fast track project.ppt
-
Upload
andrew-lbk -
Category
Documents
-
view
301 -
download
8
Transcript of fast track project.ppt
-
7/27/2019 fast track project.ppt
1/76
1
Dr. George Jergeas PEng
University of Calgary
Project Management Specialization
Managing Fast TrackProjects: A Guide and
Checklists
-
7/27/2019 fast track project.ppt
2/76
2
Reference
This presentation is based on the European
Construction Institute (ECI) - UK
ECI Manual
The Fast Track Manual
A guide to Schedule Reduction for Client and
Contractors on Engineering and Construction
Projects
-
7/27/2019 fast track project.ppt
3/76
3
Introduction
Different Project StagesConcept Stage *
Development Stage
Definition Stage *
Design Stage *
Procurement Stage
Construction Stage *
Commissioning
Operation Stage
Key Issues
Agenda
-
7/27/2019 fast track project.ppt
4/76
4
Introduction
Takes place more quickly than normal
A difficult and often stressful route to follow
There is no boundary between a normal projectand a fast track project
Projects ranged from 4 - 36 months
Schedule reduction 10 - 29%
Cost increase 10 - 20%
-
7/27/2019 fast track project.ppt
5/76
5
Reasons for Fast Track
Urgent requirements by client
To maximize profit or limit loss
Imposed deadline
Start of academic year
End of current lease
New legislation
Minimize disruption of services
-
7/27/2019 fast track project.ppt
6/76
6
Objectives
To assist who are considering a fast track tomake the right decisions
To help implement fast track strategysuccessfully
-
7/27/2019 fast track project.ppt
7/76
7
Key Success factors
The calibre of individuals and their workingrelationships
The adequacy of the definition of the project
Strategy adopted and systems for
implementation
The passion to succeed on the part of key
participants
-
7/27/2019 fast track project.ppt
8/76
8
A managerial approach to the achievement of earlyproject delivery, involving the application of innovationsin the management of construction procurement andrecent advances in the process that, bringing into play;
The integration of construction and design phases
The involvement of the contractor in both the design andconstruction phases
Overlapping of work packages to enable construction of sections
of the project to proceed while the design for other sections isbeing progressed
The employment of the expertise of suppliers in design andconstruction
Kwakye, 1991
Definitions
-
7/27/2019 fast track project.ppt
9/76
9
Design and construction are overlapped and differentsections of the plant are designed and built in parallelwith significant additional riskdue to the links
between the design of different parts of the plantTurner, 1996
The reduction of the the schedule to the minimum
practicable is the principal driving force for one or morestages of the project
Definitions
-
7/27/2019 fast track project.ppt
10/76
10
Project Stages
F
astTrackProject
Norma
lProject
-
7/27/2019 fast track project.ppt
11/76
11
Work Package Overlap
Work packages are progressed in parallel
Overlap the stages for each work package
Early Decisions
Experienced judgement and empowerment
Commence design before scope has been defined
Must accept wrong decisions
General Principles
-
7/27/2019 fast track project.ppt
12/76
12
Integrated Project TeamMain parties are combined into a single organization
and participate to the limit of their capability in
achieving the project objectivesPartnering
BenefitsAvailability of additional expertise
Avoiding learning curve errors
Reduction in the overall workload
Commitment to the project definition and schedule
Design and construction developed together
General Principles
-
7/27/2019 fast track project.ppt
13/76
13
Additional StaffMore labour will be needed at peak period as a
consequence of scheduling activities in parallel
More management resource will be needed to dealwith interface and progress issues arising from inter-dependencies between disciplines and betweendesign, procurement and construction
Schedule Reduction Techniques
Project must be managed in an efficient mannermaking full use of project management and schedulereduction techniques
General Principles
-
7/27/2019 fast track project.ppt
14/76
14
Additional Risks
Decisions based on limited information,
cannot always be right first time
A structured and thorough risk management
process needed
General Principles
-
7/27/2019 fast track project.ppt
15/76
15
Advantages vs. Disadvantages
Advantages
Time to market
Commercial benefits
Short schedule (at least 10%)
Reduce time period for risk exposure
DisadvantagesAdditional risk factors, very limited alternatives
Increased amount of PM, control, etc.
Cost increase (at least 10 20%)
-
7/27/2019 fast track project.ppt
16/76
16
Characteristics that Support
Strategy
OwnershipClient support
Project sponsor or champion
Stakeholder support and commitmentOrganization
Project team needs to be simple, clear and devoid ofrigid hierarchy
If parent organization has a functional matrixstructure, the functional line must be subordinate tothe project management (task) line for the duration ofthe project team
-
7/27/2019 fast track project.ppt
17/76
17
Desirable Team Characteristics
Honesty - Openness - Trust
Anticipation and avoidance of issues rather than
waiting for them to turn into problemsMutual support - issue resolution, coaching
No blame culture
Access to all parties, no communication barriers
Lean organization, which aids communications andspeeds decision taking
Full time members
Authorized and empowered team members
Decision making on the spot without referring
Characteristics that Support
Strategy
-
7/27/2019 fast track project.ppt
18/76
18
People and RelationshipsTechnical competence
Decisiveness - self starter - can do - flexibility
Ability to forecast outcome and act accordingly
See the big picture
Willing to collaborate
EnthusiasmStrong leadership
Managerial competence
Openness
Characteristics that Support
Strategy
-
7/27/2019 fast track project.ppt
19/76
19
MotivationCreate a team culture that avoid de-motivation of
individuals who are keen to succeed, but areprevented by the organization, procedures,..
Working part of a team, working equally hard andsupporting each other
Appoint key positions to individuals known to be goodmotivators
Early identification and removal of under-performingindividuals
Team building and partnering sessions
Incentive/penalty clauses
Characteristics that Support
Strategy
-
7/27/2019 fast track project.ppt
20/76
20
Contractual arrangements
Achieve win-win situation
Pre-selected, preferred contractorReimbursable basis, with incentives
Lump-sum can also be used
PartneringUp front agreement for payment for changes
and extras
Characteristics that Support
Strategy
-
7/27/2019 fast track project.ppt
21/76
21
Communications
More informal communication - face-to-face
Barriers should be removed - informationflows directly between the parties regardless ofparent organization and level of hierarchy
Responsibility for communication lies with the
individual who has made a decisionFrequency and progress meetings
Frequent and concise reporting
Characteristics that Support
Strategy
-
7/27/2019 fast track project.ppt
22/76
22
Introduction Time to establish the concept is NOT
recoverable
The opportunity to influence theoutcome falls off rapidly
People Stakeholders (ALL Should be identified) Integrated Team (Sponsor, Project
Manager & Senior Managers fromdifferent key players)
ualified ersonnel and motivated
Concept Stage
-
7/27/2019 fast track project.ppt
23/76
23
Scope Identify the real Goal and Objectives of
the client
Identify Critical Success Factors (CSFs)
Strategy
Fast tracking should be avoided unless
the client business benefits from earlycompletion significantly and outweighrisks
Contract strategy addressed andoutlined
Concept Stage
-
7/27/2019 fast track project.ppt
24/76
24
Business and PM SystemsBusiness Planningprocess for weeding out poor projectsA smooth transition from business process to PM process
Stage gates process
CommunicationsRapid transmission of informationIT systemsPublicity needs to be controlled
Risk Management
Cost and RiskDetermination of cost is difficultLimited industry information on fast track projects
As accurate as possible estimate to help in the decision toadopt a fast track strategy
Concept Stage
-
7/27/2019 fast track project.ppt
25/76
25
Logistics Consideration to location of new asset in relation to:Location of customersSource and availability of feedstocks, component parts
Supply routesTransport security and cost of supply and productsExisting assetsWorkforce skills and availability
Also should consider:
Locations of parties involvedClient site - design office - contractor - contractors
and sub-contractor - suppliersSources of construction equipment - material - supply routes and
methods - Site access and controls
Concept Stage
-
7/27/2019 fast track project.ppt
26/76
26
Definition Stage
Introduction
Lack of adequate definition has arguably beenresponsible for more project failures
Expenditure of 25% of the total design effort
Design will need to be progressed on thoseelements of the definition that are sufficientlysecure in order to feed information to construction
at the earliest practicable timeQuality of project definition is very often a casualty,
with the potential for overruns of cost & time
-
7/27/2019 fast track project.ppt
27/76
27
Definition Stage
People
Clarity of objectives A clear focus on the objectives as agreed with stakeholders at
the concept stage must be maintained in order to aid in thedecision making process
Stakeholders The significant stakeholders early identified should continue to
be involved, consulted and advised
Any other identified stakeholders should be involved ASAP
Integrated Team If the project has not so far been led by the project manager
who will be responsible for seeing it through to beneficial use,that individual should be appointed at the beginning of the
definition stage
-
7/27/2019 fast track project.ppt
28/76
28
Definition Stage
People
Suitably qualified and experienced personnel
The team should not be selected only on theirtechnical and managerial competencies but alsoon their ability to:
Overcome the obstacles and succeed in achieving the project CSFs
Work with high level of uncertainty
Work flexibly outside the normal work boundaries
Co-operate with others for the benefit of the project
Project Scope
It is essential that the project team have a clearunderstanding of what has been agreed bystakeholders to be in the scope and what is outside thescope
-
7/27/2019 fast track project.ppt
29/76
29
Definition Stage
Scope For technical definition consider:
Fit for purpose (which may not be ideal sometimes)
Fastest to manufacture/construct rather than
cheaperReuse of design from existing assets
Modular design
Pre-fabrication of components
Minimization of project scope lean constructionapproach
Reduction in the number of processing steps in amanufacturing plant
-
7/27/2019 fast track project.ppt
30/76
30
Definition Stage (Cont.)
ScopeReduction in the size of the asset
Elimination of non-essential elements of the design
Standardization of layout or repeated units
Standard / off-the-shelf componentsSimplification of design dependencies
Simplification of the build/construct/assembleprocess
Avoidance of innovation/new/untried elements ingeneral
Early identification and ordering of long deliveryitems
Constructability / Operability
-
7/27/2019 fast track project.ppt
31/76
31
Definition Stage (Cont.)
For the Overall Scope also consider:
Achievement of the overall project objectives,
both what is to be done and how it is to beachieved
Whether phased completion would be acceptable
Arrangements for handover and commissioning
Proving and warranty test to be carried out
Definition of beneficial operation / use as the endpoint of the project
Project specific critical success factors
-
7/27/2019 fast track project.ppt
32/76
32
Definition Stage
Project Strategy
It should take into account the same aspects whichwere considered in the concept and developmentstages that include:
Work Breakdown Structure and the ability to spilt the project intorelatively independent parts
Willingness to take early decisions and accept competent solutions
Ability to keep options open until the last responsible moment
Elimination of hold points for the approval of design
Agreement that the project will accept the best decision in light of theinformation available at the time
Acceptance of risk taking, and the impact of each risk
Delegation and empowerment of the team to promote decisions
Early applications of authorization and approvals
Availability of benefits / incentives for all project parties
Opportunities to allocate risk and share rewards
-
7/27/2019 fast track project.ppt
33/76
33
Definition Stage
Project Management Procedures
Planning It is essential that, as the definition evolves, work is scheduled on the
basis of achieving the earliest beneficial use of the finished asset
It is also essential that interactive planning process advocated as a teambuilding activity
Project Process Based on the project organization, the project procedures may be those of
the client, the contractor or one of the other parties
Standard processes need to be modified to accommodate the degree ofoverlap between various stages
Authority to approve modifications should be assigned ASAP
A project risk management system must be set up as part of the projectprocedures
A good system for project documentation is essential
-
7/27/2019 fast track project.ppt
34/76
34
Definition Stage
Project Management Procedures
Project control
Care is needed to ensure that previously rejected ideas are notreintroduced at the definition stage
The use of Value Engineering / Constructability is essential toenhance the decision making process
Project Communications
A good communications system need to be established and
maintainedThis could include: intranet, Extranet, Internet, Chat rooms,
Bulletin Boards, Event Calendars, Data Base, etc.
The greater the level of integration in the sharing and re-use ofinformation the more that the communication system will
support the project and enhance success
-
7/27/2019 fast track project.ppt
35/76
35
Definition Stage
Project Management Procedures
Cost and risk
Cost
Approval of cost will have to be given on a lower level ofdefinition and with a wider tolerance on the estimate if theproject is to proceed unhindered by the supply of funds
A cost estimate to within plus or minus 10% will not beobtained until the end of the design stage
It is recommended that a control estimate should be producedonce all the necessary details are known
During this stage it will be necessary to address the potentialcause of increased cost which may rise
-
7/27/2019 fast track project.ppt
36/76
36
Workshop 1: Risks
List risks associated with the increased level ofoverlap between definition and design stages of
a project.
-
7/27/2019 fast track project.ppt
37/76
37
Solution: Workshop 1
1. Design and construction rework arising from lack offirm definition
2. Additional management effort at peak to control theproject
3. Use of additional resources arising from repeat workand parallel working requiring more than optimalnumber of people
4. Essential additional items to achieve the CSFs which
creep into the scope through lack of firm definition5. Procurement against best/guaranteed delivery rather
than lowest price
6. Additions to equipment orders as details evolve
7. Additional expediting
-
7/27/2019 fast track project.ppt
38/76
38
Solution: Workshop 1
8. Air freighting to speed delivery
9. Incorrect initial material quantities which may give riseto surpluses, or shortages which will need to be
topped up at premium costs10. Additional contingencies being included in quotationsto cover unknown elements where there is no scope
11. High allowances in tender prices to cover penalties fordefaults
12. Overtime and shift working resulting in higher costand loss of productivity
13. Over design vs. waiting for detailed information
-
7/27/2019 fast track project.ppt
39/76
39
Design Stage
Introduction
The main purpose of this stage is to finalize the designrequirements for the project
This stage requires a good understanding of the optionsfor compressing the schedule
It requires the use of the most up-to-date provencomputer aided design
PeopleClarity of objectives
The most elegant design is useless unless it is capable of beingbuilt safely and to time and budget, this has to be fullyunderstood by the project team and senior management
-
7/27/2019 fast track project.ppt
40/76
40
Design Stage
People
Stakeholders The interests of all stakeholders should be kept under review as the
design progress so that interested parties can be kept up to date and
involved at the earliest appropriate stageAlliances
Establishment of a long-term relationship between the companies andteam involved helps to ensure a rapid start-up of the team involvedon the project at each stage
Integrated Team This stage requires the use of single design team incorporating the
expertise of all discipline and involving those responsible forsubsequent stages of the project
The design should be able to be right first time to minimize thenumber and duration of design reviews
-
7/27/2019 fast track project.ppt
41/76
41
Design Stage
Integrated TeamThe team need to be supported with appropriate collaboration
and communication systems
Team members should have clearly identified roles andobjectives to eliminate duplication and inefficiencies
The team members need proper empowerment to promoterapid and effective decision making
Team members should be very competent and experienced inorder to enhance the efficiency of the design
Project ScopeClarity of definition
The problem with some fast track projects is that detaileddesign has to proceed without total clarity of definition
It is a a matter of judgment as to which areas are sufficientlywell defined to proceed without incurring too great risk
-
7/27/2019 fast track project.ppt
42/76
42
Design Stage
Project Scope
Extent of design
The extent of design details need to be defined from thebeginning. Some elements of design has always been left to
contractors on site to complete
There will be no benefit if the easy 95% of the project is fullydetailed and the contractor is left to struggle with the difficult5%
Design can only be based on the best option at the time giveninformation available
Early involvement of contractors and suppliers is essential
-
7/27/2019 fast track project.ppt
43/76
43
Design Stage
Over-design
In the absence of hard information it is necessary to makemore generous allowances than would normally be thecase
The level of the over-design will depend on the extent ofthe un-known, the significance and perhaps the cost of thetime
The design can be based on the maximum expected valuese.g., weight of structure, pressure in system together with
an appropriate safety factor rather than waiting untilprecise values can be calculated.
Example: There maybe little cost difference for the projectas a whole if piling is 30% over-designed or 50% over-designed, but may allow site work to proceed well ahead
before the accurate details of the superstructure can bedetermined.
-
7/27/2019 fast track project.ppt
44/76
44
Design Stage
Design process
The design sequence must be planned to ensure that theschedule needs of construction drive the design processfor the production at the right time of:
Design information
Drawings
Documents
Materials
Equipment
Long lead item data sheets and specifications will need tobe produced out of sequence with the rest of the design.
-
7/27/2019 fast track project.ppt
45/76
45
Design Stage
Design process
Visual appearance and structural design may need to becompromised to achieve the fastest completion
Design option selection may be based on fastest tomanufacture or build rather than lowest cost
Design will overlap with procurement and construction
Design of work packages will be in parallel
By-pass design areas with insufficient information andwork to assumptions put experienced team members towork resolving the issues within the black boxarea
Incorporate constructability to ensure the optimumconstruction productivity
Design holdsmust be minimized as possible
Desi n reviews must be carried out ver thorou hl
-
7/27/2019 fast track project.ppt
46/76
46
Design Stage
Design process
Design freeze
The overlap between definition, design andconstruction means that the number ofunknowns remains higher than in a normalproject while work is proceeding on the
following stageOnly freeze part of the design which then have tobe accepted as constraints on the rest of thedesign
D i St
-
7/27/2019 fast track project.ppt
47/76
47
Design StageStrategy
Simplicity and repetitionReduction in the number of processing steps in a manufacturing
plant
Reduction in the size of the asset
Elimination of non-essential elements of the design (de-scoping)
Standardization of layout or repeated units
Simplification of the build / construct / assemble process
Standard / Reusable / Off-the-shelf-design
Consideration should be given to re-use design of an existing
assetAn existing asset can be used to train both the constructors and
users of the new asset
Base the design of the long delivery items on those that alreadyexist so that material procurement and fabrication can be started
at the earliest possible time.
D i St
-
7/27/2019 fast track project.ppt
48/76
48
Design StageStrategy
ModularizationIf the overall design can be structured as a series of units or
modules then there is the potential to introduce a number ofschedule reduction approaches
Progress separate modules in parallel using separate design teams,
suppliers, construction contractors
Care to identify all the interdependencies between the separatemodules and to ensure that these are taken into account as thedesign progresses.
If a number of the modules can be of similar design then should bepossible to utilize the experience gained on early modules toimprove the efficiency and time
In a process plant design as a number of parallel streams, rather
than a single large stream Smaller and off-the-shelf items
Consider the concept of sub-modules mounted within plant p maybe interchan eable
D i St
-
7/27/2019 fast track project.ppt
49/76
49
Design StageStrategy
Prefabrication / Pre-assemblyManufacture modules off the site and under factory
controlled conditions
Cladding panels complete with windows, external
fittings, internal finishesFully finished air handling units
Skid mounted plant
Fully finished bathrooms
Standardized internal partitioning
Completed, tested, validated pilot/ process plant
Design tools The low technology approach will often be found (on many projects) to be
the quickest to produce results
-
7/27/2019 fast track project.ppt
50/76
50
Design Stage
Project Management Systems and ProceduresPlanning
Planning of the design must be driven by the requirements oflater stages, mostly the construction stage.
Interactive planning which involves all members of the projectteam in problem solving and plan optimization.
Critical Chain project planning methodology has been creditedwith a significant reduction in project duration. Themethodology results in the schedule contingency, which is
normally hidden in the planned duration of each activity, beingremoved from the critical chain of activities and being replacedby a number of buffers of project contingencies that areprovided to protect blocks of activities and are visible to theproject team
D i St
-
7/27/2019 fast track project.ppt
51/76
51
Design StageProject Management Procedures
Project ControlEffective project control is one of the keys to a successful fast
track
It must be a dynamic process with a very short cycle time sothat deviations are recognized and corrected
Design progress measurements should be at the simplest level
Frequent up-dates of measurements / information
Progress information / reports are simple, concise and easilyavailable to relevant people
Monitoring of key trends flogging adverse trends and forecastout-turns that are not in accordance with the scheduleincluding schedule float.
Exception reporting of items not completed to schedule
Progress against deliverables, milestones, CSFs and forecast
out-turns
-
7/27/2019 fast track project.ppt
52/76
52
Design Stage
Project Management ProceduresDesign Approval
To ensure that the client fully understands the detail of theassets being created and does not come up with additional or
alternative requirements during procurement, construction orcommissioning phases, it is necessary to have good designapproval system which includes sign-off by the client.
Approval of the design sub-units that are the responsibilities ofspecialist vendors may need to take place on their premises to
avoid delaysDesign verification
Verification should commence as soon as possible to limit theamount of re-work
-
7/27/2019 fast track project.ppt
53/76
53
Design Stage
Project Management ProceduresChange Control
Effective change control system is essential, but is difficult to enforce dueto the increased risk of rework arising from the overlap of design andconstruction.
Rapid rejection and approval will help to limit rework and minimize theimpact of change
Communications Good verbal communications need to be established between the parties
so decisions are known quickly and design can progress rapidly.
Meetings should be kept to a minimum and focused on decision takingrather than communication of matters purely for interest.
Communications within the team should take place as needed and not berestricted to a meetings timetable
Communications with other parties outside the design team need to bekept up to speed with design details as they evolve
Full use of IT systems for storage and communication of information
-
7/27/2019 fast track project.ppt
54/76
54
Design Stage
Project Management Procedures
Constructability Reviews
The integrated team is best placed to address the
issues which arise from Constructabilityconsiderations as the structure and detailed designare evolving.
-
7/27/2019 fast track project.ppt
55/76
55
Design Stage
Cost and Risk Considerations
The main risks in this stage are of increased cost anddelay due to sub-optimum design or incorrect designresulting in rework
The root cause can be either commencing detaileddesign before a comprehensive and firm definition hasbeen agreed or from the early decision approach wherethere are interdependencies between the elements on
which parallel working is taking place.
Workshop 2: Risks at the
-
7/27/2019 fast track project.ppt
56/76
56
Workshop 2: Risks at the
Design Stage
List the risks associated with increased overlapbetween design and construction stages
List the risks associated with increased overlapbetween design and procurement stages
-
7/27/2019 fast track project.ppt
57/76
57
Workshop 2: Solution
List the risks associated with increased overlapbetween design and construction stagesProduct which is to be manufactured on the plant fails its trials
Failure of innovative designs as a result of putting them into
practice without sufficient development
Failures of innovative methodologies as a result of hasty andinsufficiently considered application
Increased level of rework as a result of:
Lack of firm definition
Omissions as a consequence of out-of-sequence design
Changes to design of fabricated items after delivery to site
Increased whole of life cost due to sub-optimum design
Conflict
-
7/27/2019 fast track project.ppt
58/76
58
Workshop 2: Solution
List the risks associated with increased overlapbetween design and construction stages
Increased capital cost arising from:
Modularization e.g., extra structural steel, extrajoint/connections, greater precision
Over-design due to judgments based on limited information
Sub-optimum design through the use of standard designs orreuse of existing design
Problem at design and construction discipline interfaces
-
7/27/2019 fast track project.ppt
59/76
59
Workshop 2: Solution
List the risks associated with increased overlapbetween design and procurement stagesLack of understanding of scope
Design changes requiring revised contract and purchase orders
leading to delays or cost increasesErrors or omissions in purchase of materials or equipment
Reduced certainty of outcome for all project parameters: cost,time, quality, safety
Interdisciplinary design conflicts arising from out of sequence
workingProblems with systems integration
Inappropriate form of contract for those contracts which are let onthe basis of inadequate or incorrect design information
Selection of inappropriate contractors
Inappropriate allocation of risk
-
7/27/2019 fast track project.ppt
60/76
60
Design Stage
Logistics
Design team location
The design team is the center of the project team activities
If the whole project team cannot be located together,
consideration should be given to locate them all togetherthrough the design stage
Access
Arrangements should be made for design team to gain access
to project site as early as possible
-
7/27/2019 fast track project.ppt
61/76
61
Construction Stage
IntroductionManage the additional risksAchieve high productivity from construction work force
Good understanding of options for compressing the schedule
Good risk management and communication system
Coordination among all contractors and suppliers
People
Clarity of objectives
The CSFs and what is expected of site staff in achieving theseCSFs should be communicated to all construction staff
The key performance indicator against which constructionperformance is to be measured should be explained
The interests of the site workforce should be identified
(working arrangements, working periods, flexibility and criticalath activities
C t ti St
-
7/27/2019 fast track project.ppt
62/76
62
Construction Stage
PeopleIntegrated team
Single integrated team with one culture should be carriedthrough to the construction site (it may be difficult with manysuppliers)
Contracts between the parties involved need to be set up topromote integration and co-operation and to enable all partiesto be available as and when demanded by the schedule.
The following elements have been noted as being helpful:
Effective management of the overall team effort
Contractual obligations for all parties to work co-operativelyregardless of direct contractual relationship
Design staff to be based on the construction site
Rapid response from engineering staff not site based
C t ti St
-
7/27/2019 fast track project.ppt
63/76
63
Construction Stage
Integrated team
Vendors available to assist in the erection, site testing andpre-commissioning
Dedicated staff to co-ordinate and expedite permits,clearness, etc.
Commissioning staff used as construction inspectors Client and commissioning staff involved in punch listing of
defects
Project facilitators to deal with hold ups, interface problems
Joint construction and commissioning punch listing team
Punch list rectification squad which is separate from thenormal construction squad to hit critical items whileavoiding disruption to construction progress
Testing as part of the installation process, not subsequentactivity
Construction Stage
-
7/27/2019 fast track project.ppt
64/76
64
Construction Stage
People
Delegation and empowermentAuthorize and empower members of the project team topromote rapid and effective decision taking at thelowest competent level
Necessary numbers and skills must be made available to meetthe demands of the schedule
Supervision ratios may need to be increased
Skilled and experienced staff are employed
Construction team motivation is essential to enhance success
Remove disincentives and provide incentives Schedule is challenging but realistic
Demonstrate management dedication and commitment
Remove underperforming staff from team
Simplify work methods
Avoid non-essential overtime
Supply design information, materials, equipment, support services
-
7/27/2019 fast track project.ppt
65/76
65
Construction Stage
ScopeA clear definition of scope in form of drawings and
specifications, codes, standards and best practices.
Need to now what is required and how to deliver he scope
StrategyConstruction plan
Satisfy conditions for plant commissioning and handover
Provision of agreed documentation to following stages
Pull through of design, materials, equipment, resources
Inclusion of output from Constructability reviews
Utilization of latest proven methods and technical improvements
Detailed planning / control for critical path and special operations
Modularization and off-site fabrication
Locations of site facilities, workshops, etc.
Complete weld preps prior to installation of steelwork/pipes -
-
7/27/2019 fast track project.ppt
66/76
66
Construction Stage
Site contractsNumber and arrangement of contractors should be optimized for speed
of construction
Management and resourcesNumber and skills supplied to meet demands of plan
Competence in required project management and discipline skills
Workforce clocking / accommodation / messing facilities close to workfaces
Materials and equipment
Materials and consumables supplied to ensure no delay throughshortage
Materials management system to supply materials and equipmentsafely and efficiently to the work face
Generous supply of construction equipment, personal protective
Construction, commissioning and operational spares ordered withe ui ment
-
7/27/2019 fast track project.ppt
67/76
67
Construction Stage
Quality assuranceBuild quality in. Do the job right the first time (inspection does
not improve quality)
Systems designed to minimize rework
Ensure that the latest revision is n use and previous issueshave been withdrawn
Access
Good, safe site access
Generous lay-down, storage and work areas for pre-fabrication,
assembly and inspection/testingSafe and unobstructed access to the work face e.g. scaffolding
Maximum use of mobile access devices such as CherryPickers and scissor lifts
Safety, Health and Environment
-
7/27/2019 fast track project.ppt
68/76
68
Construction Stage
Project Management ProceduresPlanning Construction requirements in terms of design, planning approvals,
contracts, materials, equipment services and documentation should be
built into the project plan from the earliest practicable time. Only in this way will it be possible for the preceding stages
(Development, design, procurement) to organize their work so as toproduce constructable design packages and constructable procurementpackages
Construction plan should be based on the requirements for pre-commissioning and commissioning
Keep plan under review throughout the construction period.
-
7/27/2019 fast track project.ppt
69/76
69
Construction Stage
Planning Only the minimum number of essential activities on the critical path
Maximize benefits from prefabricated elements
Plan construction of repetitive units as a manufacturing process
Package work to allow multiple work fronts in parallel
Plan construction sequence so as to meet pre-commissioning andcommissioning needs
Base the schedule on shorter time intervals i.e. days or hours for critical tasks
Site access arrangement
Establishment of site infrastructure
Work permit provision
Resource demands of the schedule recruitment, induction, training Move from area based to process system
Commence construction based on early design information
Key long lead and critical activities
Contingency planning for critical activities
Constructable work packages
Deferment of non-essential items until late in the program
-
7/27/2019 fast track project.ppt
70/76
70
Construction Stage
Project Management ProceduresProject Control
Control must be a dynamic process with very short cycle timeand include the following:
Frequent monitoring of all trends in work progress
Frequent monitoring of changes
The use of simple progress indicator graphs (S-curve) on a daily basis
Simple progress reports and easily available to relevant people
Exception reporting of items not completed to scheduled
Progress against deliverables, milestones, etc.
Earned Value measurement
Change Control Design changes are to be avoided
If design change is essential, implement through change control system
Resist verbal request at all costs
-
7/27/2019 fast track project.ppt
71/76
71
Construction Stage
Project Management ProceduresCommunications
Communications should be:
Simple limited to what is necessary
Pertinent
Timely
Using best available mechanism; face-to-face
Use of IT and 3D design tools to have a clearunderstanding of the product
Enable all parties to work together with an improvedunderstanding of the design intent to avoid delays
arising from misunderstandings and interdisciplinary
-
7/27/2019 fast track project.ppt
72/76
72
Construction Stage
Cost and Risk
Mechanism for controlling costs through efficient use oflabour and materials and the avoidance of reworkincluding rectification of defective work
Strategies to achieve high productivity
Multiple shift or night shift will add to cost
It may be necessary for the client to provide advance
payment to enable contractors to commit materials andresources ASAP.
Balance between risk and reward
-
7/27/2019 fast track project.ppt
73/76
73
Construction Stage
LogisticsDesign support for construction should be located on site
If not possible then effective IT system should be used to improvecommunications and enable marked up drawings to be rapidlytransmitted
Maintain the momentum of the construction site and avoid theneed to move site labour on to less urgent work due to hold ups onthe critical activities
Procurement support should be provided and include: Documentation covering both purchasing transaction and documentation
Good receipt procedures
Inspections requirements
Quarantine of incorrect or defective goods
Storage and conservation
Handling and delivery to the work face
Surpluses Returns of incorrect, defective materials and e ui ment
-
7/27/2019 fast track project.ppt
74/76
74
Key Issues
With Fast TrackControl is redefined from monitoring results to
making things happen
Performance is maximizing value and minimizing wasteat the project level
Value to the client is defined, created and deliveredthroughout the life of the project
Coordinating action through pulling and continuous flowas opposed to traditional schedule driven push with itsover-reliance on central authority and project scheduleto manage resources and coordinate work
Decentralizing decision making through transparency
and empowerment (effective communication)
Key Issues
-
7/27/2019 fast track project.ppt
75/76
75
Key Issues
Key organizational features include leadership, teamworkand trust
The construction requirement is the basis for planning thesupply of design, documentation, materials, equipment and
resources
Providing the wrong goods or service the right way iswaste do the right project before you do the project right
Project control is controlling the project, not just
retrospective monitoring
Good communication are needed to support decisionmaking
Eliminate ineffective time on site activities
Si nificant attention to ro ect with new technolo
-
7/27/2019 fast track project.ppt
76/76
Thank You
Managing Fast Track
Projects: A Guide and
Checklists