from the M.C. radial fields.

Page 28: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Typical EM grid point load resultants @ 6 interior points in conductor

Page 29: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Coil Displacements (SRSS) From 19.3kA EM Loads - No Axial Pre-load

No Plasma -Maximum displacement was 0.0005” at the coil mid-plane

Peak Displ. 0.0005”

Page 30: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Peak Tresca stress in the coil from 19.3kA EM loading only: 1.83 ksi

Peak Tresca: 1.83ksi

Page 31: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

Peak Tresca Stress in supports 19.3kA EM + Thermal (cool-down): 14.0 ksi

(with CONROD elements at bolt hole perimeter)

FDR - Central Solenoid Support Structure - 9/6/06

Page 32: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Peak Tresca Stress in supports 19.3kA EM + Thermal (cool-down): 2.51 ksi

(with MPCs replacing CONROD elements at bolt hole perimeter)

Page 33: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Peak Tresca Stress in Coil for 23.5 kA EM-only loading, 2.78 ksi (Loading includes the effects of the M.C. peak fields)

Peak Tresca Stress in Cu 2.78 ksi

Page 34: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Peak Tresca Stress in Support for 23.5 kA EM loading, 3.68 ksi

Page 35: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Peak Tresca Stress in coil insul. for 23.5 kA EM-Cold loading, 3.17 ksi, 2.9 ksi in Cu

Peak Tresca Stress: 3.17 ksi Peak Cu Tresca Stress: ~2.9 ksi

Page 36: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Displacements for combined gravity, thermal, EM loading

Peak Displ. 0.167” (SRSS)

Page 37: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Tresca stress in coil from combined gravity, thermal, and EM loading

Peak Tresca Stress = 3.16 ksi - insulation

Average coil Tresca stress ~2-3ksi

Page 38: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Peak Tresca Stress 2.68 ksi

Peak Stress in supports from combined gravity, thermal, and EM load

Page 39: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

*Allowable 304L @ 80 oK = 46.6 ksi (321 MPa) (2/3rd yield criteria)

Allowable CDA107(10%CW) Cu @ 80 oK = 16 ksi (110.6 MPa) (2/3rd yield criteria) **

Allowable CTD112P-w/Kapton @ 80 oK = 8.86 ksi (61.3 Mpa 2/3rd ultimate criteria) -per ITER test data

§ Actual margins on max shear are double these values

(C2 = 0.6, Sc= 0.0 - Eqn. From NCSX design criteria, 5.6 ksi no compr.)

**Sy = 124 - 0.241xT +14.1xCW - 0.166xCW2 = 230.5MPa, 2 x sigma = 64 MPa,

230 - 64 = 166, 2/3 x 166 = 110.6 MPa (16 ksi)

(From NIST Monograph 177 -Simon, Drexler, Reed)

FDR - Central Solenoid Support Structure - 9/6/06

Load case Max. Displ. (inch -SRSS)

Suppt. Coil

Max Tresca Stress -ksi

Suppt. Coil

Location

Suppt. Coil

Margin on Allowable*

Suppt. Coil

Gravity-1g

Seismic

0.0025 v 0.0025 v

0.002 h < 0.0002 h

3.44 negl.

2.0 negl.

mtg.brkt __

Rods __

13.5 __

23.3 __

Thermal (∂30 oK)

0.0112 0.005 15.6 3.3 Cu

4.6 (ins.)

@bolts corners 3.0 4.84

1.9/1.2§

EM (23.5kA) 0.0005 0.0005 3.68 1.83 @bolts mid-coil 12.6 12.3/8.7

EM + 1g

+ cooldown

0.167 0.0695

(SRSS) (SRSS)

2.68 2.9-Cu

3.16-ins.

@bolts mid-coil

outer c.

17.4 5.5

2.8

Stress Analysis Summary

QuickTime™ and aTIFF (LZW) decompressor

are needed to see this picture.

Page 40: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

Coil Testing Requirements:

Electrical

After re-configuring and re-insulation of coolant tubes, coils will require a hi-pot to ground at 2 kV (2 x Vop. +1000) and a megger at room temperature and 80 deg.K.

Insulating breaks between field periods will be meggered @ 2kV

Mechanical

During cool-down for 80 deg.K electrical test, a flow measurement for a delta-P of 10psi will be required.

Thermocouples on inlet and outlet tubes will be needed to provide a record of T vs. time for the cool-down.

FDR - Central Solenoid Support Structure - 9/6/06

Page 41: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Cost & schedule:

•Build in-house preliminary est: ~75k$

•Will issue an RFQ for 304L & 316L by late Sept.’06

•Anticipate a 4-6mo. Delivery

•A 316L material may delay things a month or two and may cost

30% more.

Page 42: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Conclusions:

Charge:

Does the coil structure provide adequate support for the PF1a coils with sufficient margins of safety?

A: Stress margins on allowables for both coil and support exceed project & code requirements.

Have the interfaces with other sub-systems been defined and are they compatible?

A: Interfaces to machine structure, cryo-system, and electrical power defined & compatible.

Are the drawings and supporting documents complete and ready for sign-off?

A: Drawings & BOM are complete and ready for checking/sign-off.

Has the analysis been documented and checked?

A: The stress & thermal analysis have been documented & are being checked.

Are the cost, procurement and assembly schedule consistent with the program schedule and budget?

A: Cost & schedule are consistent with project schedule and, pending responses from RFQ,

should fall within the current project budget.

Page 43: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

PF1a Radial Running Load

855000

860000

865000

870000

875000

880000

885000

890000

895000

900000

905000

0 60 120 180 240 300 360

Angle, deg

Running Load, N/m

PF1a OnlyPF1a + PF4&6

PF1a,4,6 & Mod

per A.Brooks 9/1/06

Page 44: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

PF1a Vertical Running Load

-30000

-25000

-20000

-15000

-10000

-5000

0

0 60 120 180 240 300 360

Angle, deg

Running Load, N/m

PF1a OnlyPF1a + PF4&6

PF1a,4,6 & Mod

per A.Brooks 9/1/06

FDR - Central Solenoid Support Structure - 9/6/06

Page 45: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Fatigue analysis:

304L Peak Tresca Stress: 15.6 ksi (EM + 1g + 30 oK delta)

Operating stress belowthe /2 @ 130,000 cycles

The 2/20 project criteria for fatigue is satisfied although the anticipated usage of the PF1a coils and supports is significantly less than the 130,000 cycles.

20x life

15

Page 46: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

Shear Strength CTD112P (w/Kapton) 13.3 ksi @77 deg.K

FDR - Central Solenoid Support Structure - 9/6/06

Page 47: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

ITER shear-compression tests

Max Shear: 6.78 ksi for 15 degree angle(12ksi compr.) @ 77 deg. K

FDR - Central Solenoid Support Structure - 9/6/06

6.7 ksi

40 MPa, 5.8 ksi-static & fatigue

Page 48: FDR - NCSX Central Solenoid Support Structure Fred Dahlgren Joe Rushinski 6 Sept 2006.

FDR - Central Solenoid Support Structure - 9/6/06

Inner radial stop will maintain central alignment of PF1a coils