    Project title

    Reduce the NPI pilot run

    setup time in SMT lines

    6

  • 8/10/2019 6s project.ppt

    3/17

    CONFIDENTIAL

    Definition:

    The NPI pilot run setup time in SMT lines,which is defined as the total time from SMTdepartment stops building the prior model to SMTdepartment starts to build the first board ofbalance quantity of NPI (except the sampleboards, normally 4pcs).

  • 8/10/2019 6s project.ppt

    4/17

    CONFIDENTIAL

    0100

    200300400

    500

    600700

    800

    Mar'04 Apr'04 May'04 Jun'04 Jul'04

    U s e

    d t i m e

    ( m i n )

    Loading Tape board Sample board W/S Test

    Target:360min

    678

    Primary Metric

    742

  • 8/10/2019 6s project.ppt

    5/17

    CONFIDENTIAL

    Process Mapping

    Tape board Pass? Sample board Check Pass?Yes

    Yes

    No No

    Build

    Loading Check

    Pass?Yes

    No

    FCTPass?Yes

    No

    W/S(If necessary)

    ICT

    Remark: non-value station

  • 8/10/2019 6s project.ppt

    6/17

    CONFIDENTIAL

    Problem 1 & SolutionItem Problem Root cuase Solution

    1

    In A26117-01C1 build, Jun.105 min wasted for awaitingmaterials

    Communication

    2In 1591-719-5-A build, Jun. 80

    mins to wait for material.Communication

    3

    In A26116-01C build, June.60 min to wait for material (use 3160622000AYS toreplace 3160619100AYS).

    Communication

    leader in time with last informations,and leader makes the last decisionand inform team in time, such as re-schedule NPI for material shortage

    4

    In C54T02P04 build, June. Westop NPI in tape boardbecause of PCB quality issue.

    Communication

    prior to SMT loading, start to buildNPI balance quantity withoutsample board result but have the FAreport of sample board from TEdepartment, etc.

    Have not the smoothcommunications between internalteam member each other, so weappoint ME colleague to be teamleader for all NPI run, that is, the

    relevant team members report to

  • 8/10/2019 6s project.ppt

    7/17

    CONFIDENTIAL

    The responsibility of NPI team leader

    1. Act as the team leader after Prog department held thekick-off meeting of NPI.

    2. Push team members to complete his/her departmentaltask and have them to report the status to team leader.

    3. Hold the NPI meeting to review team member's progress ifnecessary.4. Make the final decision if there are different opinions

    among team members.5. Push Material department to prepare the materials and

    inform Prod department to pick up materials from Store. Else,when material shortage or quality issue required 4 hrs toresolve prior to NPI build, team leader needs to inform PCdepartment to re-schedule NPI build.

  • 8/10/2019 6s project.ppt

    8/17

    CONFIDENTIAL

    The responsibility of NPI team leader(continued)

    6. Inform relevant departments to stop NPI or re-scheduleif there are some accidents in NPI process, for example,

    material quality issue in NPI process, etc.7. If sample board test failed and TE has submitted the FAreport, team leader needs to inform SMT to build or notaccording to the FA report & team members' suggestion.

    8. Summarize the FA (First Article) report and submit toteam members.

    9. Hold the close meeting for preparation of massproduction after NPI completed.

  • 8/10/2019 6s project.ppt

    9/17

    CONFIDENTIAL

    Problem 2 & Solution

    Item Problem Root cuase Solution

    Tape Board test will be parallel with Sample boardbuild to eliminate the non-value action, that means,

    EE & IPQA check the component's orientation,stuffed component and non-stuff location usingaccording to the template or assembly drawing after EE builboard, if no problem found, notify EE to continue tobuild sample board (normally 4pcs), at the sametime, EE & IPQA continue to test the tape board.

    However, production run is not allow withoutcompletion of the tape board testing.

    1

    About 300 minutes average for tape board, but we use 210minutes to check tape boardamong them.

    Non-value

  • 8/10/2019 6s project.ppt

    10/17

    CONFIDENTIAL

    Tape boardCheck orientationstuffed componentnon-stuff location

    Check componentvalue

    Build sampleboard

    Tape board

    Check componentvalue

    Before:

    Current:Build sample

    boardCheck orientationstuffed componentnon-stuff location

    Problem 2 & Solution (Continued)

  • 8/10/2019 6s project.ppt

    11/17

    CONFIDENTIAL

    Problem 3 & Solution

    Item Problem Root cuase Solution

    1. ME draw out the master list of W/S parameters for reference.2. Directly run the 4pcs sampleboards at once and manual solderingif necessary

    1 About 80minutes averagefor W/S.

    Non-value

    (Run a piece of sample board, andthen adjust the relevant parametersof WS machine, afterward, runanother sample board, and thenadjust the relevant parameters again,

    and run other 2pcs sample board likethis.)

  • 8/10/2019 6s project.ppt

    12/17

    CONFIDENTIAL

    AssemblyRun the first

    sample board

    Adjustparameters

    of W/S

    Before:

    Adjustparameters

    of W/S

    Run theSecond

    sample board

    Current:

    AssemblyDirectly run the 4pcs

    sample boards atonce.

    Adjust parameters accordingto the master list drew by ME

    dept.

    Problem 3 & Solution (Continued)

  • 8/10/2019 6s project.ppt

    13/17

    CONFIDENTIAL

    Problems 4 & Solution

    FA target < 500pcs components need 1 hrs500---1500pcs components need 1.5 hrs>1500pcs components need 2 hrs

    Item Problem Root cuase Solution

    1

    About 120minutesaverage for teststation.

    Non-value

    (We must have the result of sampleboards test and then start to buildNPI boards, actually, somedefectives are not impact SMT tobuild, such as open, short,etc.)

    If the sample board test fail, TEanalyze them and submit the FAreport to team. If the defects justlike open/short, team leader willinform SMT to build according to theFA report, at the same time, TEcontinue to re-debug & re-test tilltest ass.

  • 8/10/2019 6s project.ppt

    14/17

    CONFIDENTIAL

    Test fail

    Before:

    FA Re-debug Re-test Test pass Inform SMTto build

    Current:

    Test fail FA

    Re-debug Re-test Test pass

    Inform SMTto build

    Problems 4 & Solution (Continued)

  • 8/10/2019 6s project.ppt

    15/17

    CONFIDENTIAL

    Problems 5 & Solution

    SMT changes line as soon as they complete

    the 4pcs sample boards, if TE department has notthe golden sample to debug test program/fixtureprior to NPI build.

  • 8/10/2019 6s project.ppt

    16/17

    CONFIDENTIAL

    The micro process mapping

  • 8/10/2019 6s project.ppt

    17/17

    CONFIDENTIAL

    NPI setup time in SMT lines

    0

    100

    200

    300400

    500

    600

    700

    800

    Mar'04 Apr'04 May'04 Jun'04 Jul'04 Aug'04 Sep'04 Oct'04 Nov'04 Dec'04

    U s e

    d t i m e

    ( m i n )

    Loading Tape board Sample board W/S Test

    395

    480

    736742678

    400 390 397